22
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION Cabin Environment Physics Risk Model Chris Mattenberger, Science & Technology Corporation Donovan Mathias & Susie Go, NASA ARC Engineering Risk Assessment Team NASA Ames Research Center, Moffett Field, California Applied Modeling & Simulation (AMS) Seminar Series NASA Ames Research Center, October 7 th , 2014

Cabin Environment Physics Risk Model

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Cabin Environment Physics Risk Model

NATIONAL AERONAUTICS AND SPACE ADMINISTRATION

Cabin Environment Physics Risk Model!!Chris Mattenberger, Science & Technology Corporation!Donovan Mathias & Susie Go, NASA ARC!Engineering Risk Assessment Team!NASA Ames Research Center, Moffett Field, California!!

!Applied Modeling & Simulation (AMS) Seminar Series!

NASA Ames Research Center, October 7th, 2014!!

! ! ! ! ! !!

Page 2: Cabin Environment Physics Risk Model

Overview!

•  Engineering Risk Assessment Team Introduction

•  Probabilistic Risk Assessment Methodology

•  Cabin Environment Physics Risk (CEPR) Model

•  Application of CEPR Model to Generic ISS Mission Architecture

•  “Blow and Bleed” Sensitivity Study

•  “Feed the Leak” Sensitivity Study

•  Risk-Informed Design Examples

•  Summary and Conclusions

2

Page 3: Cabin Environment Physics Risk Model

–  7th and 8th Workshops on Probabilistic Risk Assessment

Methods (PRAM)!–  PRA Handbook!

–  Simulation-based modeling techniques and their application to PRA !

ERA Programs & Projects!

SLS Ares LSS

Mars

OSMA

–  Blast overpressure, debris, fireball physics modeling!

–  Ascent abort effectiveness assessment!

–  Campaign analysis, long-term operations and repair!

–  LOM/LOC and availability estimates!

–  Campaign analysis!

ERA also supports analysis of satellites, sample return missions and asteroid defense!3

Page 4: Cabin Environment Physics Risk Model

ERA Team Philosophy!

4

•  Risk-informed decision support − Requirement verification − Risk-informed design support − Part selection/procurement

•  Probabilistic risk assessment is informative, not predictive − Provides quantitative answers to

specific questions − Always driven by specific application − Based on traditional methods and

extended as appropriate

Pessimistic bounds!

Architecture! Model inputs!

Physical model!

Assess risk drivers!

Risk acceptable?!

Solution reached!

Assumption driven?!

Architecture driven?!

Refine inputs

Design trades

Iterative/responsive modeling approach

Risk model maturity tracks design maturity and engages engineers early in the design process, rather than a post facto analysis!

Page 5: Cabin Environment Physics Risk Model

ERA Team Methodology!

•  Dynamic nature of failures − Time dependence − State dependence − Partial & interactive failures

•  Physics-based analysis − External hazards −  Failure evolution

•  Traditional static models −  Lower part levels − Typically reliability based

Combines traditional PRA methods with dynamic methods for increased accuracy of representation of system risk!

tetR λ−=)(

5

Page 6: Cabin Environment Physics Risk Model

Cabin Environment Influence Diagram!

6

Cabin environment is impacted by many traditional spacecraft subsystems!

Page 7: Cabin Environment Physics Risk Model

Cabin Environment Physics Risk (CEPR) Model!

7

•  Estimates time interval from loss of functionality to hazardous environment Estimates time from loss of functionality to onset of hazardous environment!

Page 8: Cabin Environment Physics Risk Model

CEPR Model Implementation in GoldSim!

8

GoldSim provides a graphical representation of data flow within model!

Page 9: Cabin Environment Physics Risk Model

Loss-of-Crew Threshold Tracking!

9

CEPR tracks partial pressures of key cabin atmospheric constituents!

nRTPV =

Page 10: Cabin Environment Physics Risk Model

Avionics & PCS Implementation!

10

CEPR model captures dynamic interaction of spacecraft subsystems!

Page 11: Cabin Environment Physics Risk Model

PPRV Implementation!

11

CEPR model captures physics-based impacts of component functionality!

Page 12: Cabin Environment Physics Risk Model

ERA Generic Launch Vehicle & Spacecraft!

12

!!

!!!!

Liftoff Cape Canaveral t = 0 sec

1st Stage Separation Alt = 80 km t = 181 sec

LAS Jettison Alt = 117 km t = 211 sec

2nd Stage Separation and Orbit Insertion Alt = 350 km t = 560 sec

Earth Orbit TOF: 24 hrs

ISS Dock Duration: 6 months

Undock, Prep & Cold Soak TOF: 3 hrs

De-Orbit Burn 60 min to touchdown

Alt: 300 km

Entry Interface & SM Jettison 30 min to touchdown

Alt: 200 km

Parafoil Deployment 2 min to touchdown

Alt: 5 km

Land Ocean splashdown or

ground landing

Mission concept of operations used to demonstrate CEPR model implementation!Conceptual Launch Vehicle and Spacecraft Design for Risk Assessment, NASA/TM-2014-218366

Page 13: Cabin Environment Physics Risk Model

Assumptions!

• Cabin Properties − 16 m3 air volume − Leakage rate of 0.036 lbm/day − 297 K constant temperature − Perfectly controllable O2 mass

flow rate and O2 sensors − Perfect pressure vessel − Perfect Mixing − Ideal Gas

•  Initial Nominal Cabin State − 3.234 psi ppO2

− 0.058 psi ppCO2

− 11.408 psi ppN2

•  Crew –  4 Crew –  Consume 0.2434 kg/hr of O2

–  Produce 0.2554 kg/hr of CO2

•  Consumables –  44.7 kg of O2 at 100% Full –  167 kg of N2 at 100% Full –  297 K constant temperature

•  LiOH Canisters –  Removes 0.2554 kg/hr of CO2 at

100% effectiveness level •  LOC Thresholds & Return Time

–  Minimum ppO2 is 2.3 psi –  Maximum ppCO2 is 0.87 psi –  Return Time is 4 Hours

Green indicates Simplifying Assumption / Blue indicates Uncertain Assumption / Black indicates Uncertain Design Requirement

13

Page 14: Cabin Environment Physics Risk Model

Design Insights for Risk-Informed Decisions:“Blow and Bleed” Sensitivity Study!

14

CEPR model yields design insights to inform mission rules!

0.1

1

10

100

1000

100% 80% 60% 40% 20% 0%

Tim

e to

LO

C [h

r]

Percent Scrubbing Effectiveness

Time to LOC vs. %CO2 Scrubbing ppCO2 = 0.87 psi

0% Tank Remaining

20% Tank Remaining

40% Tank Remaining

60% Tank Remaining

80% Tank Remaining

100% Tank Remaining

Abort from Orbit - 4 hrs

)1()1(

12 −

+

⎟⎟⎠

⎞⎜⎜⎝

+=

γγ

γγρPCAm!

Page 15: Cabin Environment Physics Risk Model

Design Insights for Risk-Informed Decisions:“Feed the Leak” Sensitivity Study!

15

CEPR model yields design insights to aid in risk-informed decision making!

0.1

1

10

100

1000

0 5 10 15 20 25

Tim

e to

LO

C [h

r]

Leakage Rate [kg/hr]

Time to LOC vs. Leakage Rate ppO2 = 2.3 psi

0% Tank Remaining

20% Tank Remaining

40% Tank Remaining

60% Tank Remaining

80% Tank Remaining

100% Tank Remaining

Abort from Orbit - 4 hrs

)1()1(

12 −

+

⎟⎟⎠

⎞⎜⎜⎝

+=

γγ

γγρPCAm!

Page 16: Cabin Environment Physics Risk Model

Dynamic Mission Risk Model!

Integrated dynamic risk model captures time- and state- dependent behavior!16

Page 17: Cabin Environment Physics Risk Model

Dynamic Risk Model Integration!

17

Monte Carlo simulation enables CEPR results to impact overall mission risk!

180 hr

4 hr

0 hr

Page 18: Cabin Environment Physics Risk Model

Risk-Informed Design Example: Risk Driver Ranking!

18

0.00E+00 1.00E-04 2.00E-04 3.00E-04 4.00E-04 5.00E-04 6.00E-04 7.00E-04

Avionics Communications & Tracking

ECLSS Electrical Power

Events & Hazards Launch Vehicle Equipment

Mechanisms Propulsion

Thermal Control

Risk of LOC

Spac

ecra

ft Su

bsys

tem

ERA Spacecraft LOC Risk Drivers

LOC

LOC - CEPR

0.00E+00 2.00E-03 4.00E-03 6.00E-03 8.00E-03 1.00E-02 1.20E-02

Avionics Communications & Tracking

ECLSS Electrical Power

Events & Hazards Launch Vehicle Equipment

Mechanisms Propulsion

Thermal Control

Risk of LOM

Spac

ecra

ft Su

bsys

tem

ERA Spacecraft LOM Risk Drivers

LOM

LOM - CEPR

Excessively conservative assumptions can impact relative risk results!

Page 19: Cabin Environment Physics Risk Model

Risk-Informed Design Example: Risk Reduction Trade Study!

19

EPS - Enhanced Mass [lbs] ECLSS - Enhanced Mass [lbs]Fuel Cell Stack 10.7 Manual Valve 0.3Heater 1 Manual Valve 0.3Heat Exchanger 0.65 Manual Valve 0.3Pressure Regulator 0.635 Manual Valve 0.3Pressure Sensor 0.22 Manual Valve 0.3Hydrogen Purge Valve 0.1 Manual Valve 0.3Water Separator 0.5Total Mass Delta 13.805 Total Mass Delta 1.8

Trade Study Options

EPS ECLSS

Page 20: Cabin Environment Physics Risk Model

Risk-Informed Design Example: Risk Reduction Trade Study!

20

•  Excessively conservative assumptions can alter trade study results dramatically Excessively conservative assumptions can alter trade study results dramatically!

0.00E+00

1.00E-05

2.00E-05

3.00E-05

4.00E-05

5.00E-05

6.00E-05

7.00E-05

8.00E-05

9.00E-05

1.00E-04

0 2 4 6 8 10 12 14 16

Ris

k of

LO

C

Delta-Mass [lbs]

LOC Risk Reduction Trade Study

ECLSS - Baseline

ECLSS - Enhanced

EPS - Baseline

EPS - Enhanced

ECLSS - Baseline - CEPR

ECLSS - Enhanced - CEPR

Risk Reduction Efficiency = ΔRisk / ΔMass

Page 21: Cabin Environment Physics Risk Model

Summary & Conclusions!

•  CEPR model is used to predict the time for an initial ECLSS failure to propagate into a hazardous environment and trigger a LOC event − Can be utilized as a stand-alone model to aid in decision-making − Allows for integration of model results into dynamic mission risk models − Enables the risk analyst to remove the assumption that loss of functionality triggers LOC

•  The assumption that loss of functionality triggers LOC has been shown to be excessively conservative − Impacts overall risk driver ranking − Impacts risk reduction trade study results − Could lead to a suboptimal design that inherently increases the risk of LOC

•  Incorporating CEPR results yields more accurate design insights

21

Page 22: Cabin Environment Physics Risk Model

Future Work!

22