  • PROJECT MANUAL FOR:

    Campus Smart Meters Phase 2

    MONTANA STATE UNIVERSITY

    BOZEMAN, MONTANA

    January 12, 2018

    PPA No. 14-0175

    SET NO.:

    CAMPUS PLANNING,

    DESIGN AND CONSTRUCTION

    BOZEMAN, MONTANA PHONE: (406) 994-5413 FAX: (406) 994-5665

  • PROJECT MANUAL

    CAMPUS SMART METERS

    PHASE TWO

    MONTANA STATE UNIVERSITY

    BOZEMAN, MONTANA

    JANUARY 12, 2018

    PPA NO.: 14-0175

    SET NO.:

    PREPARED FOR:

    Montana State University

    Campus Planning, Design, and Construction

    Bozeman, MT

    Phone: (406) 994-5413 Fax: (406) 994-5665

    PREPARED BY:

    Ritter Engineering Inc

    P.O. Box 20422

    Billings, MT 59104

    Phone: (406) 651-8741

  • TABLE OF CONTENTS TOC - 1

    TABLE OF CONTENTS

    BIDDING REQUIREMENTS

    Permit Notice

    Invitation To Bid

    Instructions to Bidders

    Bid Proposal, Form 098

    CONTRACT DOCUMENTS

    Included in this Project Manual:

    Sample Standard Form of Contract, Form 110 State of Montana General Conditions

    MSU Supplemental Conditions Montana Prevailing Wage Rates

    The following documents are included in electronic versions but not included in the printed project manual.

    Substitution Request, Form 99

    Schedule of Values for Payment, Form 100

    Periodic Estimate for Partial Payment, Form 101

    Acknowledgement of Subcontractors, Form 102

    Consent of Surety to Final Payment, Form 103

    Contract Change Order, Form 104

    Contractors Affidavit, Form 106

    Certificate of Substantial Completion, Form 107

    Construction Change Directive, Form 109

    Request for Information, Form 111

    Performance Bond, Form 112

    Labor and Material Payment Bond, Form 113

    Certificate of Final Acceptance, Form 118

    Additionally these can be downloaded from our website:

    http://www.montana.edu/pdc/contract-documents.html or will be provided upon request.

    TECHNICAL SPECIFICATIONS

    Division 1 - General Requirements

    Summary ................................................................................................................................ 011000

    Price and Payment Procedures ............................................................................................... 012000

    Substitution Procedures .......................................................................................................... 012500

    Submittals .............................................................................................................................. 013000

    Project Coordination .............................................................................................................. 013100

    Quality Requirements ............................................................................................................ 014000

    Temporary Facilities .............................................................................................................. 015000

    Product Requirements ............................................................................................................ 016000

    Executions .............................................................................................................................. 017300

    Warranties Bonds ................................................................................................................... 017400

    Project Closeout ..................................................................................................................... 017700

    Operations & Maintenance Manuals ...................................................................................... 017823

    Project Record Documents ..................................................................................................... 017839

    Demonstrations & Training ................................................................................................... 017900

    Division 2 Site Construction (No requirements this Division)

    Division 3 Concrete (No requirements this Division)

    Division 4 Masonry (No requirements this Division)

    Division 5 Metals (No requirements this Division)

    Division 6 Wood and Plastics (No requirements this Division)

    Division 7 Thermal and Moisture Protection (No requirements this Division)

    Division 8 Doors and Windows (No requirements this Division)

    Division 9 Finishes (No requirements this Division)

    Division 10 Specialties (No requirements this Division)

    Division 11 Equipment (No requirements this Division)

    Division 12 Furnishings (No requirements this Division)

    http://www.montana.edu/pdc/contract-documents.html

  • i:\14-0000\14-0175 campus smart meters phase 2\2 project manual specifications\div 0\14-0175 table of contents.doc

    Division 13 Special Construction (No requirements this Division)

    Division 14 Conveying Systems (No requirements this Division)

    Division 15 Mechanical (No requirements this Division)

    Division 16 Electrical

    General Provisions... ................................ 16000

    Raceways and Fittings. ................................. 16110

    Conductors.. ................................. 16120

    Boxes.. .................................. 16130

    Wiring Devices... .................................. 16140

    Fuses... .................................. 16170

    Underground Work................................... 16420

    Grounding System.. .................................. 16450

    Panelboards and Distribution Gear. ................................. 16470

    WAGES Meters.. .................................. 16800

    MSU Digital Control System Guidelines .. .................................. 16900

    Division 17 22 (No requirements these Divisions)

    Division 23 HVAC

    Building Mechanical HVAC Requirements. .......................................................... 230000

    Demolition.. .................................... 230010

    General Duty Valves for HVAC Piping ..................................... 230523

    Hangars and Supports for HVAC Piping and Equipment ...................................... 230529

    Antifreeze ................................... 230540

    Identification for HVAC Piping, Ductwork, and Equipment..................................... 230553

    HVAC Piping Insulation .................................... 230719

    HVAC Piping and Pipe Fittings ..................................... 232113

    Hydronic Specialties System Drain and Fill ................................... 232116

    BTU Meters .................................... 232117

    CONSTRUCTION DRAWINGS

    CVR COVER SHEET

    E1.1 PARTIAL ELECTRICAL SITE PLAN

    E1.2 LEON JOHNSON BASEMENT ELECTRICAL PLAN

    E1.3 WILSON HALL LARGE SCALE BASEMENT ELECTRICAL PLAN

    E2.1 LEON JOHNSON NETWORK AND WAGES METER DETAIL

    E3.1 METER SCHEDULES

    E3.2 CALCULATED VALUES AND METER POINTS

    MS.1 PARTIAL MECHANICAL SITE PLAN

    M1.1 LEON JOHNSON OVERALL BASEMENT PLAN PIPING

    M1.2 LEON JOHNSON LARGE SCALE BASEMENT PLAN PIPING

    M1.3 LEON JOHNSON LARGE SCALE BASEMENT PLAN PIPING

    M3.1 MECHANICAL DETAILS

    M4.1 MECHANICAL SCHEDULES AND LEGEND

  • MSU Permit Notice PN-1

    CAMPUS PLANNING, DESIGN & CONSTRUCTION Sixth Avenue and Grant Street P.O. Box 172760 Bozeman, Montana 59717-2760

    Phone: (406) 994-5413 Fax: (406) 994-5665

    PERMIT NOTICE

    The Contractor will be responsible for paying the city of Bozeman Building Inspection

    Division for building, electrical, mechanical, and plumbing permits.

    The Owner will be responsible for paying the city of Bozeman plan review fee and

    impact fees.

    CITY OF BOZEMAN

    BUILDING INSPECTION DIVISION

    20 EAST OLIVE STREET

    SUITE 208

    BOZEMAN, MONTANA 59715

    (406) 582-2375

  • CAMPUS PLANNING, DESIGN & CONSTRUCTION Sixth Avenue and Grant Street

    P.O. Box 172760 Bozeman, Montana 59717-2760

    Phone: (406) 994-5413 Fax: (406) 994-5665

    Page 1 of 1

    INVITATION TO BID

    Sealed bids will be received until 2:00 PM on Thursday, February 15, 2018, and will be publicly

    opened and read aloud in the offices of MSU Campus Planning, Design and Construction, Plew

    Building, 6th & Grant, Bozeman, Montana, for: Campus Smart Meters Phase 2, PPA No. 14-

    0175

    Bids shall be submitted on the form provided within the Contract Documents. Contract documents

    may be obtained at the offices of:

    Montana State University On the web at:

    Campus Planning, Design and Construction http://www.montana.edu/pdc/bids.html

    Plew Building, 6th & Grant

    PO Box 172760

    Bozeman, Montana 59717-2760

    A PRE-BID WALK-THROUGH IS SCHEDULED FOR THURSDAY, FEBRUARY 1, 2018,

    AT 1:00 PM. PARTICIPANTS SHOULD MEET AT: PLEW BUILDING, FACILITIES

    CONFERENCE ROOM, 6TH & GRANT STREET, BOZEMAN, MONTANA.

    ATTENDANCE IS STRONGLY RECOMMENDED. Bidders should thoroughly review the

    contract documents before the pre-bid conference.

    Bids must be accompanied by a bid security meeting the requirements of the State of Montana in the

    amount of 10% of the total bid. After award, the successful bidder must furnish an approved

    Performance Security and a Labor & Material Payment Security each in the amount of 100% of the

    contract for contracts equal to or greater than $