Town of Moraga Canyon Road Bridge Replacement Project April 24, 2019 Town Council Meeting NV5 Contract Amendment and Project Update Presentation

Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

Town of MoragaCanyon Road Bridge Replacement Project

April 24, 2019 Town Council Meeting

NV5 Contract Amendment and Project Update Presentation

Page 2: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019

➔Edric Kwan, P.E., Public Works Director and Town

Engineer

➔Shawn Knapp, P.E., Senior Civil Engineer

➔Jack Walker, P.E., Director of Transportation, NV5

➔David Wang, PhD, P.E., Senior Principal, PARIKH

Consultants, Inc.

➔Kevin James Ryan, CEG, Principal, Ryan Geological

Consulting, Inc.

PRESENTATION TEAM

2

Page 3: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019

Canyon Road Bridge Reopening Project

➔April 27, 2017 - Update on Canyon Road Bridge Closure

and Consider Declaring a Local Emergency

➔June 14, 2017 - Receive Presentation on the Alternatives

for Reopening Canyon

➔October 12, 2017 - Consider Additional Appropriation

$1,234,388

➔January 24, 2018 – Consider Acceptance Canyon Road

Bridge Reopening Project

PAST PRESENTATIONS

3

Page 4: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019

Canyon Road Bridge Replacement Project

➔October 23, 2013 – Consider Awarding Bridge Engineering

Design to NV5

➔April 23, 2014 – Authorization to Execute Master Cooperative

Agreement with CCTA

➔June 27, 2018 – Consider Authorizing NV5 Amendment No. 3

➔October 4, 2018 - Consider Authorizing the Acquisition of

Permanent Right-of-Way and Temporary Construction

Easement

➔October 10, 2018 – Project Update Presentation

➔April 24, 2019 – Project Update and Consider NV5 Contract

Amendment No. 4

PAST PRESENTATIONS

4

Page 5: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019

➔Risk Management

➔Revised Canyon Road Bridge Replacement Project

➔Project Cost Estimates

➔Project Finances

➔Project Construction Schedule

➔NV5 Contract Amendment

PRESENTATION OVERVIEW

5

Page 6: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019

LOCATION MAP

Adjacent Hill and Residents

Joaquin Moraga Intermediate School

Pear Orchard

Adjacent Residents

Canyon Road Bridge

Lafayette-Moraga Regional Trail/Fire Trail

Moraga Creek and Larch Creek

Canyon Road

6

Page 7: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019

RISK MANAGEMENT

7

Page 8: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019

➔Caltrans Local Assistance Procedures Manual

➔Prescriptive Step-by-Step project procedures that addresses

Risk Analysis process by identifying, avoiding or eliminating,

transferring, mitigating or accepting the risks

RISK MANAGEMENT

8

Page 9: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019

➔Preliminary Engineering Phase

➔Field Review results in 17 Environmental Studies

➔5 Years To Complete Studies And Obtain Permits That Eliminated or Mitigated Risks And Impacts

➔Bridge Type Selection Report

➔ROW and Utility Clearance

RISK MANAGEMENT

9

Page 10: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019 1010

Original Design

110.5’ Long x 48.5’ Wide

BRIDGE DESIGN CHANGES

4/24/2019

➔56% Larger Bridge = Increases Concrete, Steel, and Pilings.

➔44% Longer Retaining Walls:

▪ 240 vs 318 ft. longer wall

▪ 40 vs. 71 more piles

▪ 1,200 vs. 2,000 ft. total length of pilings

Revised Design

165’ Long x 50.2’ Wide

Page 11: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019 11

TEMPORARY VS. PROPOSED BRIDGE LOCATION

4/24/2019

Page 12: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019

SLIDE IMPACTS NEAR BRIDGE

ABOVE TENSION

CRACKS DEVELOPED

AT PEDESTRIAN

BRIDGE LANDING

4/3/19

TENSION CRACK

APPROXIMATE LOCATION

SHOWN RELATIVE TO

STITCH-PIER WALL FOR

TEMPORARY BRIDGE

12

Page 13: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019 13

KEY SAFETY ELEMENTS

13

▪ Bike Lanes And Multi-use Path Across Bridge

▪ Lighting For Motorists And Pedestrians

▪ Widen Bridge To Current Bridge Standards

▪ Improved Sight Distance

▪ Upgraded Guard Rails

▪ Bike Railing On Concrete

Barriers

▪ Floodway Capacity

Page 14: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019 14

BRIDGE AND ROADWAY COORDINATION

Preliminary Moraga Way & Canyon - Camino Pablo Improvements

Page 15: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019 15

RENDERING PROPOSED BRIDGE DESIGN

154/24/2019

Page 16: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019

CALTRANS APPROVED PROJECT BUDGET

▪ March 7, 2019 Caltrans HQ HBP Approved the Project’s

Revised Scope and Budget

▪Includes Design Budget for NV5 Bridge for Amendment No. 4

16

PROJECT PHASES

TOTAL

BUDGET

FEDERAL

PORTION

(88.53%)

TOWN CO-

MATCH

(11.47%)

Preliminary Engineering 1,590,000$ 1,407,627$ 182,373$

Right of Way 175,000$ 154,927$ 20,073$

Construction 6,351,000$ 5,622,540$ 728,460$

Construction Contingency 635,100$ 562,254$ 72,846$

Construction Engineering 952,650$ 843,381$ 109,269$

Totals 9,703,750$ 8,590,729$ 1,113,021$

393,000$

720,021$

CCTA Major Street (Fund 700)

Net Town Contribution

Page 17: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019

PROJECT ALTERNATIVE COST COMPARISON

* Sunbelt Rental has said NO to selling of their leased temporary bridge. Add $600,000 for removal and

erection of different vendor’s steel truss bridge.

NV5 Design 154,044$ NV5 Design 965,000$ NV5 Design 965,000$

ROW 20,073$ ROW 85,000$ ROW 85,000$

Staff Time 19,040$ Staff Time 105,000$ Staff Time 105,000$

Purchase Bridge -$ Purchase Bridge 448,100$ Lease Bridge (20 yrs.) 2,832,000$

CCTA (393,000)$ CCTA 70,000$ CCTA 70,000$

Other Project Costs

(Permitting, Env.

Analysis, etc..) 4,588$

Other Project Costs

(Permitting, Env.

Analysis, etc..) 40,000$

Other Project Costs

(Permitting, Env.

Analysis, etc..) 40,000$

Bridge Modifications,

Maintenance,

Additional Inspection

(100 yrs.) -$

Bridge Modifications,

Maintenance,

Additional Inspection

(20 yrs.) 155,000$

Bridge Modifications,

Maintenance,

Additional Inspection

(20 yrs.) 155,000$

Removal and Installing

New Vendor

Temporary Bridge* -$

Removal and

Installing New Vendor

Temporary Bridge* 300,000$

Removal and

Installing New Vendor

Temporary Bridge* -$

Bridge Construction 910,575$

Creek Bank Armoring

and Vegetation 279,000$

Creek Bank Armoring

and Vegetation 279,000$

Totals 715,319$ Totals 2,447,100$ Totals 4,531,000$

OWN TEMPORARY BRIDGE LEASE TEMPORARY BRIDGE

TOWN PORTION - 100 yrs. TOWN FULL PORTION - 20 yrs.

NEW REPLACEMENT BRIDGE

TOWN FULL PORTION - 20 yrs.

17

Page 18: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019

PROJECT ALTERNATIVE COST COMPARISON

* Sunbelt Rental has said NO to selling of their leased temporary bridge. Add $600,000 for removal and

erection of different vendor’s steel truss bridge.18

NV5 Design 154,044$ NV5 Design 965,000$ NV5 Design 965,000$

ROW 20,073$ ROW 85,000$ ROW 85,000$

Staff Time 19,040$ Staff Time 105,000$ Staff Time 105,000$

Purchase Bridge -$ Purchase Bridge 448,100$ Lease Bridge (20 yrs.) 2,832,000$

CCTA (393,000)$ CCTA 70,000$ CCTA 70,000$

Other Project Costs

(Permitting, Env.

Analysis, etc..) 4,588$

Other Project Costs

(Permitting, Env.

Analysis, etc..) 40,000$

Other Project Costs

(Permitting, Env.

Analysis, etc..) 40,000$

Bridge Modifications,

Maintenance,

Additional Inspection

(100 yrs.) -$

Bridge Modifications,

Maintenance,

Additional Inspection

(20 yrs.) 155,000$

Bridge Modifications,

Maintenance,

Additional Inspection

(20 yrs.) 155,000$

Removal and Installing

New Vendor

Temporary Bridge* -$

Removal and

Installing New Vendor

Temporary Bridge* 600,000$

Removal and

Installing New Vendor

Temporary Bridge* -$

Bridge Construction 910,575$

Creek Bank Armoring

and Vegetation 279,000$

Creek Bank Armoring

and Vegetation 279,000$

Totals 715,319$ Totals 2,747,100$ Totals 4,531,000$

NEW REPLACEMENT BRIDGE OWN TEMPORARY BRIDGE LEASE TEMPORARY BRIDGE

TOWN PORTION - 100 yrs. TOWN FULL PORTION - 20 yrs. TOWN FULL PORTION - 20 yrs.

Page 19: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019

RISKS ASSOCIATED WITH TEMPORARY BRIDGE

➔Increased Project Costs

➔Potential Loss Future Grants

➔Increase CO Gases

➔Lower Long Term Site Stability

➔Shorter Lifespan 20-30 Years Vs.

100 Years For Permanent Bridge

➔Higher Maintenance Costs and Liability

➔Higher Safety Risks for Pedestrians and Cyclists

➔Slower Emergency Response and Evacuation Route

19

Page 20: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019

May 2019 – November 2019 Complete Bridge Design

October 2019 – November 2019

Final ROW Clearing Prior to Migratory Bird Nesting Season

December 2019 – January 2020

Project Advertisement

February 2020 Town Council Consider Construction Award

March 2020 – October 2020 Phase 1 Bridge Construction

March 2021 – October 2021 Phase 2 Bridge Construction

CONSTRUCTION SCHEDULE – 2 SEASONS

20

Page 21: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019

• Construct Bridge’s Northbound Lane And Approaches

Temporary Bridge Continues To Handle Traffic In Both

Directions

2020 CONSTRUCTION –PHASE I

21

Page 22: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019

Construct Bridge’s Southbound Lane And Remove Temporary

Bridge

New Northbound Lane Handles Traffic In Both Directions

2021 CONSTRUCTION - PHASE 2

22

Page 23: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019

NV5 Contract Authorizations Amounts

Original Contract $567,017

Amendment No. 1 (Reimbursed through the Temporary

Bridge project)

$130,000

Amendment No. 2 (Reimbursed through the Temporary

Bridge project)

$34,987

Amendment No. 3 $398,000

Amendment No. 4 $378,000

Total $1,508,004

NV5 AMENDMENT

23

Page 24: Canyon Road Bridge Replacement Project April 24, 2019 Town ... · 6/14/17 4/24/2019 Canyon Road Bridge Reopening Project April 27, 2017 - Update on Canyon Road Bridge Closure and

6/14/174/24/2019

➔Adopt Resolution ____ - 2019 authorizing the Town

Manager to amend the Consultant Services agreement

with Nolte Vertical 5 (NV5) (Walnut Creek) for civil

engineering and bridge design services for the Canyon

Road Bridge Replacement project (CIP 14-101) in an

amount of $378,000 for a total amount not to exceed

$1,508,004.

STAFF RECOMMENDATION