Brochure Tech in Floor Ingles

Embed Size (px)

Citation preview

  • 8/8/2019 Brochure Tech in Floor Ingles

    1/16

    TechinfloorInnovative technologies for flooring

    TENSIOPAV

    Joint-lessNo CracksNo wavingEngineeredControlled

    Guaranteed

    Post-TensionedIndustrial Floors

    With a posthumous10 Years Insurance

    Policy coveringreplacement o the job

  • 8/8/2019 Brochure Tech in Floor Ingles

    2/16

    ost-tension, applied to industrial oors represents a revolutionin the Market, a new concept o quality and proessional

    approach.

    Techinfoor is the exclusive Distributor in Europe o the Post-tension System, called TENSIOPAV, developed within anInternational partnership with ORI Martin Group, with SLM- Siderurgica Latina Martin -, manuacturing Company o steel

    unbounded strands and cables, and with TT M, a leader Firm inplanning and application o the Post-tension System on majorbuilding jobs such as bridges, aqueducts, Interports, etc.

    TT M provides complete consultancy support, rom theplanning phase to supply o the Post-tension Hard ware(accessories, electronics, stressing jacks), to the fnal

    tensioning phases. Such innovative Technology consists on

    replacing the traditional armor (electro-sealed nest, metallicfbers, synthetic fbers, glass fbers, etc.) with unbounded,

    greased and sheathed, drowned in the concrete steel strands,

    then Post-tensioned with hydraulic stressing jacks.TENSIOPAV System is guaranteed: rom the initial engineeredplanning which inuences the eects o all operation, to the

    typical techniques o the oundation, up to resistance against

    the loads, both static and dynamic; everything is engineered

    and designed, rom the thickness o the plate, to the strand

    disposition and the additional armor, as well as the specifc

    characteristics o the concrete.

    The concrete mix design, the pre-qualifed recipe veriyingthe characteristics o the mix in the concrete trucks, and the

    constant control techniques applied directly on the job site, will

    create a mapping o the constructive whole process.

    A oor fnalized with the TENSIOPAV System will thereoreresult scientifcally projected, punctually checked and guar-anteed with a 10 Years Posthumous Policy Insurancecovering replacement o partial or total work.

    P

    Post-tension: from major buildings

    The advantages

    No more Joints

    No more cracks

    No more waving eects

    No more gradient dierences among the edges o the plates

    Thickness reduction o the plate

    Flatness and improved link among the plates

    Maintenance costs dramatically reduced

    Better comort o use

    Better image and aesthetical eect

    Control o the whole building process (rom the steel strand

    production to the nal foor nalization)

    Posthumous 10 Years Insurance Policy

    tension technologys.r.l.TTMPost tension anchor system

  • 8/8/2019 Brochure Tech in Floor Ingles

    3/16

    o concrete industrial surfaces

    TENSIOPAV is the solution to the traditional problems o each

    industrial oor: it is now possible to create oors without joints,

    without cracks, without waving, wide monolithic suraces, with

    reduced thickness, which provide high atness and drastic reduction

    o maintenance costs.

    TENSIOPAV proves to be perect or all implants which are build

    to have high shelves, highly concentrated and dynamic loads,

    systematic circulation o vehicles with low wheels, oors with resin

    coverings, and in general or all the highly unctional and industrial

    suraces.

    > Post-tensioning applied to radiant suraces

    TENSIOPAV System is the perect solution where a heated oor

    is planned: the post-compression o the concrete, in act, creates

    a resistance to revealed cracks created by the continuous cycle o

    cooling and heating o the radiant foor.

    The linear expansions inducted by the thermal variations are

    limited, so a perect efciency o the whole structure in terms o

    global resistance and perormance is actually provided.

    TENSIOPAV can provide absolute application exibility versus anytraditional system: irregular geometric shapes (triangles, trapezes,

    narrow rectangles, etc.) and/or outdoor oors with complex con-

    structive parameters can be built at ease.

  • 8/8/2019 Brochure Tech in Floor Ingles

    4/16

    Techinoor

    The revolutionary TENSIOPAV System conjugates thereore

    Special steel Technology with a total process control, when it

    comes to realization o concrete oors.

    To assure the overall coverage, a constant assistance, and a

    State-o-the-Art execution o any job, Techinfoor has selected

    some o the most important Companies o the industrial

    oorings on the European market, gathering all o them in

    the TENSIOPAV Group: every member Company is active

    since many years, with high skills and proessionalism, in the

    industrial oorings Market, and represents a valid partner

    within the Group and a reerence point or Engineers and Buyers

    o their related area.

    Techinfoor provides, ater a ollowing audit rom one o the

    most important Insurance Groups, a 10 Years Posthumous

    Insurance Policy covering partial or total replacement

    o the Post-Tensioned job; this being a ormal result o the

    punctual control o the whole productive process, that assures

    the Customer or an exceptional State-o-the-Art realization.

    In order to know details

    o each dierent associated Company

    member o Tensiopav Group,

    please consult the sitewww.tensiopav.it

    Engineered planning, punctual control, no crack, no control and expansion

    joint, dramatic maintenance costs reduction, reduced thickness, resistance and

    durability are the major highlights o this new technology, that represents the topo what the market o the Industrial foorings oers on a World Wide Base today.

    TENSIOPAV Group is distinguished or:

    quli tchnicl support crti n Tst ovrll Qulity

    spcic n rlibl Know-how

    consolit businss rrncs

    constnt ssistnc to th Customr

    srious n prossionl pproch

    pculir comptncs

  • 8/8/2019 Brochure Tech in Floor Ingles

    5/16

    The building process

    Engineered PlanningThe concrete Post-Tensioned plate is dimensioned with anaccurate engineered planning o each single detail, beginning rom

    the position o the steel strands, the evaluation o the distancebetween nest strands, the position o a low armor at the bottom

    o the punctual and distributed loads, up to the organization and

    the sequence o the concrete placements with respect to the

    specifc requirements.

    Verifcation and preparation o the oundationThe careul and accurate preparation o the oundation is a un-

    damental must, when the use o the Post-tension System isplanned: it is mandatory to veriy the carrying ability, the planarity,

    the degree o compact resistance and homogeneity o the ounda-

    tion; a double layer o polyethylene is put on ground in order tocreate a layer that isolates the concrete plate rom the ground,

    and to reduce attrition during Post-Tensioning operations.

    Custom cut and position o the steel strandsPredisposition o the closing procedure with the easy-system,position o the slow armors around the pillarsand to the fxed

    points o the structure, carrying out strand distribution, cut o the

    strands and their position according to the original planning.

    Throw and punctual control o the building process

    During the distribution on ground, the strand nest is set on distancechairs to the appropriate level comparing to the thickness o

    the plate. During the concrete placement, an integrated control

    o the concrete and its technical characteristics is set in place

    by collecting the samples on which a certifed Laboratory will do

    the proper tests, and rom which it will extrapolate the minimum

    tensioning values.

    In order to enable the correct access o the stressing jacks or the

    ollowing tensioning phases, a ree band is set up two sides o

    the perimeter o the structure; this perimeter will be armed and

    subsequently covered with concrete.

    Partial and fnal TensioningThe frst stressing, or partial tension, will be applied usually ater

    24 hours with a special hydraulic stressing jack, in order to oppose

    the plastic micro-cracks o the concrete.

    As soon as the ft resistance o concrete will be reached (usually

    ater 72 hours), concrete will be fnally post-tensioned, so that this

    will coner the plate the carrying ability required by the project,

    and the construction joints will be compressing one against the

    other the linked lots.

    Superfcial fnish and closing o the perimeter bandAs soon as Post-tension System is applied, the ree perimeterband will be covered with concrete, and chemical surace

    hardening fnishes will be applied.P

    unctualcon

    trolofthew

    holeproduc

    tiveprocess

  • 8/8/2019 Brochure Tech in Floor Ingles

    6/16

    Engineered Planning

    > Floor Engineering

    The planning o the steel strand nest, with the evaluation

    o the relative distance, is a mandatory step into the

    realization o the work. It assures the correct evaluation

    o all the constructive parameters and it guarantees that

    the work is fnalized according to the engineering criteria

    related to the Post-tension Technology.TT M always will guarantee an immediate answer tothe application requirements o the Customer, assuring

    a exible and reliable approach during calculation, sizing

    and planning o the TENSIOPAV system.

    Last generation sotware application, allows to develop

    the calculations in perect relationship to the loads that

    the oor will have to bear, based on the use destination

    o the property, and to where the structural loads may be

    distributed in particular points o the structure.

    The project comprehends constructive details, passive

    armors location and slow armors placement along andaround the pillars.

    The State-o-the-Art engineering o industrial foorings

  • 8/8/2019 Brochure Tech in Floor Ingles

    7/16

    Preparation o the oundation

    > Verifcations o the oundation material char-

    acteristics and o ground conditions, through

    plate tests

    The Load Test on static plate with consequent calculation

    o the Deormation Degree, is necessary to veriy that the

    oundation will support perormance requirements imposed by

    the specifcation o the engineered plan.

    The resistance control Test on the job site, in correspondence

    o the oundation, is in act o undamental importance in order

    to be able to guarantee the minimum requirements o ground

    mechanical resistance and stability against the loads that will

    cover it. To veriy then the homogeneity degree o the ground

    oundation, the device LIGHT FALLING will be used, and then

    the WEIGHT DEFLECTOMETER as below specifed.

    The 300 mms diameter and 20 mms thick galvanized steel plate,

    can be considered sti as per the calculation targets o the plan

    submitted to the test: the load assumes orm o a damped hit,

    and the test is said to be dynamic.

    The test LFWD is a unctional beta methodology: efcient, rapid

    and representative.

    It will be necessary to compare results o the deormation orm

    versus the dynamic Evd values, and with the middle values Md

    o the test o load statics.

    > Barrier to Moist and double slide layer

    The sheet o polyethylene, in double layer, is put above the

    compacted oundation material, and it develops the double

    unction o barrier to the moist, and o layer o slide that

    allows the Post-Tensioned plate to stir without rigid ties in

    the tensioning phase or during longitudinal movements.

    In act, as quoted by the norm UNI 11146, the sheet o

    polyethylene in double layer introduces the lowest attrition

    coefcient among the plate and the oundation and it resultsideal or the post-tensioned applications.

    reparation o the oundation represents the frst operational and undamental step into the construction

    o a Post-Tensionedsurace using theTENSIOPAVSystem.The interventions particularly to be taken care o, are the ones related to the ollowings essential

    requirements:Compact pressure in order to avoid yeldings when the oor is in exercise phase;

    Leveling, in order to allow the ree slide o the plate.

    It results thereore undamental, to perorm technical surveys ocusing on the Deormation Degree o

    the oundation, applying tests on the plate, both static and dynamic.P

  • 8/8/2019 Brochure Tech in Floor Ingles

    8/16

    Easy-system Closing Procedure

    > Assemblage o the perimetral closing bends

    The easy-system is projected or this particular job, and is

    constituted o two symmetrical metal stirrup and by one closing

    wooden band.

    The upper stirrup closes on the wooden band and fxes the

    closing in a rigid way so that it is possible to regulate the plate

    thickness determined by the project requirements.

    On the wooden band are subsequently fxed the active heads, or

    the heads rom which the entrance stressing jacks are set up or

    the ollowing phases o partial and total tensioning.

    he closing procedure o the assembly plates

    has been optimized with the defnition o

    the Easy-system Closing Procedure, that

    guarantees rapidity and precision while in thephase o concrete placement preparation: the

    ollowing phases result rapid and secure and

    the construction joints are properly sealed

    and proteceted.T

  • 8/8/2019 Brochure Tech in Floor Ingles

    9/16

    Strands

    > Cut o the strands

    The strand goes out rom the wheel along a metallic line, and once

    fxed the desired length, the strand is cut to measure coherent

    with the project.

    The repeated operation creates the set o strand necessary to the

    job in an easy, sae and ast way.

    > Carrying out on the job site the strand

    placement

    The carrying out o the steel strands takes place on the job

    site thanks to a system patented by TTM, our Partner inPost-tensioning: the spool is loaded on a base with

    a particular cone connected to a pushing system controlled

    by an hydraulic device. The particular mechanism allows

    to develop the spool in simple way and in ull saety,

    paying particular attention to the ree end o the spool,

    that can result dangerous even i engaged into the conic

    base.

    The spool is pushed out beginning rom the cone, which

    controls the carrying out process and allows the correct

    placement o the long strands all over the oor.

  • 8/8/2019 Brochure Tech in Floor Ingles

    10/16

    Strand nest Placement and Heads fxing

    > Installation o the wedges in the headings and bindingo the intersections o the strand nest

    The heads anchorage is done fxing the wedges in the heads at the end o

    the strand, through the ollowing operations:

    cut o PVC cover, approximately or 5 cms, rom the end o the strand;

    positioning o the heads on the strand and insertion o the wedge in

    order to assure its fxing; this operation is necessary in order to fx, in

    a total sae environment, the passive head which, drowned into the

    concrete, will be highly solicited during the Post-tension action.

    The consequent consists o putting to strands on a network design,

    distancing them correctly in both directions, and sealing each single

    intersection in a way that can guarantee the correct positioning ater the

    concrete trucks have delivered the cements.

  • 8/8/2019 Brochure Tech in Floor Ingles

    11/16

    Additional passive armors

    > Installation o passive additional non pre-tensioned

    armors

    In order to better distribute loads along the perimeter dedicated to the

    heads, additional metal bars are put along the closing ends, so active

    heads will not mode while concrete will be stressed.

    To absorb tensions in elevation and close to the pillars, additional armors

    are positioned as per engineered planning.

    The vertical structures englobed in the concrete placement throws

    (pillars, grits, walls,etc) will become isolated with compressed but thick

    materialproven to to guarantee the slide o the plates while in post-

    tensioning phase.

  • 8/8/2019 Brochure Tech in Floor Ingles

    12/16

    Laser Screed-based concrete Placement

    > Concrete Placement on the job site

    The Concrete Placement is usually done with Laser Screed

    technology, the laser controlled Machine with vibrating control

    that guarantees highly compact pressure o the concrete, together

    with a atness degree: the vibro-placement o the upper part o

    the concrete allows air molecules to evaporate, so the oor will

    be ree o micro-cracks and nests.

    Besides that, the Laser-Screed sensitively reduces execution

    times, allows to compact suraces much better than with the

    traditional manual placement.

    Contextually to the concrete placement, the needle vibratingoperations take place, while the distance chairs are set up on the

    crossing, ollowing project specifcations.

  • 8/8/2019 Brochure Tech in Floor Ingles

    13/16

    Punctual control o the concrete

    > Punctual control o the concrete

    The technological building process o the TENSIOPAV System includesalso a pre-qualifcation o the concrete implant, in order to make sure

    that the optimal prescriptions o the mix-design and the punctual control

    o the mixture o urnished concrete are guaranteed: on the job site

    specifc tests are perormed according to normative, and according to

    the Pavical requirements to comply to the project applications in terms

    o resistance and composition that the concrete must guarantee or a

    proper application o the Post-tension System.The samples collected in square dice are submitted to crushing in

    certifed laboratories so that the resistance matured rom the concreteater 24 and 72 hours are defned and inspected and thereore, once

    extrapolated, the relative pressure levels will be applied rom the

    stressing jacks during post-tensioning operations, both partial and fnal.

  • 8/8/2019 Brochure Tech in Floor Ingles

    14/16

    Partial and fnal Tensioning operations

    The wooden band is removed the ollowing day ater the

    concrete placement, only i concrete has reached the correct

    strength in order not to be damaged.Cleaning o the anchorage hollow takes place, then it is

    important that the stressing jack does not have any obstacle,

    and that the wedges are perectly installed in the headings.

    Integrity o the concrete is checked, both along vertical and

    the longitudinal parts o the surace, and that there are not

    cracks, or nest eects, or micro-caves.

    A deep check is dedicated that strands are perpendicular to

    the anchorages and that the anchorages parallel to the ace o

    concrete, then the stressing jack is set or operation.

    The stressing jack has a designed device that exactly covers

    the taking o the strand in the exact end point o the concreteplacement.

    Introducing a small pressure on the jack, it is able to com-

    pensate, partially or totally, the traction stress nduced by the

    spontaneous withdrawal o the concrete.

    Strand Extension

    Piston excursion

    Fixing wedges are perectly positioned to avoid their separation

    during the positioning o the stressing jack.A specialized operator o TTM is there to properly apply the

    Post-tensionprocedures, coherent with the recommendations

    on saety operations defned by the same TTM.

    Ater the Tensioning operations, actual extensions o the

    strands are noticed, comparing them with the theorical onesexpected by the project requirements, and veriying the

    perect equipment efciency.

    > First partial tensioning

    > Final Tensioning

  • 8/8/2019 Brochure Tech in Floor Ingles

    15/16

    Post-tensioned Floor

    > The Concrete Industrial Flooring revolution

    Having a monolithic continuous Post-Tensioned surace is o

    paramount importance or a Logistics and Great Distribution

    Company, with electronic management systems o automated

    carts, which wont suer anymore the problems caused by

    waving oor plates or by broken joints.

    TENSIOPAV System is the absolutely best solution or Firms

    that need extremely high cleaning standard, because by

    eliminating the joints, the primary cause o dust and degrade

    o any kind is simply eliminated.

    TENSIOPAV System satisfes, thereore, the most demandingrequirements, proving to be the ideal investment or sensitive

    Buyers who ocus on high qualitative standard.

    TENSIOPAV System oers ideal support or potential super-

    fcial treatments, chemical hardeners, polishings, resin fnish-

    es based on the specifc techniques might come out rom the

    Customers requirements.

    TENSIOPAV: the beginning o a new Era.

  • 8/8/2019 Brochure Tech in Floor Ingles

    16/16

    TechinfloorInnovative technologies for flooring

    Head OFFICe

    Str Polo VI nr. 15

    91022 Cstlvtrno (TP)

    CONTaCTS

    Trapani

    Tl xx39 - 0924 92 20 66

    Fx xx39 - 0924 92 25 52

    Bergamo

    Tl xx39 - 035 44 90 412

    Milano

    Tl xx39 - 02 97 48 02 17

    www.tchinfoor.com

    [email protected]

    tension technologys.r.l.TTMPost tension anchor system

    exclusiv distributors or foor Systms

    Th nw erao Industrial foorings

    The ideal solution or

    Logistics n Grt distribution Compnis

    Highly moving Hr wr Cntrs

    automt Whrhouss

    dposits

    Inustril Sits o ny kin

    Mlls

    Multi foor prking lots

    elctronics Cntrs

    Foo Cntrs

    Frozn Foo Cntrs

    Phrmcuticl n Micl Cntrs airport Runwys n Txiwys

    airport Trminl

    Ht Floors

    Mmbrs o