31
Bus-Bar Quench Bus-Bar Quench Studies Studies Summary of Available Summary of Available Calculations Calculations LMC Meeting August 5 LMC Meeting August 5 th th 2009 2009 J. Blanco, M. Brugger, F. Cerutti, A. Ferrari, E. Lebbos, A. Mereghetti, K. Roed, R. Schmidt, V. Vlachoudis, J. Wenninger Input from: A. Verweij

Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Embed Size (px)

Citation preview

Page 1: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Bus-Bar Quench StudiesBus-Bar Quench Studies Summary of Available Summary of Available Calculations CalculationsLMC Meeting August 5LMC Meeting August 5thth 2009 2009

J. Blanco, M. Brugger, F. Cerutti, A. Ferrari, E. Lebbos, A. Mereghetti, K. Roed, R. Schmidt, V. Vlachoudis, J. Wenninger

Input from: A. Verweij

Calculations based on the FLUKA Team IR7 Layout

Page 2: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

(3) Loss in the Empty Cryostat• aiming to get peak energy deposition in the empty cryostat and the downstream

magnets (5TeV only)

MBA11 MBB11 Empty Cryostat MQ11X

(1) MQ12• aiming to get peak energy deposition in the

following interconnect and magnets• done for both energies 3TeV and 5TeV

MBA12 MBB12 MBC12 MQ12

X

MBA11 MBB11 Empty Cryostat MQ11X

(2) MQ11• aiming to get peak energy deposition in the following interconnect, empty

cryostat and magnets (5TeV only)

The Studied Cases: Loss SourceThe Studied Cases: Loss SourceGeneral•Beam-2 case assuming orbit bump at MQ locations•Two general cases studied for various locations: (a) Point-like loss in the beam-screen to get peak in the downstream interconnect/empty-cryostat or magnet(b) assuming a distribution (equal) along the element

X

August 5th 2009 2Busbar Quench Studies - LMC Meeting

250rad deflection angle

Beam 2Beam 2Beam 2

Page 3: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Models: Models: Empty CryostatEmpty Cryostat

Energy deposition on the busbars per unit length

Energy deposition on the lyra BLM particles spectra and energy

deposition. -> BLM signal

August 5th 2009 3Busbar Quench Studies - LMC Meeting

Page 4: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Interconnect: FLUKA modelInterconnect: FLUKA model

Beam Line V1 & V2Bus Bar Dipole Line M3

Linear Heat Exchanger X & YBus Bar Quadrupole LineM1 & M2

August 5th 2009 4Busbar Quench Studies - LMC Meeting

Page 5: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Assumptions for Quench & HeatingAssumptions for Quench & HeatingMB/MQ Quench Limits (for transient case)

•1mJ/cm3 (preliminary assumption -> update needed)•peak energy deposition in magnet coils:

cell size (r//z): ~1cm / 2deg / 10cm

Busbar Quench Limits (transient)•10mJ/cm (preliminary assumption -> update needed)•transversal average over

•MQ: 160mm2 (M1, M2 as shown in layout before)•MB: 280mm2 (M3)

•in the moment peak value with:•~ 1cm longitudinal average for the busbars•~ peak value in the Lyra (not averaged!)

•adiabatic assumption

(Pre)Heating-up 80K•80K: 92 J/cm for the MQ, (c.f., A.Verweij) (preliminary assumption -> possible update needed)

5Busbar Quench Studies - LMC MeetingAugust 5th 2009

!!!The Results SCALE

with these Assumptions!!!

Page 6: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Example: Distributed Loss in MQ11Example: Distributed Loss in MQ11

6Busbar Quench Studies - LMC MeetingAugust 5th 2009

MQ11R7

EmptyCryostat

MB.B11R7

MB.A11R7

Energy density given per simulated primary proton!

Beam Direction

Page 7: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Inter-Connect: Energy depositionInter-Connect: Energy deposition

Horizontal cut

Interconnect located after the MQ11 (point-like loss)

Vertical cut GeV/cm3/primary

Beam 2

Peak in the beam-pipePeak in the beam-pipe

Peak in the busbar

Coarse binning for Visualisation onlyAugust 5th 2009 7Busbar Quench Studies - LMC Meeting

Page 8: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Inter-Connect: Energy DepositionInter-Connect: Energy Deposition

Point-Like Loss

MQ11 5TeV

Distributed Loss

Length Along Inter-Connect / cm

En

erg

y D

en

sity

/ G

eV

/cm

3

Beam 2

August 5th 2009 8Busbar Quench Studies - LMC Meeting

Page 9: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Empty Cryostat Loss (Distributed)

Empty Cryostat: Energy depositionEmpty Cryostat: Energy deposition

Get Peak Value(localized)

Beam 2

Length Along Empty Cryostat / cm

En

erg

y P

er U

nit

Len

gth

/ G

eV

/cm M1 (MQ)

M2 (MQ)

Lyra Peak to be evaluated separately

August 5th 2009 9Busbar Quench Studies - LMC Meeting

Page 10: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

10

Busbar Quench

Studies - LMC

Meeting

Empty Cryostat: Energy depositionEmpty Cryostat: Energy deposition

Factor of ~10x

Edep Lyra M2 dist loss Edep Lyra M2 point loss

Edep Lyra M1 dist lossEdep Lyra M1 point loss

M2 (MQ)M2 (MQ)

M1 (MQ)M1 (MQ)

Distributed Loss

Distributed Loss

Point-Like Loss

Point-Like Loss

August 5th 2009

Page 11: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Beam 2

BLM Signal Empty Cryostat BLM Signal Empty Cryostat

Possible BLM Positions Along Beam Elements

BL

M S

ign

al (

Ide

al P

os.

) /

C/p

rim

ary Peak in the beginning

of the MB.B11

Empty Cryostat Loss (Distributed Case)

August 5th 2009 11Busbar Quench Studies - LMC Meeting

Page 12: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Analysis, Analysis, e.g.e.g., MQ11 - Point-Like Case, MQ11 - Point-Like Case

Busbar Quench Studies - LMC Meeting 12August 5th 2009

Magnet quenches ~3 orders of magnitudes earlier than the busbars in the adjacent inter-connect or empty cryostat

BLM signal in the order of nC (if in the optimum position) in the case of the MQ11 quench

Consider important uncertainties due to the loss assumptions and simulation statistics (digits are not significant)

Page 13: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

MBA11 MBB11 Empty Cryostat MQ11

Number Of Protons To Quench BothNumber Of Protons To Quench Both

Busbar Quench Studies - LMC Meeting 13August 5th 2009

Empty Cryostat 5TeV

Beam 2Beam 2Beam 2

Page 14: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

MBA12 MBB12 MBC12 MQ12

Busbar Quench Studies - LMC Meeting 14August 5th 2009

Number Of Protons To Quench BothNumber Of Protons To Quench BothMQ12 5TeV

Beam 2Beam 2Beam 2

Page 15: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Quenches: Summary TableQuenches: Summary Table

Busbar Quench Studies - LMC Meeting 15August 5th 2009

Magnet will quench significantly earlier than adjacent busbars (in inter-connects or the empty cryostat) (108) 106 protons sufficient to quench the magnets (108) 109-1010 protons required to quench the busbars

Energy dependence between 5 and 3 TeV is about a factor of two (significantly below the uncertainties due to the loss assumptions)

Respective BLM signal is a few nC for the magnet quench (3-1000nC) Loss (point-like) in the empty cryostat is considered as ‘worst-case’, however

direct losses are very unlikely (as compared to the MQs)

Page 16: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Pre-Heating to 80KPre-Heating to 80K

Busbar Quench Studies - LMC Meeting 16August 5th 2009

Only preliminary assumption for the required energy 92J for 80K (c.f., A.Verweij)

108-1010 protons required to quench the busbar` Some 1012-1013 protons required for >80K Considered as less of an issue

Page 17: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

ConclusionsConclusions Peak values location (and loss scenario) dependent, however

general conclusions possible to be drawn within the order of magnitudes (given the assumptions)

Combined busbar and magnet quench can not be excluded Magnet will quench at a significantly lower level of beam loss

than adjacent bus bars (in inter-connects or the empty cryostat) (108) 106 protons sufficient to quench the magnets (108) 109-1010 protons required to quench the busbars

Applied quench ‘limits’ require an iteration with the magnet experts – results scale accordingly

Energy dependence between 5 and 3 TeV is about a factor of two According to the present studies it’s very unlikely to quench the

busbar only (not observed in these studies) Pre-Heating to 80K seems less of an issue, but required heat

assumptions need to be clarified

Busbar Quench Studies - LMC Meeting 17August 5th 2009

Page 18: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Busbar Quench Studies - LMC Meeting 18August 5th 2009

Supporting Material

Page 19: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Problem IntroductionProblem IntroductionMotivation“Quantify the likelihood of quenching the busbar with beam.”

“Verify the respective magnet quenches and levels.”

“Analyse the related BLM signal and positions”

“Study the probability of rising the temperature of the busbar/Cu over 80K before discharging.”

The ‘Problem’Sufficiently ‘realistic’ representation of the geometrical situation

Proper implementation in the DS/ARC layout

What loss scenario to be condisered

Link between loss scenario, energy deposition (quench) and BLM signal

- simulation layout follows same layout as damage studies proposed before/after Chamonix 2009 (see V. Kain et al.)

19Busbar Quench Studies - LMC MeetingAugust 5th 2009

Page 20: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

The Required (New) IngredientsThe Required (New) IngredientsGeometry

•FLUKA model of the empty cryostat•FLUKA model (different lengths) of the interconnects•BLM ‘dummy’ regions along magnets

Technical•Routine allowing for arbitrary losses in beam elements of the DS/ARC•BLM particle energy spectra scoring as a function of ‘Lattice’•Special LYRA scoring following U-shape and allowing to get only the

contribution of the sensitive volume•Check for particles leaving the area (possible use for post-tracking studies)•Longitudinal scoring along bus-bars, as well as 3D scoring for visualization

Loss Assumption•Different cases studied for various loss locations (MQ12/11/Empty Cryostat)

and in some cases also different energies

Quench Levels & Preheating: Values and Conditions•Normalization assumptions•Quench conditions to be studied (transient,…)

20Busbar Quench Studies - LMC MeetingAugust 5th 2009

Page 21: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Geometry Models: Empty Cryostat Geometry Models: Empty Cryostat Details Included

Lyras (complex implementation through angles,…)

Radiation shield (Pb) Beam screens/pipes Central part

(He/Steel) Continuous

horizontal BLM

August 5th 2009 21Busbar Quench Studies - LMC Meeting

Page 22: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

The Interconnect ‘Challenge’ The Interconnect ‘Challenge’

August 5th 2009 22Busbar Quench Studies - LMC Meeting

MQ11Empty CryostatMBB11MBA11

MQ10

not in scale

Page 23: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

RF contact developmentin Cu alloy C17410with 5µm Au coating

Interconnect: FLUKA model (2)Interconnect: FLUKA model (2)Beam Line & Bus bar described in detail with respect to the dimensions and materials

Tube in stainlesssteel 316LN

Transition tube in Cu

Tube in stainlesssteel 316LN

Superconducting cablesCu alloy insideCu outside

August 5th 2009 23Busbar Quench Studies - LMC Meeting

Page 24: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Different Locations (distributed loss)Different Locations (distributed loss)

24Busbar Quench Studies - LMC MeetingAugust 5th 2009

Empty Cryostat MQ11

MQ12

Analysis of peak energy depositions in busbars and magnet coils for the different loss locations and distributions (as well as energy for the MQ12 case)

MQ11

MBB11

MBA11

Empty Cryostat

MQ11

MBB11

MBA11

Empty Cryostat

MQ12

MBB12

MBA12

MBC12

Page 25: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Empty Cryostat: Energy depositionEmpty Cryostat: Energy deposition

Get Peak Value(localized)

Beam 2

Length Along Empty Cryostat / cm

En

erg

y P

er U

nit

Len

gth

/ G

eV

/cm M1 (MQ)

M2 (MQ)

Empty Cryostat Loss (Point-Like)

Lyra Peak to be evaluated seperatedly

LossLocation

August 5th 2009 25Busbar Quench Studies - LMC Meeting

Page 26: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Beam 2

BLM Signal Empty Cryostat BLM Signal Empty Cryostat

Position Along Beam Elements

BL

M S

ign

al (

Ide

al P

os.

) /

C/p

rim

ary Peak in Towards the

End of the Empty Cryostat

Empty Cryostat Loss (Point-Like Case)

August 5th 2009 26Busbar Quench Studies - LMC Meeting

Page 27: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Analysis, Analysis, e.g.e.g., MQ11 - Distributed Case, MQ11 - Distributed Case

Busbar Quench Studies - LMC Meeting 27August 5th 2009

Magnet quenches 2-3 orders of magnitudes earlier than the busbars in the adjacent inter-connect or empty cryostat

BLM signal in the order of nC in the case of the MQ11 qench

Page 28: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Analysis, Analysis, e.g.e.g., Empty Cryos. Dist. Loss, Empty Cryos. Dist. Loss

Busbar Quench Studies - LMC Meeting 28August 5th 2009

Adjacent magnet quenches ‘only’ ten times earlier than the busbars in the empty cryostat

significantly higher BLM signal (some 100nC)

(Note: the BLM signal refers to the BEST possible location, thus not necessarily the one as installed in the machine )

Page 29: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

Analysis, Analysis, e.g.e.g., Empty C. Point Loss, Empty C. Point Loss

Busbar Quench Studies - LMC Meeting 29August 5th 2009

Magnet quenches about at the same time as the busbars in the empty cryostat

(Note: the Lyra quench level refers to the peak value)

Page 30: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

MBA11 MBB11 Empty Cryostat MQ11

Number Of Protons To Quench BothNumber Of Protons To Quench Both

Busbar Quench Studies - LMC Meeting 30August 5th 2009

MQ11 5TeV

Beam 2Beam 2Beam 2

Page 31: Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting August 5 th 2009 Bus-Bar Quench Studies Summary of Available Calculations LMC Meeting

MBA12 MBB12 MBC12 MQ12

Busbar Quench Studies - LMC Meeting 31August 5th 2009

Number Of Protons To Quench BothNumber Of Protons To Quench BothMQ12 3TeV

Beam 2Beam 2Beam 2