WHEELYBOAT PROJECT By the Chemring Apprentices

By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

Embed Size (px)

Citation preview

Page 1: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

WHEELYBOAT PROJECTBy the Chemring Apprentices

Page 2: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

Apprentices

Steven Dunlop (Mechanical Fitter) – 4th Year Apprentice

David Thomson (Mechanical Fitter) – 4th Year Apprentice

Jamie Henderson (Mechanical Fitter)– 3rd Year Apprentice

Ian McDonald (Mechanical Fitter) – 2nd Year Apprentice

Page 3: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

What is a Wheelyboat?

• The Wheelyboat has been specially designed with a bow door that is hinged and lowers to form a ramp enabling ‘roll-on, roll-off’ access, to accommodate disabled people and wheelchair users in particular, easily and safely.

• The wheelyboat gives mobility impaired members of the public of any age, safe dignified and ready access to motorised boating and fishing.

Page 4: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

First look at the Wheelyboat23rd Feb 2011

Page 5: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

Sourcing Materials

Deck welding

Chandlery, Cleats & Rope

Buoyancy foam

Plus donations from local businesses and friends

Page 6: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

Sourcing Materials

Unfortunately we struggled to source some of the materials that were requested by the Wheelyboat Foundation. These materials are listed below;

• Black Nylon(For Skids) - £100• Aluminium Paint - £50

Page 7: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

Buoyancy Replacement

Remove rivets from deck

Cut existing decking and remove from boat

Page 8: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

Buoyancy Replacement

Removing the buoyancy foam

Replacement of new buoyancy foam

Page 9: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

Remove Bow door

Door seal was beyond repair and needed replacement. The bow door had to be removed in order to do this.Rubber grip was also replaced.

Page 10: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

Removing Chandlery

The winch, cleats and rowlocks were all overdue replacement which can be seen to the left.

Existing door hinges and oars were beyond repair and also needed replacement.

Page 11: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

Deck Replacement

With the new buoyancy foam installed the deck had to be welded back into place and new rivets applied.

Any seams were filled with a marine spec silicone to prevent any water entering the buoyancy chambers.

Page 12: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

Repairs to bottom of boat

The bottom of the boat showed signs of leaking along the seams (circled red).

The boat was removed to the local engineering company as welding is not permitted on site. All the seams were welded and plated to give the floor a more watertight seal and to aid in rigidity.

Page 13: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

Installing new cleats& rowlocks

The local chandlery store supplied us with cleats, however these were too large for the boat and had to be cut to size.The rowlocks came with a set of sourced oars and were fitted to the boat along with the new oars.

Page 14: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

Apply new rubber grip

New rubber was sourced within our store, measured and cut to size.

Two part rubber adhesive was used to fix the rubber to the boat.

Page 15: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

Install new winch and rope

With a new winch proving difficult to source, we resulted to refurbishing the original winch as it was still in working order.

A new handle was made and new nuts & bolts were fitted.Marine grade rope was sourced from a local chandlery store and fitted to the boat.

Together, the winch and rope operate the bow door.

Page 16: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

Install repaired bow door

New rubber matting was glued down using a two part adhesive .

A replacement door seal was sourced and fixed to the door using the same adhesive.

Page 17: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

Install new drainage bungs

New drainage bungs were fixed in place to allow and water accumulation to be drained from each buoyancy chamber. This was

done using existing fittings we had available.

Page 18: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

Clean & tidy

The boat was badly needing cleaned. We rubbed down the surface using scotch-brite grinding pads and painted the boat using an aluminium paint.

Page 19: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

Finishing touches

To finish it off we managed to convince our on site joiners to make us a replacement seat made of Marine Plywood. The Wheely Boat Foundation provided the team with Vinyl stickers for the boat. All that was left was to give the oars an undercoat of paint and then gloss them. Paint was donated by on site painters.

Page 20: By the Chemring Apprentices. Steven Dunlop (Mechanical Fitter) – 4 th Year Apprentice David Thomson (Mechanical Fitter) – 4 th Year Apprentice Jamie Henderson

Acknowledgements

We would like to thank everyone who

donated materials to our project. Everything was very helpful towards us

completing our Apprentice Challenge. We would also like to thank Ayrshire Business

in the Community for giving us the opportunity to take part in the

programme. We have learned many valuable skills such as Team Working,

People skills etcc.