12
CABLED CRUISE DEPLOYMENT AND RECOVERY INSTRUCTIONS Benthic Experiment Package, Camera, and Bioacoustics Document Number Version Author 8315-61103 0-10 R. Sanders, L. Fayler Reference Designators Update Date Approver of Instructions CE02SHBP & CE04OSBP 2014-11-21 J. Fram 1. Materials List for BEP Spare parts kit o BEP instrument spare parts bin o Eye bolts for BEP lid o Metal blanking pressure caps for LPJ Instrument Test Cables (one complete set) Instrument dummy plugs (one complete set) Instrument software Laptops External hard drives Video camera DC variable power supply Multimeter Toolbox o Tie wraps (Assorted 5”, 8”, and 11”) o Desetin o Vacuum grease o Standard wrench set (large) o Metric wrench set (small, need 11mm) o 2 - Stubby metric allen wrench sets (small; for camera) o Wire cutters o Large plier/wire cutter o Super 33+ tape o Screw drivers Supplies bin o Bungee cord o Markers, pens, pencils o Lab tape o CTD syringe (predeployment instrument wetting) o Power strips o Spare connector o-rings Container for pH water bag Container for clean water

CABLED CRUISE DEPLOYMENT AND RECOVERY … · o Metal blanking pressure caps for LPJ ... and add break away twine to cable when mounted ... 8/6/2015 8:47:29 AM

  • Upload
    ngokiet

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

Page 1: CABLED CRUISE DEPLOYMENT AND RECOVERY … · o Metal blanking pressure caps for LPJ ... and add break away twine to cable when mounted ... 8/6/2015 8:47:29 AM

CABLED CRUISE DEPLOYMENT AND RECOVERY INSTRUCTIONS

Benthic Experiment Package, Camera, and Bioacoustics

Document Number Version Author 8315-61103 0-10 R. Sanders, L. Fayler Reference Designators Update Date Approver of Instructions CE02SHBP & CE04OSBP 2014-11-21 J. Fram 1. Materials List for BEP □ Spare parts kit

o BEP instrument spare parts bin o Eye bolts for BEP lid o Metal blanking pressure caps for LPJ

□ Instrument Test Cables (one complete set) □ Instrument dummy plugs (one complete set) □ Instrument software □ Laptops □ External hard drives □ Video camera □ DC variable power supply □ Multimeter □ Toolbox

o Tie wraps (Assorted 5”, 8”, and 11”) o Desetin o Vacuum grease o Standard wrench set (large) o Metric wrench set (small, need 11mm) o 2 - Stubby metric allen wrench sets (small; for camera) o Wire cutters o Large plier/wire cutter o Super 33+ tape o Screw drivers

□ Supplies bin o Bungee cord o Markers, pens, pencils o Lab tape o CTD syringe (predeployment instrument wetting) o Power strips o Spare connector o-rings

□ Container for pH water bag □ Container for clean water

Page 2: CABLED CRUISE DEPLOYMENT AND RECOVERY … · o Metal blanking pressure caps for LPJ ... and add break away twine to cable when mounted ... 8/6/2015 8:47:29 AM

2. Newport BEP prep □ Confirm BEP Readiness and Integration Checklist has been completed □ Verify that lid eyebolts are removed (place in cruise bin with dummy plugs) □ Remove Optode (DOSTA) Cap before opening and locking doors in place □ Remove dust cover bags from copper tubing inlets for OPTAA (ACS) and CTD □ Lock BEP doors in open position □ Check that ROPOS team approves locking bumpers and hydrophone frame

position if first deployment or there have been changes in this setup □ Mount cable horns on first deployment □ Mount oil-filled ROV mateable 50m cable on to cable horns; attach strain

relief yale grip; and add break away twine to cable when mounted (first deployment only)

□ Attach bungee rings to hold cable on horns. (First deployment only; Have ROPOS check bungee set up)

3. Loading BEP onto Ship □ Lift BEP from center point, leave air rides attached (Dry wt. = 3,200 lbs.; Wet

wt. = 2,100 lbs with oil filled cable and hydrophone) □ Find out preferred location and orientation on deck for ROPOS

4. Pre-Deployment (At Sea) – use DEPLOYMENT CHECKLIST, On Deck section □ Apply Desitin to ADCP and VEL3D transducers □ Remove CTDBP pump inlet covering (cellophane over copper tubing) and

verify that inlets are exposed for both CTDBP and OPTAA (ACS) □ Cut cable ties on hydrophone cap (x2) □ Remove PHSEN water bag and store □ Draw diagram with relative position of ADCP North and Vector X axis to BEP

“Forward” 5. Connect BEP to ROPOS – use DEPLOYMENT CHECKLIST, ROPOS section □ Pick up BEP and move to ROPOS area (Dry wt. = 3,200 lbs.; Wet wt. = 2,100

lbs with oil filled cable and hydrophone) □ Connect to ROPOS (see Fig. 1) □ Photos/video of ROPOS docked to BEP and deployment into water

6. Deployment (separation from ROPOS) use DEPLOYMENT CHECKLIST, Seafloor section □ Place BEP at deployment site

o Orient cable side towards LV Node o Capture orientation information for BEP (esp. heading), use

orientation diagram o Detach from ROPOS

□ Connection to LV Node

Page 3: CABLED CRUISE DEPLOYMENT AND RECOVERY … · o Metal blanking pressure caps for LPJ ... and add break away twine to cable when mounted ... 8/6/2015 8:47:29 AM

o Remove restraints on 50m cable using rope handles o While holding free WetMate, ROPOS backs away at 10° angle from

bottom o Attach WetMate cable to LV node o Return to BEP

□ Deployment of Hydrophone Frame o Approach BEP at FWD STB corner o Pull bungee pin restraint on HYDRO cable (help fall away if needed) o Pull bungee pin restraint for HYDRO frame to BEP o Right manipulator hand (RH) holds HYDRO handle "A" while left

manipulator hand (LH) grasps BEP Capture Bar Handle (see Fig. 2) o Capture Bar Handle is moved up, thus allowing HYDRO to rotate (see

Fig. 3, top) o LH grasps HYDRO handle "B" o Lift HYDRO up and away from BEP (see Fig. 3, bottom) o Back away from BEP slowly and stop before cable is taut (see Fig. 4) o Place HYDRO on bottom o Remove (turn and lift) protective cap and place in ROPOS basket (see

Fig. 5) o Return to BEP

□ Remove and stow cable horns (see Fig. 6) □ Unlock and close doors (see Fig. 7) □ Collect position and oceanographic information from ROPOS

7. Startup from Shore Station (Linda in Seattle) □ Follow startup sequence spreadsheet

8. Recovery □ Ensure that hydrophone protective cap and cable horns are secure in ROV

basket prior to ending dive 9. Unloading and return to Corvallis □ Recover air ride supports □ Bring back hydrophone protective cap and cable horns □ Remember all dummy plugs and protective covers

Page 4: CABLED CRUISE DEPLOYMENT AND RECOVERY … · o Metal blanking pressure caps for LPJ ... and add break away twine to cable when mounted ... 8/6/2015 8:47:29 AM
Page 5: CABLED CRUISE DEPLOYMENT AND RECOVERY … · o Metal blanking pressure caps for LPJ ... and add break away twine to cable when mounted ... 8/6/2015 8:47:29 AM

Figure 1. ROPOS attached to BEP. Note position of 50m extension cable on horns on Port side, and hydrophone stand attached to Forward end.

Figure 2. Close-up of hydrophone stand attached to Forward end of BEP. The upper taped grab area is labeled A and the lower grab handle is labeled B

Figure 3. Illustration of ROPOS removing the hydrophone stand from the BEP. Grab area A is grasped with the starboard manipulator while the hydrophone frame handle is lifted with the port side manipulator. The stand is then lifted free of the BEP using both manipulators.

Page 6: CABLED CRUISE DEPLOYMENT AND RECOVERY … · o Metal blanking pressure caps for LPJ ... and add break away twine to cable when mounted ... 8/6/2015 8:47:29 AM

Figure 4. Once the hydrophone cable cord restraints have been cut, and the cable has been unspooled, the frame can be moved away from the BEP, about 10 meters.

Stop before the cable goes taut.

Figure 5. The hydrophone cap is removed by turning the cap clockwise and lifting upwards, once the frame is in place. The cap should be placed in the basket of the ROV and recovered after the dive.

Page 7: CABLED CRUISE DEPLOYMENT AND RECOVERY … · o Metal blanking pressure caps for LPJ ... and add break away twine to cable when mounted ... 8/6/2015 8:47:29 AM

Figure 6. How to remove the cable horns from the BEP. Grasp the T-handle (A) and turn clockwise (B). This should loosen the horn (C), and it can be lifted off of the BEP door (D). Once removed, the cable horns should be stowed in the ROV basket and recovered after the dive.

Page 8: CABLED CRUISE DEPLOYMENT AND RECOVERY … · o Metal blanking pressure caps for LPJ ... and add break away twine to cable when mounted ... 8/6/2015 8:47:29 AM

Figure 7. How to close the BEP doors. First, slide the latch mechanism inwards (towards the opening in the BEP), then lift the door towards the ROV. Once past the midway point, the weight of the door should cause it to close by itself.

Page 9: CABLED CRUISE DEPLOYMENT AND RECOVERY … · o Metal blanking pressure caps for LPJ ... and add break away twine to cable when mounted ... 8/6/2015 8:47:29 AM

Camera Deployment Plan 1. Materials List for Camera □ Camera extra hardware □ Power supply □ Rubber tubing for camera cable management □ Zip ties □ Test cable □ Cisco router □ Internet cables □ Laptop with GUI software □ Metric stubby allen wrenches (especially need #3, 5, and 6) □ Metric combo wrench set (especially need 11 mm) □ Large standard wrench set □ Pliers and wire cutters □ Focus plate □ O-ring grease

2. Loading onto Ship □ Transport Camera disassembled to Ship □ Lift Camera lander using strap under central beam

3. Camera Assembly □ Set tripod lander frame to desired height (<53”, height of tool basket) □ Follow Kongsberg Manual to mount camera and yoke onto frame □ Use rubber tubing and zip ties to manage cables so they do not get hung up

on tripod handles and tabs □ Verify full range of motion of camera using software to travel between soft

stops 4. Pre-deployment camera operation and testing on board □ Connect green test cable to camera, power supply and Cisco router □ Power up instrument (takes up to 2 min. to wake up) □ Start up GUI Software

o Go to Set up tab and select fixed address, enter: o Select “Set” button to save (however software will forget next time it

is opened) o Go to File and select Set up to check IP address o Go to File and select Connect

Page 10: CABLED CRUISE DEPLOYMENT AND RECOVERY … · o Metal blanking pressure caps for LPJ ... and add break away twine to cable when mounted ... 8/6/2015 8:47:29 AM

o Ignore prompt that states there is already a connection and press “OK”

o Press “Play”, should see the camera display now o Confirm camera operation by rotating camera between soft stops,

which should be set at approximately 45° and 315°, see manual to reset stops

o Verify tilt of camera up and down (may need to slide tilt power all the way up if it gets stuck at bottom or top); tilt should not be angled more than 60° to avoid capturing feet in image

o Focus camera by manipulating the Zoom, Focus and Iris settings on the Lens tab. An example of a focused setting in lab was:

Zoom = 67 Focus = 21 Iris = 7 Lamp = 39

These settings will change with light and distance. o If Camera image settings become stuck try going to the Pan and Tilt

tab and entering Go To “0” in the preset window, select Go o After camera operation has been verified set the static gateway

address depending on location:

OR Offshore CAMDSB106

• IP: 010.033.009.006 • Subnet mask: 255.255.255.000 • Gateway: 010.033.009.001 • Port: 8888

OR Shelf CAMDSB107

• IP: 010.033.013.008 • Subnet mask: 255.255.255.000 • Gateway: 010.033.013.001 • Port: 8888

*Note this is very important for Shore (Linda) to communicate to the camera

5. Deployment of Camera via ROPOS □ Secure camera tripod in tool basket of ROPOS □ Coil WetMate cable in tool basket according to ROPOS instructions □ Connect tool basket to ROPOS □ Detach tool basket from ROPOS on seafloor □ Pick up camera and place <10m from LV Node; make sure node is not in

camera’s blind spot □ Record position and orientation □ Plug WetMate into LV Node

6. Startup from Shore Station (Linda in Seattle using Kongsberg GUI) □ Follow startup sequence spreadsheet

Page 11: CABLED CRUISE DEPLOYMENT AND RECOVERY … · o Metal blanking pressure caps for LPJ ... and add break away twine to cable when mounted ... 8/6/2015 8:47:29 AM
Page 12: CABLED CRUISE DEPLOYMENT AND RECOVERY … · o Metal blanking pressure caps for LPJ ... and add break away twine to cable when mounted ... 8/6/2015 8:47:29 AM

Bioacoustics Deployment Plan 1. Materials list for bioacoustics

o Monofilament fishing line (.0236”, MC # 9442T3) for bioacoustics calibration

o Tungsten balls for bioacoustics calibration 2. Loading onto Ship □ Transport assembled bioacoustics frame to Ship □ Lift frame using strap under central beam

3. Sonar Assembly □ □ □ Use rubber tubing and zip ties to manage cables □ Check tungsten sphere/float assembly, release pin, and dissolvable links

4. Pre-deployment sonar operation and testing on board □ Connect green test cable to sonar, power supply and router □ Power up instrument

5. Deployment of Sonar via ROPOS □ Pick up sonar frame and move to ROPOS area (Dry wt. = approx. 120 lbs.;

Wet wt. = xxxx lbs with oil filled cable and tungsten sphere assembly) □ Connect to ROPOS (see Fig. X) □ Check fit of frame and transducer heads □ Coil extension cable and secure with bungees □ Photos/video of ROPOS docked to sonar frame and deployment into water

6. Deployment (separation from ROPOS) □ Place sonar frame at deployment site

o Orient cable side towards MP Jbox o Place <10m from MP Jbox o Detach from ROPOS

□ Plug WetMate cable into MP Jbox □ Pull pin to release tungsten sphere float package □ Back ROPOS away slowly to avoid monofilament line

7. Startup from Shore Station (Linda in Seattle using Kongsberg script) □ Follow startup sequence spreadsheet