Campus Construction and Space Planning– What’s Next?
January 2020
Facilities Master Plan (Phases 1 & 2)• Establish Centers of Excellence for Career & Tech Education and Arts• Enhance Campus Front Door• Realign Academic Resource Centers• Incorporate Sustainability• Strengthen Athletic Facilities• Prioritize Active Learning Classrooms
Construction Timeline2018 to 20213 YEAR PLAN
2018 Jan
CTE CONSTRUCTION BEGINSFADS CONSTRUCTION BEGINS
Apr June
GYM RENOVATION STARTS
Oct
2019
JanApr
CTE OPENS
June
ATB RENO COMPLETED
Oct
SC 1ST FLOOR OPENS
2020
Jan
LIBRARY RENOVATIONS COMPLETED
Apr June
WLB REPLACEMENT BEGINS
Oct 2021
FADS OPENSLIBRARY RENOVATION BEGINS
GYM RENOVATION CONCLUDESATHLETICS FIELDS BEGINSC RENOVATION BEGINS
ATB WORK BEGINS
Hugh L. Libby Career & Technical Education Center
Fine Arts & Design Studios (FADS)
Athletics and Front Door
Library Renovations /Resource Center
Consolidation
LIB 2nd floor
LIB 1st floor
OHOW Garage
Student Center
Space Management
JCCC Space Management
• Office of Space Management• Led by Jeff Hoyer
• Facilities Rental • Processes and procedures to support Facilities Administrators
across campus by providing frameworks, common guidelines, and the tools to improve facilities utilization and the customer experience.
• Space Planning• Operationalized with Jeff taking charge of the function and
leading the college’s existing Space Committee into the future.
JCCC Space Planning Guiding PrinciplesStudent facing functions on lower floors
Administrative functions on higher floors
Reserve space for student gathering spaces
Creation of Campus / Academic “Neighborhoods”
Appropriate benchmarks are used in new assignments
Phase 3 – What comes next?
• Active Learning classrooms• Resource Center backfills• Academic “neighborhoods”• 1st Floor Student Engagement hub
Active Learning ClassroomsFY17 FY18 FY19 FY20 PlannedCC 217 CC 215 CLB 316 CC 122CC 332 CC 224 CLB 402 GEB 217ITC 134 CC 344 GEB 356 GEB 379SCI 112 GEB 353B GEB 358 OHEC 119SCI 114 HCA 117 RC 323 RC311GEB 340 SCI 222 OHOW RC361
Resource Center Backfills
• Summer 2020• Nursing program
expansion• 7 additional Active
Learning Classrooms• Helps ensure adequate
space for anticipated Science lab renovations
SCI First Floor
OCB Third FloorSCI Second Floor
LIB Third Floor
• English and Journalism Faculty in Carlsen Center relocated to LIB 3rd Floor
• Administrative staff on GEB 1st Floor relocated to Carlsen Center
• Estimated 2022 completion
GEB 1st FloorStudent Activities
Hub
Phase 1, Phase 2, and Phase 3 FMP Projects
2019 2020 2021 2022Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Phase 1 ProjectsATB RenovationWLB ReplacementPhase 2 ProjectsLibrary & Resource Centers **Phase 3 ProjectsResource Center BackfillConsolidate Engl, Journlsm, CommConsolidate Marketing Div.Relocate FoundationRelocate Fin Services and EVPRelocate Legal DeptCreate Student Engagement Hub
* Preliminary discussions, dates subject to change
Construction PhaseMove-In
Enhancing JCCC Student Experience
Other Major Project:Science LabsRenovations
�Campus Construction and Space Planning– What’s Next?�January 2020Facilities Master Plan (Phases 1 & 2)Construction TimelineHugh L. Libby Career & Technical �Education CenterSlide Number 5Fine Arts & �Design Studios (FADS)Slide Number 7Athletics and Front Door�Slide Number 9Library Renovations /�Resource Center �ConsolidationSlide Number 11Slide Number 12OHOW Garage�Slide Number 14Student Center �Slide Number 16Space Management�JCCC Space ManagementJCCC Space Planning �Guiding PrinciplesPhase 3 – What comes next?Active Learning ClassroomsResource Center BackfillsGEB 1st Floor�Student Activities HubSlide Number 24Slide Number 25Other Major Project:�Science Labs�RenovationsSlide Number 27Slide Number 28