Upload
bladimir-fuentes-molina
View
161
Download
5
Tags:
Embed Size (px)
Citation preview
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual Contents
Issue 01 (2006-09-06) Huawei Technologies Proprietary i
Contents
1 Overview of the Hardware Installation.................................................................................1-1
1.1 BTS3012AE Hardware Structure ..................................................................................................................1-2
1.1.1 Schematic Drawing of Hardware Structure..........................................................................................1-2
1.1.2 BTS3012AE Cabinet............................................................................................................................1-3
1.1.3 Base....................................................................................................................................................1-10
1.1.4 Introduction to the Cables ..................................................................................................................1-10
1.2 Installation Process......................................................................................................................................1-13
1.2.1 Hardware Installation Flow Chart ......................................................................................................1-13
1.2.2 Installation Process Description.........................................................................................................1-14
2 Installation Preparations ..........................................................................................................2-1
2.1 Preparing Technical Documents....................................................................................................................2-2
2.2 Preparing Mounting Tools and Instruments ..................................................................................................2-2
2.3 Checking Installation Conditions ..................................................................................................................2-3
2.3.1 Load-Bearing Capacity Requirements .................................................................................................2-4
2.3.2 Grounding Status Requirements...........................................................................................................2-4
2.4 Unpacking and Inspecting.............................................................................................................................2-4
2.4.1 Requirements for Unpacking ...............................................................................................................2-4
2.4.2 Unpacking the Wooden Case ...............................................................................................................2-5
2.4.3 Inspecting Items Inside the Wooden Case............................................................................................2-7
2.4.4 Unpacking the Carton ..........................................................................................................................2-8
2.4.5 Inspecting Items Inside the Carton.......................................................................................................2-9
3 Installing the BTS3012AE Cabinet .........................................................................................3-1
3.1 Installing a Cabinet on the Cement Floor with Sufficient Bearing Capacity (ƒ 800 kg/m2) .........................3-2
3.1.1 Installation Flowchart ..........................................................................................................................3-2
3.1.2 Positioning the Cabinet ........................................................................................................................3-3
3.1.3 Casting the Cement Plinth....................................................................................................................3-4
3.1.4 Positioning the Base.............................................................................................................................3-5
3.1.5 Drilling Holes and Installing Expansion Bolts.....................................................................................3-7
3.1.6 Fastening the Base ...............................................................................................................................3-9
3.1.7 Leveling the Base.................................................................................................................................3-9
3.1.8 Placing the Cabinet ............................................................................................................................3-10
Contents
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
ii Huawei Technologies Proprietary Issue 01 (2006-09-06)
3.1.9 Fastening the Cabinet.........................................................................................................................3-12
3.1.10 Leveling the Cabinet ........................................................................................................................3-16
3.1.11 Removing Lifting Lugs ....................................................................................................................3-17
3.1.12 Illustration of the Installed Cabinet..................................................................................................3-18
3.2 Installing a Cabinet on the Cement Floor with Insufficient Bearing Capacity (< 800 kg/m2).....................3-18
3.2.1 Installation Flowchart ........................................................................................................................3-18
3.2.2 Installation Process ............................................................................................................................3-20
3.2.3 Positioning the Cabinet ......................................................................................................................3-20
3.2.4 Casting Cement Plinths......................................................................................................................3-20
3.2.5 Preparing U-Bar Supports ..................................................................................................................3-21
3.2.6 Positioning U-Bar Supports ...............................................................................................................3-21
3.2.7 Drilling Holes and Installing Expansion Bolts...................................................................................3-21
3.2.8 Fastening U-Bar Supports ..................................................................................................................3-21
3.2.9 Leveling U-Bar Supports ...................................................................................................................3-22
3.2.10 Fastening the Base ...........................................................................................................................3-23
3.2.11 Leveling the Base.............................................................................................................................3-23
3.2.12 Placing the Cabinet ..........................................................................................................................3-23
3.2.13 Fastening the Cabinet.......................................................................................................................3-25
3.2.14 Leveling the Cabinet ........................................................................................................................3-28
3.2.15 Removing Lifting Lugs ....................................................................................................................3-28
3.2.16 Illustration of the Installed Cabinet..................................................................................................3-29
3.3 Installing Combined Cabinets .....................................................................................................................3-30
4 Installing Boards ........................................................................................................................4-1
4.1 Introduction to Installation Positions ............................................................................................................4-2
4.2 Preparations...................................................................................................................................................4-2
4.3 Installing the DTMU .....................................................................................................................................4-4
4.3.1 Setting DIP Switches on the DTMU ....................................................................................................4-4
4.3.2 Installation Procedure ..........................................................................................................................4-6
4.4 Installing the DATU ......................................................................................................................................4-7
4.5 Installing the PSU and DPMU ......................................................................................................................4-8
4.5.1 PSU and DPMU Installation Procedure ...............................................................................................4-8
4.6 Installing the DELU ....................................................................................................................................4-11
4.6.1 Installation Overview.........................................................................................................................4-11
4.6.2 Installation Procedure ........................................................................................................................4-11
4.7 Installing the DMLU ...................................................................................................................................4-11
4.7.1 Installation Overview.........................................................................................................................4-11
4.7.2 Installation Procedure ........................................................................................................................4-11
4.8 Installing the DTRU....................................................................................................................................4-11
4.9 Installing the DDPU and DCOM ................................................................................................................4-13
5 Installing Auxiliary Equipment ..............................................................................................5-1
5.1 Installing Transmission Unit .........................................................................................................................5-2
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual Contents
Issue 01 (2006-09-06) Huawei Technologies Proprietary iii
5.1.1 Introduction to Installation Positions ...................................................................................................5-2
5.1.2 Installation Procedure ..........................................................................................................................5-1
5.2 Installing Outdoor Interface Boxes ...............................................................................................................5-3
5.2.1 Introduction to the Outdoor Transmission Interface Box.....................................................................5-3
5.2.2 Introduction to the Outdoor Power Interface Box................................................................................5-5
5.2.3 Installing the Outdoor Interface Box on a Wall....................................................................................5-7
5.2.4 Installing the Outdoor Interface Box on a Pole....................................................................................5-8
6 Installing Cables ........................................................................................................................6-1
6.1 Introduction to the Cables to be Installed On Site.........................................................................................6-3
6.1.1 Introduction to Cabling Holes..............................................................................................................6-3
6.1.2 Cable Layout at the Cabinet Front .......................................................................................................6-4
6.1.3 Wiring on the Back of the Cabinet .......................................................................................................6-7
6.2 Installing the Power Cables...........................................................................................................................6-2
6.2.1 Introduction to the Power Cables.........................................................................................................6-2
6.2.2 Installation Principles...........................................................................................................................6-1
6.2.3 Leading the 3-Phase 220 VAC Power into the BTS3012AE Cabinet ..................................................6-1
6.2.4 Leading the Single-Phase 220 VAC Power into the BTS3012AE Cabinet ..........................................6-3
6.2.5 Leading the 110 VAC Dual-Live Power into the BTS3012AE Cabinet...............................................6-4
6.2.6 Connecting the Power Cables to the Power Interface Box...................................................................6-5
6.3 Installing PGND Cables ................................................................................................................................6-9
6.3.1 Introduction to PGND Cables ..............................................................................................................6-9
6.3.2 Installation Principles...........................................................................................................................6-9
6.3.3 Installation Procedure ........................................................................................................................6-10
6.3.4 Connecting the PGND Cable to the Transmission Interface Box ......................................................6-11
6.3.5 Connecting the PGND Cable to the Power Interface Box .................................................................6-11
6.4 Installing the E1 Cables...............................................................................................................................6-12
6.4.1 Introduction to the E1 Cables.............................................................................................................6-12
6.4.2 Installation Principles.........................................................................................................................6-14
6.4.3 Installation Procedure ........................................................................................................................6-14
6.4.4 Connecting the 75-ohm E1 Cable to the Transmission Interface Box ...............................................6-15
6.4.5 Connecting the 120-ohm E1 Cable to the Transmission Interface Box .............................................6-15
6.5 Installing Optical Fibers ..............................................................................................................................6-18
6.5.1 Introduction to the Optical Fibers ......................................................................................................6-18
6.5.2 Installation Principles.........................................................................................................................6-19
6.5.3 Installation Procedure ........................................................................................................................6-19
6.5.4 Connecting the Fibers to the Transmission Interface Box..................................................................6-20
6.6 Installing the RF Signal Cables ...................................................................................................................6-21
6.6.1 Introduction to the RF Signal Cables .................................................................................................6-21
6.6.2 Installation Principles.........................................................................................................................6-22
6.6.3 Installation Procedure ........................................................................................................................6-22
6.7 Installing the Cable for the Combiner on the DTRU...................................................................................6-22
Contents
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
iv Huawei Technologies Proprietary Issue 01 (2006-09-06)
6.7.1 Introduction to the Cable for the Combiner on the DTRU.................................................................6-22
6.7.2 Connecting the Cable for Combiner on the DTRU............................................................................6-23
6.8 Installing the 1/4-Inch RF Jumper...............................................................................................................6-23
6.8.1 Introduction to the RF Jumper ...........................................................................................................6-23
6.8.2 Installation Principles.........................................................................................................................6-24
6.8.3 Installation Procedure ........................................................................................................................6-24
6.9 Installing the 1/2-Inch RF Jumper...............................................................................................................6-25
6.9.1 Introduction to the RF Jumper ...........................................................................................................6-25
6.9.2 Installation Procedure ........................................................................................................................6-25
6.10 Installing the Boolean Value Input Signal Cable.......................................................................................6-25
6.10.1 Introduction to the Boolean Value Input Signal Cable .....................................................................6-25
6.10.2 Installation Positions ........................................................................................................................6-26
6.11 Installing the Built-In Storage Battery and Its Cables ...............................................................................6-26
6.11.1 Introduction to the Storage Battery Cabin........................................................................................6-26
6.11.2 Introduction to the Cables for the Built-in Storage Battery..............................................................6-29
6.11.3 Installation Procedure.......................................................................................................................6-29
6.12 Installing Cables for the Combined Cabinet .............................................................................................6-38
6.12.1 Introduction to Cables for the Combined Cabinet............................................................................6-38
6.12.2 Installation Procedure ......................................................................................................................6-38
6.13 Installing Cables for the Cabinet Group....................................................................................................6-39
6.13.1 Introduction to Cables for the Cabinet Group ..................................................................................6-39
6.13.2 Installation Procedure ......................................................................................................................6-39
6.14 Installing the RET Control Signal Cable...................................................................................................6-39
6.14.1 Introduction to the RET Control Signal Cable .................................................................................6-39
6.14.2 Connecting the RET Control Signal Cable ......................................................................................6-40
7 Checking Hardware Installation.............................................................................................7-1
7.1 Equipment Installation Check .......................................................................................................................7-2
7.2 Cable Installation Check ...............................................................................................................................7-2
7.2.1 Transmission Cable Installation Check ................................................................................................7-2
7.2.2 Power Cable and Protection Grounding Cable Installation Check.......................................................7-3
7.3 Power-On Check ...........................................................................................................................................7-3
7.3.1 Cabinet Power-On Check.....................................................................................................................7-4
7.3.2 Board Power-On Check .......................................................................................................................7-5
7.3.3 Power-On Check of the Heat Exchanger .............................................................................................7-6
7.3.4 Power-on Check of the Batteries..........................................................................................................7-6
7.4 Sanitation Check ...........................................................................................................................................7-7
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual Figures
Issue 01 (2006-09-06) Huawei Technologies Proprietary v
Figures
Figure 1-1 BTS3012AE hardware structure .......................................................................................................1-2
Figure 1-2 BTS3012AE cabinet .........................................................................................................................1-4
Figure 1-3 BTS3012AE cabinet without a base (in mm) ...................................................................................1-5
Figure 1-4 Dimensions of the BTS3012AE cabinet bottom (in mm) .................................................................1-6
Figure 1-5 BTS3012AE cabinet with a base (in mm) ........................................................................................1-7
Figure 1-6 Front view of the BTS3012AE cabinet under full configuration......................................................1-8
Figure 1-7 Installation space for a BTS3012AE cabinet (in mm) ......................................................................1-9
Figure 1-8 Base dimensions (in mm) ...............................................................................................................1-10
Figure 1-9 Hardware installation of the BTS3012AE ......................................................................................1-14
Figure 2-1 Straightening tongues .......................................................................................................................2-6
Figure 2-2 Removing the cover ..........................................................................................................................2-6
Figure 2-3 Removing all wooden boards ...........................................................................................................2-7
Figure 2-4 Unpacking a carton ...........................................................................................................................2-8
Figure 3-1 Process for installing a cabinet on the cement floor .........................................................................3-3
Figure 3-2 Installation position of the BTS3012AE cabinet ..............................................................................3-4
Figure 3-3 Dimensions of the cement plinth ......................................................................................................3-5
Figure 3-4 Installation holes of the expansion bolts for a single cabinet............................................................3-6
Figure 3-5 M12 expansion bolt assembly...........................................................................................................3-7
Figure 3-6 Installing the expansion bolt (1) .......................................................................................................3-8
Figure 3-7 Installing the expansion bolt (2) .......................................................................................................3-8
Figure 3-8 Installing the base .............................................................................................................................3-9
Figure 3-9 Leveling the base (1) ......................................................................................................................3-10
Figure 3-10 Leveling the base (2) ....................................................................................................................3-10
Figure 3-11 Lifting the cabinet .........................................................................................................................3-11
Figure 3-12 Placing the cabinet on the base .....................................................................................................3-12
Figure 3-13 Fastening the cabinet on the base (Rear view)..............................................................................3-13
Figures
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
vi Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 3-14 Unlocking the cabinet ...................................................................................................................3-14
Figure 3-15 Fixing the front door.....................................................................................................................3-15
Figure 3-16 Fastening the cabinet on the base (Front view).............................................................................3-15
Figure 3-17 Leveling the cabinet (1) ................................................................................................................3-16
Figure 3-18 Leveling the cabinet (2) ................................................................................................................3-17
Figure 3-19 Removing lifting lugs ...................................................................................................................3-17
Figure 3-20 Installed BTS3012AE cabinet ......................................................................................................3-18
Figure 3-21 Process for installing a cabinet on the cement floor with insufficient bearing capacity ...............3-19
Figure 3-22 Installation position of the BTS3012AE cabinet ..........................................................................3-20
Figure 3-23 Dimensions of U-bar supports (unit: mm) ....................................................................................3-21
Figure 3-24 Fastening the U-bar supports on the cement plinths .....................................................................3-22
Figure 3-25 Leveling the U-bar support (1) .....................................................................................................3-22
Figure 3-26 Leveling the U-bar support (2) .....................................................................................................3-23
Figure 3-27 Lifting the cabinet.........................................................................................................................3-24
Figure 3-28 Placing the cabinet on the U-bar supports ....................................................................................3-25
Figure 3-29 Fastening the cabinet on the base (Rear view)..............................................................................3-26
Figure 3-30 Unlocking the front door...............................................................................................................3-27
Figure 3-31 Fastening the cabinet on the base (Front view).............................................................................3-28
Figure 3-32 Removing lifting lugs ...................................................................................................................3-29
Figure 3-33 Installed cabinet ............................................................................................................................3-30
Figure 3-34 DIP switches on the DCSU...........................................................................................................3-31
Figure 4-1 Boards in the BTS3012AE subrack ..................................................................................................4-2
Figure 4-2 Wearing an antistatic wrist strap .......................................................................................................4-3
Figure 4-3 DIP switches on the DTMU..............................................................................................................4-4
Figure 4-4 Installing the DTMU.........................................................................................................................4-6
Figure 4-5 Hooking spanners on to the square holes of the subrack ..................................................................4-7
Figure 4-6 DIP switches on the DATU...............................................................................................................4-8
Figure 4-7 DIP switch of the DPMU..................................................................................................................4-9
Figure 4-8 Installing the PSU and DPMU (1) ..................................................................................................4-10
Figure 4-9 Installing the PSU and DPMU (2) ..................................................................................................4-10
Figure 4-10 Front panel of a DTRU .................................................................................................................4-12
Figure 4-11 Front panel of a DDPU .................................................................................................................4-14
Figure 5-1 Installation position of the transmission unit ....................................................................................5-2
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual Figures
Issue 01 (2006-09-06) Huawei Technologies Proprietary vii
Figure 5-2 Positions of the dummy panel and air deflector plate .......................................................................5-2
Figure 5-3 Installing transmission unit ...............................................................................................................5-2
Figure 5-4 Internal structure of the 75-ohm outdoor transmission interface box ...............................................5-4
Figure 5-5 Structure of the 12-core fusion parts.................................................................................................5-4
Figure 5-6 Internal structure of the 120-ohm transmission interface box...........................................................5-5
Figure 5-7 Internal structure of the 220 VAC power interface box ....................................................................5-6
Figure 5-8 Positions of the expansion bolts........................................................................................................5-7
Figure 5-9 Installing the outdoor interface box on a wall...................................................................................5-8
Figure 5-10 Fixing the pole fixture to the interface box.....................................................................................5-9
Figure 5-11 Fixing the interface box to the pole.................................................................................................5-9
Figure 6-1 BTS3012AE cabling holes................................................................................................................6-3
Figure 6-2 Silkscreens of the cabling holes........................................................................................................6-4
Figure 6-3 Cable layout at the cabinet front .......................................................................................................6-5
Figure 6-4 NPMI cable layout on the top of the cabinet ....................................................................................6-6
Figure 6-5 Wring on the back of the BTS3012AE cabinet.................................................................................6-8
Figure 6-6 Installing L1, L2, L3, and N .............................................................................................................6-2
Figure 6-7 Installing the short-circuiting copper bar ..........................................................................................6-3
Figure 6-8 Installing L1, L2, and N....................................................................................................................6-5
Figure 6-9 Power cable layout of the single-phase mains input .........................................................................6-6
Figure 6-10 Connection of power cables in single-phase mains and single-phase generator input modes ........6-7
Figure 6-11 Connection of power cables in three-phase mains input mode .......................................................6-8
Figure 6-12 Connection of power cables in three-phase mains and three-phase generator input mode .............6-9
Figure 6-13 Installing the PGND cable for the power interface box................................................................6-12
Figure 6-14 75-ohm E1 coaxial cable...............................................................................................................6-13
Figure 6-15 Connecting the 75-ohm E1 cable..................................................................................................6-15
Figure 6-16 Connecting the 120-ohm E1 cable................................................................................................6-16
Figure 6-17 Clamping the 120-ohm E1 cable to the 120-ohm digital unit .......................................................6-17
Figure 6-18 Connecting the E1 wire of the client.............................................................................................6-18
Figure 6-19 LC connector ................................................................................................................................6-18
Figure 6-20 Connection between a fiber and a 12-core fiber splice tray..........................................................6-20
Figure 6-21 12-route Fiber Indicator Table ......................................................................................................6-21
Figure 6-22 Structure of the RF RX signal cable and that of the TX signal cable ...........................................6-22
Figure 6-23 Cable for the combiner on the DTRU...........................................................................................6-23
Figures
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
viii Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 6-24 Structure of the RF jumper ...........................................................................................................6-24
Figure 6-25 Removing the cover plate of the RF cable....................................................................................6-24
Figure 6-26 Structure of the RF jumper ...........................................................................................................6-25
Figure 6-27 Boolean value input signal cable ..................................................................................................6-26
Figure 6-28 Full configuration of the BTS3012AE..........................................................................................6-27
Figure 6-29 Cabling of the –48 V 50-AH storage battery cabin.......................................................................6-28
Figure 6-30 Cabling of the –48 V 150-AH storage battery cabin.....................................................................6-28
Figure 6-31 Cabling for the 100-AH configuration mode (1) ..........................................................................6-30
Figure 6-32 Cabling for the 100-AH configuration mode (2) ..........................................................................6-31
Figure 6-33 Cabling for the 150-AH configuration mode (1) ..........................................................................6-33
Figure 6-34 Cabling for the 150-AH configuration mode (2) ..........................................................................6-34
Figure 6-35 Cabling for the 150-AH configuration mode (3) ..........................................................................6-35
Figure 6-36 Cabling for the 200-AH configuration mode................................................................................6-37
Figure 6-37 Cable for the combined cabinet ....................................................................................................6-38
Figure 6-38 Cable for the cabinet group...........................................................................................................6-39
Figure 6-39 Structure of the RET control signal cable .....................................................................................6-40
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual Tables
Issue 01 (2006-09-06) Huawei Technologies Proprietary ix
Tables
Table 1-1 Description of the BTS3012AE hardware ..........................................................................................1-2
Table 1-2 Weight of the BTS3012AE cabinet under different configurations ....................................................1-7
Table 1-3 Boards in the BTS3012AE cabinet.....................................................................................................1-8
Table 1-4 Base specifications ...........................................................................................................................1-10
Table 1-5 Types and installation positions of the cables...................................................................................1-11
Table 1-6 Installation process ...........................................................................................................................1-15
Table 2-1 Technical documents for reference .....................................................................................................2-2
Table 2-2 List of tools and instruments ..............................................................................................................2-3
Table 3-1 Settings for SW1...............................................................................................................................3-31
Table 3-2 Settings for SW11.............................................................................................................................3-31
Table 3-3 Settings for SW2−SW5 ....................................................................................................................3-32
Table 3-4 Settings for SW6 and SW7...............................................................................................................3-32
Table 3-5 Settings for SW8...............................................................................................................................3-33
Table 3-6 Settings for SW9 and SW10.............................................................................................................3-33
Table 4-1 S4/S5/S6/S7 setting descriptions ........................................................................................................4-4
Table 4-2 Default setting of the DIP switches on the DATU..............................................................................4-7
Table 6-1 Cables laid out at the cabinet front .....................................................................................................6-6
Table 6-2 Cables on the back of the BTS3012AE cabinet..................................................................................6-1
Table 6-3 Specifications of the AC power cables for the BTS3012AE ..............................................................6-2
Table 6-4 AC power distribution mode...............................................................................................................6-1
Table 6-5 Figure for reference in different power supply modes........................................................................6-5
Table 6-6 Pins of the coaxial cable ...................................................................................................................6-13
Table 6-7 Installation positions of the Boolean value input signal cable..........................................................6-26
Table 7-1 Equipment installation checklist.........................................................................................................7-2
Table 7-2 Transmission cable installation checklist............................................................................................7-2
Table 7-3 Power cable and grounding cable installation checklist .....................................................................7-3
Tables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
x Huawei Technologies Proprietary Issue 01 (2006-09-06)
Table 7-4 Instructions to handling different values ............................................................................................7-6
Table 7-5 Sanitation checklist.............................................................................................................................7-7
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 1 Overview of the Hardware Installation
Issue 01 (2006-09-06) Huawei Technologies Proprietary 1-1
1 Overview of the Hardware Installation About This Chapter
The following table lists the contents of this chapter.
Title Description
1.1 BTS3012AE Hardware
Structure
Describes the hardware structure of the BTS3012AE.
1.2 Installation Process Describes how to install the BTS3012AE cabinet.
1 Overview of the Hardware Installation
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
1-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)
1.1 BTS3012AE Hardware Structure
1.1.1 Schematic Drawing of Hardware Structure
The BTS3012AE system consists of the following parts:
� BTS3012AE cabinet
� Cables
� Antenna system
Figure 1-1 shows the hardware structure of the BTS3012AE.
Figure 1-1 BTS3012AE hardware structure
Antenna
Feeder
Jumper
Antennasystem
TMA
Jumper
Power cable
E1 trunk cable
Fiber
Signal cable
BTS3012AE
cabinet
For the internal configuration of the BTS3012AE cabinet, see Figure 1-6. For details of cabling, see 6
"Installing Cables."
Choose either fibers or E1 trunk cables for installation.
Table 1-1 describes the parts shown in Figure 1-1.
Table 1-1 Description of the BTS3012AE hardware
Equipment Components Installation Guide
BTS3012AE
cabinet
Mandatory 3 Installing the BTS3012AE
Cabinet
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 1 Overview of the Hardware Installation
Issue 01 (2006-09-06) Huawei Technologies Proprietary 1-3
Equipment Components Installation Guide
Cables Radio frequency (RF) cables,
signal cables, power cables,
protection grounding (PGND)
cables, transmission cables,
and storage battery cables
6 Installing Cables
Auxiliary
equipment
Transmission unit, power
interface box, and transmission
interface box. The auxiliary
equipment is optional.
5 Installing Auxiliary Equipment
Antenna system Antenna, jumper, feeder,
Tower Mounted Amplifier
(TMA)
The TMA is optional.
HUAWEI BTS3012AE Base
Station Antenna System
Installation Manual
1.1.2 BTS3012AE Cabinet
Appearance
Figure 1-2 shows the BTS3012AE cabinet.
1 Overview of the Hardware Installation
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
1-4 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 1-2 BTS3012AE cabinet
Dimensions
The dimensions of the BTS3012AE cabinet without a base are 1700 mm (Height) % 1000
mm (Width) % 880 mm (Depth). Figure 1-3 shows the dimensions of the BTS3012AE cabinet
without a base.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 1 Overview of the Hardware Installation
Issue 01 (2006-09-06) Huawei Technologies Proprietary 1-5
Figure 1-3 BTS3012AE cabinet without a base (in mm)
170
0
1000
880
Figure 1-4 shows the dimensions of the BTS3012AE cabinet bottom.
1 Overview of the Hardware Installation
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
1-6 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 1-4 Dimensions of the BTS3012AE cabinet bottom (in mm)
962.0
1000.0
910.0
682.0732.0
16.0
1
(1) Cabinet front
The dimensions of the BTS3012AE cabinet with a base are 1900 mm (Height) % 1000 mm
(Width) % 880 mm (Depth). Figure 1-5 shows the dimensions of the BTS3012AE cabinet
with a base.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 1 Overview of the Hardware Installation
Issue 01 (2006-09-06) Huawei Technologies Proprietary 1-7
Figure 1-5 BTS3012AE cabinet with a base (in mm)
1000
880
19
00
Weight
Table 1-2 lists the weight of the BTS3012AE cabinet under different configurations.
Table 1-2 Weight of the BTS3012AE cabinet under different configurations
Cabinet Configuration Weight
Empty cabinet Excludes the heat exchanger and all the
internal subracks
200 kg
Empty cabinet Includes the heat exchanger 310 kg
Cabinet under full
configuration (excluding
storage batteries)
� Cabinet with a front door
� All boards installed
390 kg
Composition
Figure 1-6 shows the front view of the BTS3012AE cabinet under full configuration.
1 Overview of the Hardware Installation
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
1-8 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 1-6 Front view of the BTS3012AE cabinet under full configuration
Cable in/outAC lightning
D
C
O
M
D
D
P
U
D
C
O
M
D
D
P
U
D
C
O
M
D
D
P
U
D
T
R
U
D
T
R
U
D
T
R
U
D
T
R
U
D
T
R
U
D
T
R
U
PSU PSU PSU PSU
PSUPSUPSUDPMU
Air return
Wire holder
Wire holder
FAN
DELU0
DELU1DMLU
AC PDU
Air return
D
T
M
U
D
T
M
U
D
A
T
U
D
C
C
U
D
C
S
U
Wire holder
DC
PDU
BAT 48V 50AH
Air inlet
Tra
nsm
issio
nu
nit
BAT 48V 150AH
Air inlet
Table 1-3 lists the boards in the BTS3012AE cabinet.
Table 1-3 Boards in the BTS3012AE cabinet
Subrack Board Full Name of Board
DTMU Transmission/Timing/Management Unit for DTRU
BTS
DCSU Combined cabinet Signal connection Unit for DTRU
BTS
DCCU Cable Connection Unit for DTRU BTS
Common subrack
DATU Antenna and TMA control Unit for DTRU BTS
DTRU subrack DTRU Double-Transceiver Unit
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 1 Overview of the Hardware Installation
Issue 01 (2006-09-06) Huawei Technologies Proprietary 1-9
Subrack Board Full Name of Board
DDPU Dual-Duplexer Unit for DTRU BTS DAFU subrack
DCOM Combining Unit for DTRU BTS
PSU Power Supply Unit Power subrack
DPMU Power and Environment Monitoring Unit for DTRU
BTS
DELU E1 Signal Lightning Protection Unit for DTRU BTS Signal lightning
protection subrack DMLU Monitor Signal Lightning Protection Unit for DTRU
BTS
Installation Space
Figure 1-7 shows the reserved space for the installation of a BTS3012AE cabinet.
Figure 1-7 Installation space for a BTS3012AE cabinet (in mm)
BTS 3012AE
1000
>
> 600
> 600
> 300
880
1300
1
(1) Front door of the cabinet
1 Overview of the Hardware Installation
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
1-10 Huawei Technologies Proprietary Issue 01 (2006-09-06)
1.1.3 Base
Dimensions
Figure 1-8 shows the dimensions of a base.
Figure 1-8 Base dimensions (in mm)
20
0
998737
Specifications
Table 1-4 lists the base specifications.
Table 1-4 Base specifications
Height 200 mm
Material Cold rolled quality steel sheet
Fixed Hole Location at the Bottom
Used for fixing the base; plugged into the cement floor through
expansion bolts
Two front installation locations (fastening bolts downwards
from inside the cabinet) Fixed Hole Location on the Top
Two rear installation locations (fastening bolts upwards
through the base from inside the cabinet)
Rectangle Hole Cable inlet/outlet at the bottom; base in open design for
cabling from four sides
1.1.4 Introduction to the Cables
Table 1-5 describes the types and installation positions of the cables to be installed on site.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 1 Overview of the Hardware Installation
Issue 01 (2006-09-06) Huawei Technologies Proprietary 1-11
Table 1-5 Types and installation positions of the cables
Cable Type Cable Category
Cable Description Connector Type Cable Installation Position
N elbow male
connector
Connects to the TCOM port
on the DTRU
RF Tx signal
cable
Transmitting RF Tx
signals
N elbow male
connector
Connects to the TXA or TXB
port on the DDPU
SMA elbow male
connector
Connects to the RXM1,
RXD1, RXM2, or RXD2 port
on the DTRU
RF Rx signal
cable
Transmitting RF Rx
signals
SMA elbow male
connector
Connects to the RXA1,
RXA2, RXA3, RXA4, RXB1,
RXB2, RXB3, or RXB4 port
on the DDPU
N male connector Connects to the TX1 or TX2
port on the DTRU
Cable for the
combiner on
the DTRU
Realizing combined
output of Tx signals
SMA male
connector
Connects to the IN1 or IN2
port on the DTRU
DIN male
connector
Connects to the feeder of the
BTS
RF cable
RF jumper Realizing signal
interaction between
the BTS and the
antenna system DIN male
connector
Connects to the ANTA or
ANTB port on the DDPU
DB44 Connects to the DB44 port on
the DMLU
Boolean value
output signal
cable
- Outputting Boolean
value control signals
Bare wire Connects to the DDF
DB44 Connects to the DB44 port on
the DMLU
Boolean value
input signal
cable
- Inputting Boolean
value control signals
Bare wire Connects to the DDF
OT terminal (made
on site)
Connects to the external
wiring terminal of the power
lightning arrester
220 VAC
3-phase
power cable
Providing 220 VAC
input power for the
cabinet
Comprising three L
wires and one N
wire
L wire: red, a
cross-sectional area
of 10 mm2
N wire: black, a
cross-sectional area
of 10 mm2
The terminal is
made based on the
onsite power
distribution unit.
Connects to the power
distribution unit provided by
the customer
Power cable
220 VAC
single-phase
power cable
Providing 220 VAC
input power for the
cabinet
OT terminal (made
on site)
Connects to the external
wiring terminal of the power
lightning arrester
1 Overview of the Hardware Installation
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
1-12 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Cable Type Cable Category
Cable Description Connector Type Cable Installation Position
Comprising one L
wire and one N wire
L wire: red, a
cross-sectional area
of 16 mm2
N wire: black, a
cross-sectional area
of 16 mm2
The terminal is
made based on the
onsite power
distribution unit.
Connects to the power
distribution unit provided by
the customer
OT terminal (made
on site)
Connects to the external
wiring terminal of the power
lightning arrester
Dual-live
power cable
Providing 110 VAC
input power for the
cabinet
Comprising two L
wires and one N
wire
L wire: red, a
cross-sectional area
of 16 mm2
N wire: black, a
cross-sectional area
of 16 mm2
The terminal is
made based on the
onsite power
distribution unit.
Connects to the power
distribution unit provided by
the customer
OT terminal (made
on site)
Connects to the protection
grounding bar inside the
cabinet
Protection
grounding
cable (PGND
cable)
- Realizing fast
discharging of
powerful surge
current
Cable
cross-sectional area:
25 mm2
Cable color: yellow
and green
OT terminal (made
on site)
Connects to the protection
grounding bar provided by the
customer
75-ohm E1
cable
Transmitting E1
signals
75-ohm mini coaxial
cable
120-ohm E1
cable
Transmitting E1
signals
120-ohm twisted
pairs
BTS3012AE side:
DB25 male
connector
Opposite side:
connector made on
site to make the
connector type
matched with that
at the peer end
DB25 male connector
connects to the DELU in the
signal lightning protection
subrack.
The connector on the opposite
side connects to the
transmission unit or
transmission interface box
provided by the customer
Connects to the optical
transmission unit in the
cabinet
Transmission
cable (any one
of the right
three)
Optical fiber Transmitting trunk
signals
Multimode optical
fiber (orange),
single-mode optical
fiber (yellow)
LC connector
Connects to the transmission
unit or transmission interface
box provided by the customer
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 1 Overview of the Hardware Installation
Issue 01 (2006-09-06) Huawei Technologies Proprietary 1-13
Cable Type Cable Category
Cable Description Connector Type Cable Installation Position
SMA male
connector
Connects to the SMA port on
the Bias Tee
RET control
signal cable
(optional)
- Transmitting signals
between the DATU
and the Bias-Tee SMA elbow male
connector
Connects to the ANT port on
the DATU
OT25-6 terminal,
preinstalled in the
cabinet
- –48 V cable Providing –48 V
input or output
power for the
storage battery
Cross-sectional area
of the cable: 25 mm2
OT25-6 terminal Connects to the negative
terminal of the storage battery
OT25-6 terminal,
preinstalled in the
cabinet
- GND cable Providing –48 V
input or output
power for the
storage battery
Cross-sectional area
of the cable: 25 mm2
OT25-6 terminal Connects to the positive
terminal of the storage battery
Cable
between
storage
batteries
Connecting the
positive terminal
with the negative
terminal of storage
batteries
Cable delivered with
the storage battery
OT16-6 terminal -
2-pin power
terminal
This terminal is
fixed to port
BTA_TEM1 on the
NPMI inside the
cabinet in advance.
-
Cable for
storage
batteries
(optional)
Cable for the
temperature
and
humidity
sensor of the
built-in
storage
battery
Transmitting
temperature
monitoring signals
of the storage
battery
2-core single cable
OT-6 terminal of
the sensor
Connects to the external
terminal of the left storage
battery inside the storage
battery cabin
1.2 Installation Process
1.2.1 Hardware Installation Flow Chart
Figure 1-9 shows the hardware installation of the BTS3012AE.
1 Overview of the Hardware Installation
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
1-14 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 1-9 Hardware installation of the BTS3012AE
Install cables
Installation checking
Pass the check?
End
Reinstall faulty parts
Yes
No
Install the outdoor interface box
No
Yes
Start
Installation preparations
Install the base
Install the cabinet
Install boards
No
Install the transmission unit
Need to install the outdoorinterface box?
Need to installthe transmission unit?
Yes
1.2.2 Installation Process Description
Table 1-6 describes the installation process.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 1 Overview of the Hardware Installation
Issue 01 (2006-09-06) Huawei Technologies Proprietary 1-15
Table 1-6 Installation process
Operation Reference Description
Installation
preparations
2 Installation Preparations Describes the preparatory work
before the installation.
Installing the cabinet 3 Installing the BTS3012AE
Cabinet
Describes the installation of the
BTS3012AE cabinet.
Installing boards 4 Installing Boards Describes the installation of
boards.
Installing auxiliary
equipment
5 Installing Auxiliary
Equipment
Describes the installation of
transmission unit, outdoor
transmission interface box, and
outdoor power interface box.
Installing cables 6 Installing Cables Describes the installation of
external cables.
Checking hardware
installation
7 Checking Hardware
Installation
Describes the inspections and
tests on the installed hardware
system.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 2 Installation Preparations
Issue 01 (2006-09-06) Huawei Technologies Proprietary 2-1
2 Installation Preparations About This Chapter
The following table lists the contents of this chapter.
Title Description
2.1 Preparing Technical
Documents
Lists the technical documents prepared for the hardware
installation.
2.2 Preparing Mounting Tools
and Instruments
Lists the tools and instruments prepared for the hardware
installation.
2.3 Checking Installation
Conditions
Describes the conditions and requirements for the
hardware installation.
2.4 Unpacking and Inspecting Describes the requirements for unpacking and inspection.
2 Installation Preparations
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
2-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)
2.1 Preparing Technical Documents
Table 2-1 shows the technical documents for reference during the installation.
Table 2-1 Technical documents for reference
Category Description
GSM Digital Cellular Mobile Base Station Network Planning
GSM Digital Cellular Mobile Base Station Project Design
Engineering design
documents
Construction Diagram
BTS3012AE Base Station Cabinet Installation Manual Installation guide
BTS3012AE Base Station Antenna Feeder Installation Manual
The documents listed in Table 2-1 are only a few of the documents available on site. They are for
reference only.
2.2 Preparing Mounting Tools and Instruments
Prepare all the tools and instruments listed in Table 2-2.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 2 Installation Preparations
Issue 01 (2006-09-06) Huawei Technologies Proprietary 2-3
Table 2-2 List of tools and instruments
Measuring and Marking Tools
50 m ribbon tape, 5 m measuring tape, 400 mm level bar, marking pen
Drilling Tools Punch drill, a few matching bits, cleaner, terminal block (with three
2-phase sockets and three 3-phase sockets, current capacity > 15 A)
Fastening Tools
Phillips screwdrivers (respectively of 4', 6', and 8')
Straight screwdrivers (respectively of 4', 6', and 8')
Adjustable wrenches (respectively of 6', 8', 10', and 12')
Combination wrenches (respectively of 17' and 19')
Inner hexagon spanners, socket wrenches, 5 kg nail hammer
Small Tools
Hacksaw (with some saw blades), tap wrench (with some M4 and M5
screw taps), sharp nose pliers (8'), diagonal pliers (8'), slip joint pliers
(8'), pincer pliers (8'), broach files (medium), electrician’s knife, flat
Phillips screwdriver (medium)
Universal Tools
Auxiliary Tools
Tweezers, paintbrush, scissors, 300 W soldering iron, 40 W soldering
iron, tin wires (some), heat blower, solder absorber, hydraulic pliers (or
Hercules crimping pliers), ladder, wire nippers, paper knife, insulation
tape
Special Tools
Non-conductive screwdriver, antistatic wrist strap, safety knife
Stripper for 75-ohm coaxial cables, connector crimping pliers for
75-ohm coaxial cables, multi-purpose crimping pliers, crimping pliers
for network cables
Instruments Multimeter, ground resistance meter, power meter, portable computer
2.3 Checking Installation Conditions
The project supervisor must perform the following steps on the installation site:
Step 1 Check the construction conditions according to the Engineering Technical Specifications and
Lightning Protection and Grounding Specifications for Communications Equipment.
Step 2 Fill in the Installation Environment Checklist.
Step 3 Sign the Kickoff Agreement with the customer if all conditions are met.
Step 4 Formulate the Project Installation Plan.
----End
If the installation preparations of the customer are not ready as required, fill in the Onsite
Work Liaison Form and give the reasons for kickoff delay.
If the customer needs immediate kickoff, ask the customer to specify the exact time when the
installation is ready for kickoff. If a project cannot be improved or does not meet the specified
requirements, both parties must sign a memo.
2 Installation Preparations
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
2-4 Huawei Technologies Proprietary Issue 01 (2006-09-06)
2.3.1 Load-Bearing Capacity Requirements
Install the BTS3012AE on a stable and level cement floor. The weight capacity of the floor
must satisfy the weight requirement of the cabinet. If the BTS3012AE is installed on the
rooftop, the weight capacity of the rooftop must meet the weight requirement of the cabinet.
� If the weight capacity of the cement is more than 800 kg/m2, install the cabinet on the
cement floor. For details, see section 3.1 "Installing a Cabinet on the Cement Floor with
Sufficient Bearing Capacity (ƒ 800 kg/m2)."
� If the weight capacity of the cement is less than 800 kg/m2, install the cabinet on the
U-bar support that is on the cement floor. For details, see section 3.2 "Installing a
Cabinet on the Cement Floor with Insufficient Bearing Capacity (< 800 kg/m2)."
2.3.2 Grounding Status Requirements
Proper grounding ensures stable operation of the equipment. It is also the prerequisite for the
access network to be protected from thunder strokes or interference. Carefully check the
grounding conditions on site to ensure proper grounding.
To protect the equipment from a lightning discharge, the earth resistance of the grounding
system is recommended to be less than 10 ohms, and the equipment grounding should be in
accordance with national and local electrical codes as well.
2.4 Unpacking and Inspecting
This section describes how to unpack and inspect items from the following aspects:
� Requirements for Unpacking
� Unpacking the Wooden Case
� Inspecting Items Inside the Wooden Case
� Unpacking the Carton
� Inspecting Items Inside the Carton
2.4.1 Requirements for Unpacking
After the project kicks off, the project supervisor must check the products along with the
customer.
The project supervisor must ensure that:
� The total number of products is consistent with that on the packing list attached to the
packing case.
� The arrival place is the installation site.
� The packing case is in good condition.
� The cabinet is not placed upside down.
If the outer package is damaged or soaked or the equipment is soaked and rusty, stop
unpacking and find the cause. Give feedback about the damaged equipment to Huawei local
office.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 2 Installation Preparations
Issue 01 (2006-09-06) Huawei Technologies Proprietary 2-5
� To protect the equipment and find the cause, store the unpacked equipment inside the
equipment room.
� Take photos of the storage environment, the rusted or corroded devices, and the packaging
cases and materials. Archive the photos.
� Take good care of the unpacked packaging cases and materials.
If the products are in good condition, unpack and inspect the items. Unpack the case labeled
Built-In Packing List, and take out the packing list. Check the case according to the Packing
List.
For any short or wrong shipment, fill in the Article Problem Feedback Form. For any
damage of articles, both parties must fill in the Cargo Replacement Application Form and
sign the Packing List.
� Prevent the equipment, components, or parts from colliding with doors, walls, or shelves
during transportation and handling.
� Do not touch the uncoated surface of the equipment, parts, or components through sweat
soaked or dirty gloves.
2.4.2 Unpacking the Wooden Case
Do not place the wooden case upside down. Otherwise, the equipment will be severely
damaged.
Wooden cases are used to pack heavy objects such as racks and batteries. A rack is usually
packed with wooden boards, steel edges, tongues, and foamed angle wraps.
Move the packing case into or near the equipment room (if possible) to avoid damage to the
cabinet during transportation. Unpack the case as follows:
Step 1 Insert one end of the ejector lever into a hole of the tongue on the cover of the wooden case.
Step 2 Turn the ejector lever to straighten the tongue, as shown in Figure 2-1. You can also use a
screwdriver or a hammer to handle the tongue.
2 Installation Preparations
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
2-6 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 2-1 Straightening tongues
Steel edgeWooden board
Tongue
Spanner
Step 3 After straightening all the tongues on the cover, remove the cover, as shown in Figure 2-2.
Figure 2-2 Removing the cover
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 2 Installation Preparations
Issue 01 (2006-09-06) Huawei Technologies Proprietary 2-7
Step 4 Straighten all the tongues that join the wooden boards around the wooden case and remove
the wooden boards, as shown in Figure 2-3.
----End
Figure 2-3 Removing all wooden boards
Unpack other cases in the same way.
When handling the cabinet, hold the strong places such as the upper cable rack or bone frame.
Do not apply too much force on places that are not firm, such as cable supports, cable
fixing-beams, to avoid any damage to the cabinet.
Remove the lining board of the rack on the installation site. Otherwise, boards and signal
cables may be damaged during transportation.
2.4.3 Inspecting Items Inside the Wooden Case
After unpacking, check the items inside the wooden case to ensure that:
� The appearance of the cabinet is not damaged.
� The front and the back doors of the cabinet match.
� The cabinet top is in good condition and the marking is legible.
� The dummy panels and nameplates of boards in the subracks are installed.
� The sanitation inside the cabinet meets the requirements.
� The feeder clips and other items are complete and in good condition.
2 Installation Preparations
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
2-8 Huawei Technologies Proprietary Issue 01 (2006-09-06)
The items checked must be placed in order.
2.4.4 Unpacking the Carton
Cartons are usually used to pack boards, modules, or terminal devices.
� After moving a board from a dry place with lower temperature to a wet place with higher
temperature, wait at least 30 minutes before unpacking. Otherwise, humidity may gather
on the surface of the board and cause damage to the equipment.
� When unpacking boards, take antistatic measures to prevent the boards from damage.
� When cutting the tape through a paper knife, take care not to cut too deep. Otherwise, the
items inside may be damaged.
� Keep the carton and antistatic plastic packing bags for future use such as holding spare
parts or parts sent back for repair.
Unpack a carton as shown in Figure 2-4.
Figure 2-4 Unpacking a carton
(a) (b)
Unpack a carton as follows:
Step 1 Check the types and quantity of boards inside according to the labels.
Step 2 Cut the tapes along the seams of the carton cover through a knife, as shown in part (a) of
Figure 2-4.
Step 3 Open the carton and take out the items.
----End
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 2 Installation Preparations
Issue 01 (2006-09-06) Huawei Technologies Proprietary 2-9
2.4.5 Inspecting Items Inside the Carton
After unpacking, check the items inside the carton to ensure that:
� The packing of things inside the carton is in good condition.
� The number and types of items such as boards are consistent with those on the packing
list.
� The printed plates are not broken and the components do not fall off.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet
Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-1
3 Installing the BTS3012AE Cabinet
About This Chapter
The following table lists the contents of this chapter.
Title Description
3.1 Installing a Cabinet on the
Cement Floor with Sufficient
Bearing Capacity (ƒ 800
kg/m2)
Describes how to install a cabinet on the cement floor
with sufficient bearing capacity.
3.2 Installing a Cabinet on the
Cement Floor with Insufficient
Bearing Capacity (< 800
kg/m2)
Describes how to install a cabinet on the cement floor
with insufficient bearing capacity.
3.3 Installing Combined
Cabinets
Describes how to install combined cabinets.
3 Installing the BTS3012AE Cabinet
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
3-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)
3.1 Installing a Cabinet on the Cement Floor with
Sufficient Bearing Capacity (ƒƒƒƒ 800 kg/m2)
� When lifting the cabinet, ensure that all the four lugs are tightened, that the angle between
the lifting rope and the top of the cabinet is at least 60o, and that the cabinet is level.
Installers must stay away from the cabinet when lifting it and ensure that the front door
and rear door are closed.
� When installing the cabinet in bad conditions (for example, in the case of strong wind),
pay extra attention to the gravity center of the cabinet to prevent the cabinet from slanting.
3.1.1 Installation Flowchart
Figure 3-1 shows the flowchart for installing a cabinet on the cement floor with sufficient
bearing capacity.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet
Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-3
Figure 3-1 Process for installing a cabinet on the cement floor
Start
Position thecabinet
Cast thecement plinth
Position the base
Fasten the base
Level the base
Drill holes and installexpansion bolts
Install the cabinet
Remove lifting lugs
End
Level the cabinet
3.1.2 Positioning the Cabinet
The BTS3012AE can be installed against wall, rear to rear, or side by side. The following
requirements must be met to ease casting the cement plinth and installing and maintaining the
equipment:
� When a single BTS3012AE cabinet is installed against wall, it is recommended to keep a
300 mm space between the rear and the wall to facilitate the installation.
3 Installing the BTS3012AE Cabinet
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
3-4 Huawei Technologies Proprietary Issue 01 (2006-09-06)
� When two BTS3012AE cabinets are installed side by side, it is recommend to keep at
least 300 mm space between two sides.
� When two BTS3012AE cabinets are installed side by side and against the wall, the space
between two sides must be more than 600 mm.
� When the BTS3012AE is installed with the left side against the wall, the space between
the left side and the wall must be more than 600 mm.
� The BTS3012AE cannot be installed in wall corners.
Figure 3-2 shows the installation position of the BTS3012AE.
Figure 3-2 Installation position of the BTS3012AE cabinet
BTS 3012AE
1000
>
> 600
> 600
> 300
880
1300
1
3.1.3 Casting the Cement Plinth
Cast a cement plinth based on the dimensions shown in Figure 3-3.
The height of the cement plinth must meet the flood protection requirement in the local area.
The cement plinth should be at least 100 mm higher than the ground surface. This helps
protect the cabinet against water damage in the case of heavy rain or flood.
Ensure that the planeness error of the upper plane is not more than 5 mm.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet
Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-5
Figure 3-3 Dimensions of the cement plinth
2500
2800
>100
3.1.4 Positioning the Base
When installing a base, ensure that the front of the base aligns with that of the cabinet
To position the base, do as follows:
Step 1 Determine the installation position of the expansion bolts based on the installation holes of the
cabinet and the positioning dimensions specified in the project design and construction
drawing.
Step 2 Use a tape to determine the marking points.
Step 3 Mark the installation holes one by one based on the design requirements.
Step 4 Measure the distance between the installation holes to ensure accuracy.
3 Installing the BTS3012AE Cabinet
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
3-6 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 3-4 shows the installation holes of the expansion bolts for the BTS3012AE cabinet.
Figure 3-4 Installation holes of the expansion bolts for a single cabinet
>600
839
723
670
1000
998
2500
>600
40
2800
>1300
737880
>600
2
4
1
5
3
(1) Cement plinth (2) Outline of the base (3) Hole of the expansion bolts
(4) Outline of the cabinet (5) Indications at the cabinet front
----End
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet
Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-7
3.1.5 Drilling Holes and Installing Expansion Bolts
� The expansion tube must be fully buried in the ground.
� The depth of the hole must range from 52 mm to 60 mm. The depth of the hole must be a
sum of the length of the expansion tube and the length of the drill bit. If the depth is less
than 52 mm or more than 60 mm, the expansion bolt cannot be fastened.
� All the holes must have the same depth. Before measuring the depth of the hole, remove
the dust inside the hole to measure the exact depth.
� After drilling holes, measure the distance between the holes. If a drilled hole is of great
deviation, relocate and drill a new one.
To drill a hole and install the expansion bolt, do as follows:
Step 1 Use the φ16 drill bit and the M12 expansion bolt assembly.
Figure 3-5 shows the M12 expansion bolt assembly.
Figure 3-5 M12 expansion bolt assembly
1
4
5
6
7
2
3
(1) M12 bolt (2) Spring washer 12 (3) Flat washer 12 (4) Expansion tube
(5) Nut (6) Guiding slot (7) Guiding rib
Step 2 Hold the drill stock firmly with your hands, and keep the drill bit vertical to the ground to drill
a hole.
If the floor is too hard and slippery to settle the drill bit, dig a pit with a chisel to help position the hole
Step 3 Clean the dust with a cleaner when drilling.
Step 4 Insert the guiding rib on the nut into the guiding slot of the expansion tube.
3 Installing the BTS3012AE Cabinet
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
3-8 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Step 5 Feed the tube and the nut into the hole vertically, and then hammer the tube until it is fully
buried in the ground, as shown in Figure 3-6.
Figure 3-6 Installing the expansion bolt (1)
Ensure that the expansion tube is fully inserted into the hole.
Step 6 Remove the M12 expansion bolt, spring washer, and flat washer, as shown in Figure 3-7.
Figure 3-7 Installing the expansion bolt (2)
----End
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet
Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-9
3.1.6 Fastening the Base
To fasten the base, do as follows:
Step 1 Place the base on the cement plinth.
Step 2 Align the installation holes of the base with the expansion bolt holes on the cement plinth.
Step 3 Fasten the base on the cement plinth by using the M12x60 bolts, spring washers, flat washers,
and bevel washers, as shown in Figure 3-8.
Figure 3-8 Installing the base
4
12
3
(1) M12x60 bolt (2) Spring washer (3) Flat washer (4) Bevel washer 12
----End
3.1.7 Leveling the Base
To level the base, do as follows:
Step 1 Place a level bar on the top plane of the base in the latitudinal and longitudinal directions, as
shown in Figure 3-9.
Step 2 Check whether the leveling bubble in the level vial is in the middle.
Step 3 If the leveling bubble is not in the middle, add adjusting shims under the base, as shown in
Figure 3-10.
3 Installing the BTS3012AE Cabinet
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
3-10 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 3-9 Leveling the base (1)
21
(1) Level bar (2) Base
Figure 3-10 Leveling the base (2)
12
(1) Adjusting shim (2) Base
Step 4 Repeat steps 1 to 3 to ensure that the leveling bubble in the level vial is in the middle.
----End
3.1.8 Placing the Cabinet
� When lifting the cabinet, ensure that all the four lugs are tightened, that the angle between
the lifting rope and the top of the cabinet is at least 60o, and that the cabinet is level.
Installers must stay away from the cabinet when lifting it and ensure that the front door
and rear door are closed.
� When installing the cabinet in bad conditions (for example, in the case of strong wind),
pay extra attention to the gravity center of the cabinet to prevent the cabinet from slanting.
To place the cabinet, do as follows:
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet
Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-11
Step 1 Use a crane to lift the cabinet, as shown in Figure 3-11.
Figure 3-11 Lifting the cabinet
Step 2 Place slowly the cabinet on the base and align the installation holes at the bottom of the
cabinet with the bolt holes on the base.
Figure 3-12 shows how to place the cabinet on the base.
3 Installing the BTS3012AE Cabinet
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
3-12 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 3-12 Placing the cabinet on the base
1
23
(1) Cabinet (2) Base (3) Cement plinth
----End
3.1.9 Fastening the Cabinet
� This section applies to the installation of the BTS3012AE cabinet on a base or on U-bar supports.
� If the front door keeps open for a long time, use a solid object to support the lower part of the door
to prevent the deformation of the door.
� Before closing the front door, lift the support bar and slide it along the rail.
To fasten the cabinet, do as follows:
Step 1 Fasten the cabinet on the base by using two M12x35 bolts, spring washers, and flat washers,
as shown in Figure 3-13.
The bolts shall be inserted from the bottom to the top of the base near the cabinet rear.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet
Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-13
Figure 3-13 Fastening the cabinet on the base (Rear view)
2
3
4
56
1
(1) Cabinet rear (2) Base (3) Cement plinth
(4) M12x35 bolt (5) Spring washer 12 (6) Big flat washer
Step 2 Unlock and open the front door, as shown in Figure 3-14.
3 Installing the BTS3012AE Cabinet
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
3-14 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 3-14 Unlocking the cabinet
Step 3 Slide the support bar to fix the front door at a suitable angle.
� The front door can be fully opened to 120°.
� The support bar can be fixed at an angle of 90° or 120°.
Step 4 Fix one end of the support bar on the rail through a fixing bolt, as shown in
Figure 3-15.
The other end of the support bar is fixed on the cabinet through a screw.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet
Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-15
Figure 3-15 Fixing the front door
12
(1) Fixing bolt (2) Support bar
Step 5 Fasten the cabinet on the base by using two M12x70 bolts, spring washers, and flat washers,
as shown in Figure 3-16.
The bolts shall be inserted from the top to the bottom of the base near the front door.
Figure 3-16 Fastening the cabinet on the base (Front view)
1
23
4
(1) M12x70 bolt (2) Spring washer
(3) Flat washer (4) Installation hole for the bolt
3 Installing the BTS3012AE Cabinet
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
3-16 Huawei Technologies Proprietary Issue 01 (2006-09-06)
----End
3.1.10 Leveling the Cabinet
To level the cabinet, do as follows:
Step 1 Place a level bar on the top plane of the cabinet in the latitudinal and longitudinal directions,
as shown in Figure 3-17.
Step 2 Check whether the leveling bubble in the level vial is in the middle.
Step 3 If the leveling bubble is not in the middle, add adjusting shims under the lower support, as
shown in Figure 3-18.
Step 4 Repeat steps 1 to 3 to ensure that the leveling bubble in the level vial is in the middle.
Figure 3-17 Leveling the cabinet (1)
1
2
(1) Level bar (2) Cabinet
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet
Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-17
Figure 3-18 Leveling the cabinet (2)
1
2
(1) Cabinet (2) Adjusting shim
----End
3.1.11 Removing Lifting Lugs
Remove the four lifting lugs on the top of the cabinet, and then use the blind choke plugs
shipped with the product to cover the bolt holes, as shown in Figure 3-19.
Figure 3-19 Removing lifting lugs
1
2
(1) Lifting lug (2) Blind choke plug
3 Installing the BTS3012AE Cabinet
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
3-18 Huawei Technologies Proprietary Issue 01 (2006-09-06)
3.1.12 Illustration of the Installed Cabinet
Figure 3-20 shows the installed BTS3012AE cabinet.
Figure 3-20 Installed BTS3012AE cabinet
3.2 Installing a Cabinet on the Cement Floor with Insufficient
Bearing Capacity (< 800 kg/m2)
3.2.1 Installation Flowchart
Figure 3-21 shows the process flowchart for installing a cabinet on the cement floor with
insufficient bearing capacity.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet
Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-19
Figure 3-21 Process for installing a cabinet on the cement floor with insufficient bearing capacity
Start
Position thecabinet
Cast cementplinth
Prepare U-barsupports
Fasten U-barsupports
Level thecabinet
Drill holes and installexpansion bolts
Fasten thecabinet
Removelifting lugs
End
Position U-barsupports
Place thecabinet
Level U-barsupports
3 Installing the BTS3012AE Cabinet
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
3-20 Huawei Technologies Proprietary Issue 01 (2006-09-06)
3.2.2 Installation Process
3.2.3 Positioning the Cabinet
The BTS3012AE can be installed against wall, rear to rear, or side by side. The following
requirements must be met to ease casting the cement plinth and installing and maintaining the
equipment:
� When a single BTS3012AE cabinet is installed against wall, it is recommended to keep a
300 mm space between the rear and the wall to facilitate the installation.
� When two BTS3012AE cabinets are installed side by side, it is recommend to keep at
least 300 mm space between two sides.
� When two BTS3012AE cabinets are installed side by side and against the wall, the space
between two sides must be more than 600 mm.
� When the BTS3012AE is installed with the left side against the wall, the space between
the left side and the wall must be more than 600 mm.
� The BTS3012AE cannot be installed in wall corners.
Figure 3-2 shows the installation position of the BTS3012AE.
Figure 3-22 Installation position of the BTS3012AE cabinet
BTS 3012AE
1000
>
> 600
> 600
> 300
880
1300
1
3.2.4 Casting Cement Plinths
Determine the position of the wall or beam that bears the BTS3012AE. Then cast two cement
plinths on the floor or platform right above the bearing wall or the beam.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet
Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-21
The cement plinth must be 100 mm in height, and the distance between the two cement
plinths must be at least 6 m.
3.2.5 Preparing U-Bar Supports
Determine the length of U-bar supports based on the distance between the cement plinths, as
shown in Figure 3-23.
Figure 3-23 Dimensions of U-bar supports (unit: mm)
300
18- 16Ø
900
100839
723
20073
6704- 14Ø
3.2.6 Positioning U-Bar Supports
Drill eighteen φ16 holes and four φ14 holes on the U-bar supports according to Figure 3-23.
3.2.7 Drilling Holes and Installing Expansion Bolts
For details, see section 3.1.5 "Drilling Holes and Installing Expansion Bolts."
3.2.8 Fastening U-Bar Supports
Use either of the following methods to secure the U-bar support on the cement plinths:
� Cast the U-bar supports and the cement plinths together.
� Use expansion bolts to fasten the U-bar supports on the cement plinths.
Figure 3-24 shows how to fasten the U-bar supports on the cement plinths.
3 Installing the BTS3012AE Cabinet
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
3-22 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 3-24 Fastening the U-bar supports on the cement plinths
1
2
3
(1) M12x60 bolt (2) Spring washer (3) Flat washer
3.2.9 Leveling U-Bar Supports
To level the U-bar supports, do as follows:
Step 1 Place a level bar on the top plane of the U-bar supports in the latitudinal and longitudinal
directions, as shown in Figure 3-25.
Step 2 Check whether the leveling bubble in the level vial is in the middle.
Step 3 If the leveling bubble is not in the middle, add adjusting shims under the U-bar supports, as
shown in Figure 3-26.
Step 4 Repeat steps 1 to 3 to ensure that the leveling bubble in the level vial is in the middle.
Figure 3-25 Leveling the U-bar support (1)
1
2
(1) Level bar (2) U-bar support
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet
Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-23
Figure 3-26 Leveling the U-bar support (2)
1
2
3
(1) Level bar (2) U-bar support (3) Adjusting shim
----End
3.2.10 Fastening the Base
For details, see 3.1.4 "Leveling the Base."
3.2.11 Leveling the Base
For details, see 3.1.7 "Leveling the Base."
3.2.12 Placing the Cabinet
� When lifting the cabinet, ensure that all the four lugs are tightened, that the angle between
the lifting rope and the top of the cabinet is at least 60o, and that the cabinet is level.
Installers must stay away from the cabinet when lifting it and ensure that the front door
and rear door are closed.
� When installing the cabinet in adverse conditions (for example, in the case of strong wind),
pay special attention to the gravity center of the cabinet to prevent the cabinet from
slanting.
To place the cabinet, do as follows:
Step 1 Lift the cabinet through a crane, as shown in Figure 3-27.
3 Installing the BTS3012AE Cabinet
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
3-24 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 3-27 Lifting the cabinet
Step 2 Place slowly the cabinet on the U-bar supports and align the installation holes at the bottom of
the cabinet with the bolt holes on the U-bar supports.
Figure 3-28 shows how to place the cabinet on the U-bar supports.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet
Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-25
Figure 3-28 Placing the cabinet on the U-bar supports
----End
3.2.13 Fastening the Cabinet
� This section applies to the installation of the BTS3012AE cabinet on a base or on U-bar supports.
� If the front door keeps open for a long time, use a solid object to support the lower part of the door
to prevent the deformation of the door.
� Before closing the front door, lift the support bar and slide it along the rail.
To fasten the cabinet, do as follows:
Step 1 Fasten the cabinet on the base by using two M12x35 bolts, some spring washers, and some
big flat washers, as shown in Figure 3-29.
The bolts shall be inserted from the bottom to the top of the base near the cabinet rear.
3 Installing the BTS3012AE Cabinet
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
3-26 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 3-29 Fastening the cabinet on the base (Rear view)
2
3
4
561
(1) Cabinet rear (2) Base (3) U-bar supports
(4) M12x35 bolt (5) Spring washer 12 (6) Big flat washer
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet
Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-27
Step 2 Unlock and open the front door, as shown in Figure 3-30.
Figure 3-30 Unlocking the front door
Step 3 Slide the support bar to fix the front door at a suitable angle.
� The front door can be fully opened to 120°.
� The support bar can be fixed at an angle of 90° or 120°.
Step 4 Fix one end of the support bar on the rail through the fixing bolt, as shown in Figure 3-15.
The other end of the support bar is fixed on the cabinet through a screw.
Step 5 Fasten the cabinet on the base by using two M12x70 bolts, spring washers, and flat washers,
as shown Figure 3-31.
The bolts shall be inserted from the top to the bottom of the base near the front door.
3 Installing the BTS3012AE Cabinet
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
3-28 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 3-31 Fastening the cabinet on the base (Front view)
1
2
3
4
(1) M 12x70 bolt (2) Spring washer
(3) Flat washer (4) Installation holes for the bolts
----End
3.2.14 Leveling the Cabinet
To level the cabinet, do as follows:
Step 1 Place a level bar on the top plane of the cabinet in the latitudinal and longitudinal directions,
as shown in Figure 3-17.
Step 2 Check whether the leveling bubble in the level vial is in the middle.
Step 3 If the leveling bubble is not in the middle, add adjusting shims under the lower support.
Step 4 Repeat steps 1 to 3 to ensure that the leveling bubble in the level vial is in the middle.
----End
3.2.15 Removing Lifting Lugs
Remove the four lifting lugs on the top of the cabinet, and then use the blind choke plugs
shipped with the product to cover the bolt holes, as shown in Figure 3-32.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet
Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-29
Figure 3-32 Removing lifting lugs
1
2
(1) Lifting lug (2) Blind choke plug
3.2.16 Illustration of the Installed Cabinet
Figure 3-33 shows the installed cabinet.
3 Installing the BTS3012AE Cabinet
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
3-30 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 3-33 Installed cabinet
3.3 Installing Combined Cabinets
When installing two BTS3012AE combined cabinets, you are recommended to keep at least
300-mm space between two cabinets.
To install the combined cabinets, perform the following steps:
Step 1 Determine the installation positions of the cabinets, and keep at least 300-mm space between
two cabinets.
Step 2 Install the cabinets. See sections 3.1 "Installing a Cabinet on the Cement Floor with Sufficient
Bearing Capacity (ƒ 800 kg/m2)" and 3.2 "Installing a Cabinet on the Cement Floor with
Insufficient Bearing Capacity (< 800 kg/m2)."
Step 3 Connect a signal cable between the combined cabinets. Connect one end of the cable to the
port TO SLAVE CABINET on the DSCB of the main cabinet and the other end to that on the
DSCB of the extension cabinet.
Step 4 Connect the signal input/output cable for the combined cabinet on the main cabinet to the
CC_OUT port.
The cable connects to the CC_IN port before delivery.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet
Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-31
Step 5 Set the DIP switches on the DCSU.
----End
The DCSU has 14 DIP switches on it. SW12, SW13, and SW14 are reserved.
Figure 3-34 shows the initial settings for the DIP switches on the DCSU.
Figure 3-34 DIP switches on the DCSU
1 4
1 4
1 41 4SW6 SW7
1 4 1 4
1 4
SW9 SW10
SW8
SW11
SW1
OFF
OFF
ON
ON
ON
ON
1 4
1 4
1 4
SW14
SW13
SW12
OFF
ON1 4
1 4
1 4
1 4
SW5
SW4
SW3
SW2
OFF
ONOFF
SW1 and SW11 are used to set the main cabinet and extension cabinet in the cabinet group,
and to select the terminal match.
Table 3-1 lists the settings for SW1.
Table 3-1 Settings for SW1
SW1 Function
All ON Main cabinet of the main cabinet group
All OFF Other cases
Table 3-2 lists the settings for SW11.
Table 3-2 Settings for SW11
SW11 Function
All ON CBUS1 terminal match
All OFF CBUS1 no terminal match
3 Installing the BTS3012AE Cabinet
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
3-32 Huawei Technologies Proprietary Issue 01 (2006-09-06)
The descriptions of SW11 in different situations are as follows:
� Single cabinet: All ON
� Combined cabinet: All ON
� Two-cabinet group: All ON
� Three-cabinet group: All OFF for the main cabinet and all ON for the other cabinets
SW2 through SW5 are used to set the main cabinet and extension cabinet, and select the
terminal match.
See Table 3-3 lists the settings for SW2−SW5.
Table 3-3 Settings for SW2−SW5
SW2–SW5 Function
All ON Main cabinet
All OFF Extension cabinet
SW6 and SW7 are used to set E1 impedance. See Table 3-4 for details.
Table 3-4 Settings for SW6 and SW7
DIP Switch DIP Digit ON/OFF Function
ON E1 1: 75 ohms 1
OFF E1 1: 120 ohms
ON E1 2: 75 ohms 2
OFF E1 2: 120 ohms
ON E1 3: 75 ohms 3
OFF E1 3: 120 ohms
ON E1 4: 75 ohms
SW6
4
OFF E1 4: 120 ohms
ON E1 5: 75 ohms 1
OFF E1 5: 120 ohms
ON E1 6: 75 ohms 2
OFF E1 6: 120 ohms
ON E1 7: 75 ohms 3
OFF E1 7: 120 ohms
ON E1 8: 75 ohms
SW7
4
OFF E1 8: 120 ohms
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet
Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-33
SW8 is used to set the cabinet number. In a cabinet group, you need to set SW8 for the main
cabinet. See Table 3-5 for details. You can use the default settings for the extension cabinets,
that is, all the extension cabinets are set to ON.
Table 3-5 Settings for SW8
DIP Digit
1 2 3 4
Function
ON ON ON ON Main cabinet of the main cabinet group
OFF OFF ON ON Main cabinet of extension cabinet group 1
ON OFF OFF ON Main cabinet of extension cabinet group 2
SW9 and SW10 are used to set cabinet type. See Table 3-6 for details.
Table 3-6 Settings for SW9 and SW10
SW9 SW10
1 2 3 4 1 2 3 4
Function
OFF ON ON ON ON ON ON ON The cabinet type is BTS3012AE.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 4 Installing Boards
Issue 01 (2006-09-06) Huawei Technologies Proprietary 4-1
4 Installing Boards About This Chapter
The following table lists the contents of this chapter.
Title Description
4.1 Introduction to Installation
Positions
Introduces the installation positions of boards in the
BTS3012AE subrack.
4.2 Preparations Describes the preparatory work before board installation.
4.3 Installing the DTMU Describes how to install the DTMU.
4.4 Installing the DATU Describes how to install the DATU.
4.5 Installing the PSU and
DPMU
Describes how to install the PSU and DPMU.
4.6 Installing the DELU Describes how to install the DELU.
4.7 Installing the DMLU Describes how to install the DMLU.
4.8 Installing the DTRU Describes how to install the DTRU.
4.9 Installing the DDPU and
DCOM
Describes how to install the DDPU and DCOM.
4 Installing Boards
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
4-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)
4.1 Introduction to Installation Positions
Figure 4-1 shows the installation positions of all the boards of the BTS3012AE.
Figure 4-1 Boards in the BTS3012AE subrack
Cable in/outAC lightning
D
C
O
M
D
D
P
U
D
C
O
M
D
D
P
U
D
C
O
M
D
D
P
U
D
T
R
U
D
T
R
U
D
T
R
U
D
T
R
U
D
T
R
U
D
T
R
U
PSU PSU PSU PSU
PSUPSUPSUDPMU
Air return
Wire holder
Wire holder
FAN
DELU0
DELU1DMLU
AC PDU
Air return
D
T
M
U
D
T
M
U
D
A
T
U
D
C
C
U
D
C
S
U
Wire holder
DC
PDU
BAT 48V 50AH
Air inlet
Tra
nsm
issio
nu
nit
BAT 48V 150AH
Air inlet
4.2 Preparations
Before installing the boards, perform the following preparations:
� Wear an antistatic wrist strap, and connect the ESD plug to the ESD connector on the
cabinet, as shown in Figure 4-2. Ensure that the wrist strap is in good contact with your
wrist.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 4 Installing Boards
Issue 01 (2006-09-06) Huawei Technologies Proprietary 4-3
� If the cabinet is not grounded, first connect the PGND wiring terminal on the left of the cabinet to
the external grounding bar. For details, see section 6.3 "Installing PGND Cables."
� Keep the ESD wrist strap in good condition. Its resistance should be between 0.75 Mega ohms and
10 Mega ohms. Typically, the life expectancy of the ESD wrist strap lasts for about two years.
Replace the strap when the resistance falls beyond the specified range.
Figure 4-2 Wearing an antistatic wrist strap
1
2
3
(1) ESD connector (2) ESD plug
(3) Antistatic wrist strap
� The antistatic wrist strap cannot prevent static electricity from being generated by
friction between a board and your clothes. Ensure that boards are not in contact with
your clothes.
� Clean up the subracks.
� Check whether there are any bent, missed, or broken pins on the backplane.
− If there is any bent pin, replace it or straighten it with a pair of nipper pliers in case of
an emergency.
− If there is any missed pin, replace the backplane.
� Check whether the sockets on the backplanes and the boards are deformed.
− If the deformation is not obvious, adjust the socket using a pair of nipper pliers.
− If the deformation is serious, replace the backplane or the board.
� Prepare a #2 crossover screwdriver whose diameter is 6 mm to tighten the M3 captive
screws on the board panels.
� Keep the boards or parts that are not installed in antistatic bags. Place the removed
boards or parts on the antistatic pad or other antistatic materials. Never pack or hold the
boards or parts using plastic foams, common plastic bags, or paper bags.
4 Installing Boards
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
4-4 Huawei Technologies Proprietary Issue 01 (2006-09-06)
If you are not clear about the specifications of the screwdrivers, try different screwdrivers until you find
a suitable one.
4.3 Installing the DTMU
The DTMU is placed in the common subrack. Set the DIP switches on the DTMU before
installation.
4.3.1 Setting DIP Switches on the DTMU
The DTMU has five DIP switches on it. S4, S5, S6, and S7 are used to select whether the
rings of E1 1 through E1 8 are grounded. S3 is reserved.
Figure 4-3 shows the initial setting of the DIP switches on the DTMU.
Figure 4-3 DIP switches on the DTMU
ON
S4
S5
S6
S7
OFF
S3
4
14
14
1
4
1
4
1
Table 4-1 describes the settings and functions of the DIP switches.
Table 4-1 S4/S5/S6/S7 setting descriptions
DIP Switch DIP Position
ON/OFF Functions
ON E1 1, sending, ring grounded 1
OFF E1 1, sending, ring ungrounded
ON E1 1, receiving, ring grounded 2
OFF E1 1, receiving, ring ungrounded
S5
3 ON E1 2, sending, ring grounded
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 4 Installing Boards
Issue 01 (2006-09-06) Huawei Technologies Proprietary 4-5
DIP Switch DIP Position
ON/OFF Functions
OFF E1 2, sending, ring ungrounded
ON E1 2, receiving, ring grounded 4
OFF E1 2, receiving, ring ungrounded
ON E1 3, sending, ring grounded 1
OFF E1 3, sending, ring ungrounded
ON E1 3, receiving, ring grounded 2
OFF E1 3, receiving, ring ungrounded
ON E1 4, sending, ring grounded 3
OFF E1 4, sending, ring ungrounded
ON E1 4, receiving, ring grounded
S4
4
OFF E1 4, receiving, ring ungrounded
ON E1 5, sending, ring grounded 1
OFF E1 5, sending, ring ungrounded
ON E1 5, receiving, ring grounded 2
OFF E1 5, receiving, ring ungrounded
ON E1 6, sending, ring grounded 3
OFF E1 6, sending, ring ungrounded
ON E1 6, receiving, ring grounded
S7
4
OFF E1 6, receiving, ring ungrounded
ON E1 7, sending, ring grounded 1
OFF E1 7, sending, ring ungrounded
ON E1 7, receiving, ring grounded 2
OFF E1 7, receiving, ring ungrounded
ON E1 8, sending, ring grounded 3
OFF E1 8, sending, ring ungrounded
ON E1 8, receiving, ring grounded
S6
4
OFF E1 8, receiving, ring ungrounded
4 Installing Boards
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
4-6 Huawei Technologies Proprietary Issue 01 (2006-09-06)
4.3.2 Installation Procedure
Wear an antistatic wrist strap when installing boards.
Install the DTMU as follows:
Step 1 Secure the captive screws on the panel by screwing them clockwise through a #2 cross
screwdriver whose diameter is 6 mm. Ensure that the screws are active, that is, the screw
threads are not stuck to the spanner. See (a) in Figure 4-4.
Step 2 Hold the spanner on the upper part of the front panel with one hand and support the board
with the other hand. Position the board in the corresponding guide rail according to the
nameplate.
Step 3 Hold the two spanners and gently push the board along the guide rail until they are in
position.
Step 4 Turn inward the two spanners to the position as shown in (b) of Figure 4-4.
Ensure that the crotchets on both ends of the spanners hook on to the square holes of the
subrack, as shown in Figure 4-5.
Step 5 Secure the captive screws on the panel by screwing them clockwise with a #2 cross
screwdriver whose diameter is 6 mm, as shown in (c) of Figure 4-4.
----End
Figure 4-4 Installing the DTMU
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 4 Installing Boards
Issue 01 (2006-09-06) Huawei Technologies Proprietary 4-7
Figure 4-5 Hooking spanners on to the square holes of the subrack
4.4 Installing the DATU
The DATU is placed in the common subrack.
Table 4-2 shows the default setting of the DIP switches before delivery.
Table 4-2 Default setting of the DIP switches on the DATU
DIP Switch 1 2 3 4
SW1 OFF OFF ON ON
SW2 ON ON ON ON
SW3 ON ON ON ON
Figure 4-6 shows the DIP switches on the DATU.
4 Installing Boards
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
4-8 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 4-6 DIP switches on the DATU
1 4SW1 SW3 SW2
ONOFF ON
OFF14
OFF
ON
14
The installation procedure for the DATU is the same as that for the DTMU. For details, see
section 4.3.2 "Installation Procedure."
4.5 Installing the PSU and DPMU
The Power Supply Unit (PSU) is located in the power subrack. The minimum configuration of
PSUs is 1 + 1. The number of PSUs under full configuration is 7.
The PSU functions as follows:
� Converting 220 VAC to –48 VDC for all modules inside the BTS3012AE.
� Monitoring module fault alarms, module protection alarms, and AC power-off alarms.
� Monitoring float charging of the storage battery and adjusting the voltage and current of
the storage battery.
The DPMU is in the power subrack of the cabinet. The BTS3012AE requires only one
DPMU.
The DPMU functions as follows:
� Power system management and battery charge and discharge management
� Water, smoke, access control, standby Boolean value, temperature and humidity, battery
temperature, and standby analog report
� Power distribution check and power distribution alarm report
� Boolean value alarm report
4.5.1 PSU and DPMU Installation Procedure
The PSU and DPMU installation procedure is as follows:
Step 1 Check that all switches of the eight-bit DIP switch are set to OFF position, as shown in Figure
4-7.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 4 Installing Boards
Issue 01 (2006-09-06) Huawei Technologies Proprietary 4-9
Figure 4-7 DIP switch of the DPMU
12345678
ON
3
1 2 3 4 5 6 7 8ON
1
2
(1) DIP switch after zoomed in and turned 180° clockwise
(2) Normal view of the DIP switch (3) Rear view of the DPMU
Step 2 Loosen the handle on the PSU panel and slide the PSU or DPMU forward along the guide rail
until you can feel obvious resisting force. See Figure 4-8.
4 Installing Boards
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
4-10 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 4-8 Installing the PSU and DPMU (1)
PSU7
PSU2 PSU3DPMU PSU1
PSU6
PSU4 PSU5
Step 3 Fasten the handle as shown in Figure 4-9.
Figure 4-9 Installing the PSU and DPMU (2)
PSU6 PSU7
PSU2 PSU3DPMU PSU1
PSU4 PSU5
Step 4 Fasten the screws on the PSU and DPMU panel.
Repeat the previous steps until the DPMU and all the configured PSUs are installed. Install
the PSUs in the ascending order from PSU1 all the way to PSU7.
----End
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 4 Installing Boards
Issue 01 (2006-09-06) Huawei Technologies Proprietary 4-11
4.6 Installing the DELU
4.6.1 Installation Overview
The E1 Signal Lightning Protection Unit for DTRU BTS (DELU) is configured in slot 0 or 2
of the DCSB. The DELU is mandatory and the minimum configuration is one. If the DMLU
is not configured, a maximum of three DELUs can be configured on the DSCB.
The main function of the DELU is to realize the lightning protection of four E1 signals on a
board. Under the full configuration of three DELUs, the lightning protection of 12 E1 signals
can be realized.
4.6.2 Installation Procedure
The DELU installation procedure is as follows:
Step 1 Level the DELU.
Step 2 Hold the left and right sides of the DELU with your hands and place it in the slot.
Step 3 Push the board at the left and right sides of the front panel until it is in secure contact with the
slot.
----End
4.7 Installing the DMLU
4.7.1 Installation Overview
The Monitor Signal Lightning Protection Unit for DTRU BTS (DMLU) is configured in slot 1
of the DCSB. The DMLU is optional and the full configuration is one.
The DMLU functions as follows:
� Supporting lightning protection of 14 external Boolean value inputs.
� Providing a 2-route 485 serial control bus interface.
4.7.2 Installation Procedure
The procedure for installing the DMLU is the same with that for the DELU. For details, see
section 4.6.2 "Installation Procedure."
4.8 Installing the DTRU
4 Installing Boards
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
4-12 Huawei Technologies Proprietary Issue 01 (2006-09-06)
After powering on the cabinet, do not touch any DTRU in case they get damaged.
The DTRUs are placed in the DTRU subrack.
Figure 4-10 shows the front panel of a DTRU.
Figure 4-10 Front panel of a DTRU
To install a DTRU, do as follows:
Step 1 Decide the slot for installing the DTRU for easy cabling and maintenance.
Step 2 Hold the handle with one hand and support the board with the other to position the board into
the guide rail.
Step 3 Push the board along the guide rail.
Step 4 Fix the board in the subrack with four screws at four corners of the panel.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 4 Installing Boards
Issue 01 (2006-09-06) Huawei Technologies Proprietary 4-13
Step 5 Remove the dustproof cap on the power cable of the DTRU and insert the cable connector
into the PWR port on the corresponding DTRU panel.
Step 6 Screw the two fastening bolts on the cable connector.
Step 7 Install the dummy panel on the vacant slot and fasten it with four screws to make the dummy
panel in close contact with the subrack.
Step 8 Use a cable tie to attach the unused power cable to the handle of the dummy panel.
----End
� Place the removed dustproof cap under the cabinet for future use.
� Install a dustproof cap on the connector of the unused power cable to prevent the inner conductor in
the cable connector from touching the edge angles of the cabinet.
4.9 Installing the DDPU and DCOM
� After powering on the cabinet, do not touch any DDPU or the DCOM in case it may get
damaged.
� When removing a DDPU, install a dustproof cap on the connector of the removed power
cable to prevent the inner conductor in the cable connector from touching the edge angles
of the cabinet.
The DDPUs and the DCOMs are placed in the DAFU subrack.
Figure 4-11 shows the front panel of a DDPU. The procedure for installing a DCOM is the
same with that for installing a DDPU.
4 Installing Boards
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
4-14 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 4-11 Front panel of a DDPU
To install a DDPU, do as follows:
Step 1 Decide the slot for installing the DTRU for easy cabling and maintenance.
Step 2 Hold the handle with one hand and support the board with the other to position the board into
the guide rail.
Step 3 Push the board along the guide rail.
Step 4 Fix the board in the subrack with four screws at four corners of the panel.
Step 5 Remove the dustproof cap on the power cable of the DDPU and insert the cable connector
into the POWER port on the corresponding DDPU panel.
Step 6 Screw the two fastening bolts on the cable connector.
Step 7 Install the dummy panel on the vacant slot and fasten it with four screws to make the dummy
panel in close contact with the subrack.
Step 8 Use a cable tie to attach the unused power cable and signal cable to the handle of the dummy
panel.
----End
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 4 Installing Boards
Issue 01 (2006-09-06) Huawei Technologies Proprietary 4-15
� Place the removed dustproof cap under the cabinet for future use.
� Install a dustproof cap on the connector of the unused power cable to prevent the inner conductor in
the cable connector from touching the edge angles of the cabinet.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 5 Installing Auxiliary Equipment
Issue 01 (2006-09-06) Huawei Technologies Proprietary 5-1
5 Installing Auxiliary Equipment About This Chapter
The following table lists the contents of this chapter.
Title Description
5.1 Installing Transmission
Unit
Describes how to install the transmission unit.
5.2 Installing Outdoor
Interface Boxes
Describes how to install outdoor interface boxes.
5 Installing Auxiliary Equipment
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
5-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)
5.1 Installing Transmission Unit
5.1.1 Introduction to Installation Positions
The transmission unit is installed in the transmission equipment subrack. Figure 5-1 shows the
installation position of the transmission unit.
Figure 5-1 Installation position of the transmission unit
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 5 Installing Auxiliary Equipment
Issue 01 (2006-09-06) Huawei Technologies Proprietary 5-1
Tra
nsm
issio
nu
nit
5.1.2 Installation Procedure
The procedure for installing the transmission unit is as follows:
Step 1 Remove the dummy panel and air deflector plate in the transmission unit subrack according to
the space required by the transmission unit.
5 Installing Auxiliary Equipment
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
5-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)
If the transmission unit (including microwave equipment) is installed in the cabinet, remove the dummy
panel and air deflector plate to avoid poor ventilation and over-high temperature. See Figure 5-2. If the
height of the transmission unit is nU, remove n (n ≤ 6) dummy panels and n (n ≤ 6) air deflector plates.
Figure 5-2 Positions of the dummy panel and air deflector plate
1 2
(1) Dummy panel (2) Air deflector plate
Step 2 Install the transmission unit in the transmission unit subrack and fasten the screws as shown
in Figure 5-3.
Figure 5-3 Installing transmission unit
1
2
(1) Transmission unit subrack (2) Transmission unit
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 5 Installing Auxiliary Equipment
Issue 01 (2006-09-06) Huawei Technologies Proprietary 5-3
----End
5.2 Installing Outdoor Interface Boxes
The outdoor interface box has two types: outdoor transmission interface box and outdoor
power interface box. The two types of interface boxes share the same installation methods.
The installation methods consist of the following:
� Installing the Outdoor Interface Box on a Wall
� Installing the Outdoor Interface Box on a Pole
5.2.1 Introduction to the Outdoor Transmission Interface Box
The TSI-DDF/ODF outdoor transmission interface box (hereinafter referred to as the
transmission interface box) serves as the interface between the transmission unit you have
prepared and Huawei BTS equipment. Huawei provides the following two types of
transmission interface boxes:
� 75-ohm transmission interface box (supporting 75-ohm transmission mode)
� 120-ohm transmission interface box (supporting 120-ohm transmission mode)
Dimensions
The 75-ohm transmission interface box and the 120-ohm transmission interface box have the
same dimensions. The dimensions are as follows:
� Length: 420 mm
� Width: 378 mm
� Height: 125 mm
Weight
The weight of the transmission interface box is 4.92 kg before delivery.
Components of the 75-ohm Transmission Interface Box
The 75-ohm transmission interface box under full configuration consists of the following
parts:
� A case
� A 75-ohm digital unit
� A grounding busbar
� 12-core fusion parts
Figure 5-4 shows the internal structure of the box.
5 Installing Auxiliary Equipment
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
5-4 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 5-4 Internal structure of the 75-ohm outdoor transmission interface box
1
2
3
4
(1) 12-core fusion parts (2) 75-ohm digital unit
(3) Grounding busbar (4) Case
The 12-core fusion parts consist of:
� A 12-core fusion box
� A fiber adaptor rack
� A fiber coiler
� A fiber stripping unit
Figure 5-5 shows these parts.
Figure 5-5 Structure of the 12-core fusion parts
1
2
3
4
(1) 12-core fusion box (2) Fiber adapter rack
(3) Fiber coiler (4) Fiber stripping unit
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 5 Installing Auxiliary Equipment
Issue 01 (2006-09-06) Huawei Technologies Proprietary 5-5
The internal parts of the 75-ohm transmission interface box are installed before delivery.
Components of the 120-ohm Transmission Interface Box
The 120-ohm transmission interface box under full configuration consists of the following
parts:
� A case
� A 120-ohm digital unit
� A grounding busbar
� 12-core fusion part
Figure 5-6 shows the internal structure of the box.
Figure 5-6 Internal structure of the 120-ohm transmission interface box
1
2
3
4
(1) 12-core fusion parts (2) 120-ohm digital unit
(3) Grounding busbar (4) Case
The 12-core fusion parts of the 120-ohm transmission interface box and those of the 75-ohm
transmission interface box have the same structure, as shown in
Figure 5-5.
The internal parts of 120-ohm transmission interface box are installed before delivery.
5.2.2 Introduction to the Outdoor Power Interface Box
The outdoor power interface box (hereinafter referred to as the power interface box) functions
as the interface between the power distribution unit you have prepared and the Huawei BTS
equipment. Huawei provides the following two types of power interface boxes:
� 220 VAC power interface box (supporting 220 VAC power inputs)
� 110 VAC power interface box (supporting 110 VAC power inputs)
5 Installing Auxiliary Equipment
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
5-6 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Dimensions
The dimensions of the power interface box are as follows:
� Length: 420 mm
� Width: 378 mm
� Height: 125 mm
Weight
The weight of the power interface box is 9.8 kg before delivery.
Components of the 220 VAC Power Interface Box
The 220 VAC power interface box under full configuration consists of the following parts:
� A case
� A Miniature Circuit Breaker (MCB) of the mains supply
� Generator components (optional, including the generator MCB and the MCB
interlocking device)
� I/O cable terminal bars
Figure 5-7 shows the internal structure of the power interface box under full configuration.
The MCB interlocking device guarantees that only one of the MCBs stays in the closed status at any
point of time.
Figure 5-7 Internal structure of the 220 VAC power interface box
1 2 3
4
5
6
(1) MCB of mains supply (2) MCB interlocking device (3) MCB of generator
(4) Case (5) I/O cable terminal bars (6) Cable passage
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 5 Installing Auxiliary Equipment
Issue 01 (2006-09-06) Huawei Technologies Proprietary 5-7
Components of the 110 VAC Power Interface Box
The 110 VAC power interface box and the 220 VAC power interface box are similar in
components, but different in MCB specifications.
5.2.3 Installing the Outdoor Interface Box on a Wall
To install the outdoor interface box on a wall, perform the following steps:
Step 1 Determine the position of the case according to the engineering requirement.
Step 2 Mark the positions for four expansion bolts on a wall with the marking template delivered
with the outdoor interface box.
Figure 5-8 shows the positions of the expansion bolts.
Figure 5-8 Positions of the expansion bolts
35
4
310
Step 3 Drill holes on the marked points.
Step 4 Put the expansion bolt into the holes, and hammer it until the expansion tube is completely
buried in the wall.
Step 5 Remove the nut, spring washer, and flat washer.
Step 6 Align the four installation holes on the outdoor interface box through the expansion bolts, and
then place the outdoor interface box at the installation position.
Step 7 Put flat washers, spring washers, and nuts to the expansion bolts. Adjust the outdoor interface
box, and then tighten the nuts and explode the expansion bolts, as shown in Figure 5-9.
5 Installing Auxiliary Equipment
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
5-8 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 5-9 Installing the outdoor interface box on a wall
4
5
6
1 2
3
(1) Outdoor interface box (2) Wall (3) Flat washer 8
(4) Spring washer 8 (5) M8 nut (6) M8x80 expansion bolt
5.2.4 Installing the Outdoor Interface Box on a Pole
The interface box can be installed on an upright steel pole. The external diameter of the steel
pole should be within 60 mm and 114 mm.
To install the outdoor interface box on a pole, perform the following steps:
Step 1 Use the bolt M8 x 25, spring washer 8, and flat washer 8 to fix the outdoor interface box to
the pole fixtures, as shown in Figure 5-10. Ensure that the holes on the pole fixtures match the
holes on the outdoor interface box.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 5 Installing Auxiliary Equipment
Issue 01 (2006-09-06) Huawei Technologies Proprietary 5-9
Figure 5-10 Fixing the pole fixture to the interface box
12
4
5
3
(1) Outdoor interface box (2) Pole fixture (3) Flat washer 8
(4) Spring washer 8 (5) Bolt M8x25
Step 2 Lift the interface box installed with two pole fixtures. Then, install another two pole fixtures.
Ensure that the pole is between the two fixture assemblies.
Step 3 Put bolts M10 through the two fixture assemblies. Add a flat washer, a spring washer, and a
nut to each bolt. Then, use a wrench to tighten the nuts, as shown in Figure 5-11.
Figure 5-11 Fixing the interface box to the pole
1
2
34
5
6
(1) Flat washer 10 (2) Bolt M10 (3) Flat washer 10
(4) Spring washer 10 (5) Nut M10 (6) Pole
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-1
6 Installing Cables
Power off the BTS3012AE cabinet before installing the external cables.
About This Chapter
The following table lists the contents of this chapter.
Title Description
6.1 Introduction to the Cables
to be Installed On Site
Introduces the cables to be installed on site.
6.2 Installing the Power
Cables
Describes how to install the power cables.
6.3 Installing PGND Cables Describes how to install PGND cables.
6.4 Installing the E1 Cables Describes how to install E1 cables.
6.5 Installing Optical Fibers Describes how to install optical fibers.
6.6 Installing the RF Signal
Cables
Describes how to install RF signal cables.
6.7 Installing the Cable for the
Combiner on the DTRU
Describes how to install the cable for the combiner on the
DTRU.
6.8 Installing the 1/4-Inch RF
Jumper
Describes how to install the 1/4-inch RF jumper.
6.9 Installing the 1/2-Inch RF
Jumper
Describes how to install the 1/2-inch RF jumper.
6.10 Installing the Boolean
Value Input Signal Cable
Describes how to install the Boolean value input signal
cable.
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Title Description
6.11 Installing the Built-In
Storage Battery and Its Cables
Describes how to install the built-in storage battery and its
cables.
6.12 Installing Cables for the
Combined Cabinet
Describes how to install cables for the combined cabinet.
6.13 Installing Cables for the
Cabinet Group
Describes how to install cables for the cabinet group.
6.14 Installing the RET
Control Signal Cable
Describes how to install the RET control signal cable.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-3
6.1 Introduction to the Cables to be Installed On Site
6.1.1 Introduction to Cabling Holes
A cabling hole is where the external cable is led into or out of the cabinet. The BTS3012AE
cabling holes are at the bottom of the cabinet, as shown in Figure 6-1.
Figure 6-1 BTS3012AE cabling holes
2
34
5
BTS3012AE cabinet floor
1
(1) GPS cabling hole (2) Waterproof module subrack
(3) Grounding bar (4) Cabling hole for the E1 trunk cable, environment monitoring
cable, and the cable between combined cabinets
(5) Cabling hole for the RF jumper
Figure 6-2 shows the silkscreens of the cabling holes.
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-4 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 6-2 Silkscreens of the cabling holes
BA
T P
GN
D
PG
ND
D1
L2 L3
N
AC
L o
ut
AC
L o
ut
COMPRESS
1
PG
ND
02
S/HDSL-01E1-3
E1-1/OUTE1-2/OUT
COMPRESS
2
Microwave 01
SW INRRU-48V
RRUGND
BATDOOR
BATTEM
Signal01
Signal02
Microwave 02S/HDSL-02
E1-4
Microwave 03
Microwave 04
ANT5
ANT4
ANT3
ANT2
ANT1
ANT0
ANT8
ANT7
ANT6
ANT11
ANT10
ANT9
3
(1) Silkscreen of the waterproof module subrack
(2) Silkscreen of the cabling hole for E1 trunk cable, environment monitoring cable,
or combined cabinet cable E1
(3) Silkscreen of the cabling hole for the RF jumper
6.1.2 Cable Layout at the Cabinet Front
Figure 6-3 shows the cable layout at the BTS3012AE cabinet front.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-5
Figure 6-3 Cable layout at the cabinet front
P1
Signal cable Power cable RF cable
DCCUDATUDCSUDTMUDTMU
FAN
DCOM
DTRU DTRU DTRU DTRU
DDPU DDPUDCOMDDPU
DTRUDTRU
R1
R8
R3R4
R5R6
R9 R10 R11 R12
R13 R15 R16 R17 R18R14
R7
S1
R20
R2
R21
R22
R23
R24
R25
R26
R27
R28 R30
R29
D
T
R
B
PSUPSU PSU PSU
AC PDU
Cable inletEMI
P2 P3
P4 P5 P6
P1
P2P3P4
P7
P7.2
P8
P9
P9
P8
S1
S2
S2
S3
S3
S4
S5
S5
S6
S6.3 S7.3S7.2
S7
S10
S8
S9
S11.1
S11.2
S11.3
S11
S12
S12
P16
P13
P15
P11
S13
P5
P6
P10
S21
S22
S21
S6.1
P7.1
S6.2
R19
R7
R13
R1
R2
R3
R4
R5
R6
R8
R11
R15 R17
R14
R9
R10
R16
R12
R18
S7.1
P7.3
DCOM
In Figure 6-3, S4 and S15 connect to the NodeB Power Monitor unit Interface Board (NPMI)
on the top of the cabinet. Figure 6-4 shows the cable layout.
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-6 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 6-4 NPMI cable layout on the top of the cabinet
JAC2 JK2
JAC1 JK1
JTD1 JTD2
JTD4 JTD5
JKM1 SMOKE DOORWATER
JTD6 JTD7
JTD3 TEM_HUM
BAT_TEM2BAT_TEM1
FU_ALM
S13S4
S14S15S16
S17 S18 S19 S20
J1
COM 1
COM 2
COM 3
COM 4
BAT_TEM3
S11
Table 6-1 lists the cables laid out at the cabinet front.
Table 6-1 Cables laid out at the cabinet front
Cable No. Cable Name Quantity
R1−R6 RF Tx signal cable 6
R7−R18 RF Rx signal cable 12
R19−R30 Cable for combiner on the DTRU 12
S1 Combined-cabinet signal cable between the DCSU
and the DSCB
1
S2 TOP1 signal cable from DCCU to DSCB 1
S3 E1 signal transfer cable 1
S4 Monitoring transfer cable from NPMI to DSCB 1
S5 TOP2 signal cable from DCSU to DSCB 1
S6 Signal cable between the DSCB and slots 0 through
2 in the DAFU subrack
1
S7 Signal cable between the DSCB and slots 3 through
5 in the DAFU subrack
1
S8 Cable for combined cabinet 1
S9 Signal cable 1 between cabinet groups 1
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-7
Cable No. Cable Name Quantity
S10 Signal cable 2 between cabinet groups 1
S11 RS485 environment monitoring signal cable 1
S12 Signal cable between the DCSU and the DTRB 1
S13 PMU monitoring cable 1
S14 Alarm cable for the air breaker 1
S15 Cable for the temperature sensor of the built-in
storage battery 1(delivered
with the
cabinet)
S16 Alarm cable for the AC lightning arrester 1
S17 Cable for the temperature and humidity sensor 1
S18 Cable for the access control sensor 1
S19 Cable for the water sensor 1(delivered
with the
cabinet)
S20 Cable for the smoke sensor 1
S21 75-ohm/120-ohm E1 cable 2
S22 Boolean value input cable 1
P1–P6 Power cable between the DC power distribution box
and DTRU 0–DTRU 6
6
P7 Power cable between the DC power distribution box
and the DAFU subrack 2
P8 Power cable between the DC power distribution box
and the DCCU
1
P9 Power cable between the DC power distribution box
and the FAN subrack
1
P10 Power cable between the DC power distribution box
and the heat exchanger
1
P11–P14 PGND cable 4
P15–P18 PGND cable 4
6.1.3 Wiring on the Back of the Cabinet
Figure 6-5 shows the wiring on the back of the cabinet.
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-8 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 6-5 Wring on the back of the BTS3012AE cabinet
L4L4L5L5L6L6L7
5432 1
RTN Load1 Load2 BAT
L7L8L8
10
-48
V L
oa
d1
-48
V L
oa
d2
9
8
13
14 15
S14
RTN -48V
1234,5
6
7
891011
12.112.2
1 2 3
4 65
7
8 910,14
P12
P17
P18
S12
airconditioner
or heatexchanger
S17
S19
S20
S18.1
S15
S14
S18.2
S11P10 12
P147
13
RT
N
Power cable Signal cable
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-1
Table 6-2 lists the cables on the back of the cabinet.
Table 6-2 Cables on the back of the BTS3012AE cabinet
Cable No. Cable Name Quantity
S11 RS485 environment monitoring signal cable 1
S12 Signal cable between the DCSU and the DTRB 1
S13 PMU monitoring cable 1
S14 Alarm cable for the air breaker 1
S15 Cable for the temperature sensor of the built-in storage
battery 1(delivered
with the
cabinet)
S17 Cable for the temperature and humidity sensor 1
S18 Cable for the access control sensor 1
S19 Cable for the water sensor 1(delivered
with the
cabinet)
S20 Cable for the smoke sensor 1
P10 Power cable between the DC power distribution box and
the heat exchanger
1
P11–P14 PGND cable 4
P15–P18 PGND cable 4
1–3 Live wire between the filter and the terminal on the back
of the AC power distribution box
3
4, 5 Neutral wire between the filter and the terminal on the
back of the AC power distribution box 2
6–8 Live wire between the terminal on the back of the AC
power distribution box and the PSU
3
9–11 Neutral wire between the terminal on the back of the AC
power distribution box and the PSU
3
12 AC power cable between the AC power distribution box
and the heat exchanger
1
13 PSU BAT output power cable to air breaker 1
14 Battery compartment positive pole 1
15 Air breaker to battery compartment negative pole 1
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)
6.2 Installing the Power Cables
Never connect the N wire of the AC power cable to the PGND cable of the exchange
equipment or communication equipment.
6.2.1 Introduction to the Power Cables
The BTS3012AE supports three power input modes:
� 220 VAC 3-phase 4-core input
� 220 VAC single-phase 2-core input
� 110 VAC dual-live input
Table 6-3 lists the specifications of the AC power cables for the BTS3012AE in different
input modes.
Table 6-3 Specifications of the AC power cables for the BTS3012AE
Power Input Mode Core Wire Core
Quantity
Sectional Area Color
L 3 10 mm2 Red 220 VAC 3-phase
4-core input N 1 10 mm
2 Black
L 1 16 mm2 Red 220 VAC
single-phase 2-core
input N 1 16 mm2 Black
L 2 16 mm2 Red 110 VAC dual-live
input N 1 16 mm
2 Black
� The AC power cables for the BTS3012AE are purchased at the local place. The colors of the cables
must comply with the local rules and regulations. If the local rules and regulations have no special
requirements for cable colors, use the cables delivered together with the BTS.
� The default color of the delivered L wire is red and that of the N wire is black.
� The OT terminals of AC power cables are made on site.
For details, see Table 1-5 "Types and installation positions of the cables."
Table 6-4 lists the rated voltage, rated frequency, and power distribution mode in different
modes.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-1
Table 6-4 AC power distribution mode
Rated Voltage (VAC) Rated Frequency
(Hz)
Power Input Mode
200–250 ! 20% 45–65 220 VAC single-phase 2-core
input
346/200–433/250 ! 20% 45–65 220 VAC 3-phase 4-core input
208/120–220/127 ! 20% 45–65 110 VAC dual-live input
Note: For example, if the rated voltage is 346/200 VAC, the circuit voltage is 346 VAC and the phase voltage
is 200 VAC.
6.2.2 Installation Principles
Adhere to the following principles when installing the power cables:
� The power cables must be cut according to the measured distance between the wiring
terminals and the power interface box. Redundant length must be reserved.
� Replace the power cable of insufficient length with a new one. Do not make connectors
or solder joints.
� The power cables must be separated from other ones.
� If the power cables are laid parallel to other ones, the space between them must be at
least 30 mm.
� The power cables tied on the metal cabling rack must be insulated.
� Switches or fuses must not be added to the power cable.
� The E1 cables must be laid neatly and tied using cable ties. The space between the cable
ties must be 200 mm.
� The cable ties must be in one line and in the same direction. The ends of the cable ties
must be evenly cut.
After the power cables are led into the cabinet through the waterproof module, the slide plate in the
storage battery cabin is difficult to move out; therefore, the cable should be prepared with redundant
length.
6.2.3 Leading the 3-Phase 220 VAC Power into the BTS3012AE Cabinet
Perform the following steps:
Step 1 Remove the cover of the filtering box.
Take care not to damage the power cables connected to the socket on the cover.
Step 2 Determine the hole (in the waterproof module) through which the power cable is routed into
the cabinet.
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Step 3 Cut the cable according to the measured distance between the power interface box and the
wiring terminals N, L1, L2, and L3.
Step 4 Attach temporary labels to both ends of the cable.
The contents of the temporary labels can be the same as the formal ones or decided on site.
Step 5 Lay the cables. For details, see section 6.2.2 "Installation Principles."
Step 6 Make an OT terminal at one end of the external power cable.
Step 7 Lead the L1, L2, L3, and N wires with OT terminals into the cabinet through the waterproof
module. Secure the OT terminals to the wiring posts, as shown in Figure 6-6.
Figure 6-6 Installing L1, L2, L3, and N
L1L2L3N
12
34
(1) External power cable L1 (2) External power cable L2
(3) External power cable L3 (4) External power cable N
Step 8 Connect the other end of the external power cable to the power interface box.
Step 9 Remove the temporary labels and attach the formal ones.
The labels must be attached 20–50 mm away from each end.
----End
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-3
6.2.4 Leading the Single-Phase 220 VAC Power into the BTS3012AE Cabinet
Ensure that the L wire and N wire are connected correctly in single-phase mode. If not, the
lightning arrester can be burnt, which causes serious faults.
In single-phase mode, two methods are used to lead the L wire into the BTS3012AE cabinet:
� The single-phase power provided by the customer is divided into three channels in the
power interface box before led into the BTS3012AE.
For how to connect the cables, see section 6.2.3 "Leading the 3-Phase 220 VAC Power
into the BTS3012AE Cabinet."
� Install a short-circuiting copper busbar on the AC lighting arrester. Lead the single-phase
power provided by the customer directly into the BTS3012AE.
For how to connect the cables, see section 6.2.3 "Leading the 3-Phase 220 VAC Power
into the BTS3012AE Cabinet."
Figure 6-7 shows the installation of the short-circuiting copper bar.
Figure 6-7 Installing the short-circuiting copper bar
L3
1
3
N
L1
L2
2
(1) M8 screw (2) Short-circuiting copper bar (3) AC power lightning arrester
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-4 Huawei Technologies Proprietary Issue 01 (2006-09-06)
6.2.5 Leading the 110 VAC Dual-Live Power into the BTS3012AE Cabinet
The BTS3012AE uses different lightning arresters and wiring terminals in different power input modes:
� 110 VAC dual-live input
� 220 VAC input
To lead the 110 VAC dual-live power into the BTS3012AE cabinet, do as follows:
The external power network is single-phase or three-phase star mode.
Step 1 Remove the cover of the filtering box.
Take care not to damage the power cables connected to the socket on the cover.
Step 2 Determine the hole (in the waterproof module) through which the power cable is routed into
the cabinet.
Step 3 Cut the cable according to the measured distance between the power interface box and the
wiring terminals N, L1, and L2.
Step 4 Attach temporary labels to both ends of the cable.
The contents of the temporary labels can be the same as the formal ones or decided on site.
Step 5 Lay the cables. For details, see section 6.2.2 "Installation Principles."
Step 6 Make an OT terminal at one end of the external power cable.
Step 7 Lead wires L1, L2, and N with OT terminals into the cabinet through the waterproof module.
Secure the OT terminals to the wiring posts, as shown in Figure 6-8.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-5
Figure 6-8 Installing L1, L2, and N
L1L2N
1
23
(1) Wire L1 (2) Wire L2
(3) Wire N
Step 8 Connect the other end of the external power cable to the power interface box.
Step 9 Remove the temporary labels and attach the formal ones.
The labels must be attached 20–50 mm away from each end.
----End
6.2.6 Connecting the Power Cables to the Power Interface Box
You can use multiple power supply modes for the BTS3012AE.
Table 6-5 lists the figures showing the connection between power cables and the power
interface box in different power supply modes.
Table 6-5 Figure for reference in different power supply modes
Power Supply Mode See Figure…
Single-phase mains input Figure 6-9 Power cable layout of the single-phase mains
input
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-6 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Power Supply Mode See Figure…
Single-mode mains ands
single-phase generator
Figure 6-10 Connection of power cables in single-phase
mains and single-phase generator input mode
Three-phase mains input Figure 6-11 Connection of power cables in three-phase
mains input mode
Three-phase mains and
three-phase generator
Figure 6-12 Connection of power cables in three-phase
mains and three-phase generator input mode
In single-phase mains or single-phase generator input mode, install a 3-terminal short-circuiting bar on
the terminal block and secure it using the delivered fastening screws.
Single-Phase Mains Input
Figure 6-9 Power cable layout of the single-phase mains input
4 5
3
2
1
A1 A2
A A
B1 B2
B B
C1 C2 N1 N2
C C N N
N1C1 B1 A1
N1C1 B1 A1
N1 L1 A B C N
(1) Air breaker for the input mains (2) 3-terminal short-circuiting bar and fastening screws
(3) Terminal block (4) Mains input (5) Mains output
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-7
Single-Phase Mains and Single-Phase Generator Input
Figure 6-10 Connection of power cables in single-phase mains and single-phase generator input
modes
67
8
5
4
4
31 2
A1 A2
A A
B1B2
B B
C1 C2 N1 N2
C C N N
A2 B2 C2 N2
A2 B2 C2 N2
N1C1 B1 A1
N1C1 B1 A1
N1 L1 A B C N L2 N2
(1) Air breaker for the input mains (2) Locking device of the air breaker
(3) Air breaker for the generator input (4) 3-terminal short-circuiting bar and fastening screws
(5) Generator input (6) Mains output (7) Mains input (8) Terminal block
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-8 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Three-Phase Mains Input
Figure 6-11 Connection of power cables in three-phase mains input mode
3 4
2
1
N1 C1 B1 A1
N1 C1 B1 A1
A1 A2
A A
B1 B2
B B
C1 C2 N1 N2
C C N N
N1 A1 A B C NB1C1
(1) Air breaker for the input mains (2) Terminal block
(3) Mains input (4) Mains output
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-9
Three-Phase Mains Input and Three-Phase Generator Input
Figure 6-12 Connection of power cables in three-phase mains and three-phase generator input
mode
56
7
3
4
1 2
N1 C1 B1 A1
N1 C1 B1 A1
A1 A2
A A
B1 B2
B B
C1 C2 N1 N2
C C N N
A2 B2 C2 N2
A2 B2 C2 N2
N1 A B C N N2A1B1C1 C2B2A2
(1) Air breaker for the input mains (2) Locking device of the air breaker
(3) Air breaker for the generator input (4) Generator input
(5) Mains output (6) Mains input (7) Terminal block
6.3 Installing PGND Cables
6.3.1 Introduction to PGND Cables
The yellow and green PGND cables of the BTS3012AE have a cross-sectional area of 25 mm2.
Choose plastic insulation copper core cables with a cross-sectional area of at least 25 mm2
if
you prepare PGND cables yourself.
The yellow and green PGND cables of the transmission interface box and power interface box
have a cross-sectional area of 25 mm2. Choose yellow and green plastic insulation copper core
cables with a cross-sectional area of at least 25 mm2 if you prepare PGND cables yourself.
6.3.2 Installation Principles
Adhere to the following principles when installing PGND cables:
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-10 Huawei Technologies Proprietary Issue 01 (2006-09-06)
� Measure the accurate distance between the two grounding ends and reserve cables with
enough length. When laying out PGND cables, replace the cables if the reserved cables
are not long enough. Solder joint or connection is not allowed.
� The PGND cables must be separated from other ones.
� If the PGND cables are laid parallel to other ones, the space between the PGND cables
and the other cables must be at least 30 mm.
� If PGND cables need to be bound with the metal cabling rack before being laid out,
insulation measures shall be taken.
� Switches or fuses must not be added to the PGND cable.
� The connection points at both ends of the PGND cables shall be in good electrical
contact and anticorrosion measures shall be taken.
� The E1 cables must be laid neatly and tied using cable ties. The space between cable ties
must be 200 mm.
� The cable ties must be in one line and in the same direction. The ends of the cable ties
must be evenly cut.
The PGND cables after being routed into the cabinet through the waterproof module may
prevent the removal of the slide plate from the storage battery cabin. To ensure that the slide
plate can be moved in and out freely, keep property redundant length of the cables that have
been routed into the cabinet through the waterproof module.
6.3.3 Installation Procedure
To install a PGND cable, do as follows:
Step 1 Determine the hole (in the waterproof module) through which the PGND cable is routed into
the cabinet.
Step 2 Measure the distance between the internal grounding bar of the BTS3012AE and the wiring
terminal of grounding bar outside the cabinet according to the actual cabling route of the
PGND cable. Obtain a cable with proper length.
Step 3 Attach temporary labels to both ends of the cable. The contents of the temporary labels can be
consistent with the formal ones or be determined based on your requirements.
Step 4 Lay out PGND cable according to the specification requirements for cabling and the cabling
mode required by the project. For the basic cabling principles of PGND cables, see "6.3.2
Installation Principles".
Step 5 Make OT terminals for the PGND cable.
Step 6 Route the PGND cable into the cabinet through the waterproof module. Connect one end of
the PGND cable to the grounding busbar in the cabinet, and secure the OT terminal using a
spring washer and a screw.
Step 7 Connect the other end of the PGND cable to the grounding copper busbar outside the cabinet.
Step 8 Attach formal labels 20m–50 mm away from both ends and remove the temporary labels.
----End
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-11
6.3.4 Connecting the PGND Cable to the Transmission Interface Box
Perform the following steps:
Step 1 Measure the distance between the grounding bar of the transmission interface box and the
wiring terminal of grounding copper bar outside the cabinet according to the actual cabling
route of the PGND cable. Obtain a cable with proper length.
Step 2 Attach temporary labels to both ends of the cable. The contents of the temporary labels can be
consistent with the formal ones or be determined based on your needs.
Step 3 Lay out PGND cables according to the specification requirements for cabling and the cabling
mode required by the project. For the basic cabling principles of PGND cables, see "6.3.2
Installation Principles."
Step 4 Strip the outer insulation layer on one end of the PGND cable.
Step 5 Loosen the adjustment screws on any vacant cable clamping interface of the grounding bar in
the transmission interface box. Insert the cable wire that is stripped of insulation layer into the
cable clamping interface of the grounding busbar, and then fasten the adjustment screws.
Step 6 Make an OT terminal at the other end of the PGND cable.
Step 7 Fix the end with an OT terminal on the grounding copper bar outside the cabinet.
Step 8 Remove the temporary labels at both ends of the cable and attach formal ones.
----End
6.3.5 Connecting the PGND Cable to the Power Interface Box
To connect the PGND cable to the power interface box, do as follows:
Step 1 Measure the distance between the grounding bar of the power interface box and the wiring
terminal of grounding copper bar outside the cabinet according to the actual cabling route of
the PGND cable. Obtain a cable with proper length.
Step 2 Attach temporary labels to both ends of the cable. The contents of the temporary labels can be
consistent with the formal ones or be determined based on your needs.
Step 3 Lay out PGND cables according to the specification requirements for cabling and the cabling
mode required by the project. For the basic cabling principles of PGND cables, see "6.3.2
Installation Principles."
Step 4 Make OT terminals at both ends of the PGND cable.
Step 5 Loosen the water-tight nut near the grounding terminal in the interface box and lead the
PGND cable through the nut. Fasten one end of the PGND cable to the grounding terminal of
the interface box and the other end to the grounding copper bar outside the cabinet. Figure
6-13 shows the position of the grounding terminal in the power interface box.
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-12 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 6-13 Installing the PGND cable for the power interface box
1
2
(1) Grounding terminals of the power interface box (2) PGND cable
Step 6 Remove the temporary labels at both ends of the cable and attach formal ones.
----End
6.4 Installing the E1 Cables
6.4.1 Introduction to the E1 Cables
The BTS3012AE has two types of E1 cables: the 75-ohm coaxial cable and the 120-ohm
twisted pair. The DB25 connectors and labels of both types of cables are the same.
Figure 6-14 shows the structure of the 75-ohm coaxial cable.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-13
Figure 6-14 75-ohm E1 coaxial cable
A
X0
1
A
Pos.25
Pos.1
W
W1
W2
W3
W4
W5
W6
W7
W8X8
X7
X6
X5
X4
X3
X2
X1
B
B
2
3
5
6
4
7
(1) DB25 male connector (X0) (2) Major label (3) Auxiliary label 1
(4) Coaxial cable wire (tip) (5) Coaxial cable external conductor (ring, that is,
shielding layer)
(6) 75-ohm E1 coaxial cable (X1–X8) (7) Auxiliary label 8
Table 6-6 lists the pins of the coaxial cable.
Table 6-6 Pins of the coaxial cable
Coaxial Wire
Coaxial Cable Wire/Outer Conductor
Pin of the DB25 Male Connector
Coaxial Cable Label
X1.tip X0.24 W1
X1.ring X0.25
CHAN 0 Tx
X2.tip X0.13 W2
X2.ring X0.12
CHAN 0 Rx
X3.tip X0.11 W3
X3.ring X0.10
CHAN 1 Tx
X4.tip X0.9 W4
X4.ring X0.8
CHAN 1 Rx
X5.tip X0.7 W5
X5.ring X0.6
CHAN 2 Tx
W6 X6.tip X0.5 CHAN 2 Rx
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-14 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Coaxial Wire
Coaxial Cable Wire/Outer Conductor
Pin of the DB25 Male Connector
Coaxial Cable Label
X6.ring X0.4
X7.tip X0.3 W7
X7.ring X0.2
CHAN 3 Tx
X8.tip X0.14 W8
X8.ring X0.15
CHAN 3 Rx
6.4.2 Installation Principles
Adhere to the following principles when installing the E1 cables:
� The E1 cables must not be routed on the outdoor cabling rack.
� The E1 cables must go through a metal tube whose ends are grounded. Or the E1 cables
with metal sheath are used with both ends grounded.
� The E1 cables must be separated from the other cables. If the E1 cables are laid parallel
to the power cable, PGND cable, or RF signal cable, the space between the E1 cables
and the other cables must be greater than 30 mm.
� The bending radius of the coaxial cable must not be less than 40 mm and the wire must
not be damaged.
� The E1 cables must be laid neatly and tied using cable ties.
� The E1 cables must not be stretched at the bend.
� The cable ties must be in one line and in the same direction. The ends of the cable ties
must be evenly cut.
6.4.3 Installation Procedure
To install the E1 cables, do as follows:
Step 1 Determine the hole (in the waterproof module) through which the E1 cable is routed into the
cabinet.
Step 2 Cut the E1 cable to a proper length according to the cabling route.
Step 3 Lay the E1 cables outside the cabinet. For details, see section 6.4.2 "Installation Principles."
Step 4 Lead the E1 cable into the waterproof module and route the cable along the column to near
the DB25 socket of the DELU.
Step 5 Connect the DB25 connector to the DELU according to the label on the E1 cable.
Step 6 Connect the other end to the transmission interface box.
Step 7 Attach labels 20–50 mm away from both ends of the E1 cable.
----End
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-15
6.4.4 Connecting the 75-ohm E1 Cable to the Transmission Interface Box
To connect the 75-ohm E1 cable to the transmission interface box, perform the following
steps:
Step 1 Install an SMB connector to one end of the E1 cable.
Step 2 Lead the 75-ohm E1 through the cable access socket into the transmission interface box.
Install the cable on the 75-ohm digital unit, as shown in Figure 6-15.
Figure 6-15 Connecting the 75-ohm E1 cable
1
2
3
(1) Bundling socket (2) Cable access socket (3) 75-ohm E1 cable
Figure 6-15 takes the connection of one trunk cable as an example.
Step 3 According to Steps 1 and 2, install the customer-prepared E1 cable to the other side of the
75-ohm digital unit and tie the cable to the bundling socket using cable ties.
Step 4 Fill in the gaps of the cable access socket using waterproof mud.
----End
6.4.5 Connecting the 120-ohm E1 Cable to the Transmission Interface Box
Perform the following steps:
Step 1 Remove the indicator card from the 120-ohm digital unit.
Step 2 Peel a proper length of the 120-ohm E1 cable.
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-16 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Step 3 Lead the 120-ohm E1 cable through the cable access socket into the transmission interface
box.
Step 4 Select the wires for the 120-ohm E1 cable according to the cable connection list delivered
together with the cables. Select the cores for the 120-ohm E1 cable.
Two signal transfer cables and one grounding cable form a group. One group provides one uplink or
downlink E1 channel.
Step 5 Lead the wires through the entrance of the cable trough on one side of the 120-ohm digital
unit into the cable clamping interface, one group for one cable trough, as shown in Figure
6-16.
Figure 6-16 Connecting the 120-ohm E1 cable
1
2
3
(1) Entrance of the cable trough (2) Cable clamping interface (3) 120-ohm E1 wire
Step 6 Use a wire punch-down tool to clamp the wires onto the latches in the cable clamping
interfaces.
Clamp the signal transfer cable onto cable clamping interfaces a and b, and the grounding
cable to cable clamping interface s, as shown in Figure 6-17.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-17
A group of cables is clamped onto three cable clamping interfaces: a, b, and s. Each cable clamping
interface has two rows of latches and each row has two latches. You can choose either two latches in
either row.
Figure 6-17 Clamping the 120-ohm E1 cable to the 120-ohm digital unit
2
1
54
3
(1) Latch (2) Entrance of the cable trough (3) Cable clamping interface s
(4) cable clamping interface b (5) cable clamping interface a
Step 7 Route the customer-prepared E1 cable from the other side of the 120-ohm digital unit.
Each wire connects to the wire from the BTS3012AE, as shown in Figure 6-18.
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-18 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 6-18 Connecting the E1 wire of the client
1
2
(1) E1 wire of the BTS3012AE (2) E1 wire of the client
Step 8 Attach the indicator plate after clamping the wires.
Step 9 Fill in the gap of the cable access socket using waterproof mud.
----End
6.5 Installing Optical Fibers
6.5.1 Introduction to the Optical Fibers
The BTS3012AE uses both multimode fibers and single-mode fibers.
The optical fibers in the BTS3012AE are LC connectors, as shown in Figure 6-19.
Figure 6-19 LC connector
The color of the PVC sheath of a multimode fiber is orange and that of the PVC sheath of a
single-mode fiber is yellow.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-19
6.5.2 Installation Principles
Adhere to the following principles when installing the fibers:
� The E1 cables must be laid neatly and tied with cable ties.
� The fibers must not be stretched at the bend. The bending radius must be greater than or
equal to 20 times the diameter.
� Do not pull or trample on the fibers, and prevent them from touching the sharp objects.
� Check whether there are creases and impresses on the fibers, and damages to the
connectors. If yes, replace with fibers in good condition
� The rest fibers must be coiled on the fiber coiler.
� The fibers outside the cabinet must be protected with PVC corrugated tubes.
� The connectors, if not used, must be covered with dustproof caps.
� Do not stare at the end face of the connectors if one end of the fiber is connected to the
optical transmission device in case that your eyes are hurt.
� The cable ties must be in one line and one direction. The ends of the cable ties must be
evenly cut.
6.5.3 Installation Procedure
To install the fibers, do as follows:
Step 1 Determine the hole (in the waterproof module) through which the fiber is routed into the
cabinet.
Step 2 Select fibers with proper length according to actual requirements on site.
The contents of the temporary labels can be the same as the formal ones or decided on site.
Step 3 Attach temporary labels to distinguish the fibers.
Step 4 Coat the fibers using PVC corrugated tubes.
� Place the fibers on a slope and then coat the fibers with PVC corrugated tubes.
� Do not cut corrugated tubes because exposed fibers may be damaged.
� Cover the cut with insulation tapes to protect the fibers from being damaged by sharp objects.
Step 5 Lay the fibers outside the cabinet. For details, see section 6.5.2 "Installation Principles."
Step 6 Lead the fibers from the waterproof module into the cabinet, and route the fibers near to the
optical transmission equipment in the cabinet.
Step 7 Align the LC connector with the optical transmission device on the cabinet top and insert the
connector until you hear a click sound.
Step 8 Use insulation tapes to seal the ports at both sides of the PVC corrugated tube.
Step 9 Attach the corresponding labels to both sides of the fibers, ensuring that the attaching points
are 20–50 mm away from the port.
----End
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-20 Huawei Technologies Proprietary Issue 01 (2006-09-06)
6.5.4 Connecting the Fibers to the Transmission Interface Box
Figure 6-20 shows the connections between fibers and the transmission interface box.
Figure 6-20 Connection between a fiber and a 12-core fiber splice tray
(1) Waterproof locking nut (2) Fiber stripping unit (3) Bare fiber (4) Reinforced core
(5) 12-core fiber splice tray (6) Fiber adapter (7) Tail fiber (8) Fiber fusion parts
(9) Fiber access socket (10) Grounding cable of the reinforced core
To connect fibers to the transmission interface box, do as follows:
Step 1 Lead the tail fiber from the BTS3012AE to the transmission interface box through the fiber
access socket, interweave the fiber on the fiber fusion part, and then connect the connector of
the fiber to the fiber adapter.
Step 2 Route the customer-prepared fiber to the transmission interface box through the waterproof
locking nut, secure the fiber and peel it at the fiber stripping unit.
Step 3 Take out the reinforced core from the fiber, fix the core to the grounding point of the fiber
stripping unit, and use a grounding cable with a sectional area of 6 mm2 to connect the
grounding point of the fiber stripping unit to the grounding busbar.
Step 4 Route the bare wire from the fiber stripping unit to the 12-core fiber splice tray, interweave
the wire, and splice the wire with the tail fiber.
Step 5 Lead the tail fiber out of the 12-core fiber splice tray, and interconnect the tail fiber to the
fiber from the BTS3012AE at the fiber adapter.
Step 6 Record the connecting steps of each fiber in the 12-route Fiber Indicator Table:
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-21
� Record the cable lead-in connections in the top left corner of the table.
� Record the cable lead-out connections in the top right corner of the table.
Figure 6-21 shows the 12-route Fiber Indicator Table.
Figure 6-21 12-route Fiber Indicator Table
Fiber Indicator Cable
1 2 3 4
I
II
III
----End
6.6 Installing the RF Signal Cables
This section describes only the installation of the RF signal cables inside the cabinet. For the procedure
for connecting the RF cables to the antenna, see the HUAWEI BTS3012AE Base Station Antenna System
Installation Manual.
6.6.1 Introduction to the RF Signal Cables
The BTS3012AE has two types of RF signal cables:
� RF RX signal cable is used to connect port RX on the DTRU with that on the DDPU
and to transmit uplink signals.
� RF TX signal cable is used to connect port TX on the DTRU with that on the DDPU
and to transmit downlink signals.
Figure 6-22 shows the structure of the RF RX signal cable and that of the RF TX signal cable.
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-22 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 6-22 Structure of the RF RX signal cable and that of the TX signal cable
RF Tx Cable
RF Rx Cable
1
2
1
2
(1) SMA elbow male connector (2) N elbow male connector
6.6.2 Installation Principles
Adhere to the following principles when connecting the RF signal cables:
� Install from the top to the bottom and from left to right.
� Attach labels or name plates after the installation. For details, see Appendix B
"Engineering Labels for Antenna System" of the HUAWEI BTS3012AE Base Station
Antenna System Installation Manual.
6.6.3 Installation Procedure
To install an RF signal cable, do as follows:
Step 1 Connect the SMA elbow male connector at one end of the cable to the RX port in the DDPU
and secure the connector.
Step 2 Connect the SMA elbow male connector at the other end to the RX port in the DTRU and
secure the connector.
Step 3 Connect the N elbow male connector at one end of the cable to the TX port in the DDPU and
secure the connector.
Step 4 Connect the SMA elbow male connector at the end of the cable to the TX port in the DTRU
and secure the connector.
----End
6.7 Installing the Cable for the Combiner on the DTRU
6.7.1 Introduction to the Cable for the Combiner on the DTRU
The cable for combiner on the DTRU connects the TX and IN ports. It outputs the transmit
signals after combination.
One end of the cable is an N male connector, and the other end is an SMA male connector.
The cable is made before delivery.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-23
Figure 6-23 shows the structure of the cable.
Figure 6-23 Cable for the combiner on the DTRU
1 2
W
3
(1) N male connector (2) SMA male connector (3) Label
6.7.2 Connecting the Cable for Combiner on the DTRU
The cable for the combiner on the DTRU connects port TX to port IN.
Perform the following steps:
Step 1 Determine which ports to connect according to the configuration of the BTS.
Step 2 Connect the N male connector to port TX1 or TX2 on the DTRU.
Step 3 Connect the SMA male connector to port IN1 or IN2.
Step 4 Secure the two connectors.
----End
The two connectors must be secured at the same time so that the cable is not twisted.
6.8 Installing the 1/4-Inch RF Jumper
6.8.1 Introduction to the RF Jumper
The 1/4-inch jumper is connected between the RF port on a DDPU and the RF cable
inlet/outlet at the cabinet top. One end of the jumper is a DIN male connector and the other
end is a DIN female connector. Figure 6-24 shows the structure of the jumper.
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-24 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 6-24 Structure of the RF jumper
1 2
(1) DIN male connector (2) DIN female connector
6.8.2 Installation Principles
Adhere to the following principles when connecting the RF jumpers:
� The jumper must be vertically routed for at least 20 cm before it is bent near to connector
at the cabinet top. If you do not do like this, the jumper connector is subject to damage
� Labels or name plates must be attached after installation.
6.8.3 Installation Procedure
To install an RF jumper, do as follows:
Step 1 Remove the cover plate from the RF cable inlet/outlet port at the right part of the cabinet
bottom, as shown in Figure 6-25.
Figure 6-25 Removing the cover plate of the RF cable
1
(1) Cover plate of RF cables
Step 2 Find the jumper end that is connected to the antenna system through the RF cable inlet/outlet.
Insert the end into the cabinet through the exposed round hole to keep about 15 cm of the
jumper in the cabinet. Interconnect the two DIN connectors.
Step 3 Waterproof the joint of the two DIN connectors, keeping the insulation tapes from covering
the bolt holes on the connectors.
Step 4 Fix the cover plate on the RF cable inlet/outlet.
Step 5 Repeat Step 2 to Step 4 to secure the connectors of the other jumpers.
----End
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-25
6.9 Installing the 1/2-Inch RF Jumper
6.9.1 Introduction to the RF Jumper
The 1/2-inch jumper is connected between the 1/4-inch RF jumper and feeder of the antenna
system. Both ends of the jumper are DIN male connectors.
Figure 6-26 shows the structure of the jumper.
Figure 6-26 Structure of the RF jumper
1 2
(1) DIN male connector (2) DIN male connector
6.9.2 Installation Procedure
To install an RF jumper, do as follows:
Step 1 Connect one end of the 1/2-inch RF jumper to the cabling hole for RF jumpers on the cabinet
bottom.
Step 2 Connect the other end to the feeder of the antenna system.
Step 3 Repeat step 1 to step 2 to secure the connectors of the other jumpers.
----End
6.10 Installing the Boolean Value Input Signal Cable
6.10.1 Introduction to the Boolean Value Input Signal Cable
The Boolean value input signal cable in the BTS3012AE can output six Boolean value signal
inputs. One end of the cable is a DB44 male connector, and the other end is a bare wire.
Figure 6-27 shows the structure of the cable.
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-26 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 6-27 Boolean value input signal cable
X0
A
W1
Pos.1
Pos.25
View A
W
W8
W7
W6
W5
W4
W3
W2
6.10.2 Installation Positions
Table 6-7 lists the installation positions of the Boolean value input signal cable.
Table 6-7 Installation positions of the Boolean value input signal cable
Cable Connector Connects to…
DB44 male connector DB44 connector on the DMLU
Bare wire DDF
6.11 Installing the Built-In Storage Battery and Its Cables
Huawei has two types of built-in storage batteries. The two types of storage batteries are similar in
appearance, but different in the distribution of positive and negative terminals. The following takes the
storage battery with the positive terminal at the left port and the negative terminal at the right part of the
battery as an example. If customers prefer to provide storage batteries themselves, storage batteries must
comply with the BTS3012AE configuration requirements.
6.11.1 Introduction to the Storage Battery Cabin
The BTS3012AE has two types of storage battery cabins: –48 V 50-AH storage battery cabin
and –48 V 150-AH storage battery cabin.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-27
The –48 V 50-AH storage cabin of the BTS3012AE can be removed to form a 7 U space with
the reserved 2 U space. This space can be used to accommodate transmission equipment or
other equipment of the operators.
� Figure 6-28 (A) lists the full configuration of the BTS3012AE under the combination of
150 AH + 50 AH + 2 U.
� Figure 6-28 (B) lists the full configuration of the BTS3012AE under the combination of
150 AH + 7U.
After the –48 V 50 AH storage battery cabin is removed, it can not be used as the storage battery cabin
again because it cannot meet the sealing requirements. That is to say, the cabinet shown Figure 6-28 (A)
can be changed to the cabinet shown Figure 6-28 (B) while the cabinet shown Figure 6-28 (B) cannot be
changed to the cabinet Figure 6-28 (A).
Figure 6-28 Full configuration of the BTS3012AE
DC
PD
U
DT
MU
DA
TU
DC
SU
DC
CU
DTRU
DTRU
DTRU
DTRU
DTRU
DTRU
BAT -48V 150AH
Wire holder
FAN
Air inlet
PSU
Cable in/outEMI
Wire holder
DT
MU
Wire holder
Air inlet
Tra
nsm
issio
n u
nit
BAT -48V 50AH
Air return
AC PDU
PSU
Air return
DPMU
PSU
PSU
PSU PSU
PSU PSU
DELU 0DMLUDELU 1
DDPU
DDPU
DDPU
DCOM
DCOM
DC
PD
U
DT
MU
DA
TU
DC
SU
DC
CU
DTRU
DTRU
DTRU
DTRU
DTRU
DTRU
BAT -48V 150AH
Wire holder
FAN
Air inlet
PSU
Cable in/outEMI
Wire holder
DT
MU
Air inlet
Transmission unit
Air return
AC PDU
PSU
Air return
DPMU
PSU
PSU
PSU PSU
PSU PSU
DELU 0DMLUDELU 1
Wire holder
(A) (B)
DCOM
DDPU
DDPU
DDPU
DCOM
DCOM
DCOM
The cabling of the –48 V 50-AH storage battery cabin is shown as Figure 6-29.
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-28 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 6-29 Cabling of the –48 V 50-AH storage battery cabin
70
100
The cabling of the –48 V 150-AH storage battery cabin is shown as Figure 6-30.
Figure 6-30 Cabling of the –48 V 150-AH storage battery cabin
60
120
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-29
6.11.2 Introduction to the Cables for the Built-in Storage Battery
The cables for the built-in storage battery are:
� Red GND cable with the sectional area of 25 mm2
� Black –48 V cable with the sectional area of 25 mm2
� Cable between storage batteries
� Cable for the temperature and humidity sensor of the built-in storage battery, with two
wires, at one end is a 2-pin terminal, and at the other end is an OT terminal
6.11.3 Installation Procedure
Before connecting the cable between storage batteries, be sure to power off them. Otherwise,
the power may result in injuries.
To power off a storage battery, insert a small round stick into the small hole beside the OFF
silkscreen on the front panel of the DPMU, push the button for at least five seconds until you
can hear that the storage battery is powered off.
The capacity of a built-in storage battery group in the BTS3012AE is 50 AH. The
BTS3012AE supports a maximum of four groups.
The BTS3012AE currently supports three configuration modes: 100 AH, 150 AH, and 200
AH. The selection of the configuration mode is subject to the system configuration.
100-AH Configuration Mode
If the BTS3012AE is configured with a 100-AH storage battery group, connect the cables as
follows:
Step 1 Connect three storage batteries through cables 1, 2, and 3 as shown in the
Figure 6-31. Place the terminal covers on the terminals.
Step 2 In the middle layer, place the connected storage batteries at the back of the storage battery
cabin.
Step 3 Place another storage battery in front of the first three batteries and make it on the right side
within the cabin.
Step 4 Use cable 2 to connect the fourth storage battery and place the terminal covers on the
terminals.
Step 5 Connect the two pieces of cable 1 to the wiring copper bar.
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-30 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 6-31 Cabling for the 100-AH configuration mode (1)
Middle layer
Plan View
1
1
2
33
Bottom layer
Step 6 In the bottom layer, place two storage batteries in the front of the cabin and make them on the
left side.
Step 7 In the middle layer, place two storage batteries in the front of the cabin and make them on the
left side.
Step 8 Use cables 2, 3, and 4 to connect the storage batteries as shown in Figure 6-32. Place the
terminal covers on the terminals.
Step 9 Connect cables 1 and 3 to the wiring copper bar.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-31
Figure 6-32 Cabling for the 100-AH configuration mode (2)
Plan View
4
2
3
1
Middle layer
Bottom layer
----End
150-AH Configuration Mode
If the BTS3012AE is configured with a 150-AH storage battery group, connect the cables as
follows:
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-32 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Step 1 Connect three storage batteries through cables 1, 2, and 3 as shown in the
Figure 6-33. Place the terminal covers on the terminals.
Step 2 In the bottom layer, place the connected storage batteries at the back of the cabin.
Step 3 Place another storage battery in front of the first three batteries and make it on the right side
within the cabin.
Step 4 Use cable 2 to connect the fourth storage battery and place the terminal covers on the
terminals.
Step 5 Connect the two pieces of cable 1 to the wiring copper bar.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-33
Figure 6-33 Cabling for the 150-AH configuration mode (1)
Plan View
2
33
1
1
Bottom layer
Step 6 Connect three storage batteries through cables 1, 2, and 3 as shown in the
Figure 6-34. Place the terminal covers on the terminals.
Step 7 In the middle layer, place the connected storage batteries at the back of the cabin.
Step 8 Place another storage battery in front of the three batteries in the middle layer and make it on
the right side within the cabin.
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-34 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Step 9 Use cable 2 to connect the fourth storage battery and place the terminal covers on the
terminals.
Step 10 Connect the two pieces of cable 1 to the wiring copper bar.
Figure 6-34 Cabling for the 150-AH configuration mode (2)
Plan View
1
1
2
33
Middle layer
Bottom layer
Step 11 In the bottom layer, place two storage batteries in the front of the cabin and make them on the
left side.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-35
Step 12 In the middle layer, place two storage batteries in the front of the cabin and make them on the
left side.
Step 13 Use cables 1, 2, and 3 to connect the storage batteries as shown in Figure 6-35. Place the
terminal covers on the terminals.
Step 14 Connect cables 1 and 2 to the wiring copper bar.
Figure 6-35 Cabling for the 150-AH configuration mode (3)
Plan View
2
1
3
3
Middle layer
Bottom layer
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-36 Huawei Technologies Proprietary Issue 01 (2006-09-06)
----End
200-AH Configuration Mode
If the BTS3012AE is configured with a 200-AH storage battery group, connect the cables as
follows:
Step 1 Refer to the methods described in the 150-AH configuration mode to connect storage batteries
in the middle and bottom layers.
Step 2 In the top layer, place two storage batteries at the back of the cabin.
Step 3 In the top layer, place another two storage batteries in the front of the cabin.
Step 4 Use cables 2 and 3 to connect the storage batteries as shown in Figure 6-36. Place the terminal
covers on the terminals.
Step 5 Connect cable 1 to the wiring copper bar.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-37
Figure 6-36 Cabling for the 200-AH configuration mode
Plan View
1
2
2
3
1
Top layer
Middle layer
Bottom layer
----End
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-38 Huawei Technologies Proprietary Issue 01 (2006-09-06)
6.12 Installing Cables for the Combined Cabinet
6.12.1 Introduction to Cables for the Combined Cabinet
The cables for the combined cabinet transmit the RF signals between the two combined
cabinet.
Both ends of the cable are MD68 male connectors. One connects to the TO SLAVE
CABINET port on the DSCB of the main cabinet and the other connects to the TO SLAVE
CABINET port on the DSCB of the extension cabinet.
Figure 6-37 shows the structure of the cable for the combined cabinet.
Figure 6-37 Cable for the combined cabinet
1
X1 X2
WA
2
View A
Pos.1
Pos.68
(1) MD68 male connector (2) MD68 male connector
6.12.2 Installation Procedure
Install the RF signal cables for the combined cabinet as follows:
Step 1 Attach labels to both ends of the cable. For details, see Appendix C "Engineering Labels for
Cables."
Step 2 Connect the MD68 male connector on one end to the TO SLAVE CABINET port on the
DSCB of the main cabinet.
Step 3 Connect the MD68 male connector on the other end to the TO SLAVE CABINET port on the
DSCB of the extension cabinet.
----End
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 6 Installing Cables
Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-39
6.13 Installing Cables for the Cabinet Group
6.13.1 Introduction to Cables for the Cabinet Group
The cables for the cabinet group transmit RF signals between two cabinet groups.
Both ends of the cable are MD36 male connectors. One connects to the port TO SLAVE
GROUP1 or TO SLAVE GROUP2 on the DSCB of the main cabinet group. The other end
connects to the port TO SLAVE GROUP1 or TO SLAVE GROUP2 on the DSCB of the
extension cabinet group.
Figure 6-38 shows the structure of the cable for the cabinet group.
Figure 6-38 Cable for the cabinet group
Pos.1
W
X1 X2
1 2
Pos.36
(1) MD36 male connector (2) MD36 male connector
6.13.2 Installation Procedure
Install the cables for cabinet group as follows:
Step 1 Attach labels to two ends of the cable. See Appendix C "Engineering Labels for Cables."
Step 2 Connect the MD36 male connector on one end to the port TO SLAVE GROUP1 or TO
SLAVE GROUP2 on the DSCB of the main cabinet group.
Step 3 Connect the MD36 male connector on the other to the port TO SLAVE GROUP1 or TO
SLAVE GROUP2 on the DSCB of the extension cabinet group.
----End
6.14 Installing the RET Control Signal Cable
6.14.1 Introduction to the RET Control Signal Cable
The RET control signal cable transmits signals between the DATU and the Bias-Tee.
One end of the cable is an SMA elbow male connector, and the other end is an SMA male
connector.
Figure 6-39 shows the structure of the RET control signal cable.
6 Installing Cables
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
6-40 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Figure 6-39 Structure of the RET control signal cable
1
W
X1
X2
2
(1) SMA male connector (2) SMA elbow male connector
6.14.2 Connecting the RET Control Signal Cable
Perform the following steps:
Step 1 Connect the SMA elbow male connector to the ANT port on the DATU.
Step 2 Connect the SMA male connector to the SMA port of the Bias-Tee.
Step 3 Connect other RET control signal cables according to steps 1 through 2.
Step 4 Arrange the cables neatly and tie them with cable ties.
Step 5 Attach the label to both ends of the cable. For details, see Appendix C "Engineering Labels
for Cables."
----End
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 7 Checking Hardware Installation
Issue 01 (2006-09-06) Huawei Technologies Proprietary 7-1
7 Checking Hardware Installation About This Chapter
The following table lists the contents of this chapter.
Title Description
7.1 Equipment Installation
Check
Provides the checklist for the equipment installation.
7.2 Cable Installation Check Provides the checklist for the cable installation.
7.3 Power-On Check Describes how to perform power-on checks.
7.4 Sanitation Check Describes how to perform sanitation checks.
7 Checking Hardware Installation
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
7-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)
7.1 Equipment Installation Check
Refer to Table 7-1 for the equipment installation check.
Table 7-1 Equipment installation checklist
SN Item
1 The cabinet is placed according to the design drawing.
2 The cabinet is properly mounted on the concrete base. After the installation,
the cabinet stands firmly on the ground.
3 The horizontal error of the cabinet position is less than 3 mm and the vertical
error is not more than 3 mm.
4 All screws are securely fastened. The spring washers are installed on the flat
washers.
5 The parts on the cabinet are not detached or damaged. The cables are not
scratched or broken.
6 The equipment is clean and neat. The external paints are intact. The labels are
correct, legible, and complete.
7 The front doors of the cabinets are easy to open or close.
7.2 Cable Installation Check
7.2.1 Transmission Cable Installation Check
Refer to Table 7-2 for the cable installation check.
Table 7-2 Transmission cable installation checklist
SN Item
1 The cables are securely connected.
2 The cable connectors are intact.
3 The cables are not broken or damaged.
4 The cables are neatly bound. The space between cable ties is uniform. The
cables are properly fastened and the cable ties face the same direction.
5 The extra tails of cable ties are completely cut off.
6 The cable layout is convenient for maintenance and expansion.
7 All labels and tags at both ends of the cables are legible.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 7 Checking Hardware Installation
Issue 01 (2006-09-06) Huawei Technologies Proprietary 7-3
7.2.2 Power Cable and Protection Grounding Cable Installation Check
Refer to Table 7-3 for the installation check on the power cables and grounding cables.
Table 7-3 Power cable and grounding cable installation checklist
SN Item
1 All power cables and grounding cables are copper-core cables and their
diameters meet the required specifications.
2 None of the power cables and grounding cables is short-circuited or reversely
connected.
3 The power cables and grounding cables are bound separately from other
cables.
4 Labels are attached to each end of the power cables and grounding cables.
5 No power cable or grounding cable is scratched or broken.
6 A proper length of power cables and grounding cables is reserved after they
are led into the cabinet through the waterproof module.
7 The power cables and grounding cables are made of one segment of materials.
Multiple segments of cables are not joined to make a power cable or grounding
cable.
8 No breaking device, such as a switch or fuse, is allowed to the electric
connection of the grounding system.
9 The extra power cables or grounding cables are cut off instead of being coiled
up.
10 The lugs at each end of the power cables or grounding cables are securely
soldered or crimped.
11 The bare wires and lug handles at the wiring terminals are completely wrapped
up through insulation tapes or heat-shrinking tubes.
12 The flat washers and spring washers are securely installed with and in close
contact with all wiring terminals.
13 The GND and PGND of the BTS and the lightning protection grounding of the
building share the same group of grounding conductors.
14 The grounding grids of the iron tower, the equipment room, and the
distribution transformer (if the distance between the transformer and the
equipment room is less than 30 m) constitute an integrated grounding grid.
7.3 Power-On Check
7 Checking Hardware Installation
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
7-4 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Take care of personal safety during the power-on check because high voltage is involved. A
fatal accident may occur if you touch the input current directly or indirectly through a wet
substance.
Before you turn the primary power supply to ON, use a multimeter to measure the resistance
between the input power and the earth and check whether they are short-circuited.
7.3.1 Cabinet Power-On Check
Before powering on the cabinet, ensure that the power cables and boards are disconnected.
The procedure for power-on check of a cabinet is as follows:
Step 1 Set all the power switches to OFF.
Step 2 Turn on the DC PDF to power on the cabinet.
Step 3 Measure the input voltage of the power distribution box on BTS3012AE cabinet. The range
allowed is –60 V to –40 V.
� If the voltage is within the range, the power-on check is complete. Continue with board
power-on check.
� If the voltage is beyond the range, go to the next step.
The rated voltage of the BTS3012AE cabinet is –48 V.
Step 4 Turn off the DC PDF to cut off the power supply to the cabinet.
Step 5 Measure the output voltage of the PDF. Check the installation and layout of power cables on
the cabinet top. Clear the faults.
Step 6 Measure the output voltage of the PDF again and take the cabinet power-on check.
If the results are normal, continue with board power-on check.
----End
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 7 Checking Hardware Installation
Issue 01 (2006-09-06) Huawei Technologies Proprietary 7-5
7.3.2 Board Power-On Check
Before power-on check of boards, ensure that:
� The cabinet passes the power-on check.
� All the power switches are set to OFF.
� All the cables are connected properly.
The procedure for power-on check of boards is as follows:
Step 1 Set the power switch of the FAN subrack to ON.
Step 2 Check whether the fan runs normally.
� If yes, infer that the power supply inside the cabinet is normal. Go to Step 4.
� If no, infer that the power supply inside the cabinet is not normal. Go to Step 3.
Step 3 Check whether the power cable connection of the FAN subrack is good. If no, reinstall the
cable, and then repeat Step 1.
Step 4 Set the power switch of the common subrack to ON.
Step 5 Check whether the indicators of the DTMU in the common subrack flash slowly (0.5 Hz).
� If yes, infer that the board has normal power supply. Go to Step 7.
� If no, infer that the board is not properly placed or there are other faults. Go to Step 6.
Step 6 Reinstall the boards or clear the faults. Then repeat Step 5.
For details about the status of indicators on boards, see the BTS3012AE Base Station Hardware
Description Manual.
Step 7 Set the power switch of the DTRU to ON. Check whether the indicators on the DTRU panels
flash slowly (0.5 Hz).
� If yes, infer that the DTRU has normal power supply. Go to Step 8.
� If no, infer that the DTRU is not properly placed or there are other faults. Clear the faults
and then repeat Step 7.
Step 8 Set the power switch of the DAFU subrack to ON, and check whether the indicators on the
DDPU panels flash slowly (0.5 Hz).
� If yes, the DDPU has normal power supply. The power-on check of the board is
complete.
� If the indicators are always on, infer that the DDPU is faulty. Go to Step 9.
� If the indicators are off, infer that the power supply fails. Go to Step 10.
� For states other than that mentioned previously, go to Step 11.
The DCOMs in the DAFU subrack do not need power and there are no indicators on them.
Step 9 Check the DDPU and the cable between the DDPU and the serial port on the DTRU. Reinstall
the cable and check whether the indicators on the DDPU panel flash slowly (0.5 Hz).
� If yes, infer that the DDPU has normal power supply. Board power-on check is complete.
� If no, go to Step 11.
7 Checking Hardware Installation
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual
7-6 Huawei Technologies Proprietary Issue 01 (2006-09-06)
Step 10 Check the power cables of the DDPU. Reinstall the cable and see if the indicators on the
DDPU panel flash slowly (0.5 Hz).
� If yes, infer that the DDPU has normal power supply. Board power-on check is complete.
� If no, go to Step 11.
Step 11 Contact Huawei for fault location. Clear the faults and then perform Step 8 again until the
indicators on the DDPU panels flash slowly (0.5 Hz).
----End
7.3.3 Power-On Check of the Heat Exchanger
The procedure for the power-on check of the heat exchanger is as follows:
After inserting the PSUs into the cabinet, turn on the ACU/HX switch on the AC power
distribution box and the HEX switch on the power distribution box. Check whether the fan on
the heat exchanger rotates fast.
� If yes, the heat exchanger works normally. The power-on check of the heat exchanger is
complete.
� If no, the heat exchanger is faulty. Contact Huawei to replace the heat exchanger.
7.3.4 Power-on Check of the Batteries
The procedure for the power-on check of batteries is as follows:
Step 1 Set the multimeter on the DC scale.
Ensure that the negative pole of the multimeter is connected to the positive pole (red) of the
battery group, and the positive pole of the multimeter to the negative pole (black) of the
battery group.
Step 2 Follow the instructions listed in Table 7-4 to handle different values.
Table 7-4 Instructions to handling different values
Measured Value Handling Suggestion
Value > 0 The connection between the –48 VDC cable and the GND cable is
incorrect. Connect the two cables correctly, and then measure the
voltage of the battery again.
Value = 0 The cable connection of the batteries is incorrect, or the batteries
are faulty. Correct the connection or clear the battery faults, and
then measure the voltage of the battery again.
HUAWEI BTS3012AE Base Station
Cabinet Installation Manual 7 Checking Hardware Installation
Issue 01 (2006-09-06) Huawei Technologies Proprietary 7-7
Measured Value Handling Suggestion
–43.2 V < Value < 0 Check whether the low voltage is caused by automatic discharge
after a long period.
If the low voltage is caused by automatic discharge after a long
period, press the ON button (located in the hole) on the PMU panel
using a proper tool. Wait until you hear a click sound. Then go to
the next step.
Otherwise, check whether the batteries are normal. If the batteries
are faulty, clear the fault, and then measure the voltage of the
battery again.
–57.6 V ≤ Value ≤
–43.2 V
The connection is correct.
Press the ON button (located in the hole) on the PMU panel using a
proper tool. Wait until you hear a click sound. Then go to the next
step.
Step 3 Turn off the AC power input switch, and check whether the BTS3012AE can work well with
reference to the board indicators.
� If yes, the batteries are functional. The power-on check of the batteries is complete.
� If no, the batteries are faulty. Go to Step 4.
Step 4 Press the button in the hole labeled OFF on the PMU panel to power off the battery. After the
fault is cleared, power on the BTS3012AE again until the BTS works well.
If all the power-on checks have been passed, the power supply system of the BTS is
functional.
----End
7.4 Sanitation Check
Refer to Table 7-5 for the sanitation check.
Table 7-5 Sanitation checklist
SN Item
1 The packing boxes and boards are neatly placed in the installation site.
2 All rubbish such as tails of cable ties is removed from the installation site.
3 There are no fingerprints or other stains on the surface of the cabinet.
4 The cabinet is clean. There is no dust inside or outside the rack.