155
HUAWEI BTS3012AE Base Station Cabinet Installation Manual Contents Issue 01 (2006-09-06) Huawei Technologies Proprietary i Contents 1 Overview of the Hardware Installation .................................................................................1-1 1.1 BTS3012AE Hardware Structure .................................................................................................................. 1-2 1.1.1 Schematic Drawing of Hardware Structure.......................................................................................... 1-2 1.1.2 BTS3012AE Cabinet............................................................................................................................ 1-3 1.1.3 Base.................................................................................................................................................... 1-10 1.1.4 Introduction to the Cables .................................................................................................................. 1-10 1.2 Installation Process...................................................................................................................................... 1-13 1.2.1 Hardware Installation Flow Chart ...................................................................................................... 1-13 1.2.2 Installation Process Description ......................................................................................................... 1-14 2 Installation Preparations ..........................................................................................................2-1 2.1 Preparing Technical Documents .................................................................................................................... 2-2 2.2 Preparing Mounting Tools and Instruments .................................................................................................. 2-2 2.3 Checking Installation Conditions .................................................................................................................. 2-3 2.3.1 Load-Bearing Capacity Requirements ................................................................................................. 2-4 2.3.2 Grounding Status Requirements........................................................................................................... 2-4 2.4 Unpacking and Inspecting ............................................................................................................................. 2-4 2.4.1 Requirements for Unpacking ............................................................................................................... 2-4 2.4.2 Unpacking the Wooden Case ............................................................................................................... 2-5 2.4.3 Inspecting Items Inside the Wooden Case ............................................................................................ 2-7 2.4.4 Unpacking the Carton .......................................................................................................................... 2-8 2.4.5 Inspecting Items Inside the Carton ....................................................................................................... 2-9 3 Installing the BTS3012AE Cabinet .........................................................................................3-1 3.1 Installing a Cabinet on the Cement Floor with Sufficient Bearing Capacity (ƒ 800 kg/m 2 ) ......................... 3-2 3.1.1 Installation Flowchart .......................................................................................................................... 3-2 3.1.2 Positioning the Cabinet ........................................................................................................................ 3-3 3.1.3 Casting the Cement Plinth.................................................................................................................... 3-4 3.1.4 Positioning the Base ............................................................................................................................. 3-5 3.1.5 Drilling Holes and Installing Expansion Bolts ..................................................................................... 3-7 3.1.6 Fastening the Base ............................................................................................................................... 3-9 3.1.7 Leveling the Base ................................................................................................................................. 3-9 3.1.8 Placing the Cabinet ............................................................................................................................ 3-10

BTS3012AE Base Station Cabinet Installation Manual

Embed Size (px)

Citation preview

Page 1: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual Contents

Issue 01 (2006-09-06) Huawei Technologies Proprietary i

Contents

1 Overview of the Hardware Installation.................................................................................1-1

1.1 BTS3012AE Hardware Structure ..................................................................................................................1-2

1.1.1 Schematic Drawing of Hardware Structure..........................................................................................1-2

1.1.2 BTS3012AE Cabinet............................................................................................................................1-3

1.1.3 Base....................................................................................................................................................1-10

1.1.4 Introduction to the Cables ..................................................................................................................1-10

1.2 Installation Process......................................................................................................................................1-13

1.2.1 Hardware Installation Flow Chart ......................................................................................................1-13

1.2.2 Installation Process Description.........................................................................................................1-14

2 Installation Preparations ..........................................................................................................2-1

2.1 Preparing Technical Documents....................................................................................................................2-2

2.2 Preparing Mounting Tools and Instruments ..................................................................................................2-2

2.3 Checking Installation Conditions ..................................................................................................................2-3

2.3.1 Load-Bearing Capacity Requirements .................................................................................................2-4

2.3.2 Grounding Status Requirements...........................................................................................................2-4

2.4 Unpacking and Inspecting.............................................................................................................................2-4

2.4.1 Requirements for Unpacking ...............................................................................................................2-4

2.4.2 Unpacking the Wooden Case ...............................................................................................................2-5

2.4.3 Inspecting Items Inside the Wooden Case............................................................................................2-7

2.4.4 Unpacking the Carton ..........................................................................................................................2-8

2.4.5 Inspecting Items Inside the Carton.......................................................................................................2-9

3 Installing the BTS3012AE Cabinet .........................................................................................3-1

3.1 Installing a Cabinet on the Cement Floor with Sufficient Bearing Capacity (ƒ 800 kg/m2) .........................3-2

3.1.1 Installation Flowchart ..........................................................................................................................3-2

3.1.2 Positioning the Cabinet ........................................................................................................................3-3

3.1.3 Casting the Cement Plinth....................................................................................................................3-4

3.1.4 Positioning the Base.............................................................................................................................3-5

3.1.5 Drilling Holes and Installing Expansion Bolts.....................................................................................3-7

3.1.6 Fastening the Base ...............................................................................................................................3-9

3.1.7 Leveling the Base.................................................................................................................................3-9

3.1.8 Placing the Cabinet ............................................................................................................................3-10

Page 2: BTS3012AE Base Station Cabinet Installation Manual

Contents

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

ii Huawei Technologies Proprietary Issue 01 (2006-09-06)

3.1.9 Fastening the Cabinet.........................................................................................................................3-12

3.1.10 Leveling the Cabinet ........................................................................................................................3-16

3.1.11 Removing Lifting Lugs ....................................................................................................................3-17

3.1.12 Illustration of the Installed Cabinet..................................................................................................3-18

3.2 Installing a Cabinet on the Cement Floor with Insufficient Bearing Capacity (< 800 kg/m2).....................3-18

3.2.1 Installation Flowchart ........................................................................................................................3-18

3.2.2 Installation Process ............................................................................................................................3-20

3.2.3 Positioning the Cabinet ......................................................................................................................3-20

3.2.4 Casting Cement Plinths......................................................................................................................3-20

3.2.5 Preparing U-Bar Supports ..................................................................................................................3-21

3.2.6 Positioning U-Bar Supports ...............................................................................................................3-21

3.2.7 Drilling Holes and Installing Expansion Bolts...................................................................................3-21

3.2.8 Fastening U-Bar Supports ..................................................................................................................3-21

3.2.9 Leveling U-Bar Supports ...................................................................................................................3-22

3.2.10 Fastening the Base ...........................................................................................................................3-23

3.2.11 Leveling the Base.............................................................................................................................3-23

3.2.12 Placing the Cabinet ..........................................................................................................................3-23

3.2.13 Fastening the Cabinet.......................................................................................................................3-25

3.2.14 Leveling the Cabinet ........................................................................................................................3-28

3.2.15 Removing Lifting Lugs ....................................................................................................................3-28

3.2.16 Illustration of the Installed Cabinet..................................................................................................3-29

3.3 Installing Combined Cabinets .....................................................................................................................3-30

4 Installing Boards ........................................................................................................................4-1

4.1 Introduction to Installation Positions ............................................................................................................4-2

4.2 Preparations...................................................................................................................................................4-2

4.3 Installing the DTMU .....................................................................................................................................4-4

4.3.1 Setting DIP Switches on the DTMU ....................................................................................................4-4

4.3.2 Installation Procedure ..........................................................................................................................4-6

4.4 Installing the DATU ......................................................................................................................................4-7

4.5 Installing the PSU and DPMU ......................................................................................................................4-8

4.5.1 PSU and DPMU Installation Procedure ...............................................................................................4-8

4.6 Installing the DELU ....................................................................................................................................4-11

4.6.1 Installation Overview.........................................................................................................................4-11

4.6.2 Installation Procedure ........................................................................................................................4-11

4.7 Installing the DMLU ...................................................................................................................................4-11

4.7.1 Installation Overview.........................................................................................................................4-11

4.7.2 Installation Procedure ........................................................................................................................4-11

4.8 Installing the DTRU....................................................................................................................................4-11

4.9 Installing the DDPU and DCOM ................................................................................................................4-13

5 Installing Auxiliary Equipment ..............................................................................................5-1

5.1 Installing Transmission Unit .........................................................................................................................5-2

Page 3: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual Contents

Issue 01 (2006-09-06) Huawei Technologies Proprietary iii

5.1.1 Introduction to Installation Positions ...................................................................................................5-2

5.1.2 Installation Procedure ..........................................................................................................................5-1

5.2 Installing Outdoor Interface Boxes ...............................................................................................................5-3

5.2.1 Introduction to the Outdoor Transmission Interface Box.....................................................................5-3

5.2.2 Introduction to the Outdoor Power Interface Box................................................................................5-5

5.2.3 Installing the Outdoor Interface Box on a Wall....................................................................................5-7

5.2.4 Installing the Outdoor Interface Box on a Pole....................................................................................5-8

6 Installing Cables ........................................................................................................................6-1

6.1 Introduction to the Cables to be Installed On Site.........................................................................................6-3

6.1.1 Introduction to Cabling Holes..............................................................................................................6-3

6.1.2 Cable Layout at the Cabinet Front .......................................................................................................6-4

6.1.3 Wiring on the Back of the Cabinet .......................................................................................................6-7

6.2 Installing the Power Cables...........................................................................................................................6-2

6.2.1 Introduction to the Power Cables.........................................................................................................6-2

6.2.2 Installation Principles...........................................................................................................................6-1

6.2.3 Leading the 3-Phase 220 VAC Power into the BTS3012AE Cabinet ..................................................6-1

6.2.4 Leading the Single-Phase 220 VAC Power into the BTS3012AE Cabinet ..........................................6-3

6.2.5 Leading the 110 VAC Dual-Live Power into the BTS3012AE Cabinet...............................................6-4

6.2.6 Connecting the Power Cables to the Power Interface Box...................................................................6-5

6.3 Installing PGND Cables ................................................................................................................................6-9

6.3.1 Introduction to PGND Cables ..............................................................................................................6-9

6.3.2 Installation Principles...........................................................................................................................6-9

6.3.3 Installation Procedure ........................................................................................................................6-10

6.3.4 Connecting the PGND Cable to the Transmission Interface Box ......................................................6-11

6.3.5 Connecting the PGND Cable to the Power Interface Box .................................................................6-11

6.4 Installing the E1 Cables...............................................................................................................................6-12

6.4.1 Introduction to the E1 Cables.............................................................................................................6-12

6.4.2 Installation Principles.........................................................................................................................6-14

6.4.3 Installation Procedure ........................................................................................................................6-14

6.4.4 Connecting the 75-ohm E1 Cable to the Transmission Interface Box ...............................................6-15

6.4.5 Connecting the 120-ohm E1 Cable to the Transmission Interface Box .............................................6-15

6.5 Installing Optical Fibers ..............................................................................................................................6-18

6.5.1 Introduction to the Optical Fibers ......................................................................................................6-18

6.5.2 Installation Principles.........................................................................................................................6-19

6.5.3 Installation Procedure ........................................................................................................................6-19

6.5.4 Connecting the Fibers to the Transmission Interface Box..................................................................6-20

6.6 Installing the RF Signal Cables ...................................................................................................................6-21

6.6.1 Introduction to the RF Signal Cables .................................................................................................6-21

6.6.2 Installation Principles.........................................................................................................................6-22

6.6.3 Installation Procedure ........................................................................................................................6-22

6.7 Installing the Cable for the Combiner on the DTRU...................................................................................6-22

Page 4: BTS3012AE Base Station Cabinet Installation Manual

Contents

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

iv Huawei Technologies Proprietary Issue 01 (2006-09-06)

6.7.1 Introduction to the Cable for the Combiner on the DTRU.................................................................6-22

6.7.2 Connecting the Cable for Combiner on the DTRU............................................................................6-23

6.8 Installing the 1/4-Inch RF Jumper...............................................................................................................6-23

6.8.1 Introduction to the RF Jumper ...........................................................................................................6-23

6.8.2 Installation Principles.........................................................................................................................6-24

6.8.3 Installation Procedure ........................................................................................................................6-24

6.9 Installing the 1/2-Inch RF Jumper...............................................................................................................6-25

6.9.1 Introduction to the RF Jumper ...........................................................................................................6-25

6.9.2 Installation Procedure ........................................................................................................................6-25

6.10 Installing the Boolean Value Input Signal Cable.......................................................................................6-25

6.10.1 Introduction to the Boolean Value Input Signal Cable .....................................................................6-25

6.10.2 Installation Positions ........................................................................................................................6-26

6.11 Installing the Built-In Storage Battery and Its Cables ...............................................................................6-26

6.11.1 Introduction to the Storage Battery Cabin........................................................................................6-26

6.11.2 Introduction to the Cables for the Built-in Storage Battery..............................................................6-29

6.11.3 Installation Procedure.......................................................................................................................6-29

6.12 Installing Cables for the Combined Cabinet .............................................................................................6-38

6.12.1 Introduction to Cables for the Combined Cabinet............................................................................6-38

6.12.2 Installation Procedure ......................................................................................................................6-38

6.13 Installing Cables for the Cabinet Group....................................................................................................6-39

6.13.1 Introduction to Cables for the Cabinet Group ..................................................................................6-39

6.13.2 Installation Procedure ......................................................................................................................6-39

6.14 Installing the RET Control Signal Cable...................................................................................................6-39

6.14.1 Introduction to the RET Control Signal Cable .................................................................................6-39

6.14.2 Connecting the RET Control Signal Cable ......................................................................................6-40

7 Checking Hardware Installation.............................................................................................7-1

7.1 Equipment Installation Check .......................................................................................................................7-2

7.2 Cable Installation Check ...............................................................................................................................7-2

7.2.1 Transmission Cable Installation Check ................................................................................................7-2

7.2.2 Power Cable and Protection Grounding Cable Installation Check.......................................................7-3

7.3 Power-On Check ...........................................................................................................................................7-3

7.3.1 Cabinet Power-On Check.....................................................................................................................7-4

7.3.2 Board Power-On Check .......................................................................................................................7-5

7.3.3 Power-On Check of the Heat Exchanger .............................................................................................7-6

7.3.4 Power-on Check of the Batteries..........................................................................................................7-6

7.4 Sanitation Check ...........................................................................................................................................7-7

Page 5: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual Figures

Issue 01 (2006-09-06) Huawei Technologies Proprietary v

Figures

Figure 1-1 BTS3012AE hardware structure .......................................................................................................1-2

Figure 1-2 BTS3012AE cabinet .........................................................................................................................1-4

Figure 1-3 BTS3012AE cabinet without a base (in mm) ...................................................................................1-5

Figure 1-4 Dimensions of the BTS3012AE cabinet bottom (in mm) .................................................................1-6

Figure 1-5 BTS3012AE cabinet with a base (in mm) ........................................................................................1-7

Figure 1-6 Front view of the BTS3012AE cabinet under full configuration......................................................1-8

Figure 1-7 Installation space for a BTS3012AE cabinet (in mm) ......................................................................1-9

Figure 1-8 Base dimensions (in mm) ...............................................................................................................1-10

Figure 1-9 Hardware installation of the BTS3012AE ......................................................................................1-14

Figure 2-1 Straightening tongues .......................................................................................................................2-6

Figure 2-2 Removing the cover ..........................................................................................................................2-6

Figure 2-3 Removing all wooden boards ...........................................................................................................2-7

Figure 2-4 Unpacking a carton ...........................................................................................................................2-8

Figure 3-1 Process for installing a cabinet on the cement floor .........................................................................3-3

Figure 3-2 Installation position of the BTS3012AE cabinet ..............................................................................3-4

Figure 3-3 Dimensions of the cement plinth ......................................................................................................3-5

Figure 3-4 Installation holes of the expansion bolts for a single cabinet............................................................3-6

Figure 3-5 M12 expansion bolt assembly...........................................................................................................3-7

Figure 3-6 Installing the expansion bolt (1) .......................................................................................................3-8

Figure 3-7 Installing the expansion bolt (2) .......................................................................................................3-8

Figure 3-8 Installing the base .............................................................................................................................3-9

Figure 3-9 Leveling the base (1) ......................................................................................................................3-10

Figure 3-10 Leveling the base (2) ....................................................................................................................3-10

Figure 3-11 Lifting the cabinet .........................................................................................................................3-11

Figure 3-12 Placing the cabinet on the base .....................................................................................................3-12

Figure 3-13 Fastening the cabinet on the base (Rear view)..............................................................................3-13

Page 6: BTS3012AE Base Station Cabinet Installation Manual

Figures

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

vi Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 3-14 Unlocking the cabinet ...................................................................................................................3-14

Figure 3-15 Fixing the front door.....................................................................................................................3-15

Figure 3-16 Fastening the cabinet on the base (Front view).............................................................................3-15

Figure 3-17 Leveling the cabinet (1) ................................................................................................................3-16

Figure 3-18 Leveling the cabinet (2) ................................................................................................................3-17

Figure 3-19 Removing lifting lugs ...................................................................................................................3-17

Figure 3-20 Installed BTS3012AE cabinet ......................................................................................................3-18

Figure 3-21 Process for installing a cabinet on the cement floor with insufficient bearing capacity ...............3-19

Figure 3-22 Installation position of the BTS3012AE cabinet ..........................................................................3-20

Figure 3-23 Dimensions of U-bar supports (unit: mm) ....................................................................................3-21

Figure 3-24 Fastening the U-bar supports on the cement plinths .....................................................................3-22

Figure 3-25 Leveling the U-bar support (1) .....................................................................................................3-22

Figure 3-26 Leveling the U-bar support (2) .....................................................................................................3-23

Figure 3-27 Lifting the cabinet.........................................................................................................................3-24

Figure 3-28 Placing the cabinet on the U-bar supports ....................................................................................3-25

Figure 3-29 Fastening the cabinet on the base (Rear view)..............................................................................3-26

Figure 3-30 Unlocking the front door...............................................................................................................3-27

Figure 3-31 Fastening the cabinet on the base (Front view).............................................................................3-28

Figure 3-32 Removing lifting lugs ...................................................................................................................3-29

Figure 3-33 Installed cabinet ............................................................................................................................3-30

Figure 3-34 DIP switches on the DCSU...........................................................................................................3-31

Figure 4-1 Boards in the BTS3012AE subrack ..................................................................................................4-2

Figure 4-2 Wearing an antistatic wrist strap .......................................................................................................4-3

Figure 4-3 DIP switches on the DTMU..............................................................................................................4-4

Figure 4-4 Installing the DTMU.........................................................................................................................4-6

Figure 4-5 Hooking spanners on to the square holes of the subrack ..................................................................4-7

Figure 4-6 DIP switches on the DATU...............................................................................................................4-8

Figure 4-7 DIP switch of the DPMU..................................................................................................................4-9

Figure 4-8 Installing the PSU and DPMU (1) ..................................................................................................4-10

Figure 4-9 Installing the PSU and DPMU (2) ..................................................................................................4-10

Figure 4-10 Front panel of a DTRU .................................................................................................................4-12

Figure 4-11 Front panel of a DDPU .................................................................................................................4-14

Figure 5-1 Installation position of the transmission unit ....................................................................................5-2

Page 7: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual Figures

Issue 01 (2006-09-06) Huawei Technologies Proprietary vii

Figure 5-2 Positions of the dummy panel and air deflector plate .......................................................................5-2

Figure 5-3 Installing transmission unit ...............................................................................................................5-2

Figure 5-4 Internal structure of the 75-ohm outdoor transmission interface box ...............................................5-4

Figure 5-5 Structure of the 12-core fusion parts.................................................................................................5-4

Figure 5-6 Internal structure of the 120-ohm transmission interface box...........................................................5-5

Figure 5-7 Internal structure of the 220 VAC power interface box ....................................................................5-6

Figure 5-8 Positions of the expansion bolts........................................................................................................5-7

Figure 5-9 Installing the outdoor interface box on a wall...................................................................................5-8

Figure 5-10 Fixing the pole fixture to the interface box.....................................................................................5-9

Figure 5-11 Fixing the interface box to the pole.................................................................................................5-9

Figure 6-1 BTS3012AE cabling holes................................................................................................................6-3

Figure 6-2 Silkscreens of the cabling holes........................................................................................................6-4

Figure 6-3 Cable layout at the cabinet front .......................................................................................................6-5

Figure 6-4 NPMI cable layout on the top of the cabinet ....................................................................................6-6

Figure 6-5 Wring on the back of the BTS3012AE cabinet.................................................................................6-8

Figure 6-6 Installing L1, L2, L3, and N .............................................................................................................6-2

Figure 6-7 Installing the short-circuiting copper bar ..........................................................................................6-3

Figure 6-8 Installing L1, L2, and N....................................................................................................................6-5

Figure 6-9 Power cable layout of the single-phase mains input .........................................................................6-6

Figure 6-10 Connection of power cables in single-phase mains and single-phase generator input modes ........6-7

Figure 6-11 Connection of power cables in three-phase mains input mode .......................................................6-8

Figure 6-12 Connection of power cables in three-phase mains and three-phase generator input mode .............6-9

Figure 6-13 Installing the PGND cable for the power interface box................................................................6-12

Figure 6-14 75-ohm E1 coaxial cable...............................................................................................................6-13

Figure 6-15 Connecting the 75-ohm E1 cable..................................................................................................6-15

Figure 6-16 Connecting the 120-ohm E1 cable................................................................................................6-16

Figure 6-17 Clamping the 120-ohm E1 cable to the 120-ohm digital unit .......................................................6-17

Figure 6-18 Connecting the E1 wire of the client.............................................................................................6-18

Figure 6-19 LC connector ................................................................................................................................6-18

Figure 6-20 Connection between a fiber and a 12-core fiber splice tray..........................................................6-20

Figure 6-21 12-route Fiber Indicator Table ......................................................................................................6-21

Figure 6-22 Structure of the RF RX signal cable and that of the TX signal cable ...........................................6-22

Figure 6-23 Cable for the combiner on the DTRU...........................................................................................6-23

Page 8: BTS3012AE Base Station Cabinet Installation Manual

Figures

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

viii Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 6-24 Structure of the RF jumper ...........................................................................................................6-24

Figure 6-25 Removing the cover plate of the RF cable....................................................................................6-24

Figure 6-26 Structure of the RF jumper ...........................................................................................................6-25

Figure 6-27 Boolean value input signal cable ..................................................................................................6-26

Figure 6-28 Full configuration of the BTS3012AE..........................................................................................6-27

Figure 6-29 Cabling of the –48 V 50-AH storage battery cabin.......................................................................6-28

Figure 6-30 Cabling of the –48 V 150-AH storage battery cabin.....................................................................6-28

Figure 6-31 Cabling for the 100-AH configuration mode (1) ..........................................................................6-30

Figure 6-32 Cabling for the 100-AH configuration mode (2) ..........................................................................6-31

Figure 6-33 Cabling for the 150-AH configuration mode (1) ..........................................................................6-33

Figure 6-34 Cabling for the 150-AH configuration mode (2) ..........................................................................6-34

Figure 6-35 Cabling for the 150-AH configuration mode (3) ..........................................................................6-35

Figure 6-36 Cabling for the 200-AH configuration mode................................................................................6-37

Figure 6-37 Cable for the combined cabinet ....................................................................................................6-38

Figure 6-38 Cable for the cabinet group...........................................................................................................6-39

Figure 6-39 Structure of the RET control signal cable .....................................................................................6-40

Page 9: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual Tables

Issue 01 (2006-09-06) Huawei Technologies Proprietary ix

Tables

Table 1-1 Description of the BTS3012AE hardware ..........................................................................................1-2

Table 1-2 Weight of the BTS3012AE cabinet under different configurations ....................................................1-7

Table 1-3 Boards in the BTS3012AE cabinet.....................................................................................................1-8

Table 1-4 Base specifications ...........................................................................................................................1-10

Table 1-5 Types and installation positions of the cables...................................................................................1-11

Table 1-6 Installation process ...........................................................................................................................1-15

Table 2-1 Technical documents for reference .....................................................................................................2-2

Table 2-2 List of tools and instruments ..............................................................................................................2-3

Table 3-1 Settings for SW1...............................................................................................................................3-31

Table 3-2 Settings for SW11.............................................................................................................................3-31

Table 3-3 Settings for SW2−SW5 ....................................................................................................................3-32

Table 3-4 Settings for SW6 and SW7...............................................................................................................3-32

Table 3-5 Settings for SW8...............................................................................................................................3-33

Table 3-6 Settings for SW9 and SW10.............................................................................................................3-33

Table 4-1 S4/S5/S6/S7 setting descriptions ........................................................................................................4-4

Table 4-2 Default setting of the DIP switches on the DATU..............................................................................4-7

Table 6-1 Cables laid out at the cabinet front .....................................................................................................6-6

Table 6-2 Cables on the back of the BTS3012AE cabinet..................................................................................6-1

Table 6-3 Specifications of the AC power cables for the BTS3012AE ..............................................................6-2

Table 6-4 AC power distribution mode...............................................................................................................6-1

Table 6-5 Figure for reference in different power supply modes........................................................................6-5

Table 6-6 Pins of the coaxial cable ...................................................................................................................6-13

Table 6-7 Installation positions of the Boolean value input signal cable..........................................................6-26

Table 7-1 Equipment installation checklist.........................................................................................................7-2

Table 7-2 Transmission cable installation checklist............................................................................................7-2

Table 7-3 Power cable and grounding cable installation checklist .....................................................................7-3

Page 10: BTS3012AE Base Station Cabinet Installation Manual

Tables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

x Huawei Technologies Proprietary Issue 01 (2006-09-06)

Table 7-4 Instructions to handling different values ............................................................................................7-6

Table 7-5 Sanitation checklist.............................................................................................................................7-7

Page 11: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 1 Overview of the Hardware Installation

Issue 01 (2006-09-06) Huawei Technologies Proprietary 1-1

1 Overview of the Hardware Installation About This Chapter

The following table lists the contents of this chapter.

Title Description

1.1 BTS3012AE Hardware

Structure

Describes the hardware structure of the BTS3012AE.

1.2 Installation Process Describes how to install the BTS3012AE cabinet.

Page 12: BTS3012AE Base Station Cabinet Installation Manual

1 Overview of the Hardware Installation

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

1-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)

1.1 BTS3012AE Hardware Structure

1.1.1 Schematic Drawing of Hardware Structure

The BTS3012AE system consists of the following parts:

� BTS3012AE cabinet

� Cables

� Antenna system

Figure 1-1 shows the hardware structure of the BTS3012AE.

Figure 1-1 BTS3012AE hardware structure

Antenna

Feeder

Jumper

Antennasystem

TMA

Jumper

Power cable

E1 trunk cable

Fiber

Signal cable

BTS3012AE

cabinet

For the internal configuration of the BTS3012AE cabinet, see Figure 1-6. For details of cabling, see 6

"Installing Cables."

Choose either fibers or E1 trunk cables for installation.

Table 1-1 describes the parts shown in Figure 1-1.

Table 1-1 Description of the BTS3012AE hardware

Equipment Components Installation Guide

BTS3012AE

cabinet

Mandatory 3 Installing the BTS3012AE

Cabinet

Page 13: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 1 Overview of the Hardware Installation

Issue 01 (2006-09-06) Huawei Technologies Proprietary 1-3

Equipment Components Installation Guide

Cables Radio frequency (RF) cables,

signal cables, power cables,

protection grounding (PGND)

cables, transmission cables,

and storage battery cables

6 Installing Cables

Auxiliary

equipment

Transmission unit, power

interface box, and transmission

interface box. The auxiliary

equipment is optional.

5 Installing Auxiliary Equipment

Antenna system Antenna, jumper, feeder,

Tower Mounted Amplifier

(TMA)

The TMA is optional.

HUAWEI BTS3012AE Base

Station Antenna System

Installation Manual

1.1.2 BTS3012AE Cabinet

Appearance

Figure 1-2 shows the BTS3012AE cabinet.

Page 14: BTS3012AE Base Station Cabinet Installation Manual

1 Overview of the Hardware Installation

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

1-4 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 1-2 BTS3012AE cabinet

Dimensions

The dimensions of the BTS3012AE cabinet without a base are 1700 mm (Height) % 1000

mm (Width) % 880 mm (Depth). Figure 1-3 shows the dimensions of the BTS3012AE cabinet

without a base.

Page 15: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 1 Overview of the Hardware Installation

Issue 01 (2006-09-06) Huawei Technologies Proprietary 1-5

Figure 1-3 BTS3012AE cabinet without a base (in mm)

170

0

1000

880

Figure 1-4 shows the dimensions of the BTS3012AE cabinet bottom.

Page 16: BTS3012AE Base Station Cabinet Installation Manual

1 Overview of the Hardware Installation

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

1-6 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 1-4 Dimensions of the BTS3012AE cabinet bottom (in mm)

962.0

1000.0

910.0

682.0732.0

16.0

1

(1) Cabinet front

The dimensions of the BTS3012AE cabinet with a base are 1900 mm (Height) % 1000 mm

(Width) % 880 mm (Depth). Figure 1-5 shows the dimensions of the BTS3012AE cabinet

with a base.

Page 17: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 1 Overview of the Hardware Installation

Issue 01 (2006-09-06) Huawei Technologies Proprietary 1-7

Figure 1-5 BTS3012AE cabinet with a base (in mm)

1000

880

19

00

Weight

Table 1-2 lists the weight of the BTS3012AE cabinet under different configurations.

Table 1-2 Weight of the BTS3012AE cabinet under different configurations

Cabinet Configuration Weight

Empty cabinet Excludes the heat exchanger and all the

internal subracks

200 kg

Empty cabinet Includes the heat exchanger 310 kg

Cabinet under full

configuration (excluding

storage batteries)

� Cabinet with a front door

� All boards installed

390 kg

Composition

Figure 1-6 shows the front view of the BTS3012AE cabinet under full configuration.

Page 18: BTS3012AE Base Station Cabinet Installation Manual

1 Overview of the Hardware Installation

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

1-8 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 1-6 Front view of the BTS3012AE cabinet under full configuration

Cable in/outAC lightning

D

C

O

M

D

D

P

U

D

C

O

M

D

D

P

U

D

C

O

M

D

D

P

U

D

T

R

U

D

T

R

U

D

T

R

U

D

T

R

U

D

T

R

U

D

T

R

U

PSU PSU PSU PSU

PSUPSUPSUDPMU

Air return

Wire holder

Wire holder

FAN

DELU0

DELU1DMLU

AC PDU

Air return

D

T

M

U

D

T

M

U

D

A

T

U

D

C

C

U

D

C

S

U

Wire holder

DC

PDU

BAT 48V 50AH

Air inlet

Tra

nsm

issio

nu

nit

BAT 48V 150AH

Air inlet

Table 1-3 lists the boards in the BTS3012AE cabinet.

Table 1-3 Boards in the BTS3012AE cabinet

Subrack Board Full Name of Board

DTMU Transmission/Timing/Management Unit for DTRU

BTS

DCSU Combined cabinet Signal connection Unit for DTRU

BTS

DCCU Cable Connection Unit for DTRU BTS

Common subrack

DATU Antenna and TMA control Unit for DTRU BTS

DTRU subrack DTRU Double-Transceiver Unit

Page 19: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 1 Overview of the Hardware Installation

Issue 01 (2006-09-06) Huawei Technologies Proprietary 1-9

Subrack Board Full Name of Board

DDPU Dual-Duplexer Unit for DTRU BTS DAFU subrack

DCOM Combining Unit for DTRU BTS

PSU Power Supply Unit Power subrack

DPMU Power and Environment Monitoring Unit for DTRU

BTS

DELU E1 Signal Lightning Protection Unit for DTRU BTS Signal lightning

protection subrack DMLU Monitor Signal Lightning Protection Unit for DTRU

BTS

Installation Space

Figure 1-7 shows the reserved space for the installation of a BTS3012AE cabinet.

Figure 1-7 Installation space for a BTS3012AE cabinet (in mm)

BTS 3012AE

1000

> 600

> 600

> 300

880

1300

1

(1) Front door of the cabinet

Page 20: BTS3012AE Base Station Cabinet Installation Manual

1 Overview of the Hardware Installation

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

1-10 Huawei Technologies Proprietary Issue 01 (2006-09-06)

1.1.3 Base

Dimensions

Figure 1-8 shows the dimensions of a base.

Figure 1-8 Base dimensions (in mm)

20

0

998737

Specifications

Table 1-4 lists the base specifications.

Table 1-4 Base specifications

Height 200 mm

Material Cold rolled quality steel sheet

Fixed Hole Location at the Bottom

Used for fixing the base; plugged into the cement floor through

expansion bolts

Two front installation locations (fastening bolts downwards

from inside the cabinet) Fixed Hole Location on the Top

Two rear installation locations (fastening bolts upwards

through the base from inside the cabinet)

Rectangle Hole Cable inlet/outlet at the bottom; base in open design for

cabling from four sides

1.1.4 Introduction to the Cables

Table 1-5 describes the types and installation positions of the cables to be installed on site.

Page 21: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 1 Overview of the Hardware Installation

Issue 01 (2006-09-06) Huawei Technologies Proprietary 1-11

Table 1-5 Types and installation positions of the cables

Cable Type Cable Category

Cable Description Connector Type Cable Installation Position

N elbow male

connector

Connects to the TCOM port

on the DTRU

RF Tx signal

cable

Transmitting RF Tx

signals

N elbow male

connector

Connects to the TXA or TXB

port on the DDPU

SMA elbow male

connector

Connects to the RXM1,

RXD1, RXM2, or RXD2 port

on the DTRU

RF Rx signal

cable

Transmitting RF Rx

signals

SMA elbow male

connector

Connects to the RXA1,

RXA2, RXA3, RXA4, RXB1,

RXB2, RXB3, or RXB4 port

on the DDPU

N male connector Connects to the TX1 or TX2

port on the DTRU

Cable for the

combiner on

the DTRU

Realizing combined

output of Tx signals

SMA male

connector

Connects to the IN1 or IN2

port on the DTRU

DIN male

connector

Connects to the feeder of the

BTS

RF cable

RF jumper Realizing signal

interaction between

the BTS and the

antenna system DIN male

connector

Connects to the ANTA or

ANTB port on the DDPU

DB44 Connects to the DB44 port on

the DMLU

Boolean value

output signal

cable

- Outputting Boolean

value control signals

Bare wire Connects to the DDF

DB44 Connects to the DB44 port on

the DMLU

Boolean value

input signal

cable

- Inputting Boolean

value control signals

Bare wire Connects to the DDF

OT terminal (made

on site)

Connects to the external

wiring terminal of the power

lightning arrester

220 VAC

3-phase

power cable

Providing 220 VAC

input power for the

cabinet

Comprising three L

wires and one N

wire

L wire: red, a

cross-sectional area

of 10 mm2

N wire: black, a

cross-sectional area

of 10 mm2

The terminal is

made based on the

onsite power

distribution unit.

Connects to the power

distribution unit provided by

the customer

Power cable

220 VAC

single-phase

power cable

Providing 220 VAC

input power for the

cabinet

OT terminal (made

on site)

Connects to the external

wiring terminal of the power

lightning arrester

Page 22: BTS3012AE Base Station Cabinet Installation Manual

1 Overview of the Hardware Installation

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

1-12 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Cable Type Cable Category

Cable Description Connector Type Cable Installation Position

Comprising one L

wire and one N wire

L wire: red, a

cross-sectional area

of 16 mm2

N wire: black, a

cross-sectional area

of 16 mm2

The terminal is

made based on the

onsite power

distribution unit.

Connects to the power

distribution unit provided by

the customer

OT terminal (made

on site)

Connects to the external

wiring terminal of the power

lightning arrester

Dual-live

power cable

Providing 110 VAC

input power for the

cabinet

Comprising two L

wires and one N

wire

L wire: red, a

cross-sectional area

of 16 mm2

N wire: black, a

cross-sectional area

of 16 mm2

The terminal is

made based on the

onsite power

distribution unit.

Connects to the power

distribution unit provided by

the customer

OT terminal (made

on site)

Connects to the protection

grounding bar inside the

cabinet

Protection

grounding

cable (PGND

cable)

- Realizing fast

discharging of

powerful surge

current

Cable

cross-sectional area:

25 mm2

Cable color: yellow

and green

OT terminal (made

on site)

Connects to the protection

grounding bar provided by the

customer

75-ohm E1

cable

Transmitting E1

signals

75-ohm mini coaxial

cable

120-ohm E1

cable

Transmitting E1

signals

120-ohm twisted

pairs

BTS3012AE side:

DB25 male

connector

Opposite side:

connector made on

site to make the

connector type

matched with that

at the peer end

DB25 male connector

connects to the DELU in the

signal lightning protection

subrack.

The connector on the opposite

side connects to the

transmission unit or

transmission interface box

provided by the customer

Connects to the optical

transmission unit in the

cabinet

Transmission

cable (any one

of the right

three)

Optical fiber Transmitting trunk

signals

Multimode optical

fiber (orange),

single-mode optical

fiber (yellow)

LC connector

Connects to the transmission

unit or transmission interface

box provided by the customer

Page 23: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 1 Overview of the Hardware Installation

Issue 01 (2006-09-06) Huawei Technologies Proprietary 1-13

Cable Type Cable Category

Cable Description Connector Type Cable Installation Position

SMA male

connector

Connects to the SMA port on

the Bias Tee

RET control

signal cable

(optional)

- Transmitting signals

between the DATU

and the Bias-Tee SMA elbow male

connector

Connects to the ANT port on

the DATU

OT25-6 terminal,

preinstalled in the

cabinet

- –48 V cable Providing –48 V

input or output

power for the

storage battery

Cross-sectional area

of the cable: 25 mm2

OT25-6 terminal Connects to the negative

terminal of the storage battery

OT25-6 terminal,

preinstalled in the

cabinet

- GND cable Providing –48 V

input or output

power for the

storage battery

Cross-sectional area

of the cable: 25 mm2

OT25-6 terminal Connects to the positive

terminal of the storage battery

Cable

between

storage

batteries

Connecting the

positive terminal

with the negative

terminal of storage

batteries

Cable delivered with

the storage battery

OT16-6 terminal -

2-pin power

terminal

This terminal is

fixed to port

BTA_TEM1 on the

NPMI inside the

cabinet in advance.

-

Cable for

storage

batteries

(optional)

Cable for the

temperature

and

humidity

sensor of the

built-in

storage

battery

Transmitting

temperature

monitoring signals

of the storage

battery

2-core single cable

OT-6 terminal of

the sensor

Connects to the external

terminal of the left storage

battery inside the storage

battery cabin

1.2 Installation Process

1.2.1 Hardware Installation Flow Chart

Figure 1-9 shows the hardware installation of the BTS3012AE.

Page 24: BTS3012AE Base Station Cabinet Installation Manual

1 Overview of the Hardware Installation

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

1-14 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 1-9 Hardware installation of the BTS3012AE

Install cables

Installation checking

Pass the check?

End

Reinstall faulty parts

Yes

No

Install the outdoor interface box

No

Yes

Start

Installation preparations

Install the base

Install the cabinet

Install boards

No

Install the transmission unit

Need to install the outdoorinterface box?

Need to installthe transmission unit?

Yes

1.2.2 Installation Process Description

Table 1-6 describes the installation process.

Page 25: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 1 Overview of the Hardware Installation

Issue 01 (2006-09-06) Huawei Technologies Proprietary 1-15

Table 1-6 Installation process

Operation Reference Description

Installation

preparations

2 Installation Preparations Describes the preparatory work

before the installation.

Installing the cabinet 3 Installing the BTS3012AE

Cabinet

Describes the installation of the

BTS3012AE cabinet.

Installing boards 4 Installing Boards Describes the installation of

boards.

Installing auxiliary

equipment

5 Installing Auxiliary

Equipment

Describes the installation of

transmission unit, outdoor

transmission interface box, and

outdoor power interface box.

Installing cables 6 Installing Cables Describes the installation of

external cables.

Checking hardware

installation

7 Checking Hardware

Installation

Describes the inspections and

tests on the installed hardware

system.

Page 26: BTS3012AE Base Station Cabinet Installation Manual
Page 27: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 2 Installation Preparations

Issue 01 (2006-09-06) Huawei Technologies Proprietary 2-1

2 Installation Preparations About This Chapter

The following table lists the contents of this chapter.

Title Description

2.1 Preparing Technical

Documents

Lists the technical documents prepared for the hardware

installation.

2.2 Preparing Mounting Tools

and Instruments

Lists the tools and instruments prepared for the hardware

installation.

2.3 Checking Installation

Conditions

Describes the conditions and requirements for the

hardware installation.

2.4 Unpacking and Inspecting Describes the requirements for unpacking and inspection.

Page 28: BTS3012AE Base Station Cabinet Installation Manual

2 Installation Preparations

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

2-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)

2.1 Preparing Technical Documents

Table 2-1 shows the technical documents for reference during the installation.

Table 2-1 Technical documents for reference

Category Description

GSM Digital Cellular Mobile Base Station Network Planning

GSM Digital Cellular Mobile Base Station Project Design

Engineering design

documents

Construction Diagram

BTS3012AE Base Station Cabinet Installation Manual Installation guide

BTS3012AE Base Station Antenna Feeder Installation Manual

The documents listed in Table 2-1 are only a few of the documents available on site. They are for

reference only.

2.2 Preparing Mounting Tools and Instruments

Prepare all the tools and instruments listed in Table 2-2.

Page 29: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 2 Installation Preparations

Issue 01 (2006-09-06) Huawei Technologies Proprietary 2-3

Table 2-2 List of tools and instruments

Measuring and Marking Tools

50 m ribbon tape, 5 m measuring tape, 400 mm level bar, marking pen

Drilling Tools Punch drill, a few matching bits, cleaner, terminal block (with three

2-phase sockets and three 3-phase sockets, current capacity > 15 A)

Fastening Tools

Phillips screwdrivers (respectively of 4', 6', and 8')

Straight screwdrivers (respectively of 4', 6', and 8')

Adjustable wrenches (respectively of 6', 8', 10', and 12')

Combination wrenches (respectively of 17' and 19')

Inner hexagon spanners, socket wrenches, 5 kg nail hammer

Small Tools

Hacksaw (with some saw blades), tap wrench (with some M4 and M5

screw taps), sharp nose pliers (8'), diagonal pliers (8'), slip joint pliers

(8'), pincer pliers (8'), broach files (medium), electrician’s knife, flat

Phillips screwdriver (medium)

Universal Tools

Auxiliary Tools

Tweezers, paintbrush, scissors, 300 W soldering iron, 40 W soldering

iron, tin wires (some), heat blower, solder absorber, hydraulic pliers (or

Hercules crimping pliers), ladder, wire nippers, paper knife, insulation

tape

Special Tools

Non-conductive screwdriver, antistatic wrist strap, safety knife

Stripper for 75-ohm coaxial cables, connector crimping pliers for

75-ohm coaxial cables, multi-purpose crimping pliers, crimping pliers

for network cables

Instruments Multimeter, ground resistance meter, power meter, portable computer

2.3 Checking Installation Conditions

The project supervisor must perform the following steps on the installation site:

Step 1 Check the construction conditions according to the Engineering Technical Specifications and

Lightning Protection and Grounding Specifications for Communications Equipment.

Step 2 Fill in the Installation Environment Checklist.

Step 3 Sign the Kickoff Agreement with the customer if all conditions are met.

Step 4 Formulate the Project Installation Plan.

----End

If the installation preparations of the customer are not ready as required, fill in the Onsite

Work Liaison Form and give the reasons for kickoff delay.

If the customer needs immediate kickoff, ask the customer to specify the exact time when the

installation is ready for kickoff. If a project cannot be improved or does not meet the specified

requirements, both parties must sign a memo.

Page 30: BTS3012AE Base Station Cabinet Installation Manual

2 Installation Preparations

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

2-4 Huawei Technologies Proprietary Issue 01 (2006-09-06)

2.3.1 Load-Bearing Capacity Requirements

Install the BTS3012AE on a stable and level cement floor. The weight capacity of the floor

must satisfy the weight requirement of the cabinet. If the BTS3012AE is installed on the

rooftop, the weight capacity of the rooftop must meet the weight requirement of the cabinet.

� If the weight capacity of the cement is more than 800 kg/m2, install the cabinet on the

cement floor. For details, see section 3.1 "Installing a Cabinet on the Cement Floor with

Sufficient Bearing Capacity (ƒ 800 kg/m2)."

� If the weight capacity of the cement is less than 800 kg/m2, install the cabinet on the

U-bar support that is on the cement floor. For details, see section 3.2 "Installing a

Cabinet on the Cement Floor with Insufficient Bearing Capacity (< 800 kg/m2)."

2.3.2 Grounding Status Requirements

Proper grounding ensures stable operation of the equipment. It is also the prerequisite for the

access network to be protected from thunder strokes or interference. Carefully check the

grounding conditions on site to ensure proper grounding.

To protect the equipment from a lightning discharge, the earth resistance of the grounding

system is recommended to be less than 10 ohms, and the equipment grounding should be in

accordance with national and local electrical codes as well.

2.4 Unpacking and Inspecting

This section describes how to unpack and inspect items from the following aspects:

� Requirements for Unpacking

� Unpacking the Wooden Case

� Inspecting Items Inside the Wooden Case

� Unpacking the Carton

� Inspecting Items Inside the Carton

2.4.1 Requirements for Unpacking

After the project kicks off, the project supervisor must check the products along with the

customer.

The project supervisor must ensure that:

� The total number of products is consistent with that on the packing list attached to the

packing case.

� The arrival place is the installation site.

� The packing case is in good condition.

� The cabinet is not placed upside down.

If the outer package is damaged or soaked or the equipment is soaked and rusty, stop

unpacking and find the cause. Give feedback about the damaged equipment to Huawei local

office.

Page 31: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 2 Installation Preparations

Issue 01 (2006-09-06) Huawei Technologies Proprietary 2-5

� To protect the equipment and find the cause, store the unpacked equipment inside the

equipment room.

� Take photos of the storage environment, the rusted or corroded devices, and the packaging

cases and materials. Archive the photos.

� Take good care of the unpacked packaging cases and materials.

If the products are in good condition, unpack and inspect the items. Unpack the case labeled

Built-In Packing List, and take out the packing list. Check the case according to the Packing

List.

For any short or wrong shipment, fill in the Article Problem Feedback Form. For any

damage of articles, both parties must fill in the Cargo Replacement Application Form and

sign the Packing List.

� Prevent the equipment, components, or parts from colliding with doors, walls, or shelves

during transportation and handling.

� Do not touch the uncoated surface of the equipment, parts, or components through sweat

soaked or dirty gloves.

2.4.2 Unpacking the Wooden Case

Do not place the wooden case upside down. Otherwise, the equipment will be severely

damaged.

Wooden cases are used to pack heavy objects such as racks and batteries. A rack is usually

packed with wooden boards, steel edges, tongues, and foamed angle wraps.

Move the packing case into or near the equipment room (if possible) to avoid damage to the

cabinet during transportation. Unpack the case as follows:

Step 1 Insert one end of the ejector lever into a hole of the tongue on the cover of the wooden case.

Step 2 Turn the ejector lever to straighten the tongue, as shown in Figure 2-1. You can also use a

screwdriver or a hammer to handle the tongue.

Page 32: BTS3012AE Base Station Cabinet Installation Manual

2 Installation Preparations

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

2-6 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 2-1 Straightening tongues

Steel edgeWooden board

Tongue

Spanner

Step 3 After straightening all the tongues on the cover, remove the cover, as shown in Figure 2-2.

Figure 2-2 Removing the cover

Page 33: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 2 Installation Preparations

Issue 01 (2006-09-06) Huawei Technologies Proprietary 2-7

Step 4 Straighten all the tongues that join the wooden boards around the wooden case and remove

the wooden boards, as shown in Figure 2-3.

----End

Figure 2-3 Removing all wooden boards

Unpack other cases in the same way.

When handling the cabinet, hold the strong places such as the upper cable rack or bone frame.

Do not apply too much force on places that are not firm, such as cable supports, cable

fixing-beams, to avoid any damage to the cabinet.

Remove the lining board of the rack on the installation site. Otherwise, boards and signal

cables may be damaged during transportation.

2.4.3 Inspecting Items Inside the Wooden Case

After unpacking, check the items inside the wooden case to ensure that:

� The appearance of the cabinet is not damaged.

� The front and the back doors of the cabinet match.

� The cabinet top is in good condition and the marking is legible.

� The dummy panels and nameplates of boards in the subracks are installed.

� The sanitation inside the cabinet meets the requirements.

� The feeder clips and other items are complete and in good condition.

Page 34: BTS3012AE Base Station Cabinet Installation Manual

2 Installation Preparations

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

2-8 Huawei Technologies Proprietary Issue 01 (2006-09-06)

The items checked must be placed in order.

2.4.4 Unpacking the Carton

Cartons are usually used to pack boards, modules, or terminal devices.

� After moving a board from a dry place with lower temperature to a wet place with higher

temperature, wait at least 30 minutes before unpacking. Otherwise, humidity may gather

on the surface of the board and cause damage to the equipment.

� When unpacking boards, take antistatic measures to prevent the boards from damage.

� When cutting the tape through a paper knife, take care not to cut too deep. Otherwise, the

items inside may be damaged.

� Keep the carton and antistatic plastic packing bags for future use such as holding spare

parts or parts sent back for repair.

Unpack a carton as shown in Figure 2-4.

Figure 2-4 Unpacking a carton

(a) (b)

Unpack a carton as follows:

Step 1 Check the types and quantity of boards inside according to the labels.

Step 2 Cut the tapes along the seams of the carton cover through a knife, as shown in part (a) of

Figure 2-4.

Step 3 Open the carton and take out the items.

----End

Page 35: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 2 Installation Preparations

Issue 01 (2006-09-06) Huawei Technologies Proprietary 2-9

2.4.5 Inspecting Items Inside the Carton

After unpacking, check the items inside the carton to ensure that:

� The packing of things inside the carton is in good condition.

� The number and types of items such as boards are consistent with those on the packing

list.

� The printed plates are not broken and the components do not fall off.

Page 36: BTS3012AE Base Station Cabinet Installation Manual
Page 37: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet

Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-1

3 Installing the BTS3012AE Cabinet

About This Chapter

The following table lists the contents of this chapter.

Title Description

3.1 Installing a Cabinet on the

Cement Floor with Sufficient

Bearing Capacity (ƒ 800

kg/m2)

Describes how to install a cabinet on the cement floor

with sufficient bearing capacity.

3.2 Installing a Cabinet on the

Cement Floor with Insufficient

Bearing Capacity (< 800

kg/m2)

Describes how to install a cabinet on the cement floor

with insufficient bearing capacity.

3.3 Installing Combined

Cabinets

Describes how to install combined cabinets.

Page 38: BTS3012AE Base Station Cabinet Installation Manual

3 Installing the BTS3012AE Cabinet

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

3-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)

3.1 Installing a Cabinet on the Cement Floor with

Sufficient Bearing Capacity (ƒƒƒƒ 800 kg/m2)

� When lifting the cabinet, ensure that all the four lugs are tightened, that the angle between

the lifting rope and the top of the cabinet is at least 60o, and that the cabinet is level.

Installers must stay away from the cabinet when lifting it and ensure that the front door

and rear door are closed.

� When installing the cabinet in bad conditions (for example, in the case of strong wind),

pay extra attention to the gravity center of the cabinet to prevent the cabinet from slanting.

3.1.1 Installation Flowchart

Figure 3-1 shows the flowchart for installing a cabinet on the cement floor with sufficient

bearing capacity.

Page 39: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet

Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-3

Figure 3-1 Process for installing a cabinet on the cement floor

Start

Position thecabinet

Cast thecement plinth

Position the base

Fasten the base

Level the base

Drill holes and installexpansion bolts

Install the cabinet

Remove lifting lugs

End

Level the cabinet

3.1.2 Positioning the Cabinet

The BTS3012AE can be installed against wall, rear to rear, or side by side. The following

requirements must be met to ease casting the cement plinth and installing and maintaining the

equipment:

� When a single BTS3012AE cabinet is installed against wall, it is recommended to keep a

300 mm space between the rear and the wall to facilitate the installation.

Page 40: BTS3012AE Base Station Cabinet Installation Manual

3 Installing the BTS3012AE Cabinet

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

3-4 Huawei Technologies Proprietary Issue 01 (2006-09-06)

� When two BTS3012AE cabinets are installed side by side, it is recommend to keep at

least 300 mm space between two sides.

� When two BTS3012AE cabinets are installed side by side and against the wall, the space

between two sides must be more than 600 mm.

� When the BTS3012AE is installed with the left side against the wall, the space between

the left side and the wall must be more than 600 mm.

� The BTS3012AE cannot be installed in wall corners.

Figure 3-2 shows the installation position of the BTS3012AE.

Figure 3-2 Installation position of the BTS3012AE cabinet

BTS 3012AE

1000

> 600

> 600

> 300

880

1300

1

3.1.3 Casting the Cement Plinth

Cast a cement plinth based on the dimensions shown in Figure 3-3.

The height of the cement plinth must meet the flood protection requirement in the local area.

The cement plinth should be at least 100 mm higher than the ground surface. This helps

protect the cabinet against water damage in the case of heavy rain or flood.

Ensure that the planeness error of the upper plane is not more than 5 mm.

Page 41: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet

Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-5

Figure 3-3 Dimensions of the cement plinth

2500

2800

>100

3.1.4 Positioning the Base

When installing a base, ensure that the front of the base aligns with that of the cabinet

To position the base, do as follows:

Step 1 Determine the installation position of the expansion bolts based on the installation holes of the

cabinet and the positioning dimensions specified in the project design and construction

drawing.

Step 2 Use a tape to determine the marking points.

Step 3 Mark the installation holes one by one based on the design requirements.

Step 4 Measure the distance between the installation holes to ensure accuracy.

Page 42: BTS3012AE Base Station Cabinet Installation Manual

3 Installing the BTS3012AE Cabinet

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

3-6 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 3-4 shows the installation holes of the expansion bolts for the BTS3012AE cabinet.

Figure 3-4 Installation holes of the expansion bolts for a single cabinet

>600

839

723

670

1000

998

2500

>600

40

2800

>1300

737880

>600

2

4

1

5

3

(1) Cement plinth (2) Outline of the base (3) Hole of the expansion bolts

(4) Outline of the cabinet (5) Indications at the cabinet front

----End

Page 43: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet

Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-7

3.1.5 Drilling Holes and Installing Expansion Bolts

� The expansion tube must be fully buried in the ground.

� The depth of the hole must range from 52 mm to 60 mm. The depth of the hole must be a

sum of the length of the expansion tube and the length of the drill bit. If the depth is less

than 52 mm or more than 60 mm, the expansion bolt cannot be fastened.

� All the holes must have the same depth. Before measuring the depth of the hole, remove

the dust inside the hole to measure the exact depth.

� After drilling holes, measure the distance between the holes. If a drilled hole is of great

deviation, relocate and drill a new one.

To drill a hole and install the expansion bolt, do as follows:

Step 1 Use the φ16 drill bit and the M12 expansion bolt assembly.

Figure 3-5 shows the M12 expansion bolt assembly.

Figure 3-5 M12 expansion bolt assembly

1

4

5

6

7

2

3

(1) M12 bolt (2) Spring washer 12 (3) Flat washer 12 (4) Expansion tube

(5) Nut (6) Guiding slot (7) Guiding rib

Step 2 Hold the drill stock firmly with your hands, and keep the drill bit vertical to the ground to drill

a hole.

If the floor is too hard and slippery to settle the drill bit, dig a pit with a chisel to help position the hole

Step 3 Clean the dust with a cleaner when drilling.

Step 4 Insert the guiding rib on the nut into the guiding slot of the expansion tube.

Page 44: BTS3012AE Base Station Cabinet Installation Manual

3 Installing the BTS3012AE Cabinet

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

3-8 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Step 5 Feed the tube and the nut into the hole vertically, and then hammer the tube until it is fully

buried in the ground, as shown in Figure 3-6.

Figure 3-6 Installing the expansion bolt (1)

Ensure that the expansion tube is fully inserted into the hole.

Step 6 Remove the M12 expansion bolt, spring washer, and flat washer, as shown in Figure 3-7.

Figure 3-7 Installing the expansion bolt (2)

----End

Page 45: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet

Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-9

3.1.6 Fastening the Base

To fasten the base, do as follows:

Step 1 Place the base on the cement plinth.

Step 2 Align the installation holes of the base with the expansion bolt holes on the cement plinth.

Step 3 Fasten the base on the cement plinth by using the M12x60 bolts, spring washers, flat washers,

and bevel washers, as shown in Figure 3-8.

Figure 3-8 Installing the base

4

12

3

(1) M12x60 bolt (2) Spring washer (3) Flat washer (4) Bevel washer 12

----End

3.1.7 Leveling the Base

To level the base, do as follows:

Step 1 Place a level bar on the top plane of the base in the latitudinal and longitudinal directions, as

shown in Figure 3-9.

Step 2 Check whether the leveling bubble in the level vial is in the middle.

Step 3 If the leveling bubble is not in the middle, add adjusting shims under the base, as shown in

Figure 3-10.

Page 46: BTS3012AE Base Station Cabinet Installation Manual

3 Installing the BTS3012AE Cabinet

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

3-10 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 3-9 Leveling the base (1)

21

(1) Level bar (2) Base

Figure 3-10 Leveling the base (2)

12

(1) Adjusting shim (2) Base

Step 4 Repeat steps 1 to 3 to ensure that the leveling bubble in the level vial is in the middle.

----End

3.1.8 Placing the Cabinet

� When lifting the cabinet, ensure that all the four lugs are tightened, that the angle between

the lifting rope and the top of the cabinet is at least 60o, and that the cabinet is level.

Installers must stay away from the cabinet when lifting it and ensure that the front door

and rear door are closed.

� When installing the cabinet in bad conditions (for example, in the case of strong wind),

pay extra attention to the gravity center of the cabinet to prevent the cabinet from slanting.

To place the cabinet, do as follows:

Page 47: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet

Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-11

Step 1 Use a crane to lift the cabinet, as shown in Figure 3-11.

Figure 3-11 Lifting the cabinet

Step 2 Place slowly the cabinet on the base and align the installation holes at the bottom of the

cabinet with the bolt holes on the base.

Figure 3-12 shows how to place the cabinet on the base.

Page 48: BTS3012AE Base Station Cabinet Installation Manual

3 Installing the BTS3012AE Cabinet

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

3-12 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 3-12 Placing the cabinet on the base

1

23

(1) Cabinet (2) Base (3) Cement plinth

----End

3.1.9 Fastening the Cabinet

� This section applies to the installation of the BTS3012AE cabinet on a base or on U-bar supports.

� If the front door keeps open for a long time, use a solid object to support the lower part of the door

to prevent the deformation of the door.

� Before closing the front door, lift the support bar and slide it along the rail.

To fasten the cabinet, do as follows:

Step 1 Fasten the cabinet on the base by using two M12x35 bolts, spring washers, and flat washers,

as shown in Figure 3-13.

The bolts shall be inserted from the bottom to the top of the base near the cabinet rear.

Page 49: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet

Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-13

Figure 3-13 Fastening the cabinet on the base (Rear view)

2

3

4

56

1

(1) Cabinet rear (2) Base (3) Cement plinth

(4) M12x35 bolt (5) Spring washer 12 (6) Big flat washer

Step 2 Unlock and open the front door, as shown in Figure 3-14.

Page 50: BTS3012AE Base Station Cabinet Installation Manual

3 Installing the BTS3012AE Cabinet

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

3-14 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 3-14 Unlocking the cabinet

Step 3 Slide the support bar to fix the front door at a suitable angle.

� The front door can be fully opened to 120°.

� The support bar can be fixed at an angle of 90° or 120°.

Step 4 Fix one end of the support bar on the rail through a fixing bolt, as shown in

Figure 3-15.

The other end of the support bar is fixed on the cabinet through a screw.

Page 51: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet

Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-15

Figure 3-15 Fixing the front door

12

(1) Fixing bolt (2) Support bar

Step 5 Fasten the cabinet on the base by using two M12x70 bolts, spring washers, and flat washers,

as shown in Figure 3-16.

The bolts shall be inserted from the top to the bottom of the base near the front door.

Figure 3-16 Fastening the cabinet on the base (Front view)

1

23

4

(1) M12x70 bolt (2) Spring washer

(3) Flat washer (4) Installation hole for the bolt

Page 52: BTS3012AE Base Station Cabinet Installation Manual

3 Installing the BTS3012AE Cabinet

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

3-16 Huawei Technologies Proprietary Issue 01 (2006-09-06)

----End

3.1.10 Leveling the Cabinet

To level the cabinet, do as follows:

Step 1 Place a level bar on the top plane of the cabinet in the latitudinal and longitudinal directions,

as shown in Figure 3-17.

Step 2 Check whether the leveling bubble in the level vial is in the middle.

Step 3 If the leveling bubble is not in the middle, add adjusting shims under the lower support, as

shown in Figure 3-18.

Step 4 Repeat steps 1 to 3 to ensure that the leveling bubble in the level vial is in the middle.

Figure 3-17 Leveling the cabinet (1)

1

2

(1) Level bar (2) Cabinet

Page 53: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet

Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-17

Figure 3-18 Leveling the cabinet (2)

1

2

(1) Cabinet (2) Adjusting shim

----End

3.1.11 Removing Lifting Lugs

Remove the four lifting lugs on the top of the cabinet, and then use the blind choke plugs

shipped with the product to cover the bolt holes, as shown in Figure 3-19.

Figure 3-19 Removing lifting lugs

1

2

(1) Lifting lug (2) Blind choke plug

Page 54: BTS3012AE Base Station Cabinet Installation Manual

3 Installing the BTS3012AE Cabinet

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

3-18 Huawei Technologies Proprietary Issue 01 (2006-09-06)

3.1.12 Illustration of the Installed Cabinet

Figure 3-20 shows the installed BTS3012AE cabinet.

Figure 3-20 Installed BTS3012AE cabinet

3.2 Installing a Cabinet on the Cement Floor with Insufficient

Bearing Capacity (< 800 kg/m2)

3.2.1 Installation Flowchart

Figure 3-21 shows the process flowchart for installing a cabinet on the cement floor with

insufficient bearing capacity.

Page 55: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet

Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-19

Figure 3-21 Process for installing a cabinet on the cement floor with insufficient bearing capacity

Start

Position thecabinet

Cast cementplinth

Prepare U-barsupports

Fasten U-barsupports

Level thecabinet

Drill holes and installexpansion bolts

Fasten thecabinet

Removelifting lugs

End

Position U-barsupports

Place thecabinet

Level U-barsupports

Page 56: BTS3012AE Base Station Cabinet Installation Manual

3 Installing the BTS3012AE Cabinet

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

3-20 Huawei Technologies Proprietary Issue 01 (2006-09-06)

3.2.2 Installation Process

3.2.3 Positioning the Cabinet

The BTS3012AE can be installed against wall, rear to rear, or side by side. The following

requirements must be met to ease casting the cement plinth and installing and maintaining the

equipment:

� When a single BTS3012AE cabinet is installed against wall, it is recommended to keep a

300 mm space between the rear and the wall to facilitate the installation.

� When two BTS3012AE cabinets are installed side by side, it is recommend to keep at

least 300 mm space between two sides.

� When two BTS3012AE cabinets are installed side by side and against the wall, the space

between two sides must be more than 600 mm.

� When the BTS3012AE is installed with the left side against the wall, the space between

the left side and the wall must be more than 600 mm.

� The BTS3012AE cannot be installed in wall corners.

Figure 3-2 shows the installation position of the BTS3012AE.

Figure 3-22 Installation position of the BTS3012AE cabinet

BTS 3012AE

1000

> 600

> 600

> 300

880

1300

1

3.2.4 Casting Cement Plinths

Determine the position of the wall or beam that bears the BTS3012AE. Then cast two cement

plinths on the floor or platform right above the bearing wall or the beam.

Page 57: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet

Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-21

The cement plinth must be 100 mm in height, and the distance between the two cement

plinths must be at least 6 m.

3.2.5 Preparing U-Bar Supports

Determine the length of U-bar supports based on the distance between the cement plinths, as

shown in Figure 3-23.

Figure 3-23 Dimensions of U-bar supports (unit: mm)

300

18- 16Ø

900

100839

723

20073

6704- 14Ø

3.2.6 Positioning U-Bar Supports

Drill eighteen φ16 holes and four φ14 holes on the U-bar supports according to Figure 3-23.

3.2.7 Drilling Holes and Installing Expansion Bolts

For details, see section 3.1.5 "Drilling Holes and Installing Expansion Bolts."

3.2.8 Fastening U-Bar Supports

Use either of the following methods to secure the U-bar support on the cement plinths:

� Cast the U-bar supports and the cement plinths together.

� Use expansion bolts to fasten the U-bar supports on the cement plinths.

Figure 3-24 shows how to fasten the U-bar supports on the cement plinths.

Page 58: BTS3012AE Base Station Cabinet Installation Manual

3 Installing the BTS3012AE Cabinet

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

3-22 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 3-24 Fastening the U-bar supports on the cement plinths

1

2

3

(1) M12x60 bolt (2) Spring washer (3) Flat washer

3.2.9 Leveling U-Bar Supports

To level the U-bar supports, do as follows:

Step 1 Place a level bar on the top plane of the U-bar supports in the latitudinal and longitudinal

directions, as shown in Figure 3-25.

Step 2 Check whether the leveling bubble in the level vial is in the middle.

Step 3 If the leveling bubble is not in the middle, add adjusting shims under the U-bar supports, as

shown in Figure 3-26.

Step 4 Repeat steps 1 to 3 to ensure that the leveling bubble in the level vial is in the middle.

Figure 3-25 Leveling the U-bar support (1)

1

2

(1) Level bar (2) U-bar support

Page 59: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet

Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-23

Figure 3-26 Leveling the U-bar support (2)

1

2

3

(1) Level bar (2) U-bar support (3) Adjusting shim

----End

3.2.10 Fastening the Base

For details, see 3.1.4 "Leveling the Base."

3.2.11 Leveling the Base

For details, see 3.1.7 "Leveling the Base."

3.2.12 Placing the Cabinet

� When lifting the cabinet, ensure that all the four lugs are tightened, that the angle between

the lifting rope and the top of the cabinet is at least 60o, and that the cabinet is level.

Installers must stay away from the cabinet when lifting it and ensure that the front door

and rear door are closed.

� When installing the cabinet in adverse conditions (for example, in the case of strong wind),

pay special attention to the gravity center of the cabinet to prevent the cabinet from

slanting.

To place the cabinet, do as follows:

Step 1 Lift the cabinet through a crane, as shown in Figure 3-27.

Page 60: BTS3012AE Base Station Cabinet Installation Manual

3 Installing the BTS3012AE Cabinet

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

3-24 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 3-27 Lifting the cabinet

Step 2 Place slowly the cabinet on the U-bar supports and align the installation holes at the bottom of

the cabinet with the bolt holes on the U-bar supports.

Figure 3-28 shows how to place the cabinet on the U-bar supports.

Page 61: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet

Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-25

Figure 3-28 Placing the cabinet on the U-bar supports

----End

3.2.13 Fastening the Cabinet

� This section applies to the installation of the BTS3012AE cabinet on a base or on U-bar supports.

� If the front door keeps open for a long time, use a solid object to support the lower part of the door

to prevent the deformation of the door.

� Before closing the front door, lift the support bar and slide it along the rail.

To fasten the cabinet, do as follows:

Step 1 Fasten the cabinet on the base by using two M12x35 bolts, some spring washers, and some

big flat washers, as shown in Figure 3-29.

The bolts shall be inserted from the bottom to the top of the base near the cabinet rear.

Page 62: BTS3012AE Base Station Cabinet Installation Manual

3 Installing the BTS3012AE Cabinet

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

3-26 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 3-29 Fastening the cabinet on the base (Rear view)

2

3

4

561

(1) Cabinet rear (2) Base (3) U-bar supports

(4) M12x35 bolt (5) Spring washer 12 (6) Big flat washer

Page 63: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet

Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-27

Step 2 Unlock and open the front door, as shown in Figure 3-30.

Figure 3-30 Unlocking the front door

Step 3 Slide the support bar to fix the front door at a suitable angle.

� The front door can be fully opened to 120°.

� The support bar can be fixed at an angle of 90° or 120°.

Step 4 Fix one end of the support bar on the rail through the fixing bolt, as shown in Figure 3-15.

The other end of the support bar is fixed on the cabinet through a screw.

Step 5 Fasten the cabinet on the base by using two M12x70 bolts, spring washers, and flat washers,

as shown Figure 3-31.

The bolts shall be inserted from the top to the bottom of the base near the front door.

Page 64: BTS3012AE Base Station Cabinet Installation Manual

3 Installing the BTS3012AE Cabinet

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

3-28 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 3-31 Fastening the cabinet on the base (Front view)

1

2

3

4

(1) M 12x70 bolt (2) Spring washer

(3) Flat washer (4) Installation holes for the bolts

----End

3.2.14 Leveling the Cabinet

To level the cabinet, do as follows:

Step 1 Place a level bar on the top plane of the cabinet in the latitudinal and longitudinal directions,

as shown in Figure 3-17.

Step 2 Check whether the leveling bubble in the level vial is in the middle.

Step 3 If the leveling bubble is not in the middle, add adjusting shims under the lower support.

Step 4 Repeat steps 1 to 3 to ensure that the leveling bubble in the level vial is in the middle.

----End

3.2.15 Removing Lifting Lugs

Remove the four lifting lugs on the top of the cabinet, and then use the blind choke plugs

shipped with the product to cover the bolt holes, as shown in Figure 3-32.

Page 65: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet

Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-29

Figure 3-32 Removing lifting lugs

1

2

(1) Lifting lug (2) Blind choke plug

3.2.16 Illustration of the Installed Cabinet

Figure 3-33 shows the installed cabinet.

Page 66: BTS3012AE Base Station Cabinet Installation Manual

3 Installing the BTS3012AE Cabinet

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

3-30 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 3-33 Installed cabinet

3.3 Installing Combined Cabinets

When installing two BTS3012AE combined cabinets, you are recommended to keep at least

300-mm space between two cabinets.

To install the combined cabinets, perform the following steps:

Step 1 Determine the installation positions of the cabinets, and keep at least 300-mm space between

two cabinets.

Step 2 Install the cabinets. See sections 3.1 "Installing a Cabinet on the Cement Floor with Sufficient

Bearing Capacity (ƒ 800 kg/m2)" and 3.2 "Installing a Cabinet on the Cement Floor with

Insufficient Bearing Capacity (< 800 kg/m2)."

Step 3 Connect a signal cable between the combined cabinets. Connect one end of the cable to the

port TO SLAVE CABINET on the DSCB of the main cabinet and the other end to that on the

DSCB of the extension cabinet.

Step 4 Connect the signal input/output cable for the combined cabinet on the main cabinet to the

CC_OUT port.

The cable connects to the CC_IN port before delivery.

Page 67: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet

Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-31

Step 5 Set the DIP switches on the DCSU.

----End

The DCSU has 14 DIP switches on it. SW12, SW13, and SW14 are reserved.

Figure 3-34 shows the initial settings for the DIP switches on the DCSU.

Figure 3-34 DIP switches on the DCSU

1 4

1 4

1 41 4SW6 SW7

1 4 1 4

1 4

SW9 SW10

SW8

SW11

SW1

OFF

OFF

ON

ON

ON

ON

1 4

1 4

1 4

SW14

SW13

SW12

OFF

ON1 4

1 4

1 4

1 4

SW5

SW4

SW3

SW2

OFF

ONOFF

SW1 and SW11 are used to set the main cabinet and extension cabinet in the cabinet group,

and to select the terminal match.

Table 3-1 lists the settings for SW1.

Table 3-1 Settings for SW1

SW1 Function

All ON Main cabinet of the main cabinet group

All OFF Other cases

Table 3-2 lists the settings for SW11.

Table 3-2 Settings for SW11

SW11 Function

All ON CBUS1 terminal match

All OFF CBUS1 no terminal match

Page 68: BTS3012AE Base Station Cabinet Installation Manual

3 Installing the BTS3012AE Cabinet

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

3-32 Huawei Technologies Proprietary Issue 01 (2006-09-06)

The descriptions of SW11 in different situations are as follows:

� Single cabinet: All ON

� Combined cabinet: All ON

� Two-cabinet group: All ON

� Three-cabinet group: All OFF for the main cabinet and all ON for the other cabinets

SW2 through SW5 are used to set the main cabinet and extension cabinet, and select the

terminal match.

See Table 3-3 lists the settings for SW2−SW5.

Table 3-3 Settings for SW2−SW5

SW2–SW5 Function

All ON Main cabinet

All OFF Extension cabinet

SW6 and SW7 are used to set E1 impedance. See Table 3-4 for details.

Table 3-4 Settings for SW6 and SW7

DIP Switch DIP Digit ON/OFF Function

ON E1 1: 75 ohms 1

OFF E1 1: 120 ohms

ON E1 2: 75 ohms 2

OFF E1 2: 120 ohms

ON E1 3: 75 ohms 3

OFF E1 3: 120 ohms

ON E1 4: 75 ohms

SW6

4

OFF E1 4: 120 ohms

ON E1 5: 75 ohms 1

OFF E1 5: 120 ohms

ON E1 6: 75 ohms 2

OFF E1 6: 120 ohms

ON E1 7: 75 ohms 3

OFF E1 7: 120 ohms

ON E1 8: 75 ohms

SW7

4

OFF E1 8: 120 ohms

Page 69: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 3 Installing the BTS3012AE Cabinet

Issue 01 (2006-09-06) Huawei Technologies Proprietary 3-33

SW8 is used to set the cabinet number. In a cabinet group, you need to set SW8 for the main

cabinet. See Table 3-5 for details. You can use the default settings for the extension cabinets,

that is, all the extension cabinets are set to ON.

Table 3-5 Settings for SW8

DIP Digit

1 2 3 4

Function

ON ON ON ON Main cabinet of the main cabinet group

OFF OFF ON ON Main cabinet of extension cabinet group 1

ON OFF OFF ON Main cabinet of extension cabinet group 2

SW9 and SW10 are used to set cabinet type. See Table 3-6 for details.

Table 3-6 Settings for SW9 and SW10

SW9 SW10

1 2 3 4 1 2 3 4

Function

OFF ON ON ON ON ON ON ON The cabinet type is BTS3012AE.

Page 70: BTS3012AE Base Station Cabinet Installation Manual
Page 71: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 4 Installing Boards

Issue 01 (2006-09-06) Huawei Technologies Proprietary 4-1

4 Installing Boards About This Chapter

The following table lists the contents of this chapter.

Title Description

4.1 Introduction to Installation

Positions

Introduces the installation positions of boards in the

BTS3012AE subrack.

4.2 Preparations Describes the preparatory work before board installation.

4.3 Installing the DTMU Describes how to install the DTMU.

4.4 Installing the DATU Describes how to install the DATU.

4.5 Installing the PSU and

DPMU

Describes how to install the PSU and DPMU.

4.6 Installing the DELU Describes how to install the DELU.

4.7 Installing the DMLU Describes how to install the DMLU.

4.8 Installing the DTRU Describes how to install the DTRU.

4.9 Installing the DDPU and

DCOM

Describes how to install the DDPU and DCOM.

Page 72: BTS3012AE Base Station Cabinet Installation Manual

4 Installing Boards

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

4-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)

4.1 Introduction to Installation Positions

Figure 4-1 shows the installation positions of all the boards of the BTS3012AE.

Figure 4-1 Boards in the BTS3012AE subrack

Cable in/outAC lightning

D

C

O

M

D

D

P

U

D

C

O

M

D

D

P

U

D

C

O

M

D

D

P

U

D

T

R

U

D

T

R

U

D

T

R

U

D

T

R

U

D

T

R

U

D

T

R

U

PSU PSU PSU PSU

PSUPSUPSUDPMU

Air return

Wire holder

Wire holder

FAN

DELU0

DELU1DMLU

AC PDU

Air return

D

T

M

U

D

T

M

U

D

A

T

U

D

C

C

U

D

C

S

U

Wire holder

DC

PDU

BAT 48V 50AH

Air inlet

Tra

nsm

issio

nu

nit

BAT 48V 150AH

Air inlet

4.2 Preparations

Before installing the boards, perform the following preparations:

� Wear an antistatic wrist strap, and connect the ESD plug to the ESD connector on the

cabinet, as shown in Figure 4-2. Ensure that the wrist strap is in good contact with your

wrist.

Page 73: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 4 Installing Boards

Issue 01 (2006-09-06) Huawei Technologies Proprietary 4-3

� If the cabinet is not grounded, first connect the PGND wiring terminal on the left of the cabinet to

the external grounding bar. For details, see section 6.3 "Installing PGND Cables."

� Keep the ESD wrist strap in good condition. Its resistance should be between 0.75 Mega ohms and

10 Mega ohms. Typically, the life expectancy of the ESD wrist strap lasts for about two years.

Replace the strap when the resistance falls beyond the specified range.

Figure 4-2 Wearing an antistatic wrist strap

1

2

3

(1) ESD connector (2) ESD plug

(3) Antistatic wrist strap

� The antistatic wrist strap cannot prevent static electricity from being generated by

friction between a board and your clothes. Ensure that boards are not in contact with

your clothes.

� Clean up the subracks.

� Check whether there are any bent, missed, or broken pins on the backplane.

− If there is any bent pin, replace it or straighten it with a pair of nipper pliers in case of

an emergency.

− If there is any missed pin, replace the backplane.

� Check whether the sockets on the backplanes and the boards are deformed.

− If the deformation is not obvious, adjust the socket using a pair of nipper pliers.

− If the deformation is serious, replace the backplane or the board.

� Prepare a #2 crossover screwdriver whose diameter is 6 mm to tighten the M3 captive

screws on the board panels.

� Keep the boards or parts that are not installed in antistatic bags. Place the removed

boards or parts on the antistatic pad or other antistatic materials. Never pack or hold the

boards or parts using plastic foams, common plastic bags, or paper bags.

Page 74: BTS3012AE Base Station Cabinet Installation Manual

4 Installing Boards

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

4-4 Huawei Technologies Proprietary Issue 01 (2006-09-06)

If you are not clear about the specifications of the screwdrivers, try different screwdrivers until you find

a suitable one.

4.3 Installing the DTMU

The DTMU is placed in the common subrack. Set the DIP switches on the DTMU before

installation.

4.3.1 Setting DIP Switches on the DTMU

The DTMU has five DIP switches on it. S4, S5, S6, and S7 are used to select whether the

rings of E1 1 through E1 8 are grounded. S3 is reserved.

Figure 4-3 shows the initial setting of the DIP switches on the DTMU.

Figure 4-3 DIP switches on the DTMU

ON

S4

S5

S6

S7

OFF

S3

4

14

14

1

4

1

4

1

Table 4-1 describes the settings and functions of the DIP switches.

Table 4-1 S4/S5/S6/S7 setting descriptions

DIP Switch DIP Position

ON/OFF Functions

ON E1 1, sending, ring grounded 1

OFF E1 1, sending, ring ungrounded

ON E1 1, receiving, ring grounded 2

OFF E1 1, receiving, ring ungrounded

S5

3 ON E1 2, sending, ring grounded

Page 75: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 4 Installing Boards

Issue 01 (2006-09-06) Huawei Technologies Proprietary 4-5

DIP Switch DIP Position

ON/OFF Functions

OFF E1 2, sending, ring ungrounded

ON E1 2, receiving, ring grounded 4

OFF E1 2, receiving, ring ungrounded

ON E1 3, sending, ring grounded 1

OFF E1 3, sending, ring ungrounded

ON E1 3, receiving, ring grounded 2

OFF E1 3, receiving, ring ungrounded

ON E1 4, sending, ring grounded 3

OFF E1 4, sending, ring ungrounded

ON E1 4, receiving, ring grounded

S4

4

OFF E1 4, receiving, ring ungrounded

ON E1 5, sending, ring grounded 1

OFF E1 5, sending, ring ungrounded

ON E1 5, receiving, ring grounded 2

OFF E1 5, receiving, ring ungrounded

ON E1 6, sending, ring grounded 3

OFF E1 6, sending, ring ungrounded

ON E1 6, receiving, ring grounded

S7

4

OFF E1 6, receiving, ring ungrounded

ON E1 7, sending, ring grounded 1

OFF E1 7, sending, ring ungrounded

ON E1 7, receiving, ring grounded 2

OFF E1 7, receiving, ring ungrounded

ON E1 8, sending, ring grounded 3

OFF E1 8, sending, ring ungrounded

ON E1 8, receiving, ring grounded

S6

4

OFF E1 8, receiving, ring ungrounded

Page 76: BTS3012AE Base Station Cabinet Installation Manual

4 Installing Boards

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

4-6 Huawei Technologies Proprietary Issue 01 (2006-09-06)

4.3.2 Installation Procedure

Wear an antistatic wrist strap when installing boards.

Install the DTMU as follows:

Step 1 Secure the captive screws on the panel by screwing them clockwise through a #2 cross

screwdriver whose diameter is 6 mm. Ensure that the screws are active, that is, the screw

threads are not stuck to the spanner. See (a) in Figure 4-4.

Step 2 Hold the spanner on the upper part of the front panel with one hand and support the board

with the other hand. Position the board in the corresponding guide rail according to the

nameplate.

Step 3 Hold the two spanners and gently push the board along the guide rail until they are in

position.

Step 4 Turn inward the two spanners to the position as shown in (b) of Figure 4-4.

Ensure that the crotchets on both ends of the spanners hook on to the square holes of the

subrack, as shown in Figure 4-5.

Step 5 Secure the captive screws on the panel by screwing them clockwise with a #2 cross

screwdriver whose diameter is 6 mm, as shown in (c) of Figure 4-4.

----End

Figure 4-4 Installing the DTMU

Page 77: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 4 Installing Boards

Issue 01 (2006-09-06) Huawei Technologies Proprietary 4-7

Figure 4-5 Hooking spanners on to the square holes of the subrack

4.4 Installing the DATU

The DATU is placed in the common subrack.

Table 4-2 shows the default setting of the DIP switches before delivery.

Table 4-2 Default setting of the DIP switches on the DATU

DIP Switch 1 2 3 4

SW1 OFF OFF ON ON

SW2 ON ON ON ON

SW3 ON ON ON ON

Figure 4-6 shows the DIP switches on the DATU.

Page 78: BTS3012AE Base Station Cabinet Installation Manual

4 Installing Boards

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

4-8 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 4-6 DIP switches on the DATU

1 4SW1 SW3 SW2

ONOFF ON

OFF14

OFF

ON

14

The installation procedure for the DATU is the same as that for the DTMU. For details, see

section 4.3.2 "Installation Procedure."

4.5 Installing the PSU and DPMU

The Power Supply Unit (PSU) is located in the power subrack. The minimum configuration of

PSUs is 1 + 1. The number of PSUs under full configuration is 7.

The PSU functions as follows:

� Converting 220 VAC to –48 VDC for all modules inside the BTS3012AE.

� Monitoring module fault alarms, module protection alarms, and AC power-off alarms.

� Monitoring float charging of the storage battery and adjusting the voltage and current of

the storage battery.

The DPMU is in the power subrack of the cabinet. The BTS3012AE requires only one

DPMU.

The DPMU functions as follows:

� Power system management and battery charge and discharge management

� Water, smoke, access control, standby Boolean value, temperature and humidity, battery

temperature, and standby analog report

� Power distribution check and power distribution alarm report

� Boolean value alarm report

4.5.1 PSU and DPMU Installation Procedure

The PSU and DPMU installation procedure is as follows:

Step 1 Check that all switches of the eight-bit DIP switch are set to OFF position, as shown in Figure

4-7.

Page 79: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 4 Installing Boards

Issue 01 (2006-09-06) Huawei Technologies Proprietary 4-9

Figure 4-7 DIP switch of the DPMU

12345678

ON

3

1 2 3 4 5 6 7 8ON

1

2

(1) DIP switch after zoomed in and turned 180° clockwise

(2) Normal view of the DIP switch (3) Rear view of the DPMU

Step 2 Loosen the handle on the PSU panel and slide the PSU or DPMU forward along the guide rail

until you can feel obvious resisting force. See Figure 4-8.

Page 80: BTS3012AE Base Station Cabinet Installation Manual

4 Installing Boards

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

4-10 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 4-8 Installing the PSU and DPMU (1)

PSU7

PSU2 PSU3DPMU PSU1

PSU6

PSU4 PSU5

Step 3 Fasten the handle as shown in Figure 4-9.

Figure 4-9 Installing the PSU and DPMU (2)

PSU6 PSU7

PSU2 PSU3DPMU PSU1

PSU4 PSU5

Step 4 Fasten the screws on the PSU and DPMU panel.

Repeat the previous steps until the DPMU and all the configured PSUs are installed. Install

the PSUs in the ascending order from PSU1 all the way to PSU7.

----End

Page 81: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 4 Installing Boards

Issue 01 (2006-09-06) Huawei Technologies Proprietary 4-11

4.6 Installing the DELU

4.6.1 Installation Overview

The E1 Signal Lightning Protection Unit for DTRU BTS (DELU) is configured in slot 0 or 2

of the DCSB. The DELU is mandatory and the minimum configuration is one. If the DMLU

is not configured, a maximum of three DELUs can be configured on the DSCB.

The main function of the DELU is to realize the lightning protection of four E1 signals on a

board. Under the full configuration of three DELUs, the lightning protection of 12 E1 signals

can be realized.

4.6.2 Installation Procedure

The DELU installation procedure is as follows:

Step 1 Level the DELU.

Step 2 Hold the left and right sides of the DELU with your hands and place it in the slot.

Step 3 Push the board at the left and right sides of the front panel until it is in secure contact with the

slot.

----End

4.7 Installing the DMLU

4.7.1 Installation Overview

The Monitor Signal Lightning Protection Unit for DTRU BTS (DMLU) is configured in slot 1

of the DCSB. The DMLU is optional and the full configuration is one.

The DMLU functions as follows:

� Supporting lightning protection of 14 external Boolean value inputs.

� Providing a 2-route 485 serial control bus interface.

4.7.2 Installation Procedure

The procedure for installing the DMLU is the same with that for the DELU. For details, see

section 4.6.2 "Installation Procedure."

4.8 Installing the DTRU

Page 82: BTS3012AE Base Station Cabinet Installation Manual

4 Installing Boards

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

4-12 Huawei Technologies Proprietary Issue 01 (2006-09-06)

After powering on the cabinet, do not touch any DTRU in case they get damaged.

The DTRUs are placed in the DTRU subrack.

Figure 4-10 shows the front panel of a DTRU.

Figure 4-10 Front panel of a DTRU

To install a DTRU, do as follows:

Step 1 Decide the slot for installing the DTRU for easy cabling and maintenance.

Step 2 Hold the handle with one hand and support the board with the other to position the board into

the guide rail.

Step 3 Push the board along the guide rail.

Step 4 Fix the board in the subrack with four screws at four corners of the panel.

Page 83: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 4 Installing Boards

Issue 01 (2006-09-06) Huawei Technologies Proprietary 4-13

Step 5 Remove the dustproof cap on the power cable of the DTRU and insert the cable connector

into the PWR port on the corresponding DTRU panel.

Step 6 Screw the two fastening bolts on the cable connector.

Step 7 Install the dummy panel on the vacant slot and fasten it with four screws to make the dummy

panel in close contact with the subrack.

Step 8 Use a cable tie to attach the unused power cable to the handle of the dummy panel.

----End

� Place the removed dustproof cap under the cabinet for future use.

� Install a dustproof cap on the connector of the unused power cable to prevent the inner conductor in

the cable connector from touching the edge angles of the cabinet.

4.9 Installing the DDPU and DCOM

� After powering on the cabinet, do not touch any DDPU or the DCOM in case it may get

damaged.

� When removing a DDPU, install a dustproof cap on the connector of the removed power

cable to prevent the inner conductor in the cable connector from touching the edge angles

of the cabinet.

The DDPUs and the DCOMs are placed in the DAFU subrack.

Figure 4-11 shows the front panel of a DDPU. The procedure for installing a DCOM is the

same with that for installing a DDPU.

Page 84: BTS3012AE Base Station Cabinet Installation Manual

4 Installing Boards

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

4-14 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 4-11 Front panel of a DDPU

To install a DDPU, do as follows:

Step 1 Decide the slot for installing the DTRU for easy cabling and maintenance.

Step 2 Hold the handle with one hand and support the board with the other to position the board into

the guide rail.

Step 3 Push the board along the guide rail.

Step 4 Fix the board in the subrack with four screws at four corners of the panel.

Step 5 Remove the dustproof cap on the power cable of the DDPU and insert the cable connector

into the POWER port on the corresponding DDPU panel.

Step 6 Screw the two fastening bolts on the cable connector.

Step 7 Install the dummy panel on the vacant slot and fasten it with four screws to make the dummy

panel in close contact with the subrack.

Step 8 Use a cable tie to attach the unused power cable and signal cable to the handle of the dummy

panel.

----End

Page 85: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 4 Installing Boards

Issue 01 (2006-09-06) Huawei Technologies Proprietary 4-15

� Place the removed dustproof cap under the cabinet for future use.

� Install a dustproof cap on the connector of the unused power cable to prevent the inner conductor in

the cable connector from touching the edge angles of the cabinet.

Page 86: BTS3012AE Base Station Cabinet Installation Manual
Page 87: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 5 Installing Auxiliary Equipment

Issue 01 (2006-09-06) Huawei Technologies Proprietary 5-1

5 Installing Auxiliary Equipment About This Chapter

The following table lists the contents of this chapter.

Title Description

5.1 Installing Transmission

Unit

Describes how to install the transmission unit.

5.2 Installing Outdoor

Interface Boxes

Describes how to install outdoor interface boxes.

Page 88: BTS3012AE Base Station Cabinet Installation Manual

5 Installing Auxiliary Equipment

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

5-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)

5.1 Installing Transmission Unit

5.1.1 Introduction to Installation Positions

The transmission unit is installed in the transmission equipment subrack. Figure 5-1 shows the

installation position of the transmission unit.

Figure 5-1 Installation position of the transmission unit

Page 89: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 5 Installing Auxiliary Equipment

Issue 01 (2006-09-06) Huawei Technologies Proprietary 5-1

Tra

nsm

issio

nu

nit

5.1.2 Installation Procedure

The procedure for installing the transmission unit is as follows:

Step 1 Remove the dummy panel and air deflector plate in the transmission unit subrack according to

the space required by the transmission unit.

Page 90: BTS3012AE Base Station Cabinet Installation Manual

5 Installing Auxiliary Equipment

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

5-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)

If the transmission unit (including microwave equipment) is installed in the cabinet, remove the dummy

panel and air deflector plate to avoid poor ventilation and over-high temperature. See Figure 5-2. If the

height of the transmission unit is nU, remove n (n ≤ 6) dummy panels and n (n ≤ 6) air deflector plates.

Figure 5-2 Positions of the dummy panel and air deflector plate

1 2

(1) Dummy panel (2) Air deflector plate

Step 2 Install the transmission unit in the transmission unit subrack and fasten the screws as shown

in Figure 5-3.

Figure 5-3 Installing transmission unit

1

2

(1) Transmission unit subrack (2) Transmission unit

Page 91: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 5 Installing Auxiliary Equipment

Issue 01 (2006-09-06) Huawei Technologies Proprietary 5-3

----End

5.2 Installing Outdoor Interface Boxes

The outdoor interface box has two types: outdoor transmission interface box and outdoor

power interface box. The two types of interface boxes share the same installation methods.

The installation methods consist of the following:

� Installing the Outdoor Interface Box on a Wall

� Installing the Outdoor Interface Box on a Pole

5.2.1 Introduction to the Outdoor Transmission Interface Box

The TSI-DDF/ODF outdoor transmission interface box (hereinafter referred to as the

transmission interface box) serves as the interface between the transmission unit you have

prepared and Huawei BTS equipment. Huawei provides the following two types of

transmission interface boxes:

� 75-ohm transmission interface box (supporting 75-ohm transmission mode)

� 120-ohm transmission interface box (supporting 120-ohm transmission mode)

Dimensions

The 75-ohm transmission interface box and the 120-ohm transmission interface box have the

same dimensions. The dimensions are as follows:

� Length: 420 mm

� Width: 378 mm

� Height: 125 mm

Weight

The weight of the transmission interface box is 4.92 kg before delivery.

Components of the 75-ohm Transmission Interface Box

The 75-ohm transmission interface box under full configuration consists of the following

parts:

� A case

� A 75-ohm digital unit

� A grounding busbar

� 12-core fusion parts

Figure 5-4 shows the internal structure of the box.

Page 92: BTS3012AE Base Station Cabinet Installation Manual

5 Installing Auxiliary Equipment

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

5-4 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 5-4 Internal structure of the 75-ohm outdoor transmission interface box

1

2

3

4

(1) 12-core fusion parts (2) 75-ohm digital unit

(3) Grounding busbar (4) Case

The 12-core fusion parts consist of:

� A 12-core fusion box

� A fiber adaptor rack

� A fiber coiler

� A fiber stripping unit

Figure 5-5 shows these parts.

Figure 5-5 Structure of the 12-core fusion parts

1

2

3

4

(1) 12-core fusion box (2) Fiber adapter rack

(3) Fiber coiler (4) Fiber stripping unit

Page 93: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 5 Installing Auxiliary Equipment

Issue 01 (2006-09-06) Huawei Technologies Proprietary 5-5

The internal parts of the 75-ohm transmission interface box are installed before delivery.

Components of the 120-ohm Transmission Interface Box

The 120-ohm transmission interface box under full configuration consists of the following

parts:

� A case

� A 120-ohm digital unit

� A grounding busbar

� 12-core fusion part

Figure 5-6 shows the internal structure of the box.

Figure 5-6 Internal structure of the 120-ohm transmission interface box

1

2

3

4

(1) 12-core fusion parts (2) 120-ohm digital unit

(3) Grounding busbar (4) Case

The 12-core fusion parts of the 120-ohm transmission interface box and those of the 75-ohm

transmission interface box have the same structure, as shown in

Figure 5-5.

The internal parts of 120-ohm transmission interface box are installed before delivery.

5.2.2 Introduction to the Outdoor Power Interface Box

The outdoor power interface box (hereinafter referred to as the power interface box) functions

as the interface between the power distribution unit you have prepared and the Huawei BTS

equipment. Huawei provides the following two types of power interface boxes:

� 220 VAC power interface box (supporting 220 VAC power inputs)

� 110 VAC power interface box (supporting 110 VAC power inputs)

Page 94: BTS3012AE Base Station Cabinet Installation Manual

5 Installing Auxiliary Equipment

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

5-6 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Dimensions

The dimensions of the power interface box are as follows:

� Length: 420 mm

� Width: 378 mm

� Height: 125 mm

Weight

The weight of the power interface box is 9.8 kg before delivery.

Components of the 220 VAC Power Interface Box

The 220 VAC power interface box under full configuration consists of the following parts:

� A case

� A Miniature Circuit Breaker (MCB) of the mains supply

� Generator components (optional, including the generator MCB and the MCB

interlocking device)

� I/O cable terminal bars

Figure 5-7 shows the internal structure of the power interface box under full configuration.

The MCB interlocking device guarantees that only one of the MCBs stays in the closed status at any

point of time.

Figure 5-7 Internal structure of the 220 VAC power interface box

1 2 3

4

5

6

(1) MCB of mains supply (2) MCB interlocking device (3) MCB of generator

(4) Case (5) I/O cable terminal bars (6) Cable passage

Page 95: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 5 Installing Auxiliary Equipment

Issue 01 (2006-09-06) Huawei Technologies Proprietary 5-7

Components of the 110 VAC Power Interface Box

The 110 VAC power interface box and the 220 VAC power interface box are similar in

components, but different in MCB specifications.

5.2.3 Installing the Outdoor Interface Box on a Wall

To install the outdoor interface box on a wall, perform the following steps:

Step 1 Determine the position of the case according to the engineering requirement.

Step 2 Mark the positions for four expansion bolts on a wall with the marking template delivered

with the outdoor interface box.

Figure 5-8 shows the positions of the expansion bolts.

Figure 5-8 Positions of the expansion bolts

35

4

310

Step 3 Drill holes on the marked points.

Step 4 Put the expansion bolt into the holes, and hammer it until the expansion tube is completely

buried in the wall.

Step 5 Remove the nut, spring washer, and flat washer.

Step 6 Align the four installation holes on the outdoor interface box through the expansion bolts, and

then place the outdoor interface box at the installation position.

Step 7 Put flat washers, spring washers, and nuts to the expansion bolts. Adjust the outdoor interface

box, and then tighten the nuts and explode the expansion bolts, as shown in Figure 5-9.

Page 96: BTS3012AE Base Station Cabinet Installation Manual

5 Installing Auxiliary Equipment

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

5-8 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 5-9 Installing the outdoor interface box on a wall

4

5

6

1 2

3

(1) Outdoor interface box (2) Wall (3) Flat washer 8

(4) Spring washer 8 (5) M8 nut (6) M8x80 expansion bolt

5.2.4 Installing the Outdoor Interface Box on a Pole

The interface box can be installed on an upright steel pole. The external diameter of the steel

pole should be within 60 mm and 114 mm.

To install the outdoor interface box on a pole, perform the following steps:

Step 1 Use the bolt M8 x 25, spring washer 8, and flat washer 8 to fix the outdoor interface box to

the pole fixtures, as shown in Figure 5-10. Ensure that the holes on the pole fixtures match the

holes on the outdoor interface box.

Page 97: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 5 Installing Auxiliary Equipment

Issue 01 (2006-09-06) Huawei Technologies Proprietary 5-9

Figure 5-10 Fixing the pole fixture to the interface box

12

4

5

3

(1) Outdoor interface box (2) Pole fixture (3) Flat washer 8

(4) Spring washer 8 (5) Bolt M8x25

Step 2 Lift the interface box installed with two pole fixtures. Then, install another two pole fixtures.

Ensure that the pole is between the two fixture assemblies.

Step 3 Put bolts M10 through the two fixture assemblies. Add a flat washer, a spring washer, and a

nut to each bolt. Then, use a wrench to tighten the nuts, as shown in Figure 5-11.

Figure 5-11 Fixing the interface box to the pole

1

2

34

5

6

(1) Flat washer 10 (2) Bolt M10 (3) Flat washer 10

(4) Spring washer 10 (5) Nut M10 (6) Pole

Page 98: BTS3012AE Base Station Cabinet Installation Manual
Page 99: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-1

6 Installing Cables

Power off the BTS3012AE cabinet before installing the external cables.

About This Chapter

The following table lists the contents of this chapter.

Title Description

6.1 Introduction to the Cables

to be Installed On Site

Introduces the cables to be installed on site.

6.2 Installing the Power

Cables

Describes how to install the power cables.

6.3 Installing PGND Cables Describes how to install PGND cables.

6.4 Installing the E1 Cables Describes how to install E1 cables.

6.5 Installing Optical Fibers Describes how to install optical fibers.

6.6 Installing the RF Signal

Cables

Describes how to install RF signal cables.

6.7 Installing the Cable for the

Combiner on the DTRU

Describes how to install the cable for the combiner on the

DTRU.

6.8 Installing the 1/4-Inch RF

Jumper

Describes how to install the 1/4-inch RF jumper.

6.9 Installing the 1/2-Inch RF

Jumper

Describes how to install the 1/2-inch RF jumper.

6.10 Installing the Boolean

Value Input Signal Cable

Describes how to install the Boolean value input signal

cable.

Page 100: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Title Description

6.11 Installing the Built-In

Storage Battery and Its Cables

Describes how to install the built-in storage battery and its

cables.

6.12 Installing Cables for the

Combined Cabinet

Describes how to install cables for the combined cabinet.

6.13 Installing Cables for the

Cabinet Group

Describes how to install cables for the cabinet group.

6.14 Installing the RET

Control Signal Cable

Describes how to install the RET control signal cable.

Page 101: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-3

6.1 Introduction to the Cables to be Installed On Site

6.1.1 Introduction to Cabling Holes

A cabling hole is where the external cable is led into or out of the cabinet. The BTS3012AE

cabling holes are at the bottom of the cabinet, as shown in Figure 6-1.

Figure 6-1 BTS3012AE cabling holes

2

34

5

BTS3012AE cabinet floor

1

(1) GPS cabling hole (2) Waterproof module subrack

(3) Grounding bar (4) Cabling hole for the E1 trunk cable, environment monitoring

cable, and the cable between combined cabinets

(5) Cabling hole for the RF jumper

Figure 6-2 shows the silkscreens of the cabling holes.

Page 102: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-4 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 6-2 Silkscreens of the cabling holes

BA

T P

GN

D

PG

ND

D1

L2 L3

N

AC

L o

ut

AC

L o

ut

COMPRESS

1

PG

ND

02

S/HDSL-01E1-3

E1-1/OUTE1-2/OUT

COMPRESS

2

Microwave 01

SW INRRU-48V

RRUGND

BATDOOR

BATTEM

Signal01

Signal02

Microwave 02S/HDSL-02

E1-4

Microwave 03

Microwave 04

ANT5

ANT4

ANT3

ANT2

ANT1

ANT0

ANT8

ANT7

ANT6

ANT11

ANT10

ANT9

3

(1) Silkscreen of the waterproof module subrack

(2) Silkscreen of the cabling hole for E1 trunk cable, environment monitoring cable,

or combined cabinet cable E1

(3) Silkscreen of the cabling hole for the RF jumper

6.1.2 Cable Layout at the Cabinet Front

Figure 6-3 shows the cable layout at the BTS3012AE cabinet front.

Page 103: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-5

Figure 6-3 Cable layout at the cabinet front

P1

Signal cable Power cable RF cable

DCCUDATUDCSUDTMUDTMU

FAN

DCOM

DTRU DTRU DTRU DTRU

DDPU DDPUDCOMDDPU

DTRUDTRU

R1

R8

R3R4

R5R6

R9 R10 R11 R12

R13 R15 R16 R17 R18R14

R7

S1

R20

R2

R21

R22

R23

R24

R25

R26

R27

R28 R30

R29

D

T

R

B

PSUPSU PSU PSU

AC PDU

Cable inletEMI

P2 P3

P4 P5 P6

P1

P2P3P4

P7

P7.2

P8

P9

P9

P8

S1

S2

S2

S3

S3

S4

S5

S5

S6

S6.3 S7.3S7.2

S7

S10

S8

S9

S11.1

S11.2

S11.3

S11

S12

S12

P16

P13

P15

P11

S13

P5

P6

P10

S21

S22

S21

S6.1

P7.1

S6.2

R19

R7

R13

R1

R2

R3

R4

R5

R6

R8

R11

R15 R17

R14

R9

R10

R16

R12

R18

S7.1

P7.3

DCOM

In Figure 6-3, S4 and S15 connect to the NodeB Power Monitor unit Interface Board (NPMI)

on the top of the cabinet. Figure 6-4 shows the cable layout.

Page 104: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-6 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 6-4 NPMI cable layout on the top of the cabinet

JAC2 JK2

JAC1 JK1

JTD1 JTD2

JTD4 JTD5

JKM1 SMOKE DOORWATER

JTD6 JTD7

JTD3 TEM_HUM

BAT_TEM2BAT_TEM1

FU_ALM

S13S4

S14S15S16

S17 S18 S19 S20

J1

COM 1

COM 2

COM 3

COM 4

BAT_TEM3

S11

Table 6-1 lists the cables laid out at the cabinet front.

Table 6-1 Cables laid out at the cabinet front

Cable No. Cable Name Quantity

R1−R6 RF Tx signal cable 6

R7−R18 RF Rx signal cable 12

R19−R30 Cable for combiner on the DTRU 12

S1 Combined-cabinet signal cable between the DCSU

and the DSCB

1

S2 TOP1 signal cable from DCCU to DSCB 1

S3 E1 signal transfer cable 1

S4 Monitoring transfer cable from NPMI to DSCB 1

S5 TOP2 signal cable from DCSU to DSCB 1

S6 Signal cable between the DSCB and slots 0 through

2 in the DAFU subrack

1

S7 Signal cable between the DSCB and slots 3 through

5 in the DAFU subrack

1

S8 Cable for combined cabinet 1

S9 Signal cable 1 between cabinet groups 1

Page 105: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-7

Cable No. Cable Name Quantity

S10 Signal cable 2 between cabinet groups 1

S11 RS485 environment monitoring signal cable 1

S12 Signal cable between the DCSU and the DTRB 1

S13 PMU monitoring cable 1

S14 Alarm cable for the air breaker 1

S15 Cable for the temperature sensor of the built-in

storage battery 1(delivered

with the

cabinet)

S16 Alarm cable for the AC lightning arrester 1

S17 Cable for the temperature and humidity sensor 1

S18 Cable for the access control sensor 1

S19 Cable for the water sensor 1(delivered

with the

cabinet)

S20 Cable for the smoke sensor 1

S21 75-ohm/120-ohm E1 cable 2

S22 Boolean value input cable 1

P1–P6 Power cable between the DC power distribution box

and DTRU 0–DTRU 6

6

P7 Power cable between the DC power distribution box

and the DAFU subrack 2

P8 Power cable between the DC power distribution box

and the DCCU

1

P9 Power cable between the DC power distribution box

and the FAN subrack

1

P10 Power cable between the DC power distribution box

and the heat exchanger

1

P11–P14 PGND cable 4

P15–P18 PGND cable 4

6.1.3 Wiring on the Back of the Cabinet

Figure 6-5 shows the wiring on the back of the cabinet.

Page 106: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-8 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 6-5 Wring on the back of the BTS3012AE cabinet

L4L4L5L5L6L6L7

5432 1

RTN Load1 Load2 BAT

L7L8L8

10

-48

V L

oa

d1

-48

V L

oa

d2

9

8

13

14 15

S14

RTN -48V

1234,5

6

7

891011

12.112.2

1 2 3

4 65

7

8 910,14

P12

P17

P18

S12

airconditioner

or heatexchanger

S17

S19

S20

S18.1

S15

S14

S18.2

S11P10 12

P147

13

RT

N

Power cable Signal cable

Page 107: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-1

Table 6-2 lists the cables on the back of the cabinet.

Table 6-2 Cables on the back of the BTS3012AE cabinet

Cable No. Cable Name Quantity

S11 RS485 environment monitoring signal cable 1

S12 Signal cable between the DCSU and the DTRB 1

S13 PMU monitoring cable 1

S14 Alarm cable for the air breaker 1

S15 Cable for the temperature sensor of the built-in storage

battery 1(delivered

with the

cabinet)

S17 Cable for the temperature and humidity sensor 1

S18 Cable for the access control sensor 1

S19 Cable for the water sensor 1(delivered

with the

cabinet)

S20 Cable for the smoke sensor 1

P10 Power cable between the DC power distribution box and

the heat exchanger

1

P11–P14 PGND cable 4

P15–P18 PGND cable 4

1–3 Live wire between the filter and the terminal on the back

of the AC power distribution box

3

4, 5 Neutral wire between the filter and the terminal on the

back of the AC power distribution box 2

6–8 Live wire between the terminal on the back of the AC

power distribution box and the PSU

3

9–11 Neutral wire between the terminal on the back of the AC

power distribution box and the PSU

3

12 AC power cable between the AC power distribution box

and the heat exchanger

1

13 PSU BAT output power cable to air breaker 1

14 Battery compartment positive pole 1

15 Air breaker to battery compartment negative pole 1

Page 108: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)

6.2 Installing the Power Cables

Never connect the N wire of the AC power cable to the PGND cable of the exchange

equipment or communication equipment.

6.2.1 Introduction to the Power Cables

The BTS3012AE supports three power input modes:

� 220 VAC 3-phase 4-core input

� 220 VAC single-phase 2-core input

� 110 VAC dual-live input

Table 6-3 lists the specifications of the AC power cables for the BTS3012AE in different

input modes.

Table 6-3 Specifications of the AC power cables for the BTS3012AE

Power Input Mode Core Wire Core

Quantity

Sectional Area Color

L 3 10 mm2 Red 220 VAC 3-phase

4-core input N 1 10 mm

2 Black

L 1 16 mm2 Red 220 VAC

single-phase 2-core

input N 1 16 mm2 Black

L 2 16 mm2 Red 110 VAC dual-live

input N 1 16 mm

2 Black

� The AC power cables for the BTS3012AE are purchased at the local place. The colors of the cables

must comply with the local rules and regulations. If the local rules and regulations have no special

requirements for cable colors, use the cables delivered together with the BTS.

� The default color of the delivered L wire is red and that of the N wire is black.

� The OT terminals of AC power cables are made on site.

For details, see Table 1-5 "Types and installation positions of the cables."

Table 6-4 lists the rated voltage, rated frequency, and power distribution mode in different

modes.

Page 109: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-1

Table 6-4 AC power distribution mode

Rated Voltage (VAC) Rated Frequency

(Hz)

Power Input Mode

200–250 ! 20% 45–65 220 VAC single-phase 2-core

input

346/200–433/250 ! 20% 45–65 220 VAC 3-phase 4-core input

208/120–220/127 ! 20% 45–65 110 VAC dual-live input

Note: For example, if the rated voltage is 346/200 VAC, the circuit voltage is 346 VAC and the phase voltage

is 200 VAC.

6.2.2 Installation Principles

Adhere to the following principles when installing the power cables:

� The power cables must be cut according to the measured distance between the wiring

terminals and the power interface box. Redundant length must be reserved.

� Replace the power cable of insufficient length with a new one. Do not make connectors

or solder joints.

� The power cables must be separated from other ones.

� If the power cables are laid parallel to other ones, the space between them must be at

least 30 mm.

� The power cables tied on the metal cabling rack must be insulated.

� Switches or fuses must not be added to the power cable.

� The E1 cables must be laid neatly and tied using cable ties. The space between the cable

ties must be 200 mm.

� The cable ties must be in one line and in the same direction. The ends of the cable ties

must be evenly cut.

After the power cables are led into the cabinet through the waterproof module, the slide plate in the

storage battery cabin is difficult to move out; therefore, the cable should be prepared with redundant

length.

6.2.3 Leading the 3-Phase 220 VAC Power into the BTS3012AE Cabinet

Perform the following steps:

Step 1 Remove the cover of the filtering box.

Take care not to damage the power cables connected to the socket on the cover.

Step 2 Determine the hole (in the waterproof module) through which the power cable is routed into

the cabinet.

Page 110: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Step 3 Cut the cable according to the measured distance between the power interface box and the

wiring terminals N, L1, L2, and L3.

Step 4 Attach temporary labels to both ends of the cable.

The contents of the temporary labels can be the same as the formal ones or decided on site.

Step 5 Lay the cables. For details, see section 6.2.2 "Installation Principles."

Step 6 Make an OT terminal at one end of the external power cable.

Step 7 Lead the L1, L2, L3, and N wires with OT terminals into the cabinet through the waterproof

module. Secure the OT terminals to the wiring posts, as shown in Figure 6-6.

Figure 6-6 Installing L1, L2, L3, and N

L1L2L3N

12

34

(1) External power cable L1 (2) External power cable L2

(3) External power cable L3 (4) External power cable N

Step 8 Connect the other end of the external power cable to the power interface box.

Step 9 Remove the temporary labels and attach the formal ones.

The labels must be attached 20–50 mm away from each end.

----End

Page 111: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-3

6.2.4 Leading the Single-Phase 220 VAC Power into the BTS3012AE Cabinet

Ensure that the L wire and N wire are connected correctly in single-phase mode. If not, the

lightning arrester can be burnt, which causes serious faults.

In single-phase mode, two methods are used to lead the L wire into the BTS3012AE cabinet:

� The single-phase power provided by the customer is divided into three channels in the

power interface box before led into the BTS3012AE.

For how to connect the cables, see section 6.2.3 "Leading the 3-Phase 220 VAC Power

into the BTS3012AE Cabinet."

� Install a short-circuiting copper busbar on the AC lighting arrester. Lead the single-phase

power provided by the customer directly into the BTS3012AE.

For how to connect the cables, see section 6.2.3 "Leading the 3-Phase 220 VAC Power

into the BTS3012AE Cabinet."

Figure 6-7 shows the installation of the short-circuiting copper bar.

Figure 6-7 Installing the short-circuiting copper bar

L3

1

3

N

L1

L2

2

(1) M8 screw (2) Short-circuiting copper bar (3) AC power lightning arrester

Page 112: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-4 Huawei Technologies Proprietary Issue 01 (2006-09-06)

6.2.5 Leading the 110 VAC Dual-Live Power into the BTS3012AE Cabinet

The BTS3012AE uses different lightning arresters and wiring terminals in different power input modes:

� 110 VAC dual-live input

� 220 VAC input

To lead the 110 VAC dual-live power into the BTS3012AE cabinet, do as follows:

The external power network is single-phase or three-phase star mode.

Step 1 Remove the cover of the filtering box.

Take care not to damage the power cables connected to the socket on the cover.

Step 2 Determine the hole (in the waterproof module) through which the power cable is routed into

the cabinet.

Step 3 Cut the cable according to the measured distance between the power interface box and the

wiring terminals N, L1, and L2.

Step 4 Attach temporary labels to both ends of the cable.

The contents of the temporary labels can be the same as the formal ones or decided on site.

Step 5 Lay the cables. For details, see section 6.2.2 "Installation Principles."

Step 6 Make an OT terminal at one end of the external power cable.

Step 7 Lead wires L1, L2, and N with OT terminals into the cabinet through the waterproof module.

Secure the OT terminals to the wiring posts, as shown in Figure 6-8.

Page 113: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-5

Figure 6-8 Installing L1, L2, and N

L1L2N

1

23

(1) Wire L1 (2) Wire L2

(3) Wire N

Step 8 Connect the other end of the external power cable to the power interface box.

Step 9 Remove the temporary labels and attach the formal ones.

The labels must be attached 20–50 mm away from each end.

----End

6.2.6 Connecting the Power Cables to the Power Interface Box

You can use multiple power supply modes for the BTS3012AE.

Table 6-5 lists the figures showing the connection between power cables and the power

interface box in different power supply modes.

Table 6-5 Figure for reference in different power supply modes

Power Supply Mode See Figure…

Single-phase mains input Figure 6-9 Power cable layout of the single-phase mains

input

Page 114: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-6 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Power Supply Mode See Figure…

Single-mode mains ands

single-phase generator

Figure 6-10 Connection of power cables in single-phase

mains and single-phase generator input mode

Three-phase mains input Figure 6-11 Connection of power cables in three-phase

mains input mode

Three-phase mains and

three-phase generator

Figure 6-12 Connection of power cables in three-phase

mains and three-phase generator input mode

In single-phase mains or single-phase generator input mode, install a 3-terminal short-circuiting bar on

the terminal block and secure it using the delivered fastening screws.

Single-Phase Mains Input

Figure 6-9 Power cable layout of the single-phase mains input

4 5

3

2

1

A1 A2

A A

B1 B2

B B

C1 C2 N1 N2

C C N N

N1C1 B1 A1

N1C1 B1 A1

N1 L1 A B C N

(1) Air breaker for the input mains (2) 3-terminal short-circuiting bar and fastening screws

(3) Terminal block (4) Mains input (5) Mains output

Page 115: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-7

Single-Phase Mains and Single-Phase Generator Input

Figure 6-10 Connection of power cables in single-phase mains and single-phase generator input

modes

67

8

5

4

4

31 2

A1 A2

A A

B1B2

B B

C1 C2 N1 N2

C C N N

A2 B2 C2 N2

A2 B2 C2 N2

N1C1 B1 A1

N1C1 B1 A1

N1 L1 A B C N L2 N2

(1) Air breaker for the input mains (2) Locking device of the air breaker

(3) Air breaker for the generator input (4) 3-terminal short-circuiting bar and fastening screws

(5) Generator input (6) Mains output (7) Mains input (8) Terminal block

Page 116: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-8 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Three-Phase Mains Input

Figure 6-11 Connection of power cables in three-phase mains input mode

3 4

2

1

N1 C1 B1 A1

N1 C1 B1 A1

A1 A2

A A

B1 B2

B B

C1 C2 N1 N2

C C N N

N1 A1 A B C NB1C1

(1) Air breaker for the input mains (2) Terminal block

(3) Mains input (4) Mains output

Page 117: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-9

Three-Phase Mains Input and Three-Phase Generator Input

Figure 6-12 Connection of power cables in three-phase mains and three-phase generator input

mode

56

7

3

4

1 2

N1 C1 B1 A1

N1 C1 B1 A1

A1 A2

A A

B1 B2

B B

C1 C2 N1 N2

C C N N

A2 B2 C2 N2

A2 B2 C2 N2

N1 A B C N N2A1B1C1 C2B2A2

(1) Air breaker for the input mains (2) Locking device of the air breaker

(3) Air breaker for the generator input (4) Generator input

(5) Mains output (6) Mains input (7) Terminal block

6.3 Installing PGND Cables

6.3.1 Introduction to PGND Cables

The yellow and green PGND cables of the BTS3012AE have a cross-sectional area of 25 mm2.

Choose plastic insulation copper core cables with a cross-sectional area of at least 25 mm2

if

you prepare PGND cables yourself.

The yellow and green PGND cables of the transmission interface box and power interface box

have a cross-sectional area of 25 mm2. Choose yellow and green plastic insulation copper core

cables with a cross-sectional area of at least 25 mm2 if you prepare PGND cables yourself.

6.3.2 Installation Principles

Adhere to the following principles when installing PGND cables:

Page 118: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-10 Huawei Technologies Proprietary Issue 01 (2006-09-06)

� Measure the accurate distance between the two grounding ends and reserve cables with

enough length. When laying out PGND cables, replace the cables if the reserved cables

are not long enough. Solder joint or connection is not allowed.

� The PGND cables must be separated from other ones.

� If the PGND cables are laid parallel to other ones, the space between the PGND cables

and the other cables must be at least 30 mm.

� If PGND cables need to be bound with the metal cabling rack before being laid out,

insulation measures shall be taken.

� Switches or fuses must not be added to the PGND cable.

� The connection points at both ends of the PGND cables shall be in good electrical

contact and anticorrosion measures shall be taken.

� The E1 cables must be laid neatly and tied using cable ties. The space between cable ties

must be 200 mm.

� The cable ties must be in one line and in the same direction. The ends of the cable ties

must be evenly cut.

The PGND cables after being routed into the cabinet through the waterproof module may

prevent the removal of the slide plate from the storage battery cabin. To ensure that the slide

plate can be moved in and out freely, keep property redundant length of the cables that have

been routed into the cabinet through the waterproof module.

6.3.3 Installation Procedure

To install a PGND cable, do as follows:

Step 1 Determine the hole (in the waterproof module) through which the PGND cable is routed into

the cabinet.

Step 2 Measure the distance between the internal grounding bar of the BTS3012AE and the wiring

terminal of grounding bar outside the cabinet according to the actual cabling route of the

PGND cable. Obtain a cable with proper length.

Step 3 Attach temporary labels to both ends of the cable. The contents of the temporary labels can be

consistent with the formal ones or be determined based on your requirements.

Step 4 Lay out PGND cable according to the specification requirements for cabling and the cabling

mode required by the project. For the basic cabling principles of PGND cables, see "6.3.2

Installation Principles".

Step 5 Make OT terminals for the PGND cable.

Step 6 Route the PGND cable into the cabinet through the waterproof module. Connect one end of

the PGND cable to the grounding busbar in the cabinet, and secure the OT terminal using a

spring washer and a screw.

Step 7 Connect the other end of the PGND cable to the grounding copper busbar outside the cabinet.

Step 8 Attach formal labels 20m–50 mm away from both ends and remove the temporary labels.

----End

Page 119: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-11

6.3.4 Connecting the PGND Cable to the Transmission Interface Box

Perform the following steps:

Step 1 Measure the distance between the grounding bar of the transmission interface box and the

wiring terminal of grounding copper bar outside the cabinet according to the actual cabling

route of the PGND cable. Obtain a cable with proper length.

Step 2 Attach temporary labels to both ends of the cable. The contents of the temporary labels can be

consistent with the formal ones or be determined based on your needs.

Step 3 Lay out PGND cables according to the specification requirements for cabling and the cabling

mode required by the project. For the basic cabling principles of PGND cables, see "6.3.2

Installation Principles."

Step 4 Strip the outer insulation layer on one end of the PGND cable.

Step 5 Loosen the adjustment screws on any vacant cable clamping interface of the grounding bar in

the transmission interface box. Insert the cable wire that is stripped of insulation layer into the

cable clamping interface of the grounding busbar, and then fasten the adjustment screws.

Step 6 Make an OT terminal at the other end of the PGND cable.

Step 7 Fix the end with an OT terminal on the grounding copper bar outside the cabinet.

Step 8 Remove the temporary labels at both ends of the cable and attach formal ones.

----End

6.3.5 Connecting the PGND Cable to the Power Interface Box

To connect the PGND cable to the power interface box, do as follows:

Step 1 Measure the distance between the grounding bar of the power interface box and the wiring

terminal of grounding copper bar outside the cabinet according to the actual cabling route of

the PGND cable. Obtain a cable with proper length.

Step 2 Attach temporary labels to both ends of the cable. The contents of the temporary labels can be

consistent with the formal ones or be determined based on your needs.

Step 3 Lay out PGND cables according to the specification requirements for cabling and the cabling

mode required by the project. For the basic cabling principles of PGND cables, see "6.3.2

Installation Principles."

Step 4 Make OT terminals at both ends of the PGND cable.

Step 5 Loosen the water-tight nut near the grounding terminal in the interface box and lead the

PGND cable through the nut. Fasten one end of the PGND cable to the grounding terminal of

the interface box and the other end to the grounding copper bar outside the cabinet. Figure

6-13 shows the position of the grounding terminal in the power interface box.

Page 120: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-12 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 6-13 Installing the PGND cable for the power interface box

1

2

(1) Grounding terminals of the power interface box (2) PGND cable

Step 6 Remove the temporary labels at both ends of the cable and attach formal ones.

----End

6.4 Installing the E1 Cables

6.4.1 Introduction to the E1 Cables

The BTS3012AE has two types of E1 cables: the 75-ohm coaxial cable and the 120-ohm

twisted pair. The DB25 connectors and labels of both types of cables are the same.

Figure 6-14 shows the structure of the 75-ohm coaxial cable.

Page 121: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-13

Figure 6-14 75-ohm E1 coaxial cable

A

X0

1

A

Pos.25

Pos.1

W

W1

W2

W3

W4

W5

W6

W7

W8X8

X7

X6

X5

X4

X3

X2

X1

B

B

2

3

5

6

4

7

(1) DB25 male connector (X0) (2) Major label (3) Auxiliary label 1

(4) Coaxial cable wire (tip) (5) Coaxial cable external conductor (ring, that is,

shielding layer)

(6) 75-ohm E1 coaxial cable (X1–X8) (7) Auxiliary label 8

Table 6-6 lists the pins of the coaxial cable.

Table 6-6 Pins of the coaxial cable

Coaxial Wire

Coaxial Cable Wire/Outer Conductor

Pin of the DB25 Male Connector

Coaxial Cable Label

X1.tip X0.24 W1

X1.ring X0.25

CHAN 0 Tx

X2.tip X0.13 W2

X2.ring X0.12

CHAN 0 Rx

X3.tip X0.11 W3

X3.ring X0.10

CHAN 1 Tx

X4.tip X0.9 W4

X4.ring X0.8

CHAN 1 Rx

X5.tip X0.7 W5

X5.ring X0.6

CHAN 2 Tx

W6 X6.tip X0.5 CHAN 2 Rx

Page 122: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-14 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Coaxial Wire

Coaxial Cable Wire/Outer Conductor

Pin of the DB25 Male Connector

Coaxial Cable Label

X6.ring X0.4

X7.tip X0.3 W7

X7.ring X0.2

CHAN 3 Tx

X8.tip X0.14 W8

X8.ring X0.15

CHAN 3 Rx

6.4.2 Installation Principles

Adhere to the following principles when installing the E1 cables:

� The E1 cables must not be routed on the outdoor cabling rack.

� The E1 cables must go through a metal tube whose ends are grounded. Or the E1 cables

with metal sheath are used with both ends grounded.

� The E1 cables must be separated from the other cables. If the E1 cables are laid parallel

to the power cable, PGND cable, or RF signal cable, the space between the E1 cables

and the other cables must be greater than 30 mm.

� The bending radius of the coaxial cable must not be less than 40 mm and the wire must

not be damaged.

� The E1 cables must be laid neatly and tied using cable ties.

� The E1 cables must not be stretched at the bend.

� The cable ties must be in one line and in the same direction. The ends of the cable ties

must be evenly cut.

6.4.3 Installation Procedure

To install the E1 cables, do as follows:

Step 1 Determine the hole (in the waterproof module) through which the E1 cable is routed into the

cabinet.

Step 2 Cut the E1 cable to a proper length according to the cabling route.

Step 3 Lay the E1 cables outside the cabinet. For details, see section 6.4.2 "Installation Principles."

Step 4 Lead the E1 cable into the waterproof module and route the cable along the column to near

the DB25 socket of the DELU.

Step 5 Connect the DB25 connector to the DELU according to the label on the E1 cable.

Step 6 Connect the other end to the transmission interface box.

Step 7 Attach labels 20–50 mm away from both ends of the E1 cable.

----End

Page 123: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-15

6.4.4 Connecting the 75-ohm E1 Cable to the Transmission Interface Box

To connect the 75-ohm E1 cable to the transmission interface box, perform the following

steps:

Step 1 Install an SMB connector to one end of the E1 cable.

Step 2 Lead the 75-ohm E1 through the cable access socket into the transmission interface box.

Install the cable on the 75-ohm digital unit, as shown in Figure 6-15.

Figure 6-15 Connecting the 75-ohm E1 cable

1

2

3

(1) Bundling socket (2) Cable access socket (3) 75-ohm E1 cable

Figure 6-15 takes the connection of one trunk cable as an example.

Step 3 According to Steps 1 and 2, install the customer-prepared E1 cable to the other side of the

75-ohm digital unit and tie the cable to the bundling socket using cable ties.

Step 4 Fill in the gaps of the cable access socket using waterproof mud.

----End

6.4.5 Connecting the 120-ohm E1 Cable to the Transmission Interface Box

Perform the following steps:

Step 1 Remove the indicator card from the 120-ohm digital unit.

Step 2 Peel a proper length of the 120-ohm E1 cable.

Page 124: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-16 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Step 3 Lead the 120-ohm E1 cable through the cable access socket into the transmission interface

box.

Step 4 Select the wires for the 120-ohm E1 cable according to the cable connection list delivered

together with the cables. Select the cores for the 120-ohm E1 cable.

Two signal transfer cables and one grounding cable form a group. One group provides one uplink or

downlink E1 channel.

Step 5 Lead the wires through the entrance of the cable trough on one side of the 120-ohm digital

unit into the cable clamping interface, one group for one cable trough, as shown in Figure

6-16.

Figure 6-16 Connecting the 120-ohm E1 cable

1

2

3

(1) Entrance of the cable trough (2) Cable clamping interface (3) 120-ohm E1 wire

Step 6 Use a wire punch-down tool to clamp the wires onto the latches in the cable clamping

interfaces.

Clamp the signal transfer cable onto cable clamping interfaces a and b, and the grounding

cable to cable clamping interface s, as shown in Figure 6-17.

Page 125: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-17

A group of cables is clamped onto three cable clamping interfaces: a, b, and s. Each cable clamping

interface has two rows of latches and each row has two latches. You can choose either two latches in

either row.

Figure 6-17 Clamping the 120-ohm E1 cable to the 120-ohm digital unit

2

1

54

3

(1) Latch (2) Entrance of the cable trough (3) Cable clamping interface s

(4) cable clamping interface b (5) cable clamping interface a

Step 7 Route the customer-prepared E1 cable from the other side of the 120-ohm digital unit.

Each wire connects to the wire from the BTS3012AE, as shown in Figure 6-18.

Page 126: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-18 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 6-18 Connecting the E1 wire of the client

1

2

(1) E1 wire of the BTS3012AE (2) E1 wire of the client

Step 8 Attach the indicator plate after clamping the wires.

Step 9 Fill in the gap of the cable access socket using waterproof mud.

----End

6.5 Installing Optical Fibers

6.5.1 Introduction to the Optical Fibers

The BTS3012AE uses both multimode fibers and single-mode fibers.

The optical fibers in the BTS3012AE are LC connectors, as shown in Figure 6-19.

Figure 6-19 LC connector

The color of the PVC sheath of a multimode fiber is orange and that of the PVC sheath of a

single-mode fiber is yellow.

Page 127: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-19

6.5.2 Installation Principles

Adhere to the following principles when installing the fibers:

� The E1 cables must be laid neatly and tied with cable ties.

� The fibers must not be stretched at the bend. The bending radius must be greater than or

equal to 20 times the diameter.

� Do not pull or trample on the fibers, and prevent them from touching the sharp objects.

� Check whether there are creases and impresses on the fibers, and damages to the

connectors. If yes, replace with fibers in good condition

� The rest fibers must be coiled on the fiber coiler.

� The fibers outside the cabinet must be protected with PVC corrugated tubes.

� The connectors, if not used, must be covered with dustproof caps.

� Do not stare at the end face of the connectors if one end of the fiber is connected to the

optical transmission device in case that your eyes are hurt.

� The cable ties must be in one line and one direction. The ends of the cable ties must be

evenly cut.

6.5.3 Installation Procedure

To install the fibers, do as follows:

Step 1 Determine the hole (in the waterproof module) through which the fiber is routed into the

cabinet.

Step 2 Select fibers with proper length according to actual requirements on site.

The contents of the temporary labels can be the same as the formal ones or decided on site.

Step 3 Attach temporary labels to distinguish the fibers.

Step 4 Coat the fibers using PVC corrugated tubes.

� Place the fibers on a slope and then coat the fibers with PVC corrugated tubes.

� Do not cut corrugated tubes because exposed fibers may be damaged.

� Cover the cut with insulation tapes to protect the fibers from being damaged by sharp objects.

Step 5 Lay the fibers outside the cabinet. For details, see section 6.5.2 "Installation Principles."

Step 6 Lead the fibers from the waterproof module into the cabinet, and route the fibers near to the

optical transmission equipment in the cabinet.

Step 7 Align the LC connector with the optical transmission device on the cabinet top and insert the

connector until you hear a click sound.

Step 8 Use insulation tapes to seal the ports at both sides of the PVC corrugated tube.

Step 9 Attach the corresponding labels to both sides of the fibers, ensuring that the attaching points

are 20–50 mm away from the port.

----End

Page 128: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-20 Huawei Technologies Proprietary Issue 01 (2006-09-06)

6.5.4 Connecting the Fibers to the Transmission Interface Box

Figure 6-20 shows the connections between fibers and the transmission interface box.

Figure 6-20 Connection between a fiber and a 12-core fiber splice tray

(1) Waterproof locking nut (2) Fiber stripping unit (3) Bare fiber (4) Reinforced core

(5) 12-core fiber splice tray (6) Fiber adapter (7) Tail fiber (8) Fiber fusion parts

(9) Fiber access socket (10) Grounding cable of the reinforced core

To connect fibers to the transmission interface box, do as follows:

Step 1 Lead the tail fiber from the BTS3012AE to the transmission interface box through the fiber

access socket, interweave the fiber on the fiber fusion part, and then connect the connector of

the fiber to the fiber adapter.

Step 2 Route the customer-prepared fiber to the transmission interface box through the waterproof

locking nut, secure the fiber and peel it at the fiber stripping unit.

Step 3 Take out the reinforced core from the fiber, fix the core to the grounding point of the fiber

stripping unit, and use a grounding cable with a sectional area of 6 mm2 to connect the

grounding point of the fiber stripping unit to the grounding busbar.

Step 4 Route the bare wire from the fiber stripping unit to the 12-core fiber splice tray, interweave

the wire, and splice the wire with the tail fiber.

Step 5 Lead the tail fiber out of the 12-core fiber splice tray, and interconnect the tail fiber to the

fiber from the BTS3012AE at the fiber adapter.

Step 6 Record the connecting steps of each fiber in the 12-route Fiber Indicator Table:

Page 129: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-21

� Record the cable lead-in connections in the top left corner of the table.

� Record the cable lead-out connections in the top right corner of the table.

Figure 6-21 shows the 12-route Fiber Indicator Table.

Figure 6-21 12-route Fiber Indicator Table

Fiber Indicator Cable

1 2 3 4

I

II

III

----End

6.6 Installing the RF Signal Cables

This section describes only the installation of the RF signal cables inside the cabinet. For the procedure

for connecting the RF cables to the antenna, see the HUAWEI BTS3012AE Base Station Antenna System

Installation Manual.

6.6.1 Introduction to the RF Signal Cables

The BTS3012AE has two types of RF signal cables:

� RF RX signal cable is used to connect port RX on the DTRU with that on the DDPU

and to transmit uplink signals.

� RF TX signal cable is used to connect port TX on the DTRU with that on the DDPU

and to transmit downlink signals.

Figure 6-22 shows the structure of the RF RX signal cable and that of the RF TX signal cable.

Page 130: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-22 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 6-22 Structure of the RF RX signal cable and that of the TX signal cable

RF Tx Cable

RF Rx Cable

1

2

1

2

(1) SMA elbow male connector (2) N elbow male connector

6.6.2 Installation Principles

Adhere to the following principles when connecting the RF signal cables:

� Install from the top to the bottom and from left to right.

� Attach labels or name plates after the installation. For details, see Appendix B

"Engineering Labels for Antenna System" of the HUAWEI BTS3012AE Base Station

Antenna System Installation Manual.

6.6.3 Installation Procedure

To install an RF signal cable, do as follows:

Step 1 Connect the SMA elbow male connector at one end of the cable to the RX port in the DDPU

and secure the connector.

Step 2 Connect the SMA elbow male connector at the other end to the RX port in the DTRU and

secure the connector.

Step 3 Connect the N elbow male connector at one end of the cable to the TX port in the DDPU and

secure the connector.

Step 4 Connect the SMA elbow male connector at the end of the cable to the TX port in the DTRU

and secure the connector.

----End

6.7 Installing the Cable for the Combiner on the DTRU

6.7.1 Introduction to the Cable for the Combiner on the DTRU

The cable for combiner on the DTRU connects the TX and IN ports. It outputs the transmit

signals after combination.

One end of the cable is an N male connector, and the other end is an SMA male connector.

The cable is made before delivery.

Page 131: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-23

Figure 6-23 shows the structure of the cable.

Figure 6-23 Cable for the combiner on the DTRU

1 2

W

3

(1) N male connector (2) SMA male connector (3) Label

6.7.2 Connecting the Cable for Combiner on the DTRU

The cable for the combiner on the DTRU connects port TX to port IN.

Perform the following steps:

Step 1 Determine which ports to connect according to the configuration of the BTS.

Step 2 Connect the N male connector to port TX1 or TX2 on the DTRU.

Step 3 Connect the SMA male connector to port IN1 or IN2.

Step 4 Secure the two connectors.

----End

The two connectors must be secured at the same time so that the cable is not twisted.

6.8 Installing the 1/4-Inch RF Jumper

6.8.1 Introduction to the RF Jumper

The 1/4-inch jumper is connected between the RF port on a DDPU and the RF cable

inlet/outlet at the cabinet top. One end of the jumper is a DIN male connector and the other

end is a DIN female connector. Figure 6-24 shows the structure of the jumper.

Page 132: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-24 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 6-24 Structure of the RF jumper

1 2

(1) DIN male connector (2) DIN female connector

6.8.2 Installation Principles

Adhere to the following principles when connecting the RF jumpers:

� The jumper must be vertically routed for at least 20 cm before it is bent near to connector

at the cabinet top. If you do not do like this, the jumper connector is subject to damage

� Labels or name plates must be attached after installation.

6.8.3 Installation Procedure

To install an RF jumper, do as follows:

Step 1 Remove the cover plate from the RF cable inlet/outlet port at the right part of the cabinet

bottom, as shown in Figure 6-25.

Figure 6-25 Removing the cover plate of the RF cable

1

(1) Cover plate of RF cables

Step 2 Find the jumper end that is connected to the antenna system through the RF cable inlet/outlet.

Insert the end into the cabinet through the exposed round hole to keep about 15 cm of the

jumper in the cabinet. Interconnect the two DIN connectors.

Step 3 Waterproof the joint of the two DIN connectors, keeping the insulation tapes from covering

the bolt holes on the connectors.

Step 4 Fix the cover plate on the RF cable inlet/outlet.

Step 5 Repeat Step 2 to Step 4 to secure the connectors of the other jumpers.

----End

Page 133: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-25

6.9 Installing the 1/2-Inch RF Jumper

6.9.1 Introduction to the RF Jumper

The 1/2-inch jumper is connected between the 1/4-inch RF jumper and feeder of the antenna

system. Both ends of the jumper are DIN male connectors.

Figure 6-26 shows the structure of the jumper.

Figure 6-26 Structure of the RF jumper

1 2

(1) DIN male connector (2) DIN male connector

6.9.2 Installation Procedure

To install an RF jumper, do as follows:

Step 1 Connect one end of the 1/2-inch RF jumper to the cabling hole for RF jumpers on the cabinet

bottom.

Step 2 Connect the other end to the feeder of the antenna system.

Step 3 Repeat step 1 to step 2 to secure the connectors of the other jumpers.

----End

6.10 Installing the Boolean Value Input Signal Cable

6.10.1 Introduction to the Boolean Value Input Signal Cable

The Boolean value input signal cable in the BTS3012AE can output six Boolean value signal

inputs. One end of the cable is a DB44 male connector, and the other end is a bare wire.

Figure 6-27 shows the structure of the cable.

Page 134: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-26 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 6-27 Boolean value input signal cable

X0

A

W1

Pos.1

Pos.25

View A

W

W8

W7

W6

W5

W4

W3

W2

6.10.2 Installation Positions

Table 6-7 lists the installation positions of the Boolean value input signal cable.

Table 6-7 Installation positions of the Boolean value input signal cable

Cable Connector Connects to…

DB44 male connector DB44 connector on the DMLU

Bare wire DDF

6.11 Installing the Built-In Storage Battery and Its Cables

Huawei has two types of built-in storage batteries. The two types of storage batteries are similar in

appearance, but different in the distribution of positive and negative terminals. The following takes the

storage battery with the positive terminal at the left port and the negative terminal at the right part of the

battery as an example. If customers prefer to provide storage batteries themselves, storage batteries must

comply with the BTS3012AE configuration requirements.

6.11.1 Introduction to the Storage Battery Cabin

The BTS3012AE has two types of storage battery cabins: –48 V 50-AH storage battery cabin

and –48 V 150-AH storage battery cabin.

Page 135: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-27

The –48 V 50-AH storage cabin of the BTS3012AE can be removed to form a 7 U space with

the reserved 2 U space. This space can be used to accommodate transmission equipment or

other equipment of the operators.

� Figure 6-28 (A) lists the full configuration of the BTS3012AE under the combination of

150 AH + 50 AH + 2 U.

� Figure 6-28 (B) lists the full configuration of the BTS3012AE under the combination of

150 AH + 7U.

After the –48 V 50 AH storage battery cabin is removed, it can not be used as the storage battery cabin

again because it cannot meet the sealing requirements. That is to say, the cabinet shown Figure 6-28 (A)

can be changed to the cabinet shown Figure 6-28 (B) while the cabinet shown Figure 6-28 (B) cannot be

changed to the cabinet Figure 6-28 (A).

Figure 6-28 Full configuration of the BTS3012AE

DC

PD

U

DT

MU

DA

TU

DC

SU

DC

CU

DTRU

DTRU

DTRU

DTRU

DTRU

DTRU

BAT -48V 150AH

Wire holder

FAN

Air inlet

PSU

Cable in/outEMI

Wire holder

DT

MU

Wire holder

Air inlet

Tra

nsm

issio

n u

nit

BAT -48V 50AH

Air return

AC PDU

PSU

Air return

DPMU

PSU

PSU

PSU PSU

PSU PSU

DELU 0DMLUDELU 1

DDPU

DDPU

DDPU

DCOM

DCOM

DC

PD

U

DT

MU

DA

TU

DC

SU

DC

CU

DTRU

DTRU

DTRU

DTRU

DTRU

DTRU

BAT -48V 150AH

Wire holder

FAN

Air inlet

PSU

Cable in/outEMI

Wire holder

DT

MU

Air inlet

Transmission unit

Air return

AC PDU

PSU

Air return

DPMU

PSU

PSU

PSU PSU

PSU PSU

DELU 0DMLUDELU 1

Wire holder

(A) (B)

DCOM

DDPU

DDPU

DDPU

DCOM

DCOM

DCOM

The cabling of the –48 V 50-AH storage battery cabin is shown as Figure 6-29.

Page 136: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-28 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 6-29 Cabling of the –48 V 50-AH storage battery cabin

70

100

The cabling of the –48 V 150-AH storage battery cabin is shown as Figure 6-30.

Figure 6-30 Cabling of the –48 V 150-AH storage battery cabin

60

120

Page 137: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-29

6.11.2 Introduction to the Cables for the Built-in Storage Battery

The cables for the built-in storage battery are:

� Red GND cable with the sectional area of 25 mm2

� Black –48 V cable with the sectional area of 25 mm2

� Cable between storage batteries

� Cable for the temperature and humidity sensor of the built-in storage battery, with two

wires, at one end is a 2-pin terminal, and at the other end is an OT terminal

6.11.3 Installation Procedure

Before connecting the cable between storage batteries, be sure to power off them. Otherwise,

the power may result in injuries.

To power off a storage battery, insert a small round stick into the small hole beside the OFF

silkscreen on the front panel of the DPMU, push the button for at least five seconds until you

can hear that the storage battery is powered off.

The capacity of a built-in storage battery group in the BTS3012AE is 50 AH. The

BTS3012AE supports a maximum of four groups.

The BTS3012AE currently supports three configuration modes: 100 AH, 150 AH, and 200

AH. The selection of the configuration mode is subject to the system configuration.

100-AH Configuration Mode

If the BTS3012AE is configured with a 100-AH storage battery group, connect the cables as

follows:

Step 1 Connect three storage batteries through cables 1, 2, and 3 as shown in the

Figure 6-31. Place the terminal covers on the terminals.

Step 2 In the middle layer, place the connected storage batteries at the back of the storage battery

cabin.

Step 3 Place another storage battery in front of the first three batteries and make it on the right side

within the cabin.

Step 4 Use cable 2 to connect the fourth storage battery and place the terminal covers on the

terminals.

Step 5 Connect the two pieces of cable 1 to the wiring copper bar.

Page 138: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-30 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 6-31 Cabling for the 100-AH configuration mode (1)

Middle layer

Plan View

1

1

2

33

Bottom layer

Step 6 In the bottom layer, place two storage batteries in the front of the cabin and make them on the

left side.

Step 7 In the middle layer, place two storage batteries in the front of the cabin and make them on the

left side.

Step 8 Use cables 2, 3, and 4 to connect the storage batteries as shown in Figure 6-32. Place the

terminal covers on the terminals.

Step 9 Connect cables 1 and 3 to the wiring copper bar.

Page 139: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-31

Figure 6-32 Cabling for the 100-AH configuration mode (2)

Plan View

4

2

3

1

Middle layer

Bottom layer

----End

150-AH Configuration Mode

If the BTS3012AE is configured with a 150-AH storage battery group, connect the cables as

follows:

Page 140: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-32 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Step 1 Connect three storage batteries through cables 1, 2, and 3 as shown in the

Figure 6-33. Place the terminal covers on the terminals.

Step 2 In the bottom layer, place the connected storage batteries at the back of the cabin.

Step 3 Place another storage battery in front of the first three batteries and make it on the right side

within the cabin.

Step 4 Use cable 2 to connect the fourth storage battery and place the terminal covers on the

terminals.

Step 5 Connect the two pieces of cable 1 to the wiring copper bar.

Page 141: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-33

Figure 6-33 Cabling for the 150-AH configuration mode (1)

Plan View

2

33

1

1

Bottom layer

Step 6 Connect three storage batteries through cables 1, 2, and 3 as shown in the

Figure 6-34. Place the terminal covers on the terminals.

Step 7 In the middle layer, place the connected storage batteries at the back of the cabin.

Step 8 Place another storage battery in front of the three batteries in the middle layer and make it on

the right side within the cabin.

Page 142: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-34 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Step 9 Use cable 2 to connect the fourth storage battery and place the terminal covers on the

terminals.

Step 10 Connect the two pieces of cable 1 to the wiring copper bar.

Figure 6-34 Cabling for the 150-AH configuration mode (2)

Plan View

1

1

2

33

Middle layer

Bottom layer

Step 11 In the bottom layer, place two storage batteries in the front of the cabin and make them on the

left side.

Page 143: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-35

Step 12 In the middle layer, place two storage batteries in the front of the cabin and make them on the

left side.

Step 13 Use cables 1, 2, and 3 to connect the storage batteries as shown in Figure 6-35. Place the

terminal covers on the terminals.

Step 14 Connect cables 1 and 2 to the wiring copper bar.

Figure 6-35 Cabling for the 150-AH configuration mode (3)

Plan View

2

1

3

3

Middle layer

Bottom layer

Page 144: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-36 Huawei Technologies Proprietary Issue 01 (2006-09-06)

----End

200-AH Configuration Mode

If the BTS3012AE is configured with a 200-AH storage battery group, connect the cables as

follows:

Step 1 Refer to the methods described in the 150-AH configuration mode to connect storage batteries

in the middle and bottom layers.

Step 2 In the top layer, place two storage batteries at the back of the cabin.

Step 3 In the top layer, place another two storage batteries in the front of the cabin.

Step 4 Use cables 2 and 3 to connect the storage batteries as shown in Figure 6-36. Place the terminal

covers on the terminals.

Step 5 Connect cable 1 to the wiring copper bar.

Page 145: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-37

Figure 6-36 Cabling for the 200-AH configuration mode

Plan View

1

2

2

3

1

Top layer

Middle layer

Bottom layer

----End

Page 146: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-38 Huawei Technologies Proprietary Issue 01 (2006-09-06)

6.12 Installing Cables for the Combined Cabinet

6.12.1 Introduction to Cables for the Combined Cabinet

The cables for the combined cabinet transmit the RF signals between the two combined

cabinet.

Both ends of the cable are MD68 male connectors. One connects to the TO SLAVE

CABINET port on the DSCB of the main cabinet and the other connects to the TO SLAVE

CABINET port on the DSCB of the extension cabinet.

Figure 6-37 shows the structure of the cable for the combined cabinet.

Figure 6-37 Cable for the combined cabinet

1

X1 X2

WA

2

View A

Pos.1

Pos.68

(1) MD68 male connector (2) MD68 male connector

6.12.2 Installation Procedure

Install the RF signal cables for the combined cabinet as follows:

Step 1 Attach labels to both ends of the cable. For details, see Appendix C "Engineering Labels for

Cables."

Step 2 Connect the MD68 male connector on one end to the TO SLAVE CABINET port on the

DSCB of the main cabinet.

Step 3 Connect the MD68 male connector on the other end to the TO SLAVE CABINET port on the

DSCB of the extension cabinet.

----End

Page 147: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 6 Installing Cables

Issue 01 (2006-09-06) Huawei Technologies Proprietary 6-39

6.13 Installing Cables for the Cabinet Group

6.13.1 Introduction to Cables for the Cabinet Group

The cables for the cabinet group transmit RF signals between two cabinet groups.

Both ends of the cable are MD36 male connectors. One connects to the port TO SLAVE

GROUP1 or TO SLAVE GROUP2 on the DSCB of the main cabinet group. The other end

connects to the port TO SLAVE GROUP1 or TO SLAVE GROUP2 on the DSCB of the

extension cabinet group.

Figure 6-38 shows the structure of the cable for the cabinet group.

Figure 6-38 Cable for the cabinet group

Pos.1

W

X1 X2

1 2

Pos.36

(1) MD36 male connector (2) MD36 male connector

6.13.2 Installation Procedure

Install the cables for cabinet group as follows:

Step 1 Attach labels to two ends of the cable. See Appendix C "Engineering Labels for Cables."

Step 2 Connect the MD36 male connector on one end to the port TO SLAVE GROUP1 or TO

SLAVE GROUP2 on the DSCB of the main cabinet group.

Step 3 Connect the MD36 male connector on the other to the port TO SLAVE GROUP1 or TO

SLAVE GROUP2 on the DSCB of the extension cabinet group.

----End

6.14 Installing the RET Control Signal Cable

6.14.1 Introduction to the RET Control Signal Cable

The RET control signal cable transmits signals between the DATU and the Bias-Tee.

One end of the cable is an SMA elbow male connector, and the other end is an SMA male

connector.

Figure 6-39 shows the structure of the RET control signal cable.

Page 148: BTS3012AE Base Station Cabinet Installation Manual

6 Installing Cables

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

6-40 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Figure 6-39 Structure of the RET control signal cable

1

W

X1

X2

2

(1) SMA male connector (2) SMA elbow male connector

6.14.2 Connecting the RET Control Signal Cable

Perform the following steps:

Step 1 Connect the SMA elbow male connector to the ANT port on the DATU.

Step 2 Connect the SMA male connector to the SMA port of the Bias-Tee.

Step 3 Connect other RET control signal cables according to steps 1 through 2.

Step 4 Arrange the cables neatly and tie them with cable ties.

Step 5 Attach the label to both ends of the cable. For details, see Appendix C "Engineering Labels

for Cables."

----End

Page 149: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 7 Checking Hardware Installation

Issue 01 (2006-09-06) Huawei Technologies Proprietary 7-1

7 Checking Hardware Installation About This Chapter

The following table lists the contents of this chapter.

Title Description

7.1 Equipment Installation

Check

Provides the checklist for the equipment installation.

7.2 Cable Installation Check Provides the checklist for the cable installation.

7.3 Power-On Check Describes how to perform power-on checks.

7.4 Sanitation Check Describes how to perform sanitation checks.

Page 150: BTS3012AE Base Station Cabinet Installation Manual

7 Checking Hardware Installation

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

7-2 Huawei Technologies Proprietary Issue 01 (2006-09-06)

7.1 Equipment Installation Check

Refer to Table 7-1 for the equipment installation check.

Table 7-1 Equipment installation checklist

SN Item

1 The cabinet is placed according to the design drawing.

2 The cabinet is properly mounted on the concrete base. After the installation,

the cabinet stands firmly on the ground.

3 The horizontal error of the cabinet position is less than 3 mm and the vertical

error is not more than 3 mm.

4 All screws are securely fastened. The spring washers are installed on the flat

washers.

5 The parts on the cabinet are not detached or damaged. The cables are not

scratched or broken.

6 The equipment is clean and neat. The external paints are intact. The labels are

correct, legible, and complete.

7 The front doors of the cabinets are easy to open or close.

7.2 Cable Installation Check

7.2.1 Transmission Cable Installation Check

Refer to Table 7-2 for the cable installation check.

Table 7-2 Transmission cable installation checklist

SN Item

1 The cables are securely connected.

2 The cable connectors are intact.

3 The cables are not broken or damaged.

4 The cables are neatly bound. The space between cable ties is uniform. The

cables are properly fastened and the cable ties face the same direction.

5 The extra tails of cable ties are completely cut off.

6 The cable layout is convenient for maintenance and expansion.

7 All labels and tags at both ends of the cables are legible.

Page 151: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 7 Checking Hardware Installation

Issue 01 (2006-09-06) Huawei Technologies Proprietary 7-3

7.2.2 Power Cable and Protection Grounding Cable Installation Check

Refer to Table 7-3 for the installation check on the power cables and grounding cables.

Table 7-3 Power cable and grounding cable installation checklist

SN Item

1 All power cables and grounding cables are copper-core cables and their

diameters meet the required specifications.

2 None of the power cables and grounding cables is short-circuited or reversely

connected.

3 The power cables and grounding cables are bound separately from other

cables.

4 Labels are attached to each end of the power cables and grounding cables.

5 No power cable or grounding cable is scratched or broken.

6 A proper length of power cables and grounding cables is reserved after they

are led into the cabinet through the waterproof module.

7 The power cables and grounding cables are made of one segment of materials.

Multiple segments of cables are not joined to make a power cable or grounding

cable.

8 No breaking device, such as a switch or fuse, is allowed to the electric

connection of the grounding system.

9 The extra power cables or grounding cables are cut off instead of being coiled

up.

10 The lugs at each end of the power cables or grounding cables are securely

soldered or crimped.

11 The bare wires and lug handles at the wiring terminals are completely wrapped

up through insulation tapes or heat-shrinking tubes.

12 The flat washers and spring washers are securely installed with and in close

contact with all wiring terminals.

13 The GND and PGND of the BTS and the lightning protection grounding of the

building share the same group of grounding conductors.

14 The grounding grids of the iron tower, the equipment room, and the

distribution transformer (if the distance between the transformer and the

equipment room is less than 30 m) constitute an integrated grounding grid.

7.3 Power-On Check

Page 152: BTS3012AE Base Station Cabinet Installation Manual

7 Checking Hardware Installation

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

7-4 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Take care of personal safety during the power-on check because high voltage is involved. A

fatal accident may occur if you touch the input current directly or indirectly through a wet

substance.

Before you turn the primary power supply to ON, use a multimeter to measure the resistance

between the input power and the earth and check whether they are short-circuited.

7.3.1 Cabinet Power-On Check

Before powering on the cabinet, ensure that the power cables and boards are disconnected.

The procedure for power-on check of a cabinet is as follows:

Step 1 Set all the power switches to OFF.

Step 2 Turn on the DC PDF to power on the cabinet.

Step 3 Measure the input voltage of the power distribution box on BTS3012AE cabinet. The range

allowed is –60 V to –40 V.

� If the voltage is within the range, the power-on check is complete. Continue with board

power-on check.

� If the voltage is beyond the range, go to the next step.

The rated voltage of the BTS3012AE cabinet is –48 V.

Step 4 Turn off the DC PDF to cut off the power supply to the cabinet.

Step 5 Measure the output voltage of the PDF. Check the installation and layout of power cables on

the cabinet top. Clear the faults.

Step 6 Measure the output voltage of the PDF again and take the cabinet power-on check.

If the results are normal, continue with board power-on check.

----End

Page 153: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 7 Checking Hardware Installation

Issue 01 (2006-09-06) Huawei Technologies Proprietary 7-5

7.3.2 Board Power-On Check

Before power-on check of boards, ensure that:

� The cabinet passes the power-on check.

� All the power switches are set to OFF.

� All the cables are connected properly.

The procedure for power-on check of boards is as follows:

Step 1 Set the power switch of the FAN subrack to ON.

Step 2 Check whether the fan runs normally.

� If yes, infer that the power supply inside the cabinet is normal. Go to Step 4.

� If no, infer that the power supply inside the cabinet is not normal. Go to Step 3.

Step 3 Check whether the power cable connection of the FAN subrack is good. If no, reinstall the

cable, and then repeat Step 1.

Step 4 Set the power switch of the common subrack to ON.

Step 5 Check whether the indicators of the DTMU in the common subrack flash slowly (0.5 Hz).

� If yes, infer that the board has normal power supply. Go to Step 7.

� If no, infer that the board is not properly placed or there are other faults. Go to Step 6.

Step 6 Reinstall the boards or clear the faults. Then repeat Step 5.

For details about the status of indicators on boards, see the BTS3012AE Base Station Hardware

Description Manual.

Step 7 Set the power switch of the DTRU to ON. Check whether the indicators on the DTRU panels

flash slowly (0.5 Hz).

� If yes, infer that the DTRU has normal power supply. Go to Step 8.

� If no, infer that the DTRU is not properly placed or there are other faults. Clear the faults

and then repeat Step 7.

Step 8 Set the power switch of the DAFU subrack to ON, and check whether the indicators on the

DDPU panels flash slowly (0.5 Hz).

� If yes, the DDPU has normal power supply. The power-on check of the board is

complete.

� If the indicators are always on, infer that the DDPU is faulty. Go to Step 9.

� If the indicators are off, infer that the power supply fails. Go to Step 10.

� For states other than that mentioned previously, go to Step 11.

The DCOMs in the DAFU subrack do not need power and there are no indicators on them.

Step 9 Check the DDPU and the cable between the DDPU and the serial port on the DTRU. Reinstall

the cable and check whether the indicators on the DDPU panel flash slowly (0.5 Hz).

� If yes, infer that the DDPU has normal power supply. Board power-on check is complete.

� If no, go to Step 11.

Page 154: BTS3012AE Base Station Cabinet Installation Manual

7 Checking Hardware Installation

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual

7-6 Huawei Technologies Proprietary Issue 01 (2006-09-06)

Step 10 Check the power cables of the DDPU. Reinstall the cable and see if the indicators on the

DDPU panel flash slowly (0.5 Hz).

� If yes, infer that the DDPU has normal power supply. Board power-on check is complete.

� If no, go to Step 11.

Step 11 Contact Huawei for fault location. Clear the faults and then perform Step 8 again until the

indicators on the DDPU panels flash slowly (0.5 Hz).

----End

7.3.3 Power-On Check of the Heat Exchanger

The procedure for the power-on check of the heat exchanger is as follows:

After inserting the PSUs into the cabinet, turn on the ACU/HX switch on the AC power

distribution box and the HEX switch on the power distribution box. Check whether the fan on

the heat exchanger rotates fast.

� If yes, the heat exchanger works normally. The power-on check of the heat exchanger is

complete.

� If no, the heat exchanger is faulty. Contact Huawei to replace the heat exchanger.

7.3.4 Power-on Check of the Batteries

The procedure for the power-on check of batteries is as follows:

Step 1 Set the multimeter on the DC scale.

Ensure that the negative pole of the multimeter is connected to the positive pole (red) of the

battery group, and the positive pole of the multimeter to the negative pole (black) of the

battery group.

Step 2 Follow the instructions listed in Table 7-4 to handle different values.

Table 7-4 Instructions to handling different values

Measured Value Handling Suggestion

Value > 0 The connection between the –48 VDC cable and the GND cable is

incorrect. Connect the two cables correctly, and then measure the

voltage of the battery again.

Value = 0 The cable connection of the batteries is incorrect, or the batteries

are faulty. Correct the connection or clear the battery faults, and

then measure the voltage of the battery again.

Page 155: BTS3012AE Base Station Cabinet Installation Manual

HUAWEI BTS3012AE Base Station

Cabinet Installation Manual 7 Checking Hardware Installation

Issue 01 (2006-09-06) Huawei Technologies Proprietary 7-7

Measured Value Handling Suggestion

–43.2 V < Value < 0 Check whether the low voltage is caused by automatic discharge

after a long period.

If the low voltage is caused by automatic discharge after a long

period, press the ON button (located in the hole) on the PMU panel

using a proper tool. Wait until you hear a click sound. Then go to

the next step.

Otherwise, check whether the batteries are normal. If the batteries

are faulty, clear the fault, and then measure the voltage of the

battery again.

–57.6 V ≤ Value ≤

–43.2 V

The connection is correct.

Press the ON button (located in the hole) on the PMU panel using a

proper tool. Wait until you hear a click sound. Then go to the next

step.

Step 3 Turn off the AC power input switch, and check whether the BTS3012AE can work well with

reference to the board indicators.

� If yes, the batteries are functional. The power-on check of the batteries is complete.

� If no, the batteries are faulty. Go to Step 4.

Step 4 Press the button in the hole labeled OFF on the PMU panel to power off the battery. After the

fault is cleared, power on the BTS3012AE again until the BTS works well.

If all the power-on checks have been passed, the power supply system of the BTS is

functional.

----End

7.4 Sanitation Check

Refer to Table 7-5 for the sanitation check.

Table 7-5 Sanitation checklist

SN Item

1 The packing boxes and boards are neatly placed in the installation site.

2 All rubbish such as tails of cable ties is removed from the installation site.

3 There are no fingerprints or other stains on the surface of the cabinet.

4 The cabinet is clean. There is no dust inside or outside the rack.