CA96 and CA97 Clarification
Citation preview
This is the Routing for 10000051 plant 2110.Here maintained standard values as Set up 1440 min, Machine -1440 min etc.. (Labour time will not be considered for processing time calculation)
For work center (TEST) capacity utilization is only 900 min per day
For work center (WCTEST4) capacity utilization is only 900 min per day
As per the scheduling the set up time is 1440 min, according to the work center capacity it will takes 1.6 days (for work center 1 day = 15 hrs)to complete, Like processing time alsoFor 4 work centers the total set up time should be 4 X 1.6 = 6.4 days
For 4 work centers the total Processing time should be 4 X 1.6 = 6.4 days
It will calculate from RoutingIt will fetch from material master directly
Removed the existing values in the material master
Scheduling done in the Routing and click on update material master.
Then it will update in CA96 .click on update material master button
The log shows that updated in the material master
Then the material will not show in CA96
Display of material master (updated the values)