Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of Technology, Poland

Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

Embed Size (px)

Citation preview

Page 1: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

Calculating Risk of Cost Using Monte Carlo Simulation

with Fuzzy Parameters in Civil Engineering

Michał BętkowskiAndrzej Pownuk

Silesian University of Technology, Poland

Page 2: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

2/56

Risk of cost overruns

We can define risk as possibility of occurrence of loss.

There is always the difference between the planned costs and real costs.

Page 3: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

3/56

Direct costs (DC)

Indirect costs (IC)

Direct costs are expenses that are directly linked to the project

For example: materials, labour, equipment etc.

Other costs.

For example: management costs, cost of insurance etc.

Calculating of cost

Page 4: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

4/56

Estimating of direct cost (DC)

The project can be decomposed into elementsiDC

i

iDCDC

Page 5: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

5/56

Direct cost (DC)

DC = Cost 1 + Cost 2+ Cost 3

Cost 1 Cost 2 Cost 3

Materials Labour Equipment

Page 6: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

6/56

Methods of calculating of directional cost

Deterministic

Probabilistic

Page 7: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

7/56

Deterministic methods of calculating costs

- appearance of task is deterministic

- cost of each task is deterministic

Page 8: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

8/56

Calculating Risk in deterministic methods

Risk in deterministic methods is taken into account as additional constant component of cost.

(It is possible to express the risk in percent)

Page 9: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

9/56

Typical problems with deterministic methods of

calculating of costs

Unknown characteristics of costs (labour, whether),

- Alternative tasks, - Additional tasks.

Page 10: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

10/56

Probabilistic methods

Alternative tasks

Additional task

Changeable costs of tasks

Page 11: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

11/56

Alternative tasks

hamburger

Cola Beer

Begin

End

Page 12: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

12/56

Additional task

hamburger

Cola Beer

chips

End

Begin

Page 13: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

13/56

Changeable costs of tasks

Old car is cheaper than the new one

Page 14: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

14/56

Probabilistic definition of risk

0,0, 1 TTTT ccPccPR

- real cost (random variable)

- fixed cost

Tc

0,Tc

Page 15: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

15/56

Probabilistic definition of risk

Probability density function Tc cf

T

Cumulative distribution function

0,0, TTTc ccPcT

0,0, 1 TT ccR Risk of cost

Page 16: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

16/56

Beta Pert distribution

6

4 pmo ccccE

11

, 1

xxxf

4

Page 17: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

17/56

Beta Pert distribution

Page 18: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

18/56

Beta Pert distribution

op

om

cc

cc

4 4

po

p

po cc

cxf

ccxf ,,

1)(

Page 19: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

19/56

Alternative tasks

Cost 1

Cost 2 Cost 3

1p 2p

121 ppTotal cost = Cost 1 + Cost 2

orTotal cost = Cost 1 + Cost 3

Page 20: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

20/56

Existing software

- Pert Master, - Risk, - MS Project

Etc.

Page 21: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

21/56

Advantages of probabilistic methods

- Express realistic character of the realization of the process.

- Using probabilistic methods it is possible describe random parameters (unpredictable weather, material cost, inaccurate materials estimates)

Page 22: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

22/56

Limitation of pure probabilistic

methods

- unique character of many civil engineering project

- different conditions of the realization (weather, geological conditions, geographical region etc.)

Because of that we do not know reliable statistical data

Page 23: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

23/56

Main problem

It is very difficult to obtain exact values of probabilistic characteristics of the structure

For example: m, σ etc.

Page 24: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

24/56

Basic assumption According to many experiments parameters of the system can be

characterized by typical probability distribution of cost (if we know the data):

- Normal distribution- Beta-Pert distribution- Lognormal distribution etc.

Page 25: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

25/56

However we do not know the parameters

x

xf1

xf 2 xfi

Probability density function of costs

Page 26: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

26/56

What we know? We know deterministic values of costs

from the catalogue

We have expert knowledge about particular cost (i.e. what happened usually)

Sometimes we have some experimental data

Page 27: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

27/56

Information from experts Lower bound Upper bound Most probable

cost

oc

ocpc

mc

Page 28: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

28/56

If we have many experts then we can get more information

Lower bound

Upper bound

Most probable cost

pp cc ,

mm cc ,

oo cc ,

Page 29: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

29/56

Fuzzy numbers (clouds)

We can also ask experts about confidence intervals

for different probability levels(alpha-cuts, degree of membership)

Page 30: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

30/56

Confidence intervals

},,ˆ:{1 ,, ooo cccP hhh

,oc

,oc

1

oc

Page 31: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

31/56

Calculation of fuzzy numbersusing the data

dPXmidxc ˆ

PXmidxc ˆ

xxXP ,ˆ:1

xx

Page 32: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

32/56

Advantages of fuzzy sets description (clouds)

In order to define the worst case (intervals) we do not need many information

Confidence intervals can be defined for set valued data (random sets)

Page 33: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

33/56

Dependency problem

It is not a good idea to convert interval probability density function to interval cumulative distribution function(overestimation problem)

Page 34: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

34/56

Dependency problem

ba,x ,1

ba,x ,0

1

ab

xf X

ba,x ,1

ba,x ,0

2

ab

xf X

bbaxabab

xba

baaxab

ax

bax

xf XX

2,,1

,2,2

2,2,0

2

221

P-box method consider all possible probability distribution i.e. some of them do not corresponds to any parameters a, b

Page 35: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

35/56

Dependency problem

X

Envelop does not correspond to any combination of parameters

Page 36: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

36/56

Probability density function with fuzzy parameters

111),,(

xxxf

omp ccc ,, omp ccc ,,

ompompomp ccccccxfcccxf ,,,,,,),,,(

Page 37: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

37/56

Application of extension principle

0,Tc RRR ,ˆ

,0 ,0ˆ ˆ 1 , :

TT c TR c c h h h

RRRRsupR ˆ,:

Page 38: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

38/56

- Risk for particular cost

h,0,Tc - Cumulative distribution function

npnm

nopmo cccccc ,,,...,,, 111h

,0 ,0ˆ ˆ 1 , :

TT c TR c c h h h

- vector of uncertain parameters

RRR ,ˆ

Page 39: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

39/56

Modified extension principle(clouds)

RcRRP o hhh ,,ˆ:1

RRRsupR ,:

RRR ,ˆ

Page 40: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

40/56

Discretization of α-cuts

iiiihhh ˆ...ˆˆˆ h

miiimi jmjjjjj hhh ,,,2,,1,,...,,, ,...,,

2121 h

imi jjj hh ˆ,...,,, 21

Page 41: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

41/56

Monte Carlo simulations

1 2

,0

,0 , , ,..., 1 1 , : ,..., 1,...,

i

T i m

T

c T j j j m

R c

min c j j k

h

kjjcmax

cR

mjjjTc

T

miT

i

,...,1 ,...,:,1 1,...,,,0,

0,

21

h

Page 42: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

42/56

Advantages of Monte Carlo method

- it is possible to get full description of probability density function of the results

- the method is able to take into account any type of uncertainty and dependency

Page 43: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

43/56

Graph description of the system

Page 44: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

44/56

Numerical results

Page 45: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

45/56

Numerical results

Page 46: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

46/56

Numerical results

Page 47: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

47/56

Numerical results

Page 48: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

48/56

Computer implementation of the algorithm

Algorithm was implemented in C++ language.

GSL library was also applied.

Page 49: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

49/56

Numerical data for node 0

Page 50: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

50/56

Description of the node

NodeNumberOfNode 0, NumberOfChildren 2, Children 1 3, Probability 0.415,IntervalProbability 0.088, xMinMin 198.766, xMinMax 206.016, xMidMin 215.688, xMidMax 219.313, xMaxMin 231.391, xMaxMax 238.641, ProbabilityGrids 3NumberOfGrid 3End

Page 51: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

51/56

Types of nodes - Normal distribution

(with uncertain parameters) - Beta Pert distribution

(with uncertain parameters) - constant value

- intervals (not implemented) - fuzzy numbers (not implemented)

Page 52: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

52/56

Sum of fuzzy number and probability density function Using presented algorithm it is possible

to calculate sum of probability density function and fuzzy number (clouds).

In calculation one can apply:- min-max extension principle (classical solution - controversial)- new extension principle(recommended, has clear interpretation based on clouds)

Page 53: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

53/56

Results:

Classic extension principle:- fuzzy probability

New extension principle:- fuzzy probability- fuzzy number (confidence intervals, clouds)

Page 54: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

54/56

One more remark about dependency problem

Due to nonlinearity alpha cat method is not always good method of transformation of confidence intervals.

Because of that we have to check some additional conditions before using this method.

Page 55: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

55/56

Additional information necessary for computation

ResultsXmin 820, Xmax 1120, NumberOfSimulations 10000, NumberOfClasses 20,NumberOfGrids 3, DistributionType 2End

TcTc

Tc

Tc cfT

Page 56: Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of

56/56

Conclusions

Presented method allows estimating the direct cost risk of civil engineering projects in the case when there are no credible data.

In presented algorithm the costs can be deterministic, probabilistic, fuzzy number.

It is also possible to take into account the cost which is modeledby probability density function with fuzzy parameters.

The method shows the relation between the assumed maximaldirect costs, the risk of overrun and the uncertainty of the statisticaldata.