Rice Annual Forum
Amish Sabharwal, EVP Americas, AVEVA
November 14, 2017 | Version 1
CAN INDUSTRY 4.0 IMPACT PROJECT EXECUTION?
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
2
Steam Assembly Line Automation Digitalization
Industry 4.0
WHAT DOES DIGITALIZATION MEAN?
“Digitalization is the use of
digital technologies to change a
business model and provide
new revenue and value-
producing opportunities”
-Gartner
DIGITALIZATIONAVEVA
Research results
October 2017
4
DEMOGRAPHICS
AVEVA - Plant digitalisation research results5
Chemicals/petrochemicals - US, Singapore, Russia,
Netherlands, Germany, Belgium
Pharmaceuticals - US, Ireland, UK, South Africa, France, Belgium,
Switzerland, Germany
Mining – US, South Africa, Australia, Russia, Ukraine, Chile, Peru
Power generation - US, Canada, UK, Germany, Japan, China,
France
Pulp and paper – US, Canada, Finland, Sweden, Brazil, Russia
Figure D1: “Within which primary sector is your organisation?”, asked to all respondents (400)
400 senior decision makers with responsibility or
involvement in software purchasing decisions were
interviewed in August and September 2017, split
across the below sectors and countries…
100
100
100
50
50
Chemicals/petrochemicals
Pharmaceuticals
Mining
Power generation
Pulp and paper
PRIORITISATION OF PLANT DIGITALISATION
AVEVA - Plant digitalisation research results6
Overall, across all sectors surveyed, plant digitalisation is most likely to be seen as the number one/top
priority (26%) compared to other areas of digital transformation
Figure 2: Analysis showing the percentage of respondents who report that each of the above
digitalisation initiatives are the number one/top priority for their organisation, asked to all
respondents (400)
Figure 3: Analysis showing the percentage of respondents who report that plant digitalisation is
the number one/top priority or a high priority for their organisation, split by sector, asked
to all respondents (400)
26%
16%
10%
7%
6%
6%
Plant digitalisation
Customer experience digitalisation
Workplace digitalisation
Marketing digitalisation
Financial digitalisation
Purchasing digitalisation
26%
34%
29%
25%
22%
20%
55%
54%
54%
58%
68%
48%
Total
Pulp and paper
Chemicals/petrochemicals
Mining
Power generation
Pharmaceuticals
Number one/top priority High priority
DIGITAL TECHNOLOGIES OFFERING THE GREATEST OPPORTUNITIES TO EXPLOIT
AVEVA - Plant digitalisation research results7
Figure 25: Analysis showing the top seven most commonly reported digital technologies that offer the greatest opportunity to exploit, split by sector, asked to all respondents (400)
Cloud and intelligent information management are top priorities!
27%
20%
10% 10%
8%6%
5%
Cloud Intelligent information
management
Robotic process
automation
IoT Advanced analytics Drones Sensors
INTELLIGENT INFORMATION MANAGEMENTPLANT OPERATIONS PERSPECTIVE
IOT IS ALL ABOUT REAL TIME OPERATIONAL INFORMATION
CONNECTED
FinancialInformation
Maintenance Information
Real-time Operations Information
WHAT ABOUT ENGINEERING INFORMATION?
3D Models
Shop
Drawings
Laser Scans
Isometrics
Line Lists Instrument
Index
Datasheets
P&IDs
1D
2D
3D
ENGINEERING INFORMATION
Status information /
Maturity
Relationships / Context
EPC
HANDOVER
Owner
THE PROBLEM?
Document
Centric
Drafting Table CADD
(PDMS)
Global
Execution
Digital
Asset
EPC 4.0
14
BARRIERS TO ADOPTION
EPC 4.0ASK YOURSELF…
➢ Can we propagate engineering and design changes quickly and reliably across all
disciplines?
➢ Can we incorporate late changes to design with minimal impact to execution?
➢ Can we quickly and reliably recalculate TIC as the design changes?
➢ Can we incorporate additional cost reduction cycles without impacting schedule?
➢ Do our projects pass over from good ideas that are too late?
➢ Can we reliably and automatically produce engineering and construction
deliverables from your source tools?
➢ Do we resort to offshore “value” centers (EPC 3.0) to produce deliverables?
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.16
TYPICAL PROJECT COST BREAKDOWN
Engineering Supply Chain Fabrication/Install CommissioningCMT
EXAMPLE OF EPC DATA CHALLENGE
Tag
Dataset1
Dataset1
Dataset1
PO
Parts List 1
Req
Parts List 1
Req Req
Tag
Dataset1
Dataset1
Dataset1
Work Package(Construction)
Scheduled Activity
Docs List 1
Budget
Work Package(Fabrication)
Parts List 1
Parts List 2
Scheduled Activity
Docs List 1
Budget
Work Package(Commissioning)
Parts List 1
Parts List 2
Scheduled Activity
Docs List 1
BudgetPO
Parts List 2 Issued
Working
On Hold
Key to Status/Lifecycle Maturity
In Consistency
Pipeline
Vessel
WORK PROCESS
Change of one single
Temperature value
Insulation needs to be added Insulation
clashes
Equipment Datasheets need to be updated
and re-issued
Pipe stress calcs need to
be re-assessed
Pipe has now become safety
cricital
P&IDs need to be updated
and re-issued
Spec Change
Different Instrument
arrangement needed
Wrong piping/equip-ment specs to suppliers
Planning is no
longer valid
Rework
DelaysCost
Overrun
Company reputation
Wasted materials
Re-ordering
1. FEED (Front-End Engineering Design) Validation Deliverables
2. Level 3 Baseline Schedule
3. Constructability Inputs
4. P&IDs(Piping & Instrumentation Diagrams)
5. Equipment Specifications & Data Sheets
6. Maintainability Inputs
7. Vendor Data
8. 3D Model (& Clash Detection)
9. Piping Routing and Isometrics
10. Nozzles, Ladders, and Platform for Towers/Vessels/Tanks
11. Miscellaneous Pipe Support Drawings
11THE MOST PROBLEMATIC DELIVERABLES
This information is based on the research outputs by Research Team 320
supported by the Construction Industry Institute.™
40%Procurement
40%Construction
10%
Engineering &
Design
Miscellaneous
(Love et al. 2014)
14.2%of contract value
Direct + Indirect
AVERAGE COST OF ENGINEERING ERRORS
This presentation is based on the research outputs by
Research Team 320 supported by the Construction Industry
40%Procurement
40%Construction
10%
Engineering &
Design
Miscellaneous
TYPICAL WBS HIERARCHY
Tasks
Area Area Area
Phase
(FEED)
Phase
(Detail Design)
Sub-Area
(Initial Design)
Sub-Area
(Initial Design)
ItemP-201
ItemV-205
Seawater
CoolingChill Water Ballast
E P C
System System
1 2 1 2
Long Lead
Equipment
Bulks Commodities
Project Materials Fabricated Items
Mech Equip Electrical
EquipInstruments
Pump PO Vessel PO
Engineering Procurement Commissioning
Equipment Instrumentation
& Controls
Layout
ItemP-201
ItemV-205
ItemP-201
ItemV-205
REALITY – WBS ARE RELATIONAL
FPSO
Total
Construction
Cost
Process
System
Control
System
Fabrication
Estimates
Module
Area
Structural
Design
Construction
Estimates
Bulk
Commodities
Piping
LayoutPipe Stress
Utilities
Instrument
Mechanical
Datasheet
Bulk Steel
PO
Bulk Pipe &
Fitting PO
Procure-
ment Plan
Vendor
Data
Cabling
Layout
Electrical
SystemElectrical
Loads
Pump POPump PO
Electrical
Datasheet
Item
P-201
➢ Plan to manage complex Engineering Information in a relational not hierarchical
way
➢ Go beyond technical data, captures data maturity, status and relationships
➢ Leverage a data authoring and storage system for Engineering Information that
provides “single points of truth” for all data consumers
➢ Auditable/Traceable records of changes
➢ Generate Documents/Lists/Drawings from the data
➢ Allows data consumers to view data to meet their needs without creating new
documents
➢ 24/7 information access – avoid lags in sharing discreet pieces of technical
information
THE DATA CENTRIC PROJECT APPROACH
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.28
Engineering Supply Chain Fabrication/Install CommissioningCMT
CHANGE INSTIGATED IN PROCESS
Tag
Dataset1
Dataset1
Dataset1
PO
Parts List 1
Req
Parts List 1
Req Req
Tag
Dataset1
Dataset1
Dataset1
Work Package(Construction)
Scheduled Activity
Docs List 1
Budget
Work Package(Fabrication)
Parts List 1
Parts List 2
Scheduled Activity
Docs List 1
Budget
Work Package(Commissioning)
Parts List 1
Parts List 2
Scheduled Activity
Docs List 1
BudgetPO
Parts List 2 Issued
Working
On Hold
Key to Status/Lifecycle Maturity
In Consistency
Pipeline
Vessel
AFFECTED OBJECTS LOCKED DOWN
Engineering Supply Chain Fabrication/Install CommissioningCMT
Tag
Dataset1
Dataset1
Dataset1
PO
Parts List 1
Req
Parts List 1
Req Req
Tag
Dataset1
Dataset1
Dataset1
Work Package(Construction)
Scheduled Activity
Docs List 1
Budget
Work Package(Fabrication)
Parts List 1
Parts List 2
Scheduled Activity
Docs List 1
Budget
Work Package(Commissioning)
Parts List 1
Parts List 2
Scheduled Activity
Docs List 1
BudgetPO
Parts List 2 Issued
Working
On Hold
Key to Status/Lifecycle Maturity
In Consistency
Pipeline
Vessel
Engineering Supply Chain Fabrication/Install CommissioningCMT
CHANGE PROPAGATED TO AFFECTED OBJECTS
Tag
Dataset1
Dataset1
Dataset1
PO
Parts List 1
Req
Parts List 1
Req Req
Tag
Dataset1
Dataset1
Dataset1
Work Package(Construction)
Scheduled Activity
Docs List 1
Budget
Work Package(Fabrication)
Parts List 1
Parts List 2
Scheduled Activity
Docs List 1
Budget
Work Package(Commissioning)
Parts List 1
Parts List 2
Scheduled Activity
Docs List 1
BudgetPO
Parts List 2 Issued
Working
On Hold
Key to Status/Lifecycle Maturity
In Consistency
Pipeline
Vessel
Engineering Supply Chain Fabrication/Install CommissioningCMT
ENGINEERING ITEM RE ISSUED AND ALL OTHER OBJECTS UPDATED.
Tag
Dataset1
Dataset1
Dataset1
PO
Parts List 1
Req
Parts List 1
Req Req
Tag
Dataset1
Dataset1
Dataset1
Work Package(Construction)
Scheduled Activity
Docs List 1
Budget
Work Package(Fabrication)
Parts List 1
Parts List 2
Scheduled Activity
Docs List 1
Budget
Work Package(Commissioning)
Parts List 1
Parts List 2
Scheduled Activity
Docs List 1
BudgetPO
Parts List 2 Issued
Working
On Hold
Key to Status/Lifecycle Maturity
In Consistency
Pipeline
Vessel
IMPROVED WORK PROCESS
Lists and Datasheets are all aligned with 3D models and schematics,
ensuring quality deliverables
Avoiding procurement errors
and delays
Avoiding rework in construction
IMPACT OF AVEVA’S EPC 4.0 STRATEGY
• Engineering
• Concept, FEED, Detail Design
• Procurement
• Fabrication/Construction
• Advanced Work packaging
• Workface Planning
• Materials Management
• Commissioning and Startup
AVEVA’S EPC 4.0 STRATEGY
PROCUREMENT
FABRICATION
MATERIAL MANAGEMENT
ENTERPRISE ASSET MANAGEMENT
ASSET PERFORMANCE & RELIABILITY
ASSET SAFETY & COMPLIANCE
3D 2DStandards
EXAMPLE OF A DIGITAL ENGINEERING WORK PROCESS
Show Southern Company video here!
| Copyright © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.36
| Copyright © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.37
THE IT’S NOT JUST ABOUT TECHNOLOGY
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.38
Technology
People
Processes
Enables
Development
Enables
Development of
Work/Business Processes
Training
10%
Savings is
enabled by
technology
| Copyright © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.39
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.40
To learn more about how AVEVA can help you execute projects more efficiently, visit http://www.aveva.com/en/Contact/