Upload
haphuc
View
278
Download
5
Embed Size (px)
Citation preview
Foundation Fieldbus Seminar MalaysiaNovember 20091
Fieldbus FoundationTM
Bus diagnostics and troubleshooting
Andreas AgostinMTL Instruments Pte Ltd Singapore
On behalf ofFieldbus Foundation TM Marketing Committee (Malaysia)
Foundation Fieldbus Seminar MalaysiaNovember 20092
Bus diagnostics and troubleshooting
• Plant life cycle• Costs of diagnosis
Foundation Fieldbus Seminar MalaysiaNovember 20093
Plant life cycle
Which tools for which purpose?
Calculation tools
Engineering
Wiring tools
Installation
Commissioning & troubleshooting tools
Commissioning &Troubleshooting
PredictiveMaintenance
tools
Operation &Maintenance
Foundation Fieldbus Seminar MalaysiaNovember 20094
Plant life cycle
Which tools for which purpose?
Calculation tools
Engineering
Proper engineering ensures that the plant works as designed.Flaws in engineering will cause the actual plant not to work, and will trigger expensive redesign and re-work.
Foundation Fieldbus Seminar MalaysiaNovember 20095
Plant life cycle
Which tools for which purpose?
Wiring tools
Installation
According to field experience, approx. 95%1 of the problems occuring in a plant’s lifetime are related to installation.Cause can be:- Wrong ferrule diameter- Wrong crimping tool- Wrong crimping method- Wrong wire cutter- Wrong screw driver- Wrong torque- …
1 Source:http://forums.fieldbus.org/showthread.php?t=1298
Foundation Fieldbus Seminar MalaysiaNovember 20096
Plant life cycle
Which tools for which purpose?
Commissioning & troubleshooting tools
Commissioning &Troubleshooting
Commissioning should be done one-by-one. There are voices suggesting to connect all instruments and then switch on. However, a fault such as the frequently seen short-to-shield, will be impossible to locate. Connecting devices one-by-one will tell you that the problem occurred at the device you connected last.
Foundation Fieldbus Seminar MalaysiaNovember 20097
Plant life cycle
Which tools for which purpose?
PredictiveMaintenance
tools
Operation &Maintenance
In large installations with hundreds of bus segments, it can be of help to use physical layer online monitoring (“advanced diagnostics for the physical layer”). Using such tool you can detect degradation in the installation.
There are voices suggesting to use such tool for troubleshooting. However, due to the location of the tool in the control room, accurate measurements are not possible, and some faults are even not detectable (e.g. short to shield on a spur of a fieldbus barrier).
Foundation Fieldbus Seminar MalaysiaNovember 20098
Maintenance Strategies
• Failure already occurred• Failure causes production
loss• Potentially very high
costs
Maintenance
Repair
Time based Condition basedOn a schedule When required
Failure occurred already…
Foundation Fieldbus Seminar MalaysiaNovember 20099
Maintenance Strategies
Maintenance
Repair Preventive
Time based Condition basedOn a schedule When required
Failure occurred already…
No failure yet…
• No failure yet• High and regular
maintenance costs
Foundation Fieldbus Seminar MalaysiaNovember 200910
Maintenance Strategies
Maintenance
Repair Preventive
Time based Condition based
Predictive
On a schedule When required
In time beforefailure occurs
(Condition: “Warning”)
Failure occurred already…
No failure yet…
Foundation Fieldbus Seminar MalaysiaNovember 200911
Device Maintenance Effort
63% of time is spent investigating “problems” that do not exist. On Fieldbus, the fieldbus diagnostic module will alert you
when maintenance is needed, and will keep quiet if not.
Source: ARC Advisory Group, Intelligent Devices Provide Foundation for Operational Excellence – ARC Strategies, January 2003.
Routine check; 35%
Failure suspect, but no problem found; 28%
Re-ranging; 20%
Zero Drift; 6%
ProcessInterface; 6%
Failure;4% Preventive
Repair
Predictive
Foundation Fieldbus Seminar MalaysiaNovember 200912
Why Predictive Intelligence?
Time to Fail0%
100%C
ondi
tion
of A
sset
s
Too Late
Foundation Fieldbus Seminar MalaysiaNovember 200913
Why Predictive Intelligence?
Time to Fail0%
100%C
ondi
tion
of A
sset
s
Prediction gives you enough time to make
proper decision and to prevent abnormal
situations
Too Late
Conditions:(Alarms)
OKNeeds maintenance soon
Needs maintenance now
Foundation Fieldbus Seminar MalaysiaNovember 200914
Why Predictive Intelligence?
Time to Fail0%
100%C
ondi
tion
of A
sset
s
Prediction gives you enough time to make
proper decision and to prevent abnormal
situations
Conditions:(Alarms)
OKNeeds maintenance soon
Needs maintenance now
Foundation Fieldbus Seminar MalaysiaNovember 200915
Typical Problems
Foundation Fieldbus Seminar MalaysiaNovember 200916
Case study: faults in operation
Water in junction box, cable or device:
• Increasing number of retransmissions• Indication of shorts to shield• Can be a combination of both
Foundation Fieldbus Seminar MalaysiaNovember 200917
Bend radius too tight, Upward facing gland risks water ingress
Two cables into one glandprevents sealing of gland
Foundation Fieldbus Seminar MalaysiaNovember 200918
Corroded terminals:
• Increasing number of retransmissions• Increase of FF noise• Can be a combination of both
Foundation Fieldbus Seminar MalaysiaNovember 200919
Case study: faults in operation
Short to shield on fieldbus trunk:
• Indication of short to shield• Increasing number of retransmissions on all
devices
Foundation Fieldbus Seminar MalaysiaNovember 200920
Case study: faults in operation
Short to shield on fieldbus spur (wiring block):
• Indication of short to shield• Increasing number of retransmissions on this
specific device or on the devices of this wiring block
Foundation Fieldbus Seminar MalaysiaNovember 200921
Case study: faults in operation
Short to shield on fieldbus barrier spur:
• Indication of short to shield only on Handheld tester (due to galvanic isolation of fieldbus barrier)
• Increasing number of retransmissions on this specific device or on the devices of this fieldbus barrier
Foundation Fieldbus Seminar MalaysiaNovember 200922
Bad wiring technique
Welding, variable frequency drives (VFD), Motors, machinery:
• Increase of HF noise• Increasing number of retransmissions• Can be a combination of both
Foundation Fieldbus Seminar MalaysiaNovember 200923
Case study: faults in operation
Cable jacket stripped back too far can cause instrument malfunction:
– Water ingress– Wires shorted to housing– Corrosion– Tearing wires (increasing
resistance)
• Increasing number of retransmissions
• Signal amplitude rises• Increase of FF noise• Can be a combination of
above
Foundation Fieldbus Seminar MalaysiaNovember 200924
Case study: faults in operation
Fieldbus terminator missing:
• All signal amplitudes rise (best indicator)• Increased noise in all frequency bands• Increasing number of retransmissions (usually on all
devices)• One or more devices drop off the bus (may or may not
come back)
Note: likely to be the terminator in the field, not on the baseplate (soldered, controlled environment)
Foundation Fieldbus Seminar MalaysiaNovember 200925
Wires coming out of ferrules:
Spur:• Device drops off (may or may not return)• Increasing number of retransmissions
Trunk:• Devices drop off (may or may not return)• Signal amplitude sometimes ok, sometimes high• Increasing number of retransmissions
Foundation Fieldbus Seminar MalaysiaNovember 200926
Problem indicated by Diagnostic Module
Foundation Fieldbus Seminar MalaysiaNovember 200927
Warning or alarm levels exceeded?
Foundation Fieldbus Seminar MalaysiaNovember 200928
On which segment?
Foundation Fieldbus Seminar MalaysiaNovember 200929
What’s the problem on the segment?
Foundation Fieldbus Seminar MalaysiaNovember 200930
……
Device Signal Level Low-Low Alarm
If only one device low: check 1. alarm limits have not been wrongly set, 2. spur cabling, spur and device connections
are tight3. for water in spur cable or device4. device operation. If several/all devices on segment low check: 1. for more than two terminators on
segment, check that terminator switches on the fieldbus barrier are set to “off”.
2. for water in devices, junction boxes and cabling.
Device Signal Level Low Alarm
Device Signal Level High Alarm
If only one device high: check: 1. alarm limits have not been wrongly set, 2. device operation. If several/all devices on segment check: 1. for only one terminator on segment 2. for failed terminator.
Device Signal Level High-High Alarm
Corrective ActionName and Description
And what does that mean, what is the cause of the alarm?
Alarm Identification
Foundation Fieldbus Seminar MalaysiaNovember 200931
In the device manager, you:• Compare actual vs historical data• See information about each device• See alarms of physical layer of device
Foundation Fieldbus Seminar MalaysiaNovember 200932
All data is communicated via FF, allowing fullIntegration into all host software packages.Example: Trending of noise and voltage levels in the historian.
Foundation Fieldbus Seminar MalaysiaNovember 200933
Example: Noise level trendingN
oise
Alarm level (critical)
Warning level
2008 2009 2010 20122011
Warning and alarm levels are set so that there is sufficient time to fix the problem e.g. during a regular shutdown
Foundation Fieldbus Seminar MalaysiaNovember 200934
On-line monitoring
FFPST
FF Power Supply& Conditioner&Terminator
24VDC
HostComputer
H1 Interface
Fieldbus barrier
Device 1 Device 3 Device 2
Fieldbus barrier& Terminator
IntrinsicallySafe Spurs
TFieldbus
barrier
DM F809F FieldbusDiagnostic Module
Permanently installed at the fieldbus power supply in the control room.
Foundation Fieldbus Seminar MalaysiaNovember 200935
Portable diagnostic tools
PDIPortable
Diagnostic Instrument
FFPST
FF Power Supply& Conditioner&Terminator
24VDC
HostComputer
H1 Interface
Fieldbus barrier
Device 1 Device 3 Device 2
Fieldbus barrier& Terminator
IntrinsicallySafe Spurs
TFieldbus
barrier
To measure at fieldbus barrier, PDI needs to be Ex i approved.Important since the galvanic isolation of fieldbus barrier impacts on measurement.
Foundation Fieldbus Seminar MalaysiaNovember 200936
Typical measured parameters
• DC voltage– Indicates correct function of power supply/conditioner– Instrument supposed to operate from 9V onwards
• Shield short (+ or – connected to shield/ground/screen)– Easy to measure and understand– Further measurements can identify location
• Signal level– Minimum level is specified by Fieldbus specification– Low or high levels on all devices suggests incorrect bus termination– If only one device, suggests problem on single spur
Foundation Fieldbus Seminar MalaysiaNovember 200937
Typical measured parameters
• Noise– Maximum level is specified by Fieldbus specification– Tri-band measurement helps to identify source
• LF: bulk supply• IF: fieldbus device• HF: induction from outside the network
• Retransmissions / Retransmission rate– Good measurement of physical layer health– Measured in absolute retransmissions and in % of total transmissions
(rate)– Re-tries can obscure faulty device or network
http://forums.fieldbus.org/showthread.php?t=1298Follow link to access Fieldbus Forum posting on physical layer problem(see summary on next page)
Foundation Fieldbus Seminar MalaysiaNovember 200938
http://forums.fieldbus.org/showthread.php?t=1298
Foundation Fieldbus Seminar MalaysiaNovember 200939
Amount of diagnostic information
• Fieldbus Diagnostic Modules can provide a multitude of data and information
• Not every maintenance technician is a fieldbus expert
• Tools must match the employee skills
Foundation Fieldbus Seminar MalaysiaNovember 200940
The various solutions
Foundation Fieldbus Seminar MalaysiaNovember 200941
The various solutions
Differentiators:- Physical Interface(FF H1 / FF HSE / RS485 / Contact)
- Measurements- Level of detail- User Interface(H1 Host integration / DTM / OPC)
Foundation Fieldbus Seminar MalaysiaNovember 200942
Conclusion
“Key Three”:• Foundation Fieldbus communication is very
robust• If you do your installation right, you avoid many
problems down the road• Online-diagnostic of the physical layer is an add-
on that can help you to identify problems before they cause a failure
Foundation Fieldbus Seminar MalaysiaNovember 200943
Any Questions?
Andreas Agostin contact:+65 9758 5161
Foundation Fieldbus Seminar MalaysiaNovember 200944
www.fieldbus.org