Environmental Due Diligence Report Project Number: 41403-013 November 2019 Cambodia: Urban Water Supply Project – Stoung Subproject (Expansion), Drilling of Deep Well and Construction of New Office Building Prepared by the Ministry of Industry, Science, Technology & Innovation for the Asian Development Bank. This environmental due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

Environmental Due Diligence Report

Project Number: 41403-013 November 2019

Cambodia: Urban Water Supply Project – Stoung

Subproject (Expansion), Drilling of Deep Well and

Construction of New Office Building

Prepared by the Ministry of Industry, Science, Technology & Innovation for the Asian Development Bank. This environmental due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 2: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

ii

TABLE OF CONTE NTS

Page

I. INTR ODUCTION ........................................................................................................... 5 II. S UBPR OJ E CT DE S CR IPTION ..................................................................................... 5 III. BR IE F DES CR IPTION OF THE E NVIR ONMENT .......................................................11

A. S ite Visit ...................................................................................................................11 B. R apid E nvironmental Assessment Checklist and Categorization ..............................13 C . Description of S urrounding E nvironment ..................................................................13

IV. GE NE R AL IS S UE S RE LATE D TO THE E NVIR ONME NT ..........................................13 V. E XIS TING FACILITIE S AUDIT ....................................................................................17 VI. E NVIRONME NTAL MANAGE ME NT PLAN ................................................................17

A. R eview of Impacts ....................................................................................................17 B. Institutional Arrangements .......................................................................................24 C . E nvironmental Monitoring Plan ................................................................................27

VII. PUBLIC CONS ULTATION AND DIS CLOS URE ........................................................29 A. Public Consultation ..................................................................................................29 B. Disclosure ................................................................................................................29

VIII. GRIE VANCE R E DR E S S ME CHANIS M ....................................................................29 IX . CONCLUS IONS AND R E COMME NDATIONS ...........................................................30

A. Conclusions .............................................................................................................30 B. R ecommendations ...................................................................................................30

Appendix 1: R apid E nvironmental Assessment (R EA) Checklist ......................................32

LIS T OF TABLE S

Page

Table 1. Materials for the Proposed E xpansion ofPipelines… … … … … … … … … … … … … .7 Table 2: Potential E nvironmental Impacts and Mitigation Measures .................................18 Table 3: R oles and Responsibilities .................................................................................26 Table 4: E nvironmental Monitoring Plan...........................................................................28

L IS T OF FIGUR E S

Page

F igure 1: Layout of the Proposed E xpansion of Pipelines … … … ....................................7 F igure 2: Layout of the Proposed S toung Water Works Office ...........................................8

Page 3: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

iii

ABBR E VIATIONS ADB : Asian Development Bank AP : Affected Person CAP : Corrective Action Plan CC : Construction Contractor CE MO : Contractor E nvironmental Management Officer CE MP : Contractor’s E nvironmental Management Plan CMP : Construction Management Plan DBS T : Double Bituminous S urface Treatment DDE : Detail Design E ngineering DDR : Due Diligence R eport DE IA : Department of E nvironmental Impact Assessment DOE : Department of E nvironment DPWT : Department of Public Works and Transport DS C : Design and S upervision Consultant E IA : E nvironmental Impact Assessment E MAP : E nvironmental Management Action Plan E lope : E nvironmental Monitoring Plan E MP : E nvironmental Management Plan E S : E nvironmental S pecialist GDPWS : General Department of Potable Water S upply GOC : Government of Cambodia GR C : Grievance R edress Committee GR M : Grievance R edress Mechanism MIH : Ministry of Industry and Handicraft MOE : Ministry of E nvironment NE S : National E nvironmental S pecialist NGO : NoncGovernment Organization NR : National Road OHS : Occupationalb Health and S afety PDOE : Provincial Department of E nvironment PE : Polyethylene Pipes PE MO : PMU E nvironmental Management Plan PIA : Project Implementation Assistance PIAC : Project Implementation Assistance Consultant PIU : Project Implementation Unit PMU : Project Management Unit PPE : Personal protective equipment PS MO : PMU S afeguard Management Officer PWW : Provincial Water Works R E A : R apid E nvironmental Assessment (Checklist) R GC : R oyal Government of Cambodia R P : R esettlement Plan S PS : S afeguard Policy S tatement (2009) S OP : S tandard Operation Procedure UWS P : Urban Water S upply Project UXO : Unexploded ordnance

Page 4: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

iv

UNITS

cm : centimeter dBA : decibels km : kilometer kW : kilowatt m : meter m3/day : cubic meter per day mm : millimeter R OW : right of way • : diameter % : percent

Page 5: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

5

I. INTR ODUCTION 1.The Government of Cambodia availed a loan from the Asian Development Bank (ADB) to fund the Urban Water S upply Project (UWS P). This was approved on 11 December 2014 and became effective on 16 J une 2015. The project was estimated to cost $37.4 million. ADB provided a loan of $34.0 million from ADB’s concessional ordinary capital resources and the remaining $3.4 million was to be financed by the government. The executing agency is MIH and the implementing agency is the PMU under the General Department of Potable Water S upply. The loan closing date is scheduled on 30 J une 2020. 2. The project’s impact will be expanded access to sustainable and safe water supply services for the urban population in Cambodia. This will contribute to the government’s 2025 target of 100% coverage for urban areas. Its outcome will be improved water supply infrastructure and service provision in nine towns. The project consists of four main outputsb namely:

Output 1: Improvement of water supply systems in seven towns. Output 2: New water supply system for S tung Teng Output 3: E xpansion of water supply coverage in S oem R eap Output 4: Project implementation support.

3. Improvement of S towing Water Works is one of the subprojectsb which covers the construction of Water Treatment Plantb Pumping S tationb F loating Intake and new intake structure under Output 1. Construction is ongoing. The pipelaying works was completed in May 2019 under Output 3. Under the subprojectb the strung Provincial Water Works through PMU submitted a proposal for additional components. These include the expansion of the distribution networkb drilling of deep well and the construction of new office building to replace the old structure. The proposed structures are combined in this due diligence report. 4. The subproject is classified as a Category C Project according to ADB S afeguards Policy S tatement (S PS ) (2009). Impacts of the installation of additional distribution pipelines are considered insignificant. Additional pipe laying works will be undertaken within the right of way. The other components which include the drilling of deep well and the Office Building will be located within the PWW Property both with minor effects on its surrounding areas. II. S UBPR OJ E CT DE S CR IPTION 5. S toung is a district within Kampong Thom Provinceb in central Cambodia. It is located along National R oad (NR) 6. The sources of water for the existing water supply facility in S toung are from S toung R iver and boreholes. Drilling of another deep well will augment the source of water. The proposed extension lines cover 27 villages in five communes/ S angkat of S toung province (Table 1 and F igure 1). With this proposed expansion lineb it is expected that 1b626 households will benefit from this expansion.

Page 6: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

6

6. The proposed S toung Water Works Office will be 2cstorey building with a total floor area of 565 square meters. Land area requirement is approximately 266 square meters. Construction activities include the following:

Clear the building site (demolition of old office building) S urvey to stake out for the foundation E xcavate the foundation Install plumbing grounds Pour a foundation and footers with concrete Build the main loadcbearing structure Add floor and ceiling joist and install subfloor panel Install roof Cover the walls Install windows Add internal plumbingb electricalb and utilities Finishing works

Figure 2 provides the layout of the proposed structure and the existing PWW facilities.

Page 7: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

7

Table 2. Materials for the Proposed E xpansion of Pipelines

No. Commune Name Village Name No. of Households

Quantity Pipe size 160 mm

Quantity Pipe size 63 mm

E dge Pressure

1 S outh Kampong Chen J i Y ouk 47 734 2bar 2 S vay S or 130 998 2 Gnoun S eam 93 712 888 3 Msang Krorng O Doung 60 508 1016 4 S outh S ambou 63 608 1216 5 S outh Msang Krorng 68 966 1932 6 Kouk Trea 82 820 1640 7 Kampong Brodom 93 654 1308 S ubctotal 636 8000 8000 8 North Kampong Chen Chek 133 1325 2.5 bar 9 Chork 83 1114 839 10 Roka 57 1052 1052 11 Msang Krorng S om Parn 49 661 661 12 Chi Meas 86 887 887 13 North S ambou 78 989 989 14 North Msang Krorng 57 972 972 S ubctotal 543 7000 5400 15 S outh Kampong Chen Kampong Kdey 38 366 2.5 bar 16 Trea Korh 49 428 17 Tor Tea 26 386 18 S am Ka Ouk 88 812 19 North Kampong Chen Tnout (Inside road) 65 488

S ubctotal 266 2480 20 North Kampong Chen Tnout (S teng Meas) 33 2440 1650 2bar 21 Tnout (PM) 65 2230 2000

Total 98 4670 3650 22 S outh Kampong Chen Leab Tong Tnol 81 731

Page 8: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

8

23 S or Prouch Mo Chheay 83 1224 1200 1.8 bar 24 Bro Det 46 580 1160

S ubctotal 210 2535 2360 25 North Kampong Chen Leab Tong (Asian

road) 17 1950 1950 2bar

26 Trea Chrang S or 35 2280 2280 27 Trea 31 1b720 1720

S ubctotal 83 5950 5950 Total 1626 26100 23000

Page 9: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

9

Figure 1: Layout of the Proposed E xpansion of Pipelines

Page 10: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

10

F igure 2: Layout of the Proposed S toung Waterworks Office Building

Sour e: Doogle ap.

Page 11: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

11

III. BR IE F DE S CRIPTION OF THE E NVIRONME NT A . S ite Vis it 7. The PIAC E nvironmental Team visited the S toung Provincial Water Works Facility on 13 November 2019 as assisted by PMU and PIU. Observations on the ongoing construction activities in the site (i.e. underground tankb the river water intake) were noted.

Office Building

8. S toung Provincial Water Works through the MIHcPMU submitted a proposal for the construction of a new office building to replace the existing structureb which has been built and in use for several decades. The old building has several cracks exposing the occupants to hazard if the replacement of the new building is deferred. Location is the place where the old building operates which is within the property of S toung PWW.

9. E xtension line

c PIU proposes new extension lines for about 25km on both sides of S toung stream (D160 and D63).

c Along the new extension linesb there are some pagodas and schools (primary and secondary schools).

c R oads along the extension lines are relatively narrow and people build their fences within the ROW.

c People along the proposed pipeline extension would like to have access to clean water at reasonable price. According to them if water is available in their housesb there is no need for them to go to the stream which is risky for them.

c Pipeline installation is within the R OW (about 0.5m from electrical pole) as informed by the DPWTb Department of Land Managementb Urban Planningb Construction and Cadastralb and local authorities.

c It was observed that the water in the stream is moderately turbid. 10. Drilling of Deep Well c The proposed well will be a replica of an existing well. Well casing is bigger and expected flow will also be bigger. Based on the previous information from PWWb the flow is 60m3/hourb with 210 meters depth and 200mm casing. PWW PIU mostly used the well during dry season. R efer to F igurec3b PWW property showing existing and propose facilities. 11. Documentation is shown below.

S ite Vis it in S toung Water Works Facility on November 13b 2019

Page 12: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

12

V iew of the Old Office Building . New Office Building is proposed.

Construction of underground tank under Contract NCB/1a.

S ite Vis it in the proposed Area for the E xpansion of S toung Water Works Distribution Network

A residential area to be served by the project. S hown in the photo are MIHcPMU Manager DDG S ok Y animolb PMU S afeguards S taffb the PIU Officers and PIAC c Deputy Team Leader and the E nvironmental Team.

Page 13: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

13

Proposed Area for the Expansion of Distribution Network

S tretch of the road where the pipe lines will be installed.

30 September Dam at the downstream of S toung R iver and source of water for Preah Vihea province

B . R apid E nvironmental Assessment Checklist and Categorization 12. Based on discussions with the PMUb PIUb onsite inspection and prior knowledge of the surrounding areab the rapid environmental assessment checklist (R EA Checklist) was completed and is found in Appendix 1.

C . Description of S urrounding E nvironment

13. The proposed expansion line is situated within the residential and water works’ service areas. These will be directly connected to the existing pipelines and will be undertaken within ROWsb which are determined by the Provincial Department of Public Works and Transport (DPWT)b of S toung Province (Table 1 and F igure 1). Thereforeb it is strongly believed that unexploded ordnance (UXO) do not exist along the project alignment. 14. The current water sources of the people living along the proposed expansion lines are either borehole or from S toung R iver. People living along the proposed expansion lines expressed their eagerness to have access on clean water. IV. GE NE R AL IS S UE S R E LATED TO THE E NVIR ONMENT 15.. The proposed pipe laying project will be an extension of the existing one to be carried out under the same environmental condition. E xpansion lines will be laid within R OWs and the water works' service areas. Adverse impacts on the villages and environmental resources along the project routes are not expected. Impacts that could be encountered during the pipe laying works at minor level are listed below:

Damage to existing community structures and facilities.

Page 14: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

14

Dust and air emissions from soil excavation and movement of vehicles. Noise disturbance. Generation of excavated soil and other construction debris. Hazards to workers. R isks to community health and safety. Traffic congestion.

15. The following mitigation measures are proposed to minimize the potential impacts. 16. Damage to community facilities. The installation of water supply distribution lines will be on the sides of the roads within ruralclike area. Valvesb fittingsb laying of pipesb installation of meters for homes and businesses composed the proposed works. To mitigate this impactb the following mitigation measures will be applied:

Before the commencement of construction activitiesb PIU shall consult the persons where housesb driveways and other structures could be affected.

Coordinate with DPWTb local authoritiesb and owners of affected properties prior to commencement of pipe laying works.

The Contractor is required to repair structures that may be damaged such as roadsb canalsb drivewaysb and paths. Any damage to community structures will be restored at precproject condition at the cost of the Contractor.

17. Worker health and safety. Workers may be exposed to risks to health and safety due to physical hazardsb exposure to dust and noiseb falling objectsb and ergonomic injuries. Potential conflict with local people will occur if migrant workers will be brought to the site. To mitigate this impactb the following measures will be applied: 18. PIU will require the Contractor to provide the basic safety and health protective measures for workers such as personal protective gear suitable to the type of works being performed. F irst aid kit will be made available onsite. 18. Dust and air emission. Windcblown dust may be generated due to presence of loose soil and movement of vehicles at the work areas. To mitigate this impactb the following measures will be applied:

Cover and keep excavated soil and stockpiles moist. Conduct water sprinkling in areas prone to airborne dust. Cover materials for dug soil and stockpiles at the end of the day’s work. R egularly clean and sweep dust and accumulated soil at work areas at the end of

the day’s work. Maintain vehicles and equipment to ensure that emissions comply with the MOE ’s

standards. Prohibit open burning of waste materials. Instruct delivery trucks to cover materials with tarpaulin or other suitable materials

during hauling of materials. Impose speed limits on construction vehicles. R egularly clean and sweep dust in the work area. Inform and educate workers on the implementation of air emission and dust control

measures.

Page 15: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

15

19. Noise. There will be minimal noise to be generated during construction works except in areas where there is a need to break the concrete or asphalt pavement. Noise levels ranging from 82 to 88 dBA may be experienced in the areas at the distance of 15 to 30 meters from the source. To avoid nuisance to adjacent establishmentsb works that generate such noise level will not be undertaken at night time or from 22:00 to 06:00.

20. Community health and safety. The laying of water pipes along existing roadsides will result to impacts to community health and safetyb including traffic and restriction of community access. Distribution pipes will be installed under a variety of local conditions including along asphaltcconcrete roads and along unpaved roads. To mitigate this impactb the following mitigation measures will be applied:

Pipes will be installed in the roadsides of paved roads to avoid cuts on road

pavements. S pecial precautions need to be taken in built up areas and sensitive receptors

such as schoolsb temples and hospitals/health centers. PIU will require the Contractor to follow the existing S tandard Operating

Procedure (S OP) on pipe installation. These measures include the following: c Minimize the period of time that an excavation segment is kept open by not

allowing trenching and pipeclaying by more than a week for each 500cmeter segment. Trenches should be backfilled and ground leveled after installation of pipes.

c Install signs at the beginning and end of section of works. c Provide concrete barriers to avoid conflict with live traffic. c Place only bedding and pipe materials at the location that will be used within the

next few days’ workb well out of the line of traffic. c C lean up and remove from the site any excess spoilb wood used for shoring and

construction materialsb upon completion of the segment. c Compact soil in trench and clean surrounding pavement areas to reduce

blowing dust. c Provide temporary bridging across the trench at entries to residences and

businesses. Likewiseb provide safety tape barriers to reduce the possibility of accidents.

c Once work is complete on a segmentb pavement surfaces and masonry works (curbsb abutmentsb drainsb drivewaysb and sidewalk) will be repaired and returned to precproject condition.

c Provide advance notification of proposed pipe laying activitiesb locations and schedules to local residentsb hospitalsb schoolsb businessesb and other institutions. Regularly coordinate with affected parties during project construction.

c Install safety barriers in open excavations to avoid unauthorized or accidental access by the public.

21. Traffic. Pipe laying activities may potentially affect traffic movements and could result to closure of a road section. There will be no need for traffic rerouting since the pipe installation will require a small space at the road easement. A road lane may be blocked but not the entire road. Mitigation measures to manage traffic are as follows:

Page 16: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

16

Coordinate the proposed construction activitiesb schedulesb and traffic management plan with the local authorities and police.

Post informational boards in case of temporary lane closures. E mploy trained flaggers to direct traffic movements in areas with lane closures. Use traffic control and warning devices such as lightsb signsb traffic conesb flashing

boardb bollardsb and barricades to alert vehicles and pedestrians about lane closuresb equipment useb excavationsb and other potential hazards.

In areas that are busy during the dayb construction work may be conducted during nighttime to minimize disruption to traffic.

Construction of New S toung Water Works Office 23. Construction of the new office building entails the establishment of temporary facilitiesb site clearing that includes demolition of the old structureb excavation worksb formworksb masonryb plumbingb power supply and finishing works. It will be completed in six months and will employ 20 c 30 workers. Some impacts due to pipe laying will be encountered also in the construction of new office building specifically dustb noise and wastes from the demolition of building and excavation works. Applicable mitigation measures will be implemented. The contractor will be required to submit the construction methods and Contractor's E nvironmental Management Plan for approval of the MIHcPMU and PIAC. Drilling of Deep Well 24. The proposed deep well is almost the same as a Bank F iltrate which is about 50 meters away from the river. Proposed deep well with bigger casing is deeper to be able to tap the aquifer and the river as the main recharging source. A Control Panel complete with accessories will be properly installed.

Page 17: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

17

V. E XISTING FACILITIES AUDIT 24. Appendix I of the ADB S PS (2009) requires thatb “when the project involves existing activities or facilitiesb relevant external experts will perform environmental audits to determine the existence of any areas where the project may cause or is causing environmental risks or impacts.” The rapid environmental assessment checklist (Appendix 1) includes a section in which the existing facilities have been audited to identify the presence of wasteb spentb outcofcspec and discarded water treatment chemicalsb oilsb cleaning fluids and solventsb as well as contaminated soils that have or have the potential for causing environmental impacts or risks. Waste materials that pose a hazard to human health or the environment have not been identified at the facility. The director of the water works confirms the absence of any such materials within the water supply system buildings or on property under the control of the water works. There is no need to prepare a corrective action plan to dispose of materials of this nature or remediate soils or structures for purposes of reducing environmental impact and risk. 25. In additionb the potential presence of unexploded ordnance (UXO) has been evaluated within the subproject area based on discussion with PIU and inspection of the project routes where the work is to take place. The routes are residential areas for so many years. They have been determined that there is no basis for suspecting that UXO or mines are present.

VI. E NVIRONME NTAL MANAGE ME NT PLAN A . R eview of Impacts 26. Potential impacts of the installation of expansion linesb drilling of deep well and construction of Office Building are summarized in Table 2. With the previous studies and due diligence works for the existing pipe laying project in S toung Provincial Water Worksb the extension works by nature have similar methods in its implementationb thus contractors will adopt the S OP on pipe laying activities. As environmental setting and expected impacts are common both for the existing and proposed network expansionb applicable requirements for the existing E MP are adopted in this due diligence report while other provisions have been updated. To reiterateb the contractors will be required to prepare the Contractor's E nvironmental Management Plan.

Page 18: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

18

Table 3: Potential E nvironmental Impacts and Mitigation Measures Project Activity Potential Negative Impact Proposed Mitigation Measure Institutional

R esponsibility Cost

E stimates Construction Pipe laying activities

Disruption and damage to existing community structures and facilities c Pipe laying will cause temporary

disruption of community services and access to properties.

c Damage community facilities such as roadsb driveways to properties and pathways to private and public areas during pipe laying.

c Particularly at pipe road crossingsb construction activities along roads may lead to temporary blockage of lane and hamper movement of vehicles and people in the community.

c Provide temporary accesses to affected properties using durable materials. Particular attention will be given to ensuring safety along roads and paths normally used by school children.

c S ide street parking of construction vehicles on prolonged basis will not be allowed.

c Install barriers and safety warning signs on road sections and if necessary deploy traffic aid/flag persons at affected locations.

c Provide information boards on the project detailsb schedule and PWW contact numbers.

c Immediately repair the excavated areas and any damaged structures such as roadsb drivewaysb gatesb and paths. E nsure that restoration is accepted by the affected person.

Construction Contractor

Included in bid price for work

S oil digging and movement of construction materials due to pipe layingb office building and drilling of deep well

A ir pollution c Dust and air emissions from

digging and movement of vehicles.

c Require the Contractor to cover materials with tarpaulin or other suitable materials while in transit to avoid spillage of materials.

c Moisten earthen roads during dry and dusty conditionsb particularly roads near residences and through the town core area.

c Impose speed limits on construction vehicles. c Conduct maintenance on construction

equipment and vehicles to control air emissions during vehicle operation.

Construction Contractor

Included in bid price for work

Page 19: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

19

Project Activity Potential Negative Impact Proposed Mitigation Measure Institutional R esponsibility

Cost E stimates

Breaking concrete or asphalt pavement as applicable to subcproject components

Noise c There will be minimal noise to be

generated during construction works except in areas where there is a need to break the concrete or asphalt pavement. Noise levels ranging from 82 to 88 dBA may be experienced in areas at the distance of 15 to 30 meters from the source.

c Limit construction activities particularly operation of noise generating equipment at night.

c Position any stationary equipment that produce high noise levels such as excavator as far as practical from sensitive receptors.

c E rect temporary walls around construction sites especially near schoolsb hospitalsb and houses.

c Install noise suppression devices to noise generating equipment.

c Require drivers to minimize blowing of horn and to comply with speed limits

c Provide information to community on schedule of construction activities through billboard/ signs and complaint hotline.

Construction Contractor

Included in bid price for work

S oil excavationb disposal of debris to and from the siteb and construction worker offsite housing

Generation of dug soil and other construction debris c Generation of dug materials during

pipe laying. c Domestic solid wastesb domestic

wastewaterb inert construction wastesb and hazardous wastes during construction may result to pollution of the environment.

c During pipe layingb excavated material will be reused to cover back the trench. The Contractor will be required to properly reinstate the excavated trench after completion of pipe laying.

c Undertake segregation of hazardous and nonchazardous wastesb including properly labeled waste disposal bins.

c Instruct workers not to indiscriminately dispose wastes particularly at surrounding areasb canalsb riversb fieldb and other public areas.

c All solid waste will be regularly collected and removed from the work camps and disposed to areas approved by local authorities.

Construction Contractor

Included in bid price for work

Page 20: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

20

Project Activity Potential Negative Impact Proposed Mitigation Measure Institutional R esponsibility

Cost E stimates

Construction works

Worker health and safety c Workers may be exposed to risks

to health and safety due to physical hazardsb exposure to dust and noiseb falling objectsb and ergonomic injuries.

c Potential conflict with local people will occur if migrant workers will be brought to the site.

c Orient workers and implement measures to ensure construction safety; fire prevention and management; worker education and awareness for HIV/AIDS and other sexually transmitted diseases; and control measure for mosquito and other vector diseases.

c Require workers to adhere to guidelines relating to minimum distances for excavationsb toolsb vehiclesb and other activities in the R OWs of the water distribution lines.

c Provision of firstcaid kit and it is readily accessible by workers.

c Conduct training of workers in the identification and management of occupational hazards.

c Post safety signsb remindersb or warning notices at visible areas onsite.

c S trictly implement a “NocAlcoholb NocGambling and NocDangerous Drug Policy” at the construction site.

c Provide PPE s such as hard hatsb glovesb safety bootsb ear protectionb breathing masksb etc. Wearing of PPE sb while working onsite will be a mandatory requirement for workers.

c The Contractor should ensure that child laborers and trafficked workers are not employed.

c The Contractor will be required to provide priority hiring of qualified construction workers

Construction Contractor

Included in bid price for work

Page 21: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

21

Project Activity Potential Negative Impact Proposed Mitigation Measure Institutional R esponsibility

Cost E stimates

from the villages and to consult with the local to avoid conflict if migrant workers will be brought to the site.

Construction works

Community health and safety c R isks to community health and

safety due to pipe laying and unauthorized entry of villagers into dangerous working areas

c Provide advance notification of proposed pipe laying activitiesb locations and schedules to local residentsb hospitalsb schoolsb businessesb and other institutions. R egular coordinate with affected parties during project construction.

c Install safety barriers and plates in open excavations to avoid unauthorized or accidental access by the public.

c Provide safe access and passageways to properties and establishments for pedestrians affected by pipe laying works. This will include temporary pathways and crossings (e.g. metal or durable wooden plates) over excavated areas or trenches.

c Conduct daily cleaning of the work area and sweeping of the road shoulder.

c Backfill and cover the excavated areas after pipe laying activities.

c Reinstate good quality permanent accesses following completion of construction works.

c Post informational boards with contact name and numbers whereby local residentsb business operatorsb farmers and other establishments can report issues related to access restrictions.

Construction Contractor

Included in bid price for work

Page 22: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

22

Project Activity Potential Negative Impact Proposed Mitigation Measure Institutional R esponsibility

Cost E stimates

c Implement the Grievance R edress Mechanism to manage complaints from the community. Assign a focal person to receive community complaints in accordance with the Grievance R edress Mechanism (GR M).

c Document all complaints received and actions taken by the contractor to resolve the complaint.

Pipe laying and other construction works

Traffic Pipe laying activities may potentially affect traffic movements and could result to closure of a road section.

c Coordinate the proposed construction activitiesb schedulesb and traffic management plan with the local authorities and police.

c Post informational boards in case of temporary lane closures.

c E mploy trained flaggers to direct traffic movements in areas with lane closures.

c Use traffic control and warning devices such as lightsb signsb traffic conesb flashing boardb bollardsb and barricades to alert vehicles and pedestrians about lane closuresb equipment useb excavationsb and other potential hazards.

c In areas that are busy during the daytimeb construction work may be conducted during nighttime to minimize traffic disruption.

Construction Contractor

Included in bid price for work

Pipe laying and other construction works

Impacts on Biodiversity cImpacts on the existing biodiversity elements at the construction sites.

c Protect biodiversityb avoid as much as possible disturbance to flora (e.g treesb grasses and other vegetations ) and fauna (e.g. bees or migratory species ).

c

/ ostrutio / otra tor

L luded i id prie for

work

Page 23: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

23

Project Activity Potential Negative Impact Proposed Mitigation Measure Institutional R esponsibility

Cost E stimates

c Fully reinstate pathways and any biodiversity at least to their precproject condition upon the completion of construction.

Page 24: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

24

B. Institutional Arrangements 27. Adopting the institutional arrangement for the existing projectsb the General Department of Potable Water S upply at central level under Ministry of Industry and Handicraft (MIH) is the executing agencyb and will establish the Project Management Unit (PMU) to execute the Project. The PMU will assign responsibility for environmental aspects to a particular individual as staff PMU S afeguard Management Officer (PS MO) who is engaged full time with implementation of the project to monitor implementation of mitigation measures. PWW will be the implementation agency for the subproject. PWW will establish a Project Implementation Unit (PIU) to manage the implementation of the S ubproject at S toung Province. 28. The PMU will engage Contractors for specific worksb based on the subcontract packages considered most suitable for execution. Legal clauses regarding mitigation measures are required to be included in construction contract bidding documents and become part of contract agreements. For the main construction contractsb the Contractor will be required to appoint a staff Construction E nvironmental Management Officer (CEMO) responsible for supervising implementation of mitigation measures during the execution of the contract. The contractor will be required to prepare a Construction Management Plan (CMP) to ensure construction does not adversely affect healthb safetyb amenityb traffic or the environment in the surrounding area. The CEMO working with the Contractor’s S ite Manager is responsible for preparing this plan prior to the start of construction and receiving approval for the plan from the PMU before the start of construction. The CE MO will serve as a point of contact that is accountable for environmental aspects of the construction work. For smaller construction contracts or subcontractsb the (subc) contractor will still be held accountable for implementation of mitigation measures through a system of quality assurance supervised by the PMU.

Page 25: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

25

29. General notes/reminders for the PMUb work supervisors and environmental safeguards specialists are as follows:

As a precautionary measureb the PMU team shall inform ADB prior to construction start (formless by Email)b confirming that you have received and cleared the Contractor E nvironmental Management Plan (CE MP/CMP) and that it is in line with the DDR and the updated E MP. Also the contractor shall confirm that he has a responsible officer (E HS /CEMO) as part of the construction team.

E nsure that CEMP/CMP monitoring and reporting to the project owner/client shall

be on a monthly basis throughout the construction period using the provided reporting format sample in annex to the E MP. This shall also be clearly stipulated in the bidding docs requirements for the Contractors.

As part of the precconstruction phaseb all the existing biodiversity elements at the

construction sites need to be accounted for. It is the responsibility of the contractor to fully reinstate pathways and any biodiversity at least to their precproject condition upon the completion of construction. This needs to be accounted for in the mitigation budgetb reflected in the respective CE MPs / CMPs and in the environmental safeguards monitoring report to ADB

30. The PMU has direct responsibility for monitoring the implementation of the mitigation measures. The PS MO will be assisted in tasks by the E nvironmental S pecialists (E S )b consultants who are part of the Design and S upervision Consultant (DS C) and support all the subprojects undertaken through the loan. Work will commence with updating and finalizing DDR s and their respective environmental mitigation measures and monitoring plansb submitting the environmental reviews on behalf of MIH to the Ministry of E nvironmentb incorporating legal clauses regarding mitigation measures into construction contract bidding documentsb assisting the PS MO in monitoring the implementation of those measures during the progress of constructionb and preparing the environmental sections of semicannual reports to be provided to ADB. The E S also will provide training to PMU and PIU staff. Table 3 describes the functions of various agencies engaged in the project. 31. R elative to the present projectb R GC/C lient approval for E nvironment C learance from the Ministry of E nvironment involves revision of the DDR during the design phaseb coincident with detailed design preparationb and translation of the DDR into Khmer. The DDR is submitted to the Department of E IA within MOE b which has a period of 30 days to review and respond with commentsb or approveb the DDR. A timeline for updating the DDR as well as for inclusion of the EMP and special conditions in contract and/or bidding documents is as follows:

Project design proceeds over a period of 5 months (anticipated). Monitoring of water quality over first two months. Concurrentlyb DDE is updated with new design data.

Page 26: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

26

By end of month 2b expected issues related to design are resolved. DDR undergoes translation (2 weeks). DDR submitted to DOE by midcmonth 3 of design period. DOE has 30 days to review/approve DDR. DDR approved by midcmonth 4 of design period. ADB review runs concurrently with DOE review. F inal approval from ADB and the Government obtained before detailed design

finalized in time for inclusion in procurement package. 32. The Ministry of E nvironment (MOE ) and the provincial Departments of E nvironment (PDOE s) play a role in submittalb reviewb and approval of DDR sb and monitoring and reporting. This work takes place during the implementation phase. The E S will revise and update the DDR based on final designsb and the document should be translated into Khmer prior to submittal to MOE DE IAb which will engage in the review process the provincial PDOE where the subproject takes place. Once DEIA approves the subprojectb implementation can proceed with construction mitigation measures mostly in the hands of the Contractorb and the E S b PDOE b PIU and PS MO working together to perform monitoring and reporting. It will be the job of the PIUs supported by the E S to compile quarterly reportsb which then are compiled into semicannual safeguard monitoring reports by the PMU and DS Cb supported by the ES . The PS MO and PMU Project Director will be responsible for submittal of reporting to ADB. Table 4: R oles and Responsibilities Agency R ole MIH – GDPWS Project Management Unit (PMU)

S upervision and guidance; assist to appoint staff of PMU; recruited competent national environmental specialist (NES ) as part of the DS C to assist design team and PMU; submit DDR to the Ministry of E nvironment (MOE ) for approval; consolidate and submit semicannual reports to ADB.

S toung Provincial Water Works PIU

Appoint Project E nvironmental Management Officer (PE MO) to PMUb who will work with the E S to ensure E MPs are satisfied in the design and construction of the subproject; review and approve CMP; supervise and monitor DDR/CMP implementation; prepare and conduct public consultationsb administer the grievance redress mechanismb monitor subproject activities and prepare quarterly environmental reporting at the subproject level.

Design and S upervision Consultant (DSC) National E nvironmental S pecialist (E S )

Assist the PE MOs and the PMO to reviewb update and submit DDR for approval by MOE ; incorporate E MP requirements into designb specifications and construction contract; coordinate with other government agencies regarding environmental issues; organize and implement public consultation and grievance redress mechanism; monitor activities of design engineer and construction contractors to assure mitigation measures are implemented; incorporate environmental reporting into semicannual progress reports.

MOE DE IA and PDOE

R eview of DDR; PDOE to support monitoring of mitigation measures during construction.

Page 27: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

27

Agency R ole Construction Contractors (CC)

Implement environmental requirements related to construction; incorporate environmental costs into bid estimate; prepare a Construction Management Plan (CMP); appoint the Construction E nvironmental Management Officer (CE MO); assure all environmental requirements are followed.

GDPWS /MIH Lab Implement water quality monitoring of raw and treated water supplies during operations.

C . E nvironmental Monitoring Plan 33. E nvironmental monitoring extends during the implementation of the loan and engages the previously identified groups. Table 4 identifies the monitoring to be undertaken in respect to the mitigation measures previously identified. The PE MO is responsible for the bulk of the monitoring being undertaken during the design and construction periods. During operationsb the S toung Provincial Water Works is responsible.

Page 28: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

28

Table 5: E nvironmental Monitoring Plan Parameters to be Monitored Location Means of Monitoring Monitoring

Frequency R esponsibility for Monitoring

S ource of Fund

PrecConstruction Phase S urvey of affected structures (roadsb shopsb drivewaysb fencesb gatesb portions of housesb etc.

All project routes S ite survey Prior to the start of civil works

PE MOb E S b PDOE

PMU

Construction Phase R ehabilitation of road shoulder and driveways after pipe laying

Areas with pipe laying activities

Visual inspection Daily/weekly PE MOb ES b PDOE

PMU

E MP implementation Note: To be applied also for the construction of office building

All project areas (construction sitesb camp)

Visual inspection Daily/weekly PE MOb ES b PDOE

PMU

Direct effects on communities from project impacts such as damage to propertiesb dust generationb noise and safety.

All project routes Gather views and opinions of communities through community feedback

Weekly PE MOb ES b PDOE

PMU

Monitoring of EMP during construction/excavationb including compliance to traffic management and road restoration.

R oads where pipes cross

S ite inspection Daily/weekly PE MOb E S b PDOE

PMU

Page 29: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

29

VII. PUBLIC CONS ULTATION AND DIS CLOS UR E A . Public Consultation 34. Public consultation should be held at the outset of procurement for the construction of civil works under the project. This is in order to notify the homes and businesses in the immediate vicinity of the site that work will commence on the projectb to review environmental issues of concernb and to inform the public of the grievance redress mechanism established under the project. B. Disclosure 35. Details of the subproject will be disclosed through a process of public consultation described above. Further to thatb MIH will provide the relevant environmental information for this subprojectb including information from the DDR to affected people in a timely mannerb in an accessible placeb and in a form and language(s) understandable to them by providing a copy of the DDR in Khmer language at the PWW office for review by interested parties. In additionb ADB will post on its website the subproject DDR b updates prepared during the project implementation periodb and environmental monitoring reports prepared during the implementation period. VIII. GRIE VANCE R E DR E S S ME CHANIS M

35. Grievances related to both environmental and resettlement issues are addressed through the Grievance R edress Mechanism (GR M). In order to ensure that complaints from all affected persons (APs) on any aspect of environmentb land acquisitionb compensation and resettlement are addressed in a timely and satisfactory mannerb and that all possible avenues are available to APs to air their grievancesb a wellcdefined grievance redress mechanism will be established. All APs can send any questions to the MIHcPMU about their rights in relation with redress of environmental problems and entitlement under the resettlement plan. APs are not required to pay any fee in order to file a complaint at any level. The GRM has been explained in the public information booklet distributed to all APsb and is explained here in relation to complaints related to environmental impacts. 37. A Grievance R edress Committee (GRC) shall be established before commencement of site works and shall be chaired by PMU. The GRC shall have members from the PMUb commune councilsb local NGOb and women’s organization. Grievances can be filed in writing or verbally with any member of the GRC. The committee will have 15 days to respond with a resolution. If unsatisfied with the decisionb the existence of the GR C shall not impede the complainant’s access to the Government’s judicial or administrative remedies.

S tage 1 c Complaints from APs on any aspect of environmental impacts shall first be lodged verbally or in written form to the commune or village leader. The commune or village leader will coordinate with the MIHcPMU to decide on a course of action within 5 days from the day it is lodged. Usually complaints about environmental impacts are resolved at this stage.

Page 30: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

30

S tage 2 c If no understanding or amicable solution can be reachedb or if no response from the commune or village chief is received by the AP within 5 days of registering the complaintb he/she can appeal directly to the District Office. The complaint must be settled within 5 days of registering the original complaint. S tage 3 c If the AP is not satisfied with the actions made by the District GR Cb or in the absence of any responseb the AP can appeal to the Provincial GR C which must make a written decision and submit copies to the MIHcUWS P and AP.

S tage 4 c If the AP is still not satisfied with the decision of the Provincial GR C on appealb or in absence of any response from the MIHcUWS P within the stipulated timeb the APb as a last resortb may submit his/her case to court of lawb whose judgment is final. APs may also ask for resolution from ADB’s responsible project officer consistent with the provision of the ADB’s accountability mechanism. They can file their complaint through the ADB resident mission in Phnom Penh for transmittal to the ADB headquarters in Manila.

38. At each stageb the governing official is responsible for recording the minutes of meetingsb maintaining files on all complaintsb and for distributing copies of all decisions to the PMU and lower level bodiesb including commune/village officials and affected parties and households.

39. The PIU of the S toung Provincial Water Works shall make public the existence of this grievance redress mechanism through public awareness campaigns. They shall setcup a hotline for complaints and the hotline shall be publicized through the media and numbers placed on the notice boards outside the construction site and at subnational level of local government offices (e.g.b provincialb districtb commune levels). Locally affected people will still be able to express grievances through the commune councils and these would be referred through the usual channels in those committees. 40. The PMU will be responsible for checking the procedures and resolutions of grievances and complaints. The PIA consultant may recommend further measures to be taken to address unresolved grievances. IX . CONCLUSION AND RE COMME NDATIONS A . Conclusion 41. The proposed pipeline expansion worksb drilling of deep well and the construction of the Office Building will likely cause minor environmental impacts. As screenedb an E nvironmental Management Plan shall be prepared for the two components based on the final plan/specifications for the project. B. R ecommendations 42. Potential environmental impacts from the proposed project components during construction phase are dustb noiseb generation of construction wastesb obstruction to

Page 31: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

31

accessb possible damage to existing structuresb and others. Mitigation measures have been set out to mitigate these potential impactsb reinforced by a set of environmental specifications for the construction contractor. These measures should be implemented in order to minimize any adverse environmental effects of the project. The contractor will be required to prepare and submit the construction methods and Contractor's E nvironmental Management Plan for approval of the MIHcPMU and PIAC before the commencement of construction activities. 43. Institutional measures are also in place to obtain compliance from the construction contractorb to monitor the implementation of mitigation measures and to fulfill reporting functions related to loan implementation. These institutional measures that constitute the environmental management framework should also be implemented. Costs related to mitigation and monitoring were consideredb and no special costs have been identified.

Page 32: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

32

Appendix 1: R apid Environmental Assessment (R E A) Checklist Note: The well assessment is not part of the R EA

Instructions: (i) The project team completes this checklist to support the environmental classification

of a project. It is to be attached to the environmental categorization form and submitted to the E nvironment and S afeguards Division (RS E S ) for endorsement by the Directorb R S E S and for approval by the Chief Compliance Officer.

(ii) This checklist focuses on environmental issues and concerns. To ensure that social dimensions are adequately consideredb refer also to ADB's (a) checklists on involuntary resettlement and Indigenous Peoples; (b) poverty reduction handbook; (c) staff guide to consultation and participation; and (d) gender checklists.

(iii) Answer the questions assuming the “without mitigation” case. The purpose is to identify potential impacts. Use the “remarks” section to discuss any anticipated mitigation measures.

Country/Project Title: S toung S ubproject (E xpansion) and Construction of

New Office Building S ector Division: Urban Water S upply

S creening Questions Y es No R emarks A . PR OJ E CT S ITING Is the project area…

Densely populated? X Heavy with development activities? X Adjacent to or within any

environmentally sensitive areas? X

Cultural heritage site X Protected Area

• Wetland X • Mangrove X • E stuarine X . • Buffer zone of protected area X • S pecial area for protecting biodiversity X • Bay X

B. POTE NTIAL E NVIRONME NTAL IMPACTS

Will the Project cause…

pollution of raw water supply from upstream wastewater discharge from communitiesb industriesb agricultureb and soil erosion runoff?

x

impairment of historical/cultural monuments/areas and loss/damage to

x

Page 33: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

33

S creening Questions Y es No R emarks these sites?

hazard of land subsidence caused by excessive ground water pumping?

x

social conflicts arising from displacement of communities?

x

conflicts in abstraction of raw water for water supply with other beneficial water uses for surface and ground waters?

x

unsatisfactory raw water supply (e.g. excessive pathogens or mineral constituents)?

x

delivery of unsafe water to distribution system?

x

inadequate protection of intake works or wellsb leading to pollution of water supply?

x

over pumping of ground waterb leading to salinization and ground subsidence?

x

excessive algal growth in storage reservoir?

x

increase in production of sewage beyond capabilities of community facilities?

x

inadequate disposal of sludge from water treatment plants?

x

inadequate buffer zone around pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities?

x

impairments associated with transmission lines and access roads?

x

health hazards arising from inadequate design of facilities for receivingb storingb and handling of chlorine and other hazardous chemicals?

x

health and safety hazards to workers from handling and management of chlorine used for disinfectionb other contaminantsb and biological and physical hazards during project construction and operation?

x

dislocation or involuntary resettlement of people?

x

disproportionate impacts on the poorb x

Page 34: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

34

S creening Questions Y es No R emarks women and childrenb Indigenous Peoples or other vulnerable groups?

noise and dust from construction activities?

x Minimal only. The contractor will be required to prepare and implement the Contractor's E nvironmental Management Plan (CE MP)

increased road traffic due to interference of construction activities?

x Minimal only. The contractor will be required to prepare and implement the Contractor's E nvironmental Management Plan. PIU will coordinate with Heads of Commune to oversee and assist in the management of traffic.

continuing soil erosion/silt runoff from construction operations?

x

delivery of unsafe water due to poor O&M treatment processes (especially mud accumulations in filters) and inadequate chlorination due to lack of adequate monitoring of chlorine residuals in distribution systems?

x

delivery of water to distribution systemb which is corrosive due to inadequate attention to feeding of corrective chemicals?

x

accidental leakage of chlorine gas? x excessive abstraction of water affecting

downstream water users? x

competing uses of water? x increased sewage flow due to increased

water supply? x

increased volume of sullage (wastewater from cooking and washing) and sludge from wastewater treatment plant?

x

large population influx during project construction and operation that causes increased burden on social infrastructure and services (such as water supply and sanitation systems)?

x

social conflicts if workers from other regions or countries are hired?

x

risks to community health and safety due to the transportb storageb and use and/or

x

Page 35: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

35

S creening Questions Y es No R emarks disposal of materials such as explosivesb fuel and other chemicals during operation and construction?

community safety risks due to both accidental and natural hazardsb especially where the structural elements or components of the project are accessible to members of the affected community or where their failure could result in injury to the community throughout project constructionb operation and decommissioning?

x

A . Checklist for Preliminary C limate R isk S creening

Country/Project Title: S toung S ubproject (E xpansion) and Construction of New Office Building S ector: Urban Water Supply Project S ubsector: Urban Water S upply Project Division/Department: General Department of Potable Water S upply

S creening Questions S core R emarks1 Location and Design of project

Is siting and/or routing of the project (or its components) likely to be affected by climate conditions including extreme weather related events such as floodsb droughtsb stormsb landslides?

0

Would the project design (e.g. the clearance for bridges) need to consider any hydrocmeteorological parameters (e.g.b seaclevelb peak river flowb reliable water levelb peak wind speed etc.)?

0

Materials and Maintenance

Would weatherb current and likely future climate conditions (e.g. prevailing humidity levelb temperature contrast between hot summer days and cold winter daysb exposure to wind and humidity hydrocmeteorological parameters likely affect the selection of project inputs over the life of project outputs(e.g. construction material)?

0

Would weatherb current and likely future climate conditionsb and related extreme

0

1 If possibleb provide details on the sensitivity of project components to climate conditionsb such as how climate parameters are considered in design standards for infrastructure componentsb how changes in key climate parameters and sea level might affect the siting/routing of projectb the selection of construction material and/or schedulingb performances and/or the maintenance cost/scheduling of project outputs.

Page 36: Cambodia: Urban Water Supply Project – Stoung Subproject … · 2020. 7. 16. · SPS : Safeguard Policy Statement (2009) ... 22 South Kampong Chen Leab Tong Tnol 81 731 . 8 23 Sor

36

S creening Questions S core R emarks1 events likely affect the maintenance (scheduling and cost) of project output(s)?

Performance of project outputs

Would weather/climate conditionsb and related extreme events likely affect the performance (e.g. annual power production) of project output(s) (e.g. hydrocpower generation facilities) throughout their design life time?

0

Options for answers and corresponding score are provided below:

R esponse scope Not likely 0 Likely 1 Very likely 2 R esponses when added that provide a score of 0 will be considered low risk project. If adding all responses will result to a score of 1c4 and that no score of 2 was given to any single responseb the project will be assigned a medium risk category. A total score of 5 or more (which include providing a score of 1 in all responses) or a 2 in any single responseb will be categorized as high risk project. R esult of Initial S creening (Lowb Mediumb High): _ _ _ _ _ Low_ _ _ _ _ _ Other Comments: The existing water supply project is already operating. MIHcPMU and PIU are requesting for additional distribution pipe laying works in of S toung Municipalityb (i.e. 27 villages in five communes/S angkat.)