BWM-2011-16 Statusinstallation on Tankers and Technologies

Embed Size (px)

DESCRIPTION

Presentation re BWMP (DNV)

Citation preview

  • Jad Mouawad

    2011-06-22

    BWM-2011-16

    Ballast Water Management Convention

    Status, installation on tankers and technologies

  • Det Norske Veritas AS. All rights reserved.

    Ballast Water Management Convention

    2011-06-22

    Agenda

    2

    Ratification

    Application

    Entry into force

    Status

    Hazardous areas

    APT, technical freshwater etc.

    Installation on tankers

    Manufacturers

    DNV Services

    Technologies

  • Det Norske Veritas AS. All rights reserved.

    Ballast Water Management Convention

    2011-06-22

    Iran, 28th country ratified 6th April 2011

    3

    Status: 28 of 30 parties & 25.43% of 35% tonnage required for entry into force

    Party Local requirements Party & local requirements

  • Det Norske Veritas AS. All rights reserved.

    Ballast Water Management Convention

    2011-06-22

    Application

    4

    Applies

    - Party to the Convention; or

    - Sailing in waters of a Party

    International BWM Certificate

    Exceptions

    (Reg. A-3)

    Emergency Accidental

    Uptakeand

    dischargein highseas

    Uptakeand

    dischargein thesame location

    Exemption(Reg. A-4)

    Betweenspecifiedports

    Five yearsperiod

    Based onrisk

    analysisaccordingto G7

    Does not apply

    Ballast freeships

    Local trade (flag and operationonly under same party)

    Local trade (flag ofparty and operationunder anotherparty only)

    Navyships

    Permanent ballast water

  • July 5, 2011 5

    2011 2012 2013 2014 2016 2018

    Ratification Entry into force

    Intermediate or Renewal survey

    Anniversary date in 2016

    12 months

    Exchange or Treatment

    Treatment

  • Det Norske Veritas AS. All rights reserved.

    Ballast Water Management Convention

    2011-06-22

    Installation of treatment systems schedule Reg. B-3

    66

    Ballast Water

    Capacity

    Date of construction of ship

    Before 2009 2009 2009 2011 2010 or later 2012 or later

    < 1500 m

    Ballast water

    exchange or treatment

    until 2016

    Ballast water

    treatment only after

    2016

    Ballast water

    exchange or treatment

    until 2011

    Ballast water

    treatment only from

    2011

    Ballast water

    treatment only

    1500 5000 m

    Ballast water

    exchange or treatment

    until 2014

    Ballast water

    treatment only after

    2014

    Ballast water

    exchange or treatment

    until 2011

    Ballast water

    treatment only from

    2011

    Ballast water

    treatment only

    > 5000 m

    Ballast water

    exchange or treatment

    until 2016

    Ballast water

    treatment only after

    2016

    Ballast water

    exchange or treatment

    until 2016

    Ballast water

    treatment only after

    2016

    Ballast water

    treatment only

  • Det Norske Veritas AS. All rights reserved.

    Ballast Water Management Convention

    2011-06-22

    Agenda

    7

    Ratification

    Application

    Entry into force

    Status

    Hazardous areas

    APT, technical freshwater, etc.

    Installation on tankers

    Manufacturers

    DNV Services

    Technologies

  • Det Norske Veritas AS. All rights reserved.

    Ballast Water Management Convention

    2011-06-22

    8

    Main principles Connection between cargo area

    and engine room not allowed

    Rules pre-2007:

    Intrinsically safe only allowed

    Treatment systems are not

    intrinsically safe

    Rules post-2007:

    Zones 0, 1, 2 and safe

    Certified safe, as many of the

    treatment systems

    Standards:

    IIA, T3 minimum oil tanker

    Up to IIC, T6 chemical tankers

    Gas carriers:

    Not an issue as ballast can be led

    to the engine room

    88

    Installation on tankers

  • Det Norske Veritas AS. All rights reserved.

    Ballast Water Management Convention

    2011-06-22

    9

    Aft peak tank (APT)

    Water from the cargo area not

    allowed to be pumped to the engine

    room/APT

    Water from the APT to the cargo

    area:

    Two non-return valves

    mounted in series; and

    All connections between the

    APT and the cargo area must

    be led above deck with

    penetrations to the pump-room

    and APT from the main deck

    level.

    Penetrations of the engine

    room/pump-room bulkhead are not

    acceptable.

    9

    Installation on tankers

  • Det Norske Veritas AS. All rights reserved.

    Ballast Water Management Convention

    2011-06-22

    Installation Approval & Surveys

    Approval

    (DNV Rules Pt.6 Ch.18)

    ExchangeBWM Plan

    Sequential

    Flow through

    Dilution

    Sediment management

    Sampling

    TreatmentControl & Instrumentation

    Piping systems

    Bypasses

    Capacity

    Foundation (if necessary)

    Surveys

    (Reg. E-1)

    ExchangeDocumentation

    Sampling

    Openings for flow through

    Treatment Installation

    Commissioning

    Documentation

    No sampling for organisms required by Regulation E-1

    10

  • Det Norske Veritas AS. All rights reserved.

    Ballast Water Management Convention

    2011-06-22

    Agenda

    11

    Ratification

    Application

    Entry into force

    Status

    Yard capacity

    Installation

    BWM Plan

    Implementation

    Manufacturers

    DNV services

    Technologies

  • Det Norske Veritas AS. All rights reserved.

    Ballast Water Management Convention

    2011-06-22

    Manufacturers type approval by DNV

    12

    Manufacturer BWT System Technologies Active

    Substances

    Stage of

    approval

    Other

    approval

    Alfa Laval PureBallast 2.0/2.0

    Ex

    Advanced Oxidization + filtration Yes Type

    Approved

    No

    OceanSaver OceanSaver Cavitation + electrolysis + saturation

    + filtration

    Yes Type

    Approved

    No

    Optimarin Optimarin Ballast

    System (OBS)

    UV + filtration No Type

    Approved

    No

    Headway Marine

    Technology

    OceanGuard BWMS Electrocatalysis + filtration +

    ultrasound

    Yes Final

    Approval

    CCS (China)

    Wilhelmsen Marine

    Equipment

    Unitor BWMS Cavitation + electrolysis + filtration +

    ozonation

    Yes Final

    Approval

    South Africa

    Auramarine Crystal Ballast

    BWMS

    UV + filtration No Ongoing No

    Knutsen OAS KBAL Pressure drop + UV No Ongoing No

    Trojan UV Wartsila BWT UV + filtration No Ongoing No

    MMC MMC BWMS UV + filtration No Ongoing No

    Sunrui Company Balclor BWMS Electrolysis + filtration Yes Ongoing CCS (China)

    Hyde Marine Hyde Guardian

    BWMS

    UV + filtration No Submitted LR (UK)

  • Det Norske Veritas AS. All rights reserved.

    Ballast Water Management Convention

    2011-06-22

    Manufacturers approval status by other Administrations

    13

    Manufacturer BWT System Technologies Active

    Substances

    Stage of

    approval

    Approval

    body

    Techcross Electro-Cleen Electrolysis Yes Type Approved South Korea

    NEI Ventury Oxygen

    Stripping

    Deoxygenation No Type Approved Marshall

    Islands

    NK Co., Ltd NK-O3 Blue

    Ballast

    Ozonation Yes Type Approved South Korea

    Panasia Glo-En Patrol UV + filtration No Type Approved South Korea

    JFE JFE BWMS Chemical injection + filtration Yes Type Approved Japan

    Hitachi Hitachi BWMS Filtration + coagulation +

    magnetic separation

    Yes Type Approved Japan

    RWO CleanBallast Filtration + electrolysis +

    electrochlorination

    Yes Final Approval Germany

    HHI EcoBallast UV + filtration Yes Final Approval South Korea

    Japanese Association

    of Marine Safety

    SP Hybrid Cavitation + ozonation Yes Final Approval Japan

    Ecochlor Ecochlor BWMS Chemcial injection (ClO2) Yes Final Approval Germany

    21st Century

    Shipbuilding

    ARA BWMS Filtration + high energy

    plasma + UV

    Yes Final Approval South Korea

    Severn Trent De Nora BalPure Filtration + electrolysis Yes Final Approval Germany

  • Det Norske Veritas AS. All rights reserved.

    Ballast Water Management Convention

    2011-06-22

    DNV Services

    Type Approval of treatment systems

    Approval of BWM Plan

    Certificate/Statement of Compliance

    BWM-E, BWM-EP & BWM-T notations

    Class

    Preparation of BWM Plans

    Feasiblity study for treatment systems

    Risk analysis for exemptionsAdvisory

    14

  • Det Norske Veritas AS. All rights reserved.

    Ballast Water Management Convention

    2011-06-22

    15

    Safeguarding life, property

    and the environment

    www.dnv.com