79
Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Embed Size (px)

Citation preview

Page 1: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Building Basements Safely

An overview of HSE’s approach to regulating basement excavations

James Hickman

HM INSPECTOR (CONSTRUCTION)

ROSE COURT

Page 2: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Building Basements Safely

My Background

• Geotechnical Engineer

• HM Inspector (Construction)

• Basement and Tunnel Inspector

• Basement Initiatives

Page 3: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Building Basements Safely

• Overview

• Introduction to basements

• Site findings

• What are HSE doing

Page 4: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Overview - The sales pitch for subterranean living

Page 5: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Overview - How is it achieved…?

Page 6: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Overview - When it goes wrong

Page 7: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Overview - The problems with basement construction

• Technically challenging

• Contractors often new to the industry

• Poorly planned

• Poorly supervised/managed

• Lack of competence in those planning and managing – technical/health and safety

• Complacency (60+ basements no shoring!)

Page 8: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Overview - Key Issues

• Collapse of excavations

• Undermining of adjacent structures

• Material falling into an excavation

• People, plant and equipment falling into excavation - WAH

• Temporary works / Permanent works

• Electrics

• Welfare

• Manual handling

Page 9: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Overview – Key issues cont.

• Excavation often unsafe – complacency

• Belief that vertical clay face will stand unsupported

• TW designers often absent – no calcs/drawings

• Simultaneous refurbishment with structural alteration

• Work subcontracted – main contractor absent

• Beams can weigh several hundred kg

• Vulnerable workers

Page 10: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Overview - Legislation

• Reg 19 CDM 2015 – Stability of Structures

• Reg 22 CDM 2015 – Excavations

• Schedule 2 CDM 2015 – Welfare

• Reg 6(3) WAH 2005 – Avoidance of risks from work at height

• Reg 6 EAW 1989 – Adverse or Hazardous Environments

Page 11: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Overview - Information & Guidance

• Guidance concerned with Groundworks / Excavations

• Nothing specific with regard to basement construction

• HSE Busy builder leaflet

Page 12: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Overview - Information & Guidance

• IStructE – Subsidence of low-rise buildings (Aug 2000)

• CIRIA - Trenching practice. 2nd edition (2001 revision)

• Shoring technology interest group www.cpa.uk.net/p/Shoring-Technology-Interest-Group

• Specialist Domestic: Underpinning & Subsidence Repair Techniques/Engineer Foundation Solutions /Retrofit Basement - Association of Subsidence & Underpinning Contractors (ASUC) www.asuc.org.uk

Page 13: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Introduction to basements

You probably all know this…..

……..but

Page 14: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Basic soil mechanics

• Sides relieved of lateral support from surrounding ground

• Becomes unstable

• Material above natural angle of repose will partially or totally collapse at any time

Page 15: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Angle of repose

• Just like being at the beach!

Page 16: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Angle of repose

• Starts to dry out, crack and crumble – water doesn’t help.

Page 17: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Angle of repose

• In time it will return to its natural angle of repose.

Angle of repose

Page 18: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Temporary safe slopes of soils

Table from CIRIA Report 97 - Trenching Practice

Page 19: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Temporary safe slopes of soils

Page 20: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Excavations – basic principles

• No ground can be relied upon to stand unsupported.

• In urban areas you don’t know history of previous ground disturbance.

• All practicable steps must be taken to prevent danger to any person, including, where necessary, the provision of supports or battering, to ensure that no excavation or part of an excavation collapses (Reg 22 CDM 2015).

Page 21: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Control Measures - battering or stepping back

• Battering or stepped excavations

• Based on safe angle of repose

• However you need the space on site to do this.

• A lot of sites maximise the footprint and hence no option to batter or step excavation

Page 22: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Stiff Clays and soils

Open or hit and miss shoring

Page 23: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Soft Clays, Gravels & Sands

Close boarding or interlocked sheets

clay

Sand/ gravels

Page 24: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Hit and miss or close boarding required

Stiff clay Sandy silty clay

Page 25: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Geotechnical Report – Starting point

• Ground conditions need to be known to design both the temporary and permanent (or finished) works.

• Information can be found from desktop study or previous experience of local area.

• More complicated jobs will need a site investigation including a geotechnical report – ‘BIA’.

• Information can also be used by contractor when devising construction method (including support of excavations)

Page 26: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Incidents can happen to “experts”

Geotechnical surveyor killed by collapsed trench

Sep 2008 - Geologist Alex Wright, 27, from Cheltenham, died when a 3.5m deep trial pit he was working in collapsed.

February 2011 – His employer, Cotswold Geotechnical Holdings became the first company to be convicted of the new offence of corporate manslaughter.

In convicting the company, the jury found that their system of work in digging trial pits was wholly and unnecessarily dangerous. The company ignored well-recognised industry guidance, by requiring junior employees to enter into and work in unsupported trial pits, typically from 2 to 3.5 metres deep. Mr Wright was working in

just such a pit when he died.

Company was fined £385,000, and it was upheld on appeal.

Page 27: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Maximising the Footprint. Beware of undermining - doesn’t mean you have to dig directly beneath the foundation

Stable material

Wedge of soil at angle of repose

Earth face – no support

Foundation exerts vertical load on soil below

Wall

Excavation

Unstable Material

Page 28: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Undermining doesn’t mean you have to dig directly beneath the foundation

Soil slips off stable material

Wedge of soil at angle of repose

Collapsed earth face

Foundation and load left unsupported

Wall

Stable material

Page 29: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Undermining doesn’t mean you have to dig directly beneath the foundation

Wedge of soil at angle of repose

Stable material

Page 30: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Presence of water

• Water table (geotechnical report)

• Ingress of water (e.g. broken water main)

• Affects stability of excavated face

• Washes out fines in granular soils

• Softens clay soils• Thames is tidal!

Page 31: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Planning the work – design phase

• Company Standards for excavation work

• Risk Assessment procedure

• Consider underground services

• Temporary works input (Calculations & Drawings)

• Production of Method Statements (safe system of work)

• Selection of right plant and equipment

• Competent site management and supervision (especially front line supervisors)

Page 32: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Method Statements

• Geotechnical information – BIA’s

• Method of construction and temporary support of excavation – sequencing

• Access/ egress and edge protection

• Plant/ equipment to be used

• Buried services • Adjacent structures• Supervision of work

Page 33: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Permanent v Temporary Works

• Permanent works engineer (PWE)– Responsible for designing the permanent or finished works

• Temporary works engineer (TWE)– Responsible for designing temporary works to enable

permanent works to be constructed

• Usually different people but can be the same person

• Poor contractors will not have made any provision for a temporary works engineer or think that the permanent works engineer does it all.

• The management of temporary works in the construction industry SIM (Sector Information Minute) 02/2010/04 – HSE Website

Page 34: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

New Build Basement Construction

• Easier if new build• Still need to batter back

or provide support

Page 35: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Don’t forget adjacent structures

Page 36: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Don’t forget adjacent structures

Unsupported clay face and risk of undermining adjacent structure

Boundary wall can slip or overturn

Unsupported clay face

Page 37: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Installing support after the event can be problematic and create new risks

Page 38: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Underpinning 1

Technique devised to treat subsidence now also used to form basements

Excavate belowexisting foundation

Form new pin or foundation

Heel can be designed out

Page 39: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Underpinning 2 – Schedule

Typical underpinning schedule drawn up by competent person

Page 40: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Contiguous Piles & Diaphragm Walls

Technique associated with larger projects and/or where there is space

Page 41: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Support for face of underpin section?

Page 42: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Should there be a requirement to support face of underpin section?

Need to consider sacrificial face support – usually steel sheet piles

Clay face starting to fail

Page 43: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Support of existing foundation

Underpinning – failure to survey existing wall and to prop

Page 44: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Unshored underpin excavations

• Common to find un-shored pits on site up to 4m deep

Page 45: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Shoring of pits is a must

• Need to plan support scheme and access issues• Can use timber or steel sheet piles

Page 46: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Deeper basements

3.5m-4.5m deep pins – risk of unsupported face collapsing?

Page 47: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Deeper basements

• The Gucci standard!

Page 48: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Low risk?

Page 49: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Middle mass

Page 50: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Innovative support systems emerging

Work in progress

Page 51: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Site findings

A selection of photographs taken by inspectors during site inspections showing typical working environments within a basement excavation.

Page 52: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Supporting existing structure above basement

Prohibition Notice served – evacuate site and property above - temp wks engineer came back with props at 200mm centres below main walls of house

Page 53: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Safe access/ egress

Lightwell could have been sheet piled/ timbered first to provide large access “pit”

Page 54: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Protection for the public

Page 55: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Safe place of work

Page 56: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Fail to plan – plan to fail

Page 57: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

End of terrace house – refurb + basement

Page 58: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

EOT starts to lean towards road

Page 59: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Emergency works by LA contractor

Page 60: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Putney collapse

Page 61: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Welfare

Page 62: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Welfare

Page 63: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Access

Page 64: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Access

Page 65: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Access

Page 66: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Access

Page 67: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Surcharging sides of excavation

Page 68: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Surcharging sides of excavation?

Page 69: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Water ingress

Page 70: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Conveyor belts

Page 71: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Work at height?

Page 72: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Electrics

Page 73: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Temporary props

Page 74: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

What are HSE doing about it?

• Inspections – lots of them

• Including annual 2 day concentrated inspection initiatives – most recent11/12 March 2015

• Kensington & Chelsea, Hammersmith & Fulham and Westminster – expanding.

• Intelligence gathering done by VO’s

• Recent proactive prosecutions

Page 75: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

What are HSE doing about it?

• Basement initiative headline stats:

• 127 sites visited over two days,136 contractors met.

• On average 1 in 2 sites received enforcement action (NoC, IN or PN) 

• On average 1 in 3 sites received a Notice (IN or PN).

• Main areas of enforcement were WAH, Excavation and Welfare.

• A couple of sites were shut due to management of H&S being so poor

• However…

Page 76: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Summary

• Some good news…!

• Evidence indicates that DH’s that HSE have visited in the past are showing signs of improvement

• Some of these noticeably so

• HSE working with industry on new guidance - ASUCplus

• Formation of industry associations

• DH’s met welcomed HSE intervention – want an even playing field.

Page 77: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Summary

• High Risk Work – needs careful planning before work starts on site

• Need Temporary works engineering input

• Method Statement should be in place, e.g. a clear method of how work is to be undertaken including shoring of excavations and support of existing or adjacent structures.

• Shoring material/ equipment is on site

• Competent site supervision

Page 78: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Excavator for sale - collection only!

Page 79: Building Basements Safely An overview of HSE’s approach to regulating basement excavations James Hickman HM INSPECTOR (CONSTRUCTION) ROSE COURT

Building Basements Safely

Open Forum and Q&A