BUILDING DESIGN KICKOFF MEETING

Airport Heights Elementary School May 1, 2013

BUILDING DESIGN KICKOFF MEETING

Airport Heights Elementary School May 1, 2013

McCool Carlson GreenArchitects

AnchorageSchool District

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

INTRODUCTIONS• ASD Management• Design Team• Building Design

Committee (BDC)

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

AGENDA• Process overview and schedule• Site Analysis• Educational Specification• Learning Signature

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

DESIGN PROCESS• Design Committee Guide• Ed Spec Analysis• Existing School investigation• Concept Development• Design Refinement• Phasing Analysis• Cost Verification• Bond Approval• Final Design

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

Master Plan Scenarios• Budget

• $20.9M total project• $14.6M Construction

• Maximize value within budget

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

PROJECT SCHEDULEDesign Workshops• May 1: BDC Meeting #1• May 11: Dream Big Saturday• May 15: BDC Meeting #2• May 29: BDC Meeting #3• June 12: BDC Meeting #4• June 26: BDC Meeting #5• Future Meetings TBD

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

PROJECT GOALS & OBJECTIVES• Develop consensus• Measure project

success• Keep us on track

• What are the most important things that this project should accomplish?

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

ABOUT AIRPORT HEIGHTS• Educational Program

• Staff• Students• Learning• Teaching

• Community• Site Context• Aspirations• History

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

EXISTING SITE

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

EXISTING FLOOR PLAN

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

EDUCATIONAL SPECFICATIONSPROPOSED DRAFT Teaching Existing School with 3 Relos

Station Net S.F. total # of Qty. & # of Existing1.0 CLASSROOM CLUSTERS St. Type: Qty . Each Area Students Teaching Stations Area

1.01 Kindergarten Classrooms 20 Reg 3 1,250 3,750 60 3 2605- Kindergarten Restrooms 3 60 - 4 80

1.02 Primary Classrooms: Grade 1 21 Reg 2 1,000 2,000 42 2 17301.02 Primary Classrooms: Grade 2 24 Reg 2 1,000 2,000 48 2 17901.02 Primary Classrooms: Grade 3 24 Reg 2 1,000 2,000 48 2 1790

- Primary Student Restrooms 6 60 - 2 601.03 Intermediate Classrooms 27 Reg 5 1,000 5,000 135 5 4550

- Intermediate Student Restrooms 2 200 - 2 610- Intermediate Student lockers -

1.04 Resource Classrooms Aux 2 1,000 2,000 2 18001.05 Itinerant/Small Group Room 2 240 480 0 01.06 not used - 0 01.07 Storage 2 120 240 1 240

- Staff Restrooms 2 80 - 0 0Sub-total: 14 Reg. 17,470 333 14 Reg. 15,255

2 Aux. 2 Aux.

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

EDUCATIONAL SPECFICATIONS

2.0 SPECIAL PROGRAMS Type: Qty. Each Area Total: Qty. Area2.01 Special Programs Classrooms 8 Reg 2 1,000 2,000 16 2 1780

a Student Alcovesb Cubbies 2 120 240 * *c Observation/Conference 1 120 120 0 0d not used - 0 0e Quiet Area 2 120 240 * *f Staff Work 1 100 100 0 0

g Kitchenette/Storage 1 100 100 0 0h Restroom/Changing 2 120 240 1 55

2.02 Sp Prgrms Supply/Equipment Storage 1 100 100 * *2.03 Occupational/Physical Therapy 1 500 500 * *2.04 OT/PT Equipment Storage 1 200 200 1 1102.05 Speech Therapy Instruction 1 300 300 * *2.06 Speech Therapy Small Group 1 150 150 1 200

Sub-total 2 Reg. 4,290 16 2 Reg. 2,1450 Aux. 0 Aux.

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

EDUCATIONAL SPECFICATIONS3.0 LIBRARY/MEDIA CENTER Type: Qty. Each Area Total: Qty. Area

3.01 Stacks, Desk & Teaching Areas 1 2,000 2,000 1 2,2903.02 Technology Learning Lab Aux 1 750 750 1 9003.03 Librarian's Office/Workroom 1 150 150 1 1103.04 Library Storage 1 150 150 * *3.05 IT Equip. / Communications Room 1 150 150 1 90

Sub-total 0 Reg. 3,200 0 0 Reg. 3,3901 Aux. 1 Aux.

4.0 ART & MUSIC Type: Qty. Each Area Total: Qty. Area4.01 Music Classroom Aux 1 950 950 1 1,0004.02 Music Office/Storage Room 1 175 175 * *4.03 Instrument Storage Room 1 100 100 * *4.04 Art/Science/Health Activity Lab Aux 1 1,250 1,250 1 1,0004.05 Activity Lab Storage 1 200 200 * *

Sub-total 0 Reg. 2,675 0 0 Reg. 2,0002 Aux. 2 Aux.

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

EDUCATIONAL SPECFICATIONS5.0 PHYSICAL EDUCATION Type: Qty. Each Area Total: Qty. Area

5.01 Gymnasium Aux 1 3,000 3,000 1 3,4755.02 not used - -5.03 P.E. Office 1 150 150 * *5.04 PE Equipment Storage 1 300 300 1 1305.05 Adaptive PE Equipment Storage 1 100 100 * *

Sub-total 0 Reg. 3,550 0 0 Reg. 3,6051 Aux. 1 Aux.

6.0 MULTIPURPOSE / FOOD Qty. Each Area Total: Qty. Area6.01 a Food Service 1 500 500 1 430

b Food/Nutrition Office 1 80 80 * *c Dry Storage 1 80 80 1 45d Food Service Cleaning Closet 1 50 - 1 15

6.02 Multipurpose Room 1 2,000 2,000 * *6.03 Table/Chair Storage 1 400 400 1 3406.04 Campfire Program Storage 1 100 100 * *6.05 Kitchenette (Campfire program) 1 50 50 0 0

Sub-total 3,210 0 830

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

EDUCATIONAL SPECFICATIONS7.0 ADMINISTRATION Qty. Each Area Total: Qty. Area

7.01 Reception 1 150 150 1 1507.02 Secretary 1 300 300 1 2007.03 Administrative Assistant 1 80 80 1 857.04 Storage Closet (Secure) 1 40 40 1 507.05 Student Quiet Area 1 40 40 * *7.06 Conference Room 1 200 200 0 07.07 Principal's Office 1 250 250 1 2557.08 Parent/Community Center 1 500 250 0 07.09 a Nurse Office 1 80 80 * *

b Infirmary/Treatment/Storage 1 280 280 1 175c Exam/Resting 1 60 60 * *d Restroom/Changing 1 120 120 * *

7.10 Principal Intern 1 120 120 * *7.11 Staff Lounge 1 400 400 1 4907.12 Staff Restrooms 2 80 - 2 507.13 Workroom and Storage 1 300 300 1 2457.14 not used -7.15 Lost & Found 1 30 30 * *

Sub-total 2,700 0 1,700

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

EDUCATIONAL SPECFICATIONS8.0 STUDENT SUPPORT SERVICES Qty. Each Area Total: Qty. Area

8.01 Counseling 1 200 200 1 2008.02 Indian Education 1 200 200 * *8.03 Psychology Office 1 120 120 1 818.04 Itinerant Offices 1 100 100 * *8.05 ELL, Ignite, Indian Ed, Title I Programs Aux 2 1,000 2,000 2 1,900

Sub-total 0 Reg. 2,620 0 0 Reg. 2,1812 Aux. 2 Aux.

9.0 MAINTENANCE & CUSTODIAL Qty. Each Area Total: Qty. Area9.01 Receiving 1 400 400 1 509.02 Central Building Storage 1 550 550 1 2409.03 Custodial Closets TBD - 1 509.04 Custodial Office/Storage 1 - * *9.05 Outdoor Storage 1 - 3 5009.06 Boiler Room 1 - 1 4609.07 Fan Room 1 - 1 7609.08 Electrical Room 1 - 1 909.09 Intermediate Communications Room TBD - 1 85

Sub-total 950 0 2,235

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

EDUCATIONAL SPECFICATIONS

10.0 GENERAL BUILDING AREAS Qty. Each Area Qty. Area10.01 Building Entry Vestibule(s) TBD -10.02 Main Circulation Hallways TBD -10.03 Main Circulation Stairways TBD -10.04 Restrooms 2 450 900 2 62010.05 Elevators TBD -10.06 Relocatable Classrooms (future)10.07 Camper Host (Security)

Sub-total 900 NA 620

CapacityTOTALS & Calculations Qty. Area Total: Existing School w/ Relos Area

TOTAL NET AREA (NSF): 41,565 33,961TOTAL GROSS AREA (GSF): 54,035 42,950

16 Reg. 349 16 Reg.8 Aux. 8 Aux.

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

A LEARNING SIGNATURE FOR YOUR SCHOOL

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

Learning Signature Features

• Aligns with the learning philosophy• Confirms a worthy identity for the institution• Creates an accurate image of the institution• Provides a unique character • Gives focus and coherence to all components of the institution

• Communicates powerfully the promise of the institution 

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

Using City as Place to Learn

Source: The Cunningham Group

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

Ever changing, adapting, connectingMat Su Career & Technical High School, Wasilla, Alaska

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

Open LearningChugach Optional, Anchorage

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

LEARNING SIGNATURE

Valley Pathways School

Palmer, Alaska

Choose

Commit

Achieve

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

Romig Middle &

West High School

Renewal

Anchorage, Alaska

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

Learning with Art & Nature

Su Valley High School

Talkeetna, Alaska

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

Golden Heart Ryan Middle School

Fairbanks, Alaska

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

Student OwnershipPolaris K-12, Anchorage

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

A Center for the Creation of CommunityMachetanz Elementary

Wasilla, Alaska

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

LEARNING SIGNATURE

Explore the world

Create your future!

Barnette Magnet School

Fairbanks, Alaska

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

LEARNING SIGNATURE

Where learning is inspired by nature and activated by community

Girdwood K‐8 School 

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

LEARNING SIGNATURE

AIRPORT HEIGHT’S LEARNING SIGNATURE? 

Airport Heights ES| Master Planning Process | McCool Carlson GreenArchitects

NEXT STEPS• Goals & Objectives• Ed Spec Adjustments• Site Concepts• Virtual / Real Tours• Learning Signature