BUFFALO CITY BUFFALO CITY METROPOLITAN MUNICIPALITYMETROPOLITAN MUNICIPALITY
Urban Settlement Development Grant (USDG)Urban Settlement Development Grant (USDG)
Portfolio Committee on Human SettlementsPortfolio Committee on Human Settlements
26 May 201526 May 2015
OVERVIEWOVERVIEW The preparation of the third quarter USDG performance
report is done in line with the grant framework as stipulated in the Division of Revenue Act for 2014 and section 71 of the Municipal Finance Management Act.
The USDG utilizes, as a Framework, the Built Environment Performance Plan(BEPP) that is consistent with the IDP and the SDBIP of Buffalo City Metropolitan Municipality (BCMM).
The presentation reflects what the City has achieved since the beginning of the 2014/2015 financial year.
It reflects the City’s USDG progress, measured against the IDP and the SDBIP service delivery targets for the financial year under review.
2
SOCIO-ECONOMIC
Area 2,515km²
Coastline 68 km
Population (Census 2011)
755 200
Age distribution • 27% between 20 & 34 years
• 35% is aged 19 or below
Gender 53 % Female47 % Male
Population distribution
75% of population within the urban core of the metro
Number of Households (Census 2011)
236 000
ACCESS TO SERVICES
Formal Households (Census 2011)
72%
Informal Households (Census 2011)
22.9%
Traditional Homes (Census 2011)
5.1%
Number of Informal Settlements
154 (Baseline 2011)
NUSP : 32 settlementsBCMM : 16 settlements
Unemployment (Census 2011)
35.2 % in BCMM37.4 % in EC 25 % in SA
Access to water (Census 2011)
91.6 %
Access to sanitation (Census 2011)
70%
Access to electricity (Census 2011)
76.7 %
Access to waste collection (Census 2011)
67.5 %
BCMM PROFILE BCMM PROFILE
MEDIUM TERM STRATEGIC MEDIUM TERM STRATEGIC FRAMEWORK (MTSF) RESPONSE FRAMEWORK (MTSF) RESPONSE
4
5
Programme Stand CostsAnnual Target
Annual Costs
5-Year Target Total Cost *
Upgrading of Informal
Settlements Programme
±R43,626 per site for basic services as per quantum
3796 R165,604,296 18 980 R828,021,480
MTEF BUDGET ALLOCATIONMTEF BUDGET ALLOCATION
Available Funding MTEF Allocation
2015/2016 Budget
2016/2017 Budget
2017/2018Budget
USDG (Capital) 679,784,100 715,222,100 758,942,100
HSDG (Capital) 94,400,000 106,300,000 65,000,000
TOTAL 774,184,100 821,522,100 823,942,100
* Required funding R 85,550,586 R161,198,070 R174,504,000
Note : DoRA USDG 2015/16 : R713 132 000 HSDG 2015/16 : R456 198 999 USDG 2016/17 : R748 370 000 HSDG 2016/17 : R839 800 000 USDG 2017/18 : R791 090 000 HSDG 2017/18 : R593 300 000
MTSF Priority
BCM National MTSF
Target for 5 years
Annual MTSF Target
2014/15 Delivered
2015/16 BEPP
2016/17 Annual MTSF Target
2017/18 Annual MTSF Target
2018/19 Annual MTSF Target
Deficit
Informal Settlements Upgrading
USDG (Services
only)
18 980 3 796
1 254 at 31
March 2015
Target 1 900
1 961 3 695 4 000 4 500 1028
2014/2015 USDG 2014/2015 USDG FINANCIAL PERFORMANCEFINANCIAL PERFORMANCE
7
8
Funding Source2014/2015
Budget
Own Funding 447 886 290
DoE (Integrated National Electrification Programme) 20 587 000
Department of Sports, Recreation, Arts and Culture c/o 2 686 285
Department of Economic Affairs and Tourism 199 168
Local Government, Traditional Affairs and Housing 188 726
Infrastructure Skills Development Grant 100 000
BCMET c/o 256 818
Leiden c/o 458 860
NDPG 5 000 000
USDG 639 024 500
HSDG 31 495 081
HSDG c/o 20 162 276
HSDG MPCC 700 000
Total Per Funding 1 168 745 004
CAPITAL BUDGET BREAKDOWN CAPITAL BUDGET BREAKDOWN
9
CAPITAL BUDGET BREAKDOWN CAPITAL BUDGET BREAKDOWN
Others : Grants e.g. LGTA, BCMET, DEDEAT, DSRAC etc.
USDG PER SERVICE USDG PER SERVICE As at 31 March 2015
10
11
SYNOPSISSYNOPSISFINANCIAL PERFORMANCEFINANCIAL PERFORMANCE
TOTAL USDG Expenditure Trend ~ YTD 31 March 2015
USDG EXPENDITURE TREND – QUARTER 3USDG EXPENDITURE TREND – QUARTER 3
13
PHOTOSPHOTOS
2015 / 2016 USDG2015 / 2016 USDG
14
15
2015/2016 Budget per Service2015/2016 Budget per Service
Note : Overall budget allocation (All funding sources)
16
Cemeteries upgraded and refurbished 3
Sport Fields (Mount Cokesports field, Phakamisa sports field, Dimbaza stadium, Zwelitsha stadium; Mzamomhle sports field, Nompumelelo sports field)
6
Nompumelelo Hall (construction only) and Egoli hall (PSP and design only) 2Halls ( NU1, NU7, NU10, NU12, NU15 Mdantsane halls, Billy francis hall, Robbie deLange hall, KWT town hall, Carnegie Hall, Brealyn Hall, Gcobani Hall.)
11
Seperation at source projects 12
Number of households with weekly kerb-side waste removal services in formal areas
1961
2015 / 2016 TARGETS 2015 / 2016 TARGETS
2015/2016 INDICATORSIndicator Baseline Target 2015/16
Number of sports fields upgraded 6 6
Number of public swimming pools redeveloped
2 2
Number of new cemeteries established
1 2
Number of cemeteries upgraded and refurbished
3 3
Number of community halls constructed
0 1(Nompumelelo Hall)
Number of community halls upgraded and refurbished
5 5
Number of new recreational parks established
10 10(Zwelitsha, Sweetwater,
Mzamomhle)
Indicator Baseline Target 2015/16
Number of informal settlements with upgrading plans
32 0
Number of land parcels acquired 2 2
Number of land parcels released 2 2
Number of hectares of land required for human settlement development
62,4ha 171,8ha
Number of top structures completed and allocated
1200
1700
Number of serviced sites completed (Informal settlements upgraded (service provided ): Relocated & In Situ)
1700 1961
Number of beneficiaries educated about home ownership
4500 4600
Number of beneficiaries registered for possible home ownership
3500 4000
Indicator Baseline Target 2015/16
Implementation of the Duncan Village Redevelopment Initiative Business Plan
DVRI Business Plan
Phase 1 completed
Number of highmast lights installed None
5 (Mzamomhle, Amalinda
Forest)Number of streetlights installed 350 100% households with access to a basic level of electricity (BCMM area of supply)
99% 99%
Kilometres of roads gravelled (resealed and paved roads)
100 km 150 km
Kilometres of roads surfaced
25 km 25 km
Kilometres of roads maintained 1200 km 1200 kmNumber of existing BCMM Bridges rehabilitated
1
Bridge refurbished
3
Bridges refurbishedkilometres of storm water drainage installed
20km 20km
Indicator Baseline Target 2015/16
% households with access to a basic level of electricity (BCMM area of supply)
99% 99%
Kilometres of roads gravelled (resealed and paved roads)
100 km 150 km
Kilometres of roads surfaced
25 km 25 km
Kilometres of roads maintained 1200 km 1200 km
Number of existing BCMM Bridges rehabilitated
1Bridge refurbished
3Bridges refurbished
kilometres of storm water drainage installed 20km 20km
Number of households with weekly kerb-side waste removal services in formal areas
143 000 157 300
Number of informal settlements with access to refuse removal
1700 1961
Indicator Baseline Target 2015/16
Number of additional households RDP with access to refuse removal
1500 1700
Number of jobs created through LED initiatives including implementation of capital projects
500 600
Number of jobs created using the Expanded Public Works Programme, Construction, Community Works Programme. guidelines and other municipal programmes
9900 9900
Indicator Baseline Target 2015/16
Number of consumer units provided with access to a free basic level of potable water, by means of an individual HH supply or in informal areas by means of a standpipe within 200m
950(200 komashini and 15 standpipes within
200m)
1500
% of households with access to basic level of water supply
99% (220 832)
99.4% (222 332)
Number of kilo litres reduced (physical water loss in terms of systems losses)
1 200 000kl 1 200 000kl
% of households with access to basic level of sanitation service
91% (203 598)
92% (205 598)
Indicator Baseline Target 2015/16
Number of formal domestic customers receiving sewerage services
160509 160709
Number of sanitation service points (toilets) installed for informal settlement dwellers
580 610
24
Project2015/2016
Budget
INTERNAL SERVICES - HOUSING
Reeston Phase 3 Stage 2 5,000,000
Reeston Phase 3 Stage 3 5,000,000
Potsdam Ikhwezi Block 1 8,900,000
Potsdam Ikhwezi Block 2 200,000
Potsdam North Kanana 200,000
Ilitha North 177 Units 4,000,000
Mdantsane Zone 18 CC Phase 2 8,500,000
Amalinda Co- Op 4,800,000
Amalinda Fairlands 300,000
Sunny South 100,000
Tyutyu Phase 3 500,000
Westbank Restitution 16,000,000
SUB TOTAL 53 500 000
2015 / 2016 USDG PROJECTS 2015 / 2016 USDG PROJECTS
25
Project2015/2016
Budget
INTERNAL SERVICES – INFORMAL SETTLEMENTS
Cluster 1 (Masibambane; Masibulele; Velwano; Ilinge and Dacawa)
25,000,000
Cluster 2 (Chris Hani 3; Winnie Mandela; Deluxolo Village; Sisulu Village; Francis Mei; Mahlangu Village, Mathemba Vuso, Gwentshe)
13,024,000
Cluster 3 (Fynbos Informal 1, Fynbos Informal 2, Ndancama)
25,350,000
SUB TOTAL 63 374 000
2015 / 2016 USDG PROJECTS 2015 / 2016 USDG PROJECTS
26
Project2015/2016
Budget
ENGINEERING SERVICES
Sanitation
Reeston WWTW 40 000 000
Berlin Reticulation 20 000 000
Gqozo Village 20 000 000
KWT Regional Waste Water Treatment 50 000 000
West Bank Restitution 20 000 000
Rural Sanitation 30 000 000
SUB TOTAL 190 000 000
2015 / 2016 USDG PROJECTS 2015 / 2016 USDG PROJECTS
27
Project2015/2016
Budget
ENGINEERING SERVICES
Water
West Bank Restitution - Water 8 000 000
KWT and Bisho Infrastructure (Water) 10 000 000
Amahleke Water Supply 3 000 000
Augmentation of Water Treatment Capacity 17 000 000
Upgrade Water Networks in terms of Densification and Augmentation 3 000 000
Water Supply Coastal Areas and backlog eradication 10 000 000
SUB TOTAL 51 000 000
2015 / 2016 USDG PROJECTS 2015 / 2016 USDG PROJECTS
28
Project2015/2016
Budget
Roads
Quenera Beacon Bay Link Road 20,000,000
Upgrading of Mdantsane Roads 60,000,000
KWT Roads 10,000,000
Gonubie Main Road 10,000,000
Fleet Street 50,000,000
RDP Roads - Inland, Midlands and Coastal 15,000,000
Rehabilitation of BCMM Bridges and Stormwater 5,000,000
Procurement of Graders for Rural Roads - Yellow Fleet 15,000,000
SUB TOTAL 185 000 000
2015 / 2016 USDG PROJECTS 2015 / 2016 USDG PROJECTS
29
Project2015/2016
Budget
Electricity
INEP Electrification Programme - Counterfunding 5,000,000
Electrification of Informal Dwelling Areas within BCMM 15,000,000
Street Lighting and High masts within BCMM Areas of Supply - Informal Settlements
3,500,000
Replacement and Refurbishment of Bulk ELECT Infrastructure 2,000,000
SUB TOTAL 25 500 000
SOCIAL AMENITIES
KWT Traffic Building 6,000,000
Development and Upgrading of Cemeteries (Inland, Midland and Coastal)
8,000,000
Development and Upgrading of Community Halls - War Memorial Hall - Upgrade of Parking Area, Egoli Community Hall (New Hall), Continuation of KWT Town Hall, 5 NU Halls Mdantsane and Carnegie Hall.
9,000,000
2015 / 2016 USDG PROJECTS 2015 / 2016 USDG PROJECTS
30
Project2015/2016
Budget
Construction of Nompumelelo Hall 5,000,000
Redevelopment of Mdantsane NU 2 Swimming Pool 7,500,000
Upgrading of Waterworld 5,000,000
Upgrading of Dimbaza and Zwelitsha Stadium 2,700,000
Upgrading of Floodlights at Victoria Grounds, Bhisho Stadium, Ginsberg stadium, Sisa Dukashe Stadium, Alfred Schoeman Stadium, North End Stadium, Jan Smuts Stadium, Amalinda Stadium, and Gompo Stadium
3,000,000
Fencing of Sports Fields 500,000
Upgrading of Phakamisa and Mount Coke Sports Fields 1,500,000
SUB TOTAL 48 200 000
2015 / 2016 USDG PROJECTS 2015 / 2016 USDG PROJECTS
31
Project2015/2016
Budget
SOLID WASTE
Waste Management Facilities Programme 1 000 000
Construction and Rehabilitation of Waste Cells 20 710 100
SUB TOTAL 21 710 100
Integrated Transport Plan Implementation Programme 30,000,000
Enabling Infrastructure Programme - LED 10,000,000
2015 / 2016 USDG PROJECTS 2015 / 2016 USDG PROJECTS
32
Capital Projects 2015/2016
Budget
Reeston Phase 3: Stage 2 15 000 000
Reeston Phase 3 Stage 3 30 000 000
Duncan Village Proper 20 000 000
C Section and Triangular Site 11 300 000
D Hostel 9 300 000
Braelyn ext 10 6 300 000
DVRI Infrastructure Programmes 2 500 000
TOTAL 94 400 000
Reeston MPCC - DVRI 13 068 500
2015 / 2016 HSDG PROJECTS 2015 / 2016 HSDG PROJECTS
33
Top Structures2015/2016
Budget
Reeston Phase 3: Stage 2 25 000 000
Reeston Phase 3 Stage 3 59 804 569
Ilitha Eradication of Wooden Houses to Formal Houses 380 294
Ilitha North - 177 Units 10 000 000
Reconstruction of Storm Damaged Houses 13 000 000
Sunny South 1 500 000
Potsdam Village Phase 1 & 2 34 000 000
Cluster 2 (Chris Hani 3; Winnie Mandela; Deluxolo Village; Sisulu Village; Francis Mei; Mahlangu Village, Mathemba Vuso, Gwentshe)
15 000 000
Cluster 3 (Fynbos 1; Fynbos 2; Ndancama, ) 100 861 424
Housing Needs Database and Acrreditation 10 818 705
Amalinda Fairlands P5 500 000
Amalinda Co - Op 4 000 000
Beneficiary Registration DVRI Projects (Reeston, Cambridge, DVRI Pilot, Braelyn ext 10, C Section and Triangular Site, D Hostel)
100 000
2015 / 2016 HSDG PROJECTS 2015 / 2016 HSDG PROJECTS
34
Top Structures2015/2016
Budget
Braelyn Ext 10 North - P5 10 000 000C Section and Triangular Site - P5 20 000 000D Hostel - P5 15 000 000Duncan Village Proper 0Mdantsane Zone 18CC - P5 15 000 000Potsdam Ikhwezi Block 1 - P5 20 000 000Potsdam Ikhwezi Block 2- P5 0Potsdam North Kanana - P5 0Dimbaza 110 -P 5 (Top Structure) 1 000 000Dimbaza Destitute 27 Units - P5 0Disaster Project - Tsholomnqa 7 500 000
Peelton Cluster (Majali, Mdange, Kwatrain, Nkqonqweni, Drayini & Esixekweni) - P5
28 000 000
Hanover - P5 15 000 000Skobeni - P5 15 000 000TOTAL 521 655 947
2015 / 2016 HSDG PROJECTS 2015 / 2016 HSDG PROJECTS
• Bursary Funds 2015 (30 students in scares skills categories)
• BCMM Notified Councillors & Top Management of the One learner One Agency launch at Eastern Cape Human Settlements Department (April 2015)
• As part of the Duncan Village De-densification Programme an Implementing Agent has been appointed and 30% has been set aside for small and emerging contractors and youth will surely benefit
35
2015 / 2016 YOUTH BRIGADE PLANS2015 / 2016 YOUTH BRIGADE PLANS
• Recently adopted Housing Allocation and Relocation Policies has included women and persons with special needs
• 2 of the 10 EPWP Learner contractors are women• Of the 8 appointed contractors for housing, 2 are women
contractors
36
2015 / 2016 WOMEN 2015 / 2016 WOMEN
37
2014 / 2015 WOMEN 2014 / 2015 WOMEN
Project Funding Source 2014/2015 Mid-Year
Adjustment
Infrastructure Skills Development Grant ISDG 5 400 000
ISDG
2014 / 20152014 / 2015
NON FINANCIAL PERFORMANCENON FINANCIAL PERFORMANCE
38
39
33rdrd QUARTER ACHIEVEMENTS QUARTER ACHIEVEMENTS
40
41
42
43
44
45Note : Targets not achieved in Q3 have progressed in Q4
MAJOR PROGRAMMESMAJOR PROGRAMMES
46
• Internal Services – Housing (23 Projects) – Reeston projects value R61,605,875 – Potsdam area project value R 1,500,000 – Mdantsane
• Mdantsane informal settlement upgrading projects value R60 951 775• Mdantsane Zone 18 CC Phase 2 R 5 000 000
– Duncan Village• DVRI Pilot Project (Mekeni, Haven Hills, Competition Site) R6 462 069• Duncan Village Proper R1 050 000• C Section and Triangular Site R1 470 420• D Hostel R1 300 000 • Block Yard TRA R6 149 071 • Braelyn ext 10 R618 812
– East London• Second Creek R3 647 208 • Amalinda Co- Op R1 020 000 • Cluster 3 (Fynbos Informal 1, Fynbos Informal 2, Ndancama) R23 025 000
– KWT & Surrounding Areas• Ilitha North 177 Units R 1 500 000
– Rural Projects• Sunny South project value R3 380 000
– Budget : R107,847, 873 and Total Expenditure at 65% at end of Quarter 3• Professional services appointed for designs• Most projects busy with implementation with Contractors and Implementation Agents on site
47
MAJOR PROGRAMMESMAJOR PROGRAMMES
• Bulk Water Programme– KWT and Bisho Infrastructure (Bulk) ; Amahleke Water Supply ; Upgrade
Water Networks in terms of Densification and Augmentation ; Water Supply Coastal Areas and backlog eradication
– Budget allocation R53,926,245 with 43% expenditure at the end of Quarter 3
• Sanitation Programme– Ablution Blocks/Chemical Toilets ; Hoodpoint Marine Outfall ; West Bank
Restitution ; Sludge Handling Facility
– Eastern Beach Sewers ; Rural Sanitation Backlog Programme i.e. Gqozo Village Phase 2
– Quinera Treatment Works ; Reeston Phase 3 Bulk Services Sewer ; Zwelitsha Waste Water Treatment Capacity
– Budget allocation R160 081 647 with 51% expenditure at the end of Quarter 3
48
MAJOR PROGRAMMESMAJOR PROGRAMMES
• Roads– Surfacing of Mdantsane Roads ; RDP Houses - Roads Refurbishment Programme– projects roads – Construction, upgrading of key (strategic) access roads as per IDP and BEPP e.g.
Quenera link road, Gonubie Main road, Fleet Street– Upgrading of rural access roads ; Stormwater management ; Rehabilitation of
bridges– Budget allocation R207,199,000 with 84% expenditure at the end of Quarter 3
• Electricity– Electrification of informal settlements and the provision of street lights– Counter funding for INEP– Budget allocation R18 500 000 with 62% expenditure at the end of Quarter 3
49
MAJOR PROGRAMMESMAJOR PROGRAMMES
• Integrated Transport Planning – Provision of traffic calming measures, sidewalks, traffic signals, bus embayment's,
guardrails and design of bridges (pedestrian & vehicular)– Budget allocation R24,450,000 with 57% expenditure at the end of Quarter 3
• Social Amenities– Provision of communitiy facilities (new and/or upgrading) such as halls, parks,
cemeteries, sport fields etc. – Budget allocation R23 064 949 with 18% expenditure at the end of Quarter 3
• Waste Management – Regional waste site development – Procurement process completed and to contractor to move onto site– Budget allocation R11,000,000 with 0% expenditure at the end of Quarter 3
50
MAJOR PROGRAMMESMAJOR PROGRAMMES
Name of Informal
SettlementService
Provided
No of Households benefitted
Annual Target
2014/2015
Actual Progress
1 July 2014 to 31 March 2015
Budget Expenditure
CLUSTER 1 Masibambane;
Masibulele; Velwano; Ilinge and
Dacawa
Internal Services
MdantsaneH/H : 1459
1459 132 27 166 93027 166 930
(103%)
CLUSTER 2Chris Hani 3; Winnie Mandela; Deluxolo
Village; Sisulu Village; Francis Mei; Mahlangu Village, Mathemba Vuso,
Gwentshe
Internal Services
MdantsaneH/H :908
908 11 553 2224 770 193
(41%)
CLUSTER 3Fynbos 1; Fynbos 2; Ndancama
Internal Services
Fynbos, Ndancama,
Scenery ParkH/H : 1397
100
Contract is on site delayed
with removal of illegal
occupants
20 018 64220 018 642
(87%)
51
INFORMAL SETTLEMENTSINFORMAL SETTLEMENTS
Name of Informal
SettlementService
Provided
No of Households benefitted
Annual Target
2014/2015
Actual Progress
1 July 2014 to 31 March 2015
Budget Expenditure
DVRI Pilot Project
Internal Services
Duncan Village
H/H : 323
323 121 775 000878 114(113%)
Block Yard TRAInternal Services
124 124 0 5 540 28684 375(2%)
Duncan Village & Mdantsane Zone
1 & 3Electrification 700 486 10 000 000
6 703 290(67%)
52
INFORMAL SETTLEMENTSINFORMAL SETTLEMENTS
53
NameRoads, Walk
ways & Storm Water
Sanitation WaterSolid Waste
Elect.Comm.
HallPlay Area Total
Mbekweni 442,331 71,907 92,577 15,000 477,000 __ __ 1,098,816
Scenery Park – Airport
159 730 42 434 41 434 15 000 351 000 __ __ 609 598
Amalinda Forest
6,114,834 2,824,822 1,022,464 105,000 10,656,000 750,000 200,000 21,673,120
Andrew Mlangeni
344,855 247,821 58,980 15,000 801,000 __ 100,000 1,567,657
Barcelona 204,783 177,574 51,780 15,000 333,000 __ __ 782,137
Dacawa 1,662,475 428,352 217,095 15,000 2,277,000 __ __ 4,599,923
Eskom 270,313 520,138 269,568 45,000 711,000 __ 100,000 1,916,020
Gesini 270,313 129,831 25,079 45,000 1,665,000 __ 100,000 2,235,224
Holomisa 679,880 110,341 82,118 15,000 1,080,000 __ __ 1,967,340
Khayalethu 720,837 247,553 113,977 15,000 1,350,000 __ __ 2,447,368
Ladies Park 122,869 66,931 25,753 30,000 369,000 __ __ 614,555
Lonwabo 188,400 50,434 28,370 30,000 279,000 __ __ 576,205
Mahlangu 0.00 133,710 114,986 30,000 1,926,000 __ 100,000 2,304,696
Manto 355,210 183,297 98,171 15,000 864,000 __ 100,000 1,615,679
NUSP ~ INFORMAL SETTLEMENTSNUSP ~ INFORMAL SETTLEMENTS
54
Name
Roads, Walk
ways & StormW
ater
Sanitation
WaterSolid Waste
Elect.Peds. Bridge
Consv Tank
Comm Hall
Play Area
Total
Mark Makalima
110,582 116,870 69,252 30,000 360,000 __ __ __ __ 686,706
Masibambane 153,124 126,122 66,197 15,000 315,000 __ __ __ __ 675,444
Cambridge 1,844,284 1,028,820 530,580 30,000 12,069,000 150,000 300,000 750,000 100,000 16,802,685
Daluxolo 573,227 602,038 266,028 30,000 999,000 __ 150,000 __ 100,000 2,720,294
Ekuphumleni 119,895 358,252 200,310 30,000 882,000 __ 150,000 __ __ 1,740,458
Reeston Jevon
549,402 158,393 135,766 30,000 1,035,000 __ __ 750,000 100,000 2,758,562
Eluxolweni 679,880 782,216 287,951 0.00 6,309,000 150,000 __ 750,000 200,000 9,159,049
TOTAL 15,567,234 8,407,856 3,798,436 570,000 45,108,000 300,000 600,000 3,000,000 1,200,000 78,551,526
NUSP ~ INFORMAL SETTLEMENTSNUSP ~ INFORMAL SETTLEMENTS
Project NameAnnual Target
2014/15
Number of title deeds issued1 July 2014 to 31 March 2015
Budget Expenditure
Reeston Phase 1 & 2 (4264)
420 201 0 0
Reeston 3 Phase 1(796)
420 333 0 0
Reeston 3 Phase 2(2500)
420 875 480 000 283 841
55
TITLE DEEDSTITLE DEEDS
ProjectNumber of Title Deeds
issued
Outstanding No of Title Deeds and in
process of transfer
Comments
Zwelitsha N/A 10Sub-division and new erf numbers allocated
State Land
Phakamisa 986 17Rectification / State land.
Land was not registered due ot subdivision
Dimbaza 1985 15Sharing houses challenges .
Houses were built on State Land
Ginsberg 393 43 Pre-1994. Rectification and State land
Buffalo Flats 687 14 Pre-1994
Buffalo Flats Ext 2-6
2086 150 Pre-1994
Charles Lloyd 234 10 Pre-1994
Parkridge 242 57 Pre-1994
Gompo 1021 108 Rectification and State land
Dunga 6 Sub-division Challenges
Ilitha South 820 103 Sharing units not sub-divided
Total 8 454 533
56
TITLE DEEDS – Pre-1994 Housing StockTITLE DEEDS – Pre-1994 Housing Stock
Project
Initial number of housing
units
Number of transfers in progress
(With Conveyancers)
Number of Title Deeds ready for hand-over
Number of Title Deeds
issued
Outstanding Balance
Alphendale 339 Project managed by Province 13
Amalinda Simanyane 93 23 70 0 23
Airport Phase 1 838 0 52 786 0
Airport Phase 2 195 0 55 140 0
Airport Phase 2A 612 0 0 0 612
Reeston 1 & 2 4264 409 2191 1664
Reeston Phase 3, Stage 1 796 333 0 463
Reeston Phase 3, Stage 2 2500 875 0 1625
Potsdam 500 381 0 119
57
TITLE DEEDS – Post 1994 Housing StockTITLE DEEDS – Post 1994 Housing Stock
Project
Initial number of housing
units
Number of transfers in progress
(With Conveyancers)
Number of Title Deeds ready for hand-over
Number of Title Deeds
issued
Outstanding Balance
Brealynn 646 Project managed by Province 8 638
Duncan Village 352 Project managed by Province 142
Cambridge Phase 3 198 Project managed by Province 50
Mdantsane Q/16 & 17 Project managed by Province 73
Mzamomhle 548 Project managed by Province 104
Total 11 881 23 2 175 3 117 5 384
58
TITLE DEEDS – Post 1994 Housing StockTITLE DEEDS – Post 1994 Housing Stock
Note : Illegal Occupants ; Unregistered State Land ; Disqualified beneficiaries occupying houses ; Illegal sale of RDP houses ; Dispute among beneficiaries ; Deceased estates ; Sharing houses
Project / Issue Challenge Remedial Measures
Dimbaza Destitute (27 Units)
Project delayed by community claiming that land belongs to Amahleke Traditional Authority.
Matter was referred to MEC for Local COGTA to assist
Reeston Phase 3 Bulk Services Sewer
Mechanical and Electrical contract awarded but another bidder appealed the award to the preferred bidder.
Legal process to be concluded.
Waste Water Infrastructure Capacity (KWT Regional Scheme)
Mechanical and Electrical contract awarded but another bidder appealed the award to the preferred bidder.
Legal process to be concluded.
Well Located land
Suitable and well located land for human settlement development due to ownership, topography and availability of services.
Bulk infrastructure programme ; HDA to access land from state
59
CHALLENGES & REMEDIAL MEASURESCHALLENGES & REMEDIAL MEASURES
LINK BETWEEN USDG & HSDGLINK BETWEEN USDG & HSDG
60
• USDG is used for the construction critical bulk infrastructure and the provision of internal services linked to approved housing projects
• HSDG is used for the construction of top structures on serviced sites as prepared by the USDG.
61
LINK BETWEEN USDG & HSDGLINK BETWEEN USDG & HSDG
USDG – Housing Internal Services 2014/2015 HSDG – Top Structure 2014/2015
Reeston Phase 3 Stage 2 3 183 604 Reeston Phase 3: Stage 2 7 912 256
Reeston Phase 3 Stage 3 17 500 000 Reeston Phase 3 Stage 3 48 670 718
Mdantsane Zone 18 CC Phase 2 5 000 000 Mdantsane Zone 18 CC Ph. 2 2 605 995
Block Yard TRA 5 540 286 __
DVRI Pilot Project (Mekeni, Haven Hills, Competition Site)
775 000 DVRI Pilot Project (Mekeni, Haven Hills, Competition Site)
12 622 540
Sunny South 3 380 000 Sunny South 29 396 848
Second Creek (Turn Key) 3 647 208 Second Creek (Turn Key) 3 374 275
Amalinda Co- Op 1 020 000 Amalinda Co- Op 500 000
62
LINK BETWEEN USDG & HSDGLINK BETWEEN USDG & HSDG
USDG – Housing Internal Services
2014/2015 HSDG – Top Structure
2014/2015
Cluster 1 (Chris Hani, Ilinge, Mahlangu Village, Sisulu Village, Winnie Mandela, Deluxolo Village & Francis Mei)
26 373 553
Cluster 1 (Chris Hani, Ilinge, Mahlangu Village, Sisulu Village, Winnie Mandela, Deluxolo Village & Francis Mei)
38 008 316
Cluster 2 (Masibambane, Masibulele, Velwano, Gwentshe Village, Mathemba Vuso)
11 553 222
Cluster 2 (Masibambane, Masibulele, Velwano, Gwentshe Village, Mathemba Vuso)
4 000 000
Cluster 3 (Fynbos Informal 1, Fynbos Informal 2, Ndancama)
23 025 000Cluster 3 (Fynbos Informal 1, Fynbos Informal 2, Ndancama)
10 300 000
Potsdam Ikhwezi Block 1 & 2 1 000 000 Potsdam Ikhwezi Block 1 & 2 0
Potsdam North Kanana 500 000 __
Potsdam Village 853 100 Potsdam Village 2 300 000
63
LINK BETWEEN USDG & HSDGLINK BETWEEN USDG & HSDG
USDG – Housing Internal Services 2013/2014
HSDG – Top Structure
2013/2014
__Ilitha - Eradication of Wooden Houses to Formal Houses
8 297 433
Ilitha North 177 Units 1 500 000 __
Amalinda Fairlands 300 000 __
__ Tyutyu Phase 2 100 Units 5 000 000
__ Dimbaza 110 Units 1 693 635
Hanover & Skobeni 300 000 Hanover & Skobeni
Peelton Cluster 1 000 599 Peelton Cluster 4 109 500
• BCMM made own funds available for the repair and maintenance of infrastructure for MTREF period– Water : R120m– Sanitation : R120m– Electricity : R150m
– Roads : R160m • Improvement / upscaling of technical capacity through
professionalisation of exisitng staff (SETA 3 programme)• ISDG programme for Interns (Electrical Engineering, Civil
Engineering, Valuations, GIS) • Targeted Spatial Development as per Urban Network Strategy and
BEPP Guidance notes ~ ICDG• Municipal Human Settlement Capacity Grant – Business Plan
submitted to support Mega Project from 2015/201664
SUSTAINABILITYSUSTAINABILITY
THANK YOU THANK YOU
65
ANNEXUREANNEXURE
DETAILED PROJECT PROGESSDETAILED PROJECT PROGESS
66
Project NameAreas &
benefittingNon-Financial Progress for
the 3rd QuarterTotal
BudgetExpenditure March 2015
% Expenditure
(Incl VAT)
HOUSING : INTERNAL SERVICES
Mdantsane Zone 18 CC
Phase 2Mdantsane
Contractor appointed, site establishment commenced in
January 20155 000 000 955 009 19%
Reeston Phase 3 Stage 2
Reeston & EL
Implementing agent is busy with site establishment for
first phase of the project (the upgrading of internal roads
from gravel to surfaced roads)
3 183 604 209 309 7%
Reeston Phase 3 Stage 3
Reeston & ELContractor on site and
progress very well. 17 500 000 7 137 457 41%
Block Yard TRA Duncan Village
The contractor to go back to site to proceed with the
works of internal engineering services.
5 540 286 84 375 2%
Second Creek Second Creek
The project is completed. The project is now in liability
period for 12 months, i.e. August 2015.
3 647 208 2 451 100 67%
67
Project Name
Areas &No of
Households benefitting
Non-Financial Progress for the 3rd Quarter
Total BudgetExpenditure March 2015
% Expenditure (Incl VAT)
DVRI Pilot Project Duncan Village
No H/H : 328
Contractor is on site progressing with
construction of internal services.
775 000 878 114 113%
Cluster 1 (Masibambane;
Masibulele; Velwano; Ilinge and Dacawa)
MdantsaneNo H/H : 1459
Contractor is on site progressing with
construction of internal services
26 373 553 27 166 930 103%
Cluster 2 (Chris Hani 3; Winnie Mandela;
Deluxolo Village; Sisulu Village; Francis Mei; Mahlangu Village, Mathemba Vuso,
Gwentshe)
MdantsaneNo H/H : 908
Contractor is on site, progressing with
installation of internal services.
11 553 222 4 770 193 41%
Cluster 3 (Fynbos Informal 1, Fynbos
Informal 2, Ndancama)
Fynbos, Ndancama,
Scenery ParkNo H/H : 1397
Contractor is on site, progressing with
installation of internal services.
23 025 000 20 018 642 87%
68
Project Name
Areas &No of
Households benefitting
Non-Financial Progress for the 3rd Quarter
Total Budget
Expenditure March 2015
% Expenditure (Incl VAT)
Sunny South Sunny SouthNo
H/H : 526
Contractor on site, the project will be completed in
April 2015.3 380 000 3 526 964 104%
Potsdam Ikhwezi Block 1 & 2
Potsdam & MdantsaneNo
H/H : 1531
Project on design stage. Consultants are busy with preliminary designs and
geotechnical study
1 000 000 403 357 40%
Potsdam North Kanana
Potsdam & MdantsaneNo H/ : 928
Project is at design stage. 500 000 0 0%
Ilitha North 177 Units
IlithaNo H/H : 177
The installation of services Annual contractors will be utilised to speedup work.
1 500 000 62 745 4%
West Bank Restitution
West Bank Restitution
Beneficiaries
Project on bulk implementation stage.
Budget reduced in Mid-Year Budget Adjustment
0 343 154 0%
69
Project Name
Areas &No of
Households benefitting
Non-Financial Progress for the 3rd
QuarterTotal Budget
Expenditure March 2015
% Expenditure
(Incl VAT)
Potsdam VillagePotsdam Village
HH 1617Project is at planning &
design stage853 100 738 514 87%
Amalinda Co-Op
Amalinda & ELNo H/H : 100
Project on design stage. 1 020 000 463 413 45%
Amalinda Fairlands
Amalinda & EL Project is at planning & design stage.
300 000 0 0%
Peelton Cluster (Majali, Mdange,
Kwatrain, Nkqonqweni,
Drayini & Esixekweni)
Peelton – Rural settlements
Project is at planning & design stage.
1 000 599 54 900 5%
70
Project Name
Areas &No of
Households benefitting
Non-Financial Progress for the 3rd
QuarterTotal Budget
Expenditure March 2015
% Expenditure
(Incl VAT)
Beneficiary Registration
BCMM
In most of these projects registration is ongoing and awaiting for more
approvals from Province.
KWT is slow due registration is slow
because of tittle deed issues.
In Potsdam Villages, Beneficiary Unit is busy conducting verification. Mdantsane Cluster 1 &
2, Amalinda Co-op registration is ongoing.
Budget has been adjusted.
1 275 508 890 449 70%
71
Project Name
Areas &No of
Households benefitting
Non-Financial Progress for the 3rd Quarter
Total BudgetExpenditure March 2015
% Expenditure (Incl VAT)
ROADS
Gonubie Main Road
Gonubie
Work progressing well, though minor delays due to
weather. Additional funding will be required for completion of
the project
19 689 137 22 296 244 113%
Fleet StreetBCMM ; Quigney
Multi Year ProgrammeAnnual Contractor
completing the current phase of the project
20 463 013 12 527 079 61%
Quinera Arterial Road
QuineraWork is progressing on site and no delays are expected
as yet.33 325 132 20 030 959 60%
Upgrading of Mdantsane
RoadsMdantsane
Multi Year ProgrammeWork progressing and
expenditure to reflect by November 2014
85 063 757 91 090 403 107%
72
Project Name
Areas &No of
Households benefitting
Non-Financial Progress for the 3rd Quarter
Total Budget
Expenditure March 2015
% Expenditure (Incl VAT)
Rehabilitation of BCMM Bridges
BCMMProject progressing well. Settlers Pedestrian Bridge
repaired8 000 000 5 168 910 65%
RDP Houses - Roads
Refurbishment Programme
Wards 5, 24,46RDP Housing projects
progressing well. 4 431 601 3 609 076 81%
Rehabilitation of Rural Roads
Wards 14, 17, 13, 25, 26, 35, 36, 37, 39, 40,
44, 45, 49
Multi Year ProgrammeWork ongoing
15 445 804 17 516 642 113%
Graders for Rural Roads
BCMMProcurement of plant
commenced. 10 000 000 0 0%
Urban Roads - Programme
BCMM Multi Year Programme
Work ongoing1 581 556 914 318 58%
73
Project NameAreas & No of Households benefitting
Non-Financial Progress for the 3rd Quarter
Total BudgetExpenditure March 2015
% Expenditure (Incl VAT)
WATER
West Bank Restitution
West BankNo Households :
5,073
Multi Year Programme Project progressing.
5 000 000 4 271 117 85%
Bulk Water Provision
Programme
Project details below
See projects below 48 926 245 19 076 228 39%
Project 1 : Augmentation of Water Treatment
Capacity
1-25 and 28, 29, 30, 31&33
No H/H :161 630
Installation of pump manifolds are currently
underway at Buffalo River Pump Station
Designs for further phases have been completed.
Project 2 : Water Supply Coastal
Areas and backlog eradication
27, 31, 33No H/H : 4 236
Komanishini water supply project near completion.
Contractor for the installation of bulk water mains in Ward
31 villages appointed.
74
Project NameAreas & No of Households benefitting
Non-Financial Progress for the 3rd Quarter
Total BudgetExpenditure March 2015
% Expenditure (Incl VAT)
WATER
Project 3 : KWT and Bisho
Infrastructure (Water)
Ward No: 34, 37, 38, 39, 40, 41, 43,
44, 49, 35,No H/H : 64 270
The design and implementation of new water
treatment works for Bisho/KWT areas is
finalised.Augmentation of
Bonke/Kwalini rising main is under construction.
Project 4 : Amahleke Water
Supply
Ward No: 36No H/H : 3 974
Professional service provider is on site for the provision of
Amahleke regional bulk storage. Preliminary design
report submitted.
Project 5 : Upgrade Water
Networks in terms of Densification
and Augmentation
All BCMM rural wards
No H/H : 42 605
PSP for the provision of intermediate levels of services in rural areas
appointed.
75
Project Name
Areas &No of
Households benefitting
Non-Financial Progress for the 3rd Quarter
Total Budget
Expenditure March 2015
% Expenditure (Incl VAT)
SANITATION
Rural Sanitation Backlog
Programme
Rural settlements
Multi Year Programme5 projects ongoing with rural sanitation provision
40 000 000 18 103 406 45%
Bulk Sanitation Provision
BCMM Multi Year ProgrammeProjects ongoing with
annual contractor 494 051 568 399 115%
Gqozo Village Phase 2
Gqozo VillageProcurement process in
advanced stages5 000 000 0 0%
Eastern Beach Sewers
Eastern Beach Project completed. 1 056 888 1 056 888 100%
Sludge Handling & Chlorination
FacilitiesMdantsane
Multi Year ProgrammeProject progressing.
1 729 909 206 162 12%
76
Project Name
Areas &No of
Households benefitting
Non-Financial Progress for the 3rd
Quarter
Total Budget
Expenditure March 2015
% Expenditure (Incl VAT)
Mdantsane Infrastructure – Refurbishment / Augmentation
MdantsaneMulti Year ProgrammeWork progressing on
site20 000 000 13 801 426 69%
Diversion of Amalinda &
Wilsonia effluent to Reeston
Amalinda & Wilsonia
Phase 1A complete. Design for phase 2
completed for Tunnel option. Require funds to proceed to tender
phase of project.
1 017 458 1 146 291 113%
West Bank Restitution Sewer
InfrastructureWest Bank
Annual contractor to undertake
implementation10 000 000 25 319 0%
Quinera Treatment Works
Quinera – Mzamomhle &
Gonubie
Commissioning of works.
8 164 292 3 320 474 41%
Ablution BlocksInformal
Settlements
Multi Year ProgrammeAnnual contractor has been appointed and is implementing project
3 949 029 2 705 431 69%
77
Project Name
Areas &No of
Households benefitting
Non-Financial Progress for the 3rd Quarter
Total Budget
Expenditure March 2015
% Expenditure (Incl VAT)
Berlin sewers BerlinProject progressing
on-site5 029 611 3 717 637 74%
Hoodpoint Marine Outfall
East LondonConsultant appointed for the assessemnt of the building at Hoodpoint.
505 949 391 823 77%
Reeston Phase 3 Bulk Services
SewerReeston
Multi Year ProgrammeCivil work progressing. Mechanical & Electrical Works contract awarded but bidder appealed the
award to preferred bidder
50 000 000 27 575 305 55%
Waste Water Infrastructure
Capacity (KWT Regional Scheme)
Bhisho, KWT & Zwelitsha
Multi Year ProgrammeMechanical and Electrical Contract Awarded. Civil Works contract awarded but bidder appealed the
award to preferred bidder.
12 857 892 8 369 122 65%
78
Project NameAreas &
No of Households benefitting
Non-Financial Progress for the 3rd
Quarter
Total Budget
Expenditure March 2015
% Expenditure (Incl VAT)
ELECTRICITY
INEP Electrification Programme –
Counter funding
RDP Housing in Potsdam Unit P
Reticulation of Potsdam Unit P.
Procurement stage5 000 000 3 031 095 61%
Street & High Mast Lighting within
BCMM Areas of Supply – Informal
Settlements
BCMMMulti Year ProgrammeBreidbach, Gonubie /
Mzamomhle3 500 000 1 710 454 49%
Electrification of Informal Dwelling
Areas within BCMM
Duncan Village & Ilitha, Braelynn,
Mt Ruth
Electrification of Duncan Village,
Mdantsane Zone 1 & 3, Phakamisa
10 000 000 6 703 290 67%
79
Project Name
Areas &No of
Households benefitting
Non-Financial Progress for the 3rd Quarter
Total Budget
Expenditure March 2015
% Expenditure
(Incl VAT)
TRANSPORT PLANNING
Integrated Transport Plan Implementation
BCMM
Traffic calming measures have been completed in Beacon Bay, Cambridge, Braelyn, Duncan Village, Amalinda, Sweetwaters, KWT CBD, Willow Park,
Zwelitsha, Mzamomhle and Sunnyridge.
24,450,000 16 208 744 57%
Sidewalks have been completed in Phakamisa, Mdantsane and Potsdam. The sidewalks in Scenery
park are nearing completion.
Traffic signals have been identified on NEX, Robbie de
Lange, Potters Pass and Gullsway however only
Robbie De Lange will be implemented due to the un-
availabilty of cable. 80
Project Name
Areas &No of
Households benefitting
Non-Financial Progress for the 3rd Quarter
Total BudgetExpenditure March 2015
% Expenditure
(Incl VAT)
Integrated Transport Plan Implementation
Guidance signs are at manufacturing stage,
awaiting delivery
24 450 000 16 208 744 57%
Construction of Taxi/Bus embayments in Scenery
Park, Cambridge and Mdantsane is in progress.
Amalinda, Ginsberg, Dimbaza embayments and Bonza Bay Main Road taxi
rank construction is progressing well.
Bus Embayments in
Cambridge and Mdantsane NU8 has been completed.
81
Project Name
Areas &No of
Households benefitting
Non-Financial Progress for the 3rd Quarter
Total BudgetExpenditure March 2015
% Expenditure
(Incl VAT)
TRANSPORT PLANNING
Integrated Transport Plan Implementation
Guardrails Guardrails have been identified and installed
in Mdantsane, Braelynn, Zwelitsha and Phakamisa.
24,450,000 16 208 744 57%Needs Camp / Potsdam detailed designs stage. KwaTshatshu Bridge
detailed design stage has commenced
82
Project Name
Areas &No of
Households benefitting
Non-Financial Progress for the 3rd Quarter
Total BudgetExpenditure March 2015
% Expenditure
(Incl VAT)
SOCIAL AMENITIES
Upgrade of KWT Payments Hall
KWT & Surrounding
Areas
Service provider has been appointed. Designs and specifications are now
underway.
550 000 0 0%
Development of Community Parks
BCMM
Manufacturing of playground equipment. Awaiting delivery and
installation. Installation of palisade fencing to
commence.
3 685 051 209 123 6%
Development and Upgrading of Cemeteries
Fort Jackson, Nu 15 & KWT
Upgrading of cemetery road infrastructure.
10 000 000 3 521 345 35%
Construction of Nompumelelo Halls
Nompumelelo
Project under procurement for second time. First
tender cancelled. Budget reduced during mid-year
budget adjustment.
3 500 000 12 160 0%
Development and Upgrading of
Community Halls
Needs Camp & KWT & Zwelitsha
Surfacing commenced at OR Tambo Hall & KWT
War Memorial Hall & Cambridge Hall. Needs
Camp hall is 90% complete.
6 500 000 2 971 445 46%83
Project Name
Areas &No of
Households benefitting
Non-Financial Progress for the 3rd Quarter
Total BudgetExpenditure March 2015
% Expenditure (Incl VAT)
Redevelopment of Mdantsane Nu2
Swimming pool & Upgrading of Waterworld
Mdantsane & East London Surrounding
Areas.
In Procurement Process for consultant services
5,500,000 4 849 0%
Upgrading of stadium
Dimbaza & Zwelithsa
Contractors on site and work to commence.
2,250,000 0 0%
Upgrading of floodlights
East London & Mdantsane
Work at Jan Smuts, North End, Selborne Tennis, Bunkers Hill,
Buffalo City Stadium and Sisa Dukashe completed
1 314 949 1 120 326 85%
KWT Traffic Building
KWT & Surrounding Areas
Service provider being professional planning
team has been appointed. Draft plans
being prepared based on requirements of clients.
2 069 735 0 0%
84
Project Name
Areas &No of
Households benefitting
Non-Financial Progress for the 3rd
QuarterTotal Budget
Expenditure March 2015
% Expenditure (Incl VAT)
Upgrading of Phakamisa and
Mount Coke sports fields
Phakamisa & Mount Coke
Project Implementation ongoing
1 000 000 902 952 90%
Enabling Infrastructure
Programme – LEDUpgrade of Market
BCMMAwaiting invoices for equipment ordered.
10 000 000 1 280 631 13%
Upgrading of Aquarium
BCMM
Appointment of a professional Service
Provider for the urgent remedial work on the aquarium finalised.
1 000 000 0 0%
85
Project Name
Areas &No of
Households benefitting
Non-Financial Progress for the
3rd QuarterTotal Budget
Expenditure March 2015
% Expenditure (Incl VAT)
WASTE MANAGEMENT
KWT Tannery Site
KWTIn Procurement
process1 000 000 0 0%
Construction and
Rehabilitation of Waste Cells
East London & Mdantsane
Procurement process completed – site establishment
commenced
10 000 000 0 0%
LAND ACQUISITION
Land acquisition BCMM
Land parcels acquired and the remaining land
parcels still under procurement.
5 500 000 3 109 663 57%
86