Upload
adeoye-okunoye
View
212
Download
0
Embed Size (px)
Citation preview
8/20/2019 Cad Welding12
http://slidepdf.com/reader/full/cad-welding12 1/7
CON 03-03-06 PROCEDURE
01 September 2014 CONSTRUCTION
Welding
Procedures
Thermite Welding (Cadwelding)
Replaces: CON 03-03-06 from 29 July 2008
Overview
This standard provides the procedures for using thermite welding to
attach wire to pipe.
Audience
This standard is intended for installation and operations personnel,
corrosion technicians and designers.
References
• DES 08-05 Protective Coatings for Buried Steel Piping Systems
• CON 13-02 Wrapping Wire-to-Pipe Connections
• Review of Thermite Welding on Pipelines, Dr. G.T. Beynon, March
15, 2002
• Drawing 99000-E-030-101 Typical Thermite Weld Connection
Equipment
• 5 mm ! 57 mm copper sleeves
• bonding wire or test leads
• thermite weld mold (sized for the pipe being welded to)
• #15 (15 gram) cartridges and steel disc
• flint gun
• crimping pliers
• scraper
• lino knife
• wire brush
• file
• pipe recoating material
8/20/2019 Cad Welding12
http://slidepdf.com/reader/full/cad-welding12 2/7
Safety Concerns
• Thermite weld process produces very high temperatures and moltenmetal. Wear gloves, safety goggles, and a long sleeve shirt or
coveralls when igniting the charge.
• Do not inhale the fumes from thermite welding.
• Do not thermite weld in combustible atmospheres and ensure theground below the thermite weld is free of all hydrocarbons.
• It is important that thermite welding not be performed on a wetsurface as this can cause the water to vaporize and flash molten
metal back out of the crucible.
• Only employees having taken the available training course may
thermite weld.
Other Joining Methods
There are other methods of joining wire to pipe however thermite
welding is the only company approved “welding” process for fieldconnection of test lead wires, bond wires, galvanic anode leads, rectifier
negative cables, and plastic distribution system tracer wires to live steel
piping systems.
Mechanical connections are also acceptable, but only for non-current
carrying lead wires.
Torch brazing, arc welding, or pin-brazing of field connections is not
permitted.
Procedure
1. Prepare the pipe.
• The weld area must be at least 150 mm from other thermite
welds and circumferential or longitudinal pipe welds.
• Remove wrapping or other coating from the pipe in accordance
with DES 08-05 Protective Coatings for Buried Steel Piping
Systems.
• Clean the pipe’s surface thoroughly with a wire brush and a file
attaining a bright, clean, dry surface free of mill scale and grease.
• Refer to Drawing 99000-E-030-101 Typical Thermite WeldConnection.
2. Inspect the pipe.
• Visually inspect the weld area to confirm the absence of surface
defects.
8/20/2019 Cad Welding12
http://slidepdf.com/reader/full/cad-welding12 3/7
• Ultrasonically inspect IP pipelines with an outer diameter greater
than 60.3 mm and all TP pipelines (of any diameter) to confirmadequate wall thickness (See Table 1) and the absence of
laminations.
• Select and prepare a new weld location if there are surface
defects, inadequate wall thickness or laminations.
3. Determine the maximum line pressure for safe thermite welding.
• Ensure that during thermite welding process the maximum linepressure will not exceed the value given in Table 1 for the wall
thickness of the line.Table 1: Maximum Safe Line Pressures During Thermite Welding
Nominal Pipe Wall Thickness Maximum Allowable Gas Pressure
less than 2.8 mm (0.109") thermite welding not permitted
2.8 mm (0.109") 700 kPa (100 psi)
3.2 mm (0.125") 2890 kPa (419 psi)
3.6 mm (0.141") 3450 kPa (500 psi
4.0 mm (0.156") or thicker design pressure
NOTE: The maximum safe line pressures during thermite welding arelower than the pressure rating of the gas lines and the manufacturer
ratings for thermite product because of FortisBC (Natural Gas) (FBC
(Gas)) concerns regarding the quality of older piping in the ground.
• If unable to reduce the pressure to less than the maximum
allowable pressure in Table 1, test leads can be attached to thepipe with a stainless steel clamp. However an alternative means
of attaching current carrying leads such as rectifier negative leads
will have to be determined because below ground mechanical
connections will not be permitted.
4. Prepare and position the wire on the pipe.
• Remove 65 mm of insulation from the wire.
• Make sure the bare wire is bright, clean, and dry.
• For #10, 12, or 14 AWG wire:
• slide a copper sleeve over the bare wire and crimp it into
place.
• For #6 or #8 AWG wire:
• a copper sleeve is not required
8/20/2019 Cad Welding12
http://slidepdf.com/reader/full/cad-welding12 4/7
• place the stripped end over the prepared pipe surface
• Loop the wire around the pipe “tieing” it off with sufficient slackto ensure that the finished weld will not be strained and place the
copper sleeve over the prepared pipe surface.
• Where a conductor larger than #6 AWG is required, a multi-
strand conductor must be used and the strands arranged into
groups no larger than #6 AWG. Each group will be attached to
the pipe with a separate charge.
Figure 1: Thermite Weld Connection (top view)
8/20/2019 Cad Welding12
http://slidepdf.com/reader/full/cad-welding12 5/7
Figure 2: Picture showing the wire positioned on the pipe with crucibleon top. Note the absence of voids between the crucible and the pipe.
5. Position the thermite weld mold.
• Choose the correct crucible for the job.
• Crucibles come in different configurations depending on the
size of the wire and the size of the pipe being welded.
• Ensure that the crucible is thoroughly clean and dry.
• Wet or damp crucibles produce porous welds.
• Position the thermite weld mold over the copper sleeve or bared
wire on top of the prepared surface.
8/20/2019 Cad Welding12
http://slidepdf.com/reader/full/cad-welding12 6/7
• Make sure the copper sleeve or wire extends fully into the
thermite weld mold cavity.
• There should be no wire insulation in contact with the
thermite weld mold.
• Make sure the thermite weld mold sits flat, flush with the pipe so
that there are no voids between the crucible and the pipe caused
by the curvature of the pipe.
• Insert the metal disc in the bottom of the crucible with the
concave side up.
Figure 3
6. Prepare the charge.
• Dump the entire contents of a #15 cartridge into the crucible.
DANGER: Use only #15 (15 gram) cartridges and only one cartridge
per connection.
• Do not upset the metal disc.
• Make sure the ignition powder, stored in the lower part of the
cartridge, is placed in its entirety on top of the copper oxide andaluminum powder mixture, allowing a little ignition powder to sit
on the outside edge of the crucible. Do not mix the ignition
powder with the copper oxide and aluminum powder mixture
otherwise it may be difficult to ignite the charge with a spark
gun.
• Close the cover of the crucible.
7. Ignite the charge.
DANGER: The thermite weld process produces very high temperaturesand molten metal. Wear gloves, safety goggles, and long sleeves for this
operation.
• Using the handle, hold the thermite weld mold firmly in positionon the pipe.
8/20/2019 Cad Welding12
http://slidepdf.com/reader/full/cad-welding12 7/7
• Make sure all persons are away from or protected from the flash.
Be prepared for the flash that will result so as to avoid suddenmovements (i.e., flinching). Prior to ignition turn your face away
to avoid any flash danger.
• Ignite the charge with the spark igniter.
• Do not use matches.
• If the charge fails to ignite, dump the entire thermite weld chargeand try again. Under no circumstances add another charge to
the first one!
• Hold the thermite weld mold in position for 30 seconds before
lifting it from the pipe. Clean the mold.
• Tap the slag away from the weld and file down any irregularities.
8. Ensure that the weld has achieved a good bond between the wire and
the pipe.• Examine the copper wire for any “burn throughs”.
• Test the strength of the bond by gently tugging on the wire lead
noting any give or failure in the wire.
• Tap the thermite weld “button” gently with a slag hammer.
Again noting any give or failure of the weld to the surface of the
pipe.
• If there are “burn throughs” in the wire, or if there is evidence ofgive or connection failure when the wire is gently tugged, or if
there is evidence of the weld giving or failing when the weld
button is tapped with the slag hammer, abandon the weld site andgo back to Step 1 of this procedure, selecting another site at least
150 mm removed from the abandoned site.
9. Properly coat the thermite weld connection.
• Refer to CON 13-02 Wrapping Wire-to-Pipe Connections.
10. Properly recoat the pipe.
• Refer to DES 08-05 Protective Coatings for Buried Steel Piping
Systems.