Bridge Module

Embed Size (px)

Citation preview

  • 8/3/2019 Bridge Module

    1/88

    Project Preparation andAdministration

    Bridge Module

  • 8/3/2019 Bridge Module

    2/88

    R1 Trails Project Preparation

    Why are bridges part of this training?

    Big cost.

    LongProcess

    Design iscomplicated

    Tough

    Decisions

  • 8/3/2019 Bridge Module

    3/88

    R1 Trails Project Preparation

    But they are Fun!

    Trails do nothing more than

    connect the Bridges!

    Proud crew!

  • 8/3/2019 Bridge Module

    4/88

    R1 Trails Project Preparation

    Training Focus

    Bridge DesignProcess

    Decisions to be

    made. How to make those

    decisions!

  • 8/3/2019 Bridge Module

    5/88

    R1 Trails Project Preparation

    Training Focus

    Northern Region Standard Trail Bridge Plans Intended uses

    Limitations, Inappropriate Uses

    Costs

    Maintenance

    Wilderness Bridges

    Helicopter Usage

    Preservative Treatments

    If there is time NP Wilderness Bridge ProjectPresentation

  • 8/3/2019 Bridge Module

    6/88

    R1 Trails Project Preparation

    Authorities All Decisions

    Line Office

    Approval ofBridge DesignDirector of

    Engineering Unless using

    RegionalStandard TrailBridge DesignsForest Engineer.

    All Trail Bridgesneed to bedesigned!

    Bridge in Bob Marshall Wilderness

  • 8/3/2019 Bridge Module

    7/88R1 Trails Project Preparation

    Authorities

    Design ResourcesAvailable. Forest Engineer

    Regional Bridge Group

    John Kattell

    David Scovell

    Our job is to providetechnical assistance toForest personnel and

    complete and/orapprove all bridgedesigns.

  • 8/3/2019 Bridge Module

    8/88R1 Trails Project Preparation

    ProjectScope**

    Location/Survey

    Final Design

    Construction

    Preliminary Design

    Bridge Design ProcessFunction (To bridge or not? Replace or remove?)

    Who is User? ROS? TMO?Force Account/Contract?

    Where is best spot?

    Many decisions.

    Project Funding and

    Scope finalized.

    COR

    Plans, Specs,

    Estimates.

    **Contact FE and /or ROduring Project Scope

  • 8/3/2019 Bridge Module

    9/88

    R1 Trails Project Preparation

    Project Initiation and Scope

    Function To Bridge or Not to

    Bridge?

    Replace or remove?

    PreliminaryEngineering needed?

    Factors? TMO & ROS

    User Safety

    Resource Protection

    Others?Funding Feasibility

    Aesthetics WildernessAlbino Trail Bridge Site - Gal

  • 8/3/2019 Bridge Module

    10/88

    R1 Trails Project Preparation

    Bridge Design Process

    In general, morecomplicated than

    road bridges. Why? Defining the User

    Location Access

    Wilderness

    Size?

  • 8/3/2019 Bridge Module

    11/88

    R1 Trails Project Preparation

    Bridge Design Process

    Dome Mtn. On Ktn.

    24-foot span

    Wilderness

    6-mile from TH but4000 ft elevationgain.

    Force Account

    Dangerous work.

  • 8/3/2019 Bridge Module

    12/88

    R1 Trails Project Preparation

    Bridge Design Process

    Iron Springs onD-P

    50-foot span

    Easy access

    Total cost -~$35,000

    Contract

    Maah-Taah-Hey Trail

  • 8/3/2019 Bridge Module

    13/88

    R1 Trails Project Preparation

    Project Initiation and Scope

    Define the User (TMO & ROS)

    Pedestrians

    Stock

    ATVs

    Bicycles

    Administrationvehicles

    Outfitters / otherpermittees

    User affects size, designand cost.

    Bridge many times limitsthe user!

  • 8/3/2019 Bridge Module

    14/88

    R1 Trails Project Preparation

    Project Initiation and Scope

    Force Account or Contract?(Effects design

    decisions!)

    Design (in house or A/E) Complexity of bridge project.

    Availability of Forest or RO Engineers

    Funding Typically, R1 designs are done in house.

    Construction Safety

    Force Account capability, skill level, and availability.

    Complexity of bridge. Funding

    Pros and Cons

  • 8/3/2019 Bridge Module

    15/88

    R1 Trails Project Preparation

    Force Account or Contract?

    Remote siterequired packingall materials.

    Simpleconstruction

    NP has trainedCrews.

    Force Account

    Goat Creek on NP

  • 8/3/2019 Bridge Module

    16/88

    R1 Trails Project Preparation

    Force Account or Contract?

    Bridge part of alarger trailconstruction

    project.

    Short distancefrom trailhead.

    Complicated

    construction

    Contract

    Yellow Mule on Gallatin

  • 8/3/2019 Bridge Module

    17/88

    R1 Trails Project Preparation

    Force Account or Contract?

    Site at trailhead.

    Working overlarge water

    penstock andtracks.

    Needed largeequipment

    Mystic on Custer

    Contract

  • 8/3/2019 Bridge Module

    18/88

    R1 Trails Project Preparation

    Project Initiation and Scope

    SummaryFunction (To bridge or not to bridge)

    Define Users.

    Force Account versus ContractFunding. Project a go or no go?

    May need some preliminary engineering

    this early.Who makes these decisions?

  • 8/3/2019 Bridge Module

    19/88

    R1 Trails Project Preparation

    Location / Survey

    Location Narrowest spot?

    Not necessarily

    Stable stream reach.

    Where users want it!Good trail

    approaches for user(function for hikers vsstock vs snomobiles vs

    ATVs)

    Survey - Varies Simple small creek

    Profile of trail andstream with few x-sections.

    Sketches

    Complex

    Full site survey ofarea.

    Geotechnical (drilling)

    In general, experiencedbridge engineer may getby with less.

  • 8/3/2019 Bridge Module

    20/88

    R1 Trails Project Preparation

    Location / Survey

    Holter Cut

    on Btr.

    No survey

    done.

    L i /

  • 8/3/2019 Bridge Module

    21/88

    R1 Trails Project Preparation

    Location /Survey

    Little Salmon on

    Flathead in BobMarshall.

    Full site survey

    completed.

    Needed for

    hydraulic analysis.

  • 8/3/2019 Bridge Module

    22/88

    R1 Trails Project Preparation

    Preliminary Design

    Determine Span

    Height

    Width

    Bridge Type Foundations

    FA or Contract

    Cost

    FactorsCrossing and height

    Flood waters, Clearance

    User

    Span, location, aestheticsSite geology

    See earlier slide

    All of the above.

  • 8/3/2019 Bridge Module

    23/88

    R1 Trails Project Preparation

    Preliminary Design

    Two biggest problems in R1

    Bridges too short.Abutments scour and fail

    Resource damage

  • 8/3/2019 Bridge Module

    24/88

    R1 Trails Project Preparation

    Preliminary Design

    Bridges are too low!

  • 8/3/2019 Bridge Module

    25/88

    R1 Trails Project Preparation

    Preliminary Design

    Sill-Thru

    Configuration

    Little work inwater.

    Hydraulicallyefficient. (lesssusceptible toscour).

    More $ in

    superstructure,less in abutments.

    No wingwallsneeded.

  • 8/3/2019 Bridge Module

    26/88

    R1 Trails Project Preparation

    Preliminary Design

    Vertical WallConfiguration

    More work inwater.

    Hydraulically less

    efficient. (moresusceptible toscour).

    Less $ insuperstructure,

    more inabutments.

    Need wingwalls

  • 8/3/2019 Bridge Module

    27/88

    R1 Trails Project Preparation

    Preliminary Design

    Span Length

    Field Estimate (Rule of Thumb) typicalspill-thru bridge.

    Estimated Span Length (L) = BW + 3 x BH BW Channel bottom width

    BH Bridge height from channel bottom to trail tread.

    Span Length (L)

    BH

  • 8/3/2019 Bridge Module

    28/88

    R1 Trails Project Preparation

    Preliminary Design

    Span LengthField estimate must be verified on paper.

    Do not undersize.

    Better to spend more on span than abutments.

    Evaluate existing bridge (did it function OK)

    Iterative process with what?

    Bridge height

    What controls bridge height?

  • 8/3/2019 Bridge Module

    29/88

    R1 Trails Project Preparation

    Preliminary Design

    What controls bridgeheight? Trail height

    Bridge structure

    depth Rule of thumb

    1/20 x span

    Clearance for debris

    Minimum 2 feet

    above high water(100 yr flood) tobottom of bridge.

    Little Salmon on Flathead

  • 8/3/2019 Bridge Module

    30/88

    R1 Trails Project Preparation

    Preliminary Design

    Span Length Vertical Wall abutment

    Span Length = Bankfull +. Must be able to passflood without damage to bridge or stream.

    Footings must be below stream bed as minimumunless on bedrock.

    Span Length (L)

    BH

  • 8/3/2019 Bridge Module

    31/88

    R1 Trails Project Preparation

    Preliminary Design

    Factors for Bridge Width

    - Users

    - Railing

    Bridge w/o railing

  • 8/3/2019 Bridge Module

    32/88

    R1 Trails Project Preparation

    Preliminary Design

    Variable widths Single log14

    Stock w/railing8

    Snowmobile16+

    Manual guidancebut can beanything.

    Bridge with railing

  • 8/3/2019 Bridge Module

    33/88

    R1 Trails Project Preparation

    Preliminary Design Bridge Types

    Single Log

    Timber stringer

    Glu-lam stringer

    Truss

    Suspension

    Packable

    FactorsSpan Access

    Aesthetics Materials

  • 8/3/2019 Bridge Module

    34/88

    R1 Trails Project Preparation

    Preliminary Design

    Foundations

    Spread footings

    Gabions

    Geocell

    Walls

    Generally we use spill-thru configurationwith timber sill on gabion or geocell.

    Factors

    Site geology

    Site materials

    Access

    Scour Potential

  • 8/3/2019 Bridge Module

    35/88

    R1 Trails Project Preparation

    Preliminary Design

    CostsVery difficult to estimate.

    No rules of thumb.

    Procedure Take off and price materials (variable)

    Crew up labor. $2500/day for crew of 4 with misc.tools/equipment

    Or use Davis Bacon rates

    Estimate Equipment needed (cranes,backhoe, helicopter)

  • 8/3/2019 Bridge Module

    36/88

    R1 Trails Project Preparation

    Preliminary Design

    Costs - continuedMaterials

    Sawn Timber $1350/mfbf

    GL timber $2500/mfbf

    Bolts/hardware $3.00/lbs.

    Concrete $600 - $1000/cy

    Reinforcing Steel $1.25/lb

    Gabions $125/cy

    Geocell $15/cy

    Geocell fill $25-$75/cy

  • 8/3/2019 Bridge Module

    37/88

    R1 Trails Project Preparation

    Preliminary Design

    Costs - continued Equipment

    Excavator $130/hr

    Backhoe $80/hr

    Dump Truck $75/hr

    Crane (Light) $350/hr

    Crane (medium) $650/hr

    Helicopters See later slides

    Packing $225/mule trip

    (180 lbs per mule)

  • 8/3/2019 Bridge Module

    38/88

    R1 Trails Project Preparation

    Preliminary Design

    Typical work items toaccomplish for labor. Project Management

    Mobilization Excavation

    Build Abutments

    Install Superstructure

    Build Approach walls Build Approach fills

    Less Common WorkItems Helicopter use.

    Packing Materials Supply Camp

    Install Falsework.

  • 8/3/2019 Bridge Module

    39/88

    R1 Trails Project Preparation

    Preliminary Design

    Nail Lam built 15years ago.

    Replace with glu-lam stringer bridge.

    On sills. Wilderness

    Use Helicopter to flyin stringers.

    Estimate based onContractConstruction

    Flood Creek Custer

  • 8/3/2019 Bridge Module

    40/88

    R1 Trails Project Preparation

  • 8/3/2019 Bridge Module

    41/88

    R1 Trails Project Preparation

    Preliminary Design

    Whose Responsibility / Authority forpreliminary decisions?

    Forest!

    However, Engineering must assist!

    Why?

    Call FE and or RO during Project Scope for

    assistance with alternatives and options.Meet with Rec staff and Ranger to discuss

    preliminary design options and alternatives.

  • 8/3/2019 Bridge Module

    42/88

    R1 Trails Project Preparation

    Preliminary Design

    At this point

    Re-evaluate Project Scope!

    Re-evaluate Funding!

    Why?

    Many times each site has severalalternatives being evaluated.

    Must select Final Design Alternative.

  • 8/3/2019 Bridge Module

    43/88

    R1 Trails Project Preparation

    Final Design, PS&E

    Typically done by Engineering

    Plans (as a minimum)

    Title Sheet (signatures)

    Bridge Layout (Plan and Elevation)

    On site plan from survey.

    Abutment/foundation details

    Superstructure details

    Miscellaneous details

  • 8/3/2019 Bridge Module

    44/88

    R1 Trails Project Preparation

    Final Design, PS&E

    Specifications

    FP-03, Standard Specifications forConstruction of Roads and Bridges onfederal Highway Projects.

    Special Project Specifications asneeded.

  • 8/3/2019 Bridge Module

    45/88

    R1 Trails Project Preparation

    Final Design, PS&E

    Estimates

    Estimated Construction Costs

    Update of preliminary estimate

    Estimated Schedule for Construction

  • 8/3/2019 Bridge Module

    46/88

    R1 Trails Project Preparation

    Final Design, PS&E

    Plans, Specs and EstimatesAll 3 required.

    Any difference for Force Account vsContract?

    Shouldnt be!

    Authorities

    Regional Engineer must approve PS&E

    package, UNLESS Using Standard Plans, then FE has authority

    to approve PS&E package.

  • 8/3/2019 Bridge Module

    47/88

    R1 Trails Project Preparation

    Construction

    All Trail Bridge Construction is to beadministered and inspected by

    Certified COR, Level III

    With appropriate technical endorsements.

    Any difference for Force Account vsContract?

    NO!

    RO will assist as needed or requested.

  • 8/3/2019 Bridge Module

    48/88

    R1 Trails Project Preparation

    Trail Bridge Standard Plans

    Pre-designedand detaileddrawings for:

    Typical TrailBridgeSuperstructures

    Typical simplesubstructures

    (sills).

    Iron Springs on Maay-Daay-Hey Trail

  • 8/3/2019 Bridge Module

    49/88

    R1 Trails Project Preparation

    Trail Bridge Standard Plans

    Intended Uses Simple, single spans

    Spans less than 60 feet

    Adapted for each site.

    FE can approve.

    Limitations At discretion of FE only.

    Not for complex bridges.

    Not for difficultabutments.

    Still requires, survey,hydraulic analysis, soils,etc.

  • 8/3/2019 Bridge Module

    50/88

    R1 Trails Project Preparation

    Trail Bridge Standard Plans

    Typical Superstructures: Drawing #

    Solid Sawn Timber Stringer R1920

    Log Stringer R1921

    Glu-lam timber stringer R1922

    Glu-lam longitudinal slab R1923 Single log R1924

    Nail-lam longitudinal slab R1925

    Prefabricated steel truss R1926

    Packable spliced stringer R1927

  • 8/3/2019 Bridge Module

    51/88

    R1 Trails Project Preparation

    Trail Bridge Standard Plans

    Typical abutment details Drawing #Various types of sills used R1930-34

    Will need to be customized for each site.

  • 8/3/2019 Bridge Module

    52/88

    R1 Trails Project Preparation

    Trail Bridge Standard Plans Sawn Timber Stringer

    Spans 10 to 40 feet

    Any width

    Stringers 3x10 to 8x24

    ROS - ???

    Economical if you haveused stringers.

    But stringer quality largethan 4x10 gets iffy.

    Costs increase

    significantly with largerstringers.

    Trail Bridge Standard Plans

  • 8/3/2019 Bridge Module

    53/88

    R1 Trails Project Preparation

    Trail Bridge Standard PlansSawn Stringer

  • 8/3/2019 Bridge Module

    54/88

    R1 Trails Project Preparation

    Trail Bridge Standard Plans

    Log Stringer

    Spans 10 to 45 feet.

    Any width.

    Diameter from 8 to

    22 ROS ???

    Costs are higherThan other types for

    similar spans.More difficult to build

    and maintain.

    Trail Bridge Standard Plans

  • 8/3/2019 Bridge Module

    55/88

    R1 Trails Project Preparation

    Trail Bridge Standard PlansLog Stringer

  • 8/3/2019 Bridge Module

    56/88

    R1 Trails Project Preparation

    Trail Bridge Standard Plans Glu-laminated Stringer

    Spans 25 to 60 feet.

    Any width.

    Stringers 3.125 x 15 to8.75 x 39.

    Requires diaphragms. ROS - ????

    Most ecomomical forspans 40 feet or longer.

    Easy construction but

    requires larger equipment. Low maintenance.

    Trail Bridge Standard Plans

  • 8/3/2019 Bridge Module

    57/88

    R1 Trails Project Preparation

    Trail Bridge Standard PlansGL Stringer

  • 8/3/2019 Bridge Module

    58/88

    R1 Trails Project Preparation

    Trail Bridge Standard Plans GL Longitudinal Slab

    Spans 10 to 35 feet.

    Best for widths < 8.

    Come in panels, max4 width.

    ROS - ??? Very ecomomical

    Easy to build.

    Low maintenance

    Handrail more difficult

    to attach.

    Trail Bridge Standard Plans

  • 8/3/2019 Bridge Module

    59/88

    R1 Trails Project Preparation

    Trail Bridge Standard PlansGL Longitudinal Slab

    T il B id S d d Pl

  • 8/3/2019 Bridge Module

    60/88

    R1 Trails Project Preparation

    Trail Bridge Standard Plans

    Single Log Stringer

    User is hiker only.

    Spans 10 to 45 feet.

    Diameters 16 to 24

    ROS ???.

    Handrail is hard toattach and align.

    Handrail may bemaintenanceproblem.

    Trail Bridge Standard Plans

  • 8/3/2019 Bridge Module

    61/88

    R1 Trails Project Preparation

    Trail Bridge Standard PlansSingle Log

    T il B id S d d Pl

  • 8/3/2019 Bridge Module

    62/88

    R1 Trails Project Preparation

    Trail Bridge Standard PlansNail-Lam Longitudinal Slab

    Spans 12 to 30 feet.

    Best for widths < 8.

    Materials 2x6 to 2x14.

    ROS - ???

    Labor intensive.

    Materials less expensive butlabor is higher.

    Good for sites shortdistance from trailhead butnot accessible for

    equipment Moderate maintenance.

    Handrail difficult to attach.

    Trail Bridge Standard Plans

  • 8/3/2019 Bridge Module

    63/88

    R1 Trails Project Preparation

    Trail Bridge Standard PlansNail Laminated Slab

  • 8/3/2019 Bridge Module

    64/88

    Trail Bridge Standard Plans

  • 8/3/2019 Bridge Module

    65/88

    R1 Trails Project Preparation

    Trail Bridge Standard PlansPrefabricated Truss

    T il B id St d d Pl

  • 8/3/2019 Bridge Module

    66/88

    R1 Trails Project Preparation

    Trail Bridge Standard Plans Packable Bridge

    Span 36 feet or less.

    Any width.

    ROS - ???

    Alternative to

    helicopter use. Expensive materials.

    Labor intensive.

    More difficult to

    build. Increased

    maintenance.

    Trail Bridge Standard Plans

  • 8/3/2019 Bridge Module

    67/88

    R1 Trails Project Preparation

    Trail Bridge Standard PlansPackable Bridge

    T il B id St d d Pl

  • 8/3/2019 Bridge Module

    68/88

    R1 Trails Project Preparation

    Trail Bridge Standard Plans

    Abutment Details Sill designs - Spill-thru

    Keep away from streamedge.

    Not applicable if scour

    issues. Do not stack sills to gain

    height.

    Place on geocell, gabion,or concrete pad.

    Need to be site adapted.

    Ti b C ibbi & R k G bi

  • 8/3/2019 Bridge Module

    69/88

    R1 Trails Project Preparation

    Timber Cribbing & Rock Gabions

    Sill on Gabion

    Sill on Timber crib on geocell

    Oth T il B id T

  • 8/3/2019 Bridge Module

    70/88

    R1 Trails Project Preparation

    Others Trail Bridge Types

    Timber Truss Spans 50 to 100+

    feet.

    Any width

    ROS ???

    Labor intensive.

    Difficult to build

    Moderatemaintenance.

    Can be built withsemi- primitive toolsor heavy equipment.

    Others Trail Bridge Types

  • 8/3/2019 Bridge Module

    71/88

    R1 Trails Project Preparation

    g ypTimber Truss

    Others Trail Bridge T pes

  • 8/3/2019 Bridge Module

    72/88

    R1 Trails Project Preparation

    Others Trail Bridge Types

    SuspensionBridges

    Spans > 100 feet

    Up to 8 feet.

    ROS ??? Very difficult to

    build.

    Very high

    maintenance. Very high cost

    General Guidance

  • 8/3/2019 Bridge Module

    73/88

    R1 Trails Project Preparation

    General Guidance

    Trail Types Clear width Rail HeightHiking 4 42

    Mountain Biking 4 54

    Pack and Saddle 5 w/o rail6 w/rail 54

    Cross Country Skiing 6 42

    Snowmobile 6 Site specific

    Motorcycle 42 42

    ATV 50 27

    General Guidance

  • 8/3/2019 Bridge Module

    74/88

    R1 Trails Project Preparation

    General Guidance

    Railing Are they needed?

    Proposed manual direction says:In general, rails shall be required for all trail and pedestrian bridges.However, railings may be eliminated and potentially curbssubstituted for rails when an appropriate analysis as describedbelow has been completed:

    An analysis has identified and evaluated the potential users anddetermined that the potential hazards along the trail are the same orgreater than that of a bridge without a rail. The analysis shallinclude the possibility of using a rail on only one side of the bridge.

    In general, rural and urban ROS settings are likely to have smallchildren and less experienced users. Thus, a railing is warranted inmost instances. In backcountry or wilderness settings, where users

    are normally more experienced, rails may not be needed.

    General Guidance

  • 8/3/2019 Bridge Module

    75/88

    R1 Trails Project Preparation

    General GuidancePettibone to left, Goat to

    below on NP. Selwaywilderness.

    General Guidance

  • 8/3/2019 Bridge Module

    76/88

    R1 Trails Project Preparation

    General Guidance

    Dome Mtn.

    Kootenai.

    Cabinet

    Wilderness

    No

    Handrail!

  • 8/3/2019 Bridge Module

    77/88

    R1 Trails Project Preparation

    Type ROS Spans Equipment Maint. Cost

    Sawn Stgr. 10 to 40 Light Low Low/Med

    Log Stgr. 10 to 45 Light/Med Low Low/Med

    GL Stgr. 25 to 60 Medium Low Low/Med

    GL Slab 10 to 35 Light Low Low

    Single Log 10 to 45 Primitive/Light Low Low

    NL Slab 12 to 30 Primitive/Light Moderate Medium

    Steel Truss > 60 Heavy Low High

    Packable < 36 Primitive/Light Moderate HighTbr. Truss > 60 Light/Heavy Moderate High

    Suspension > 100 Medium High High

    General Guidance

    Wilderness Trail Bridges

  • 8/3/2019 Bridge Module

    78/88

    R1 Trails Project Preparation

    Wilderness Trail Bridges

    Unique

    What isappropriate?

    What can youbuild?

    Is a bridgeneeded?

    Bob Marshall Wilderness

    Wilderness Trail Bridges

  • 8/3/2019 Bridge Module

    79/88

    R1 Trails Project Preparation

    Wilderness Trail Bridges

    Design Process

    Add conceptualdesign before Project

    Scope Need alternatives

    Bridge Type

    Construction methods

    Materials

    Costs

    Conceptual Design

    Project Scope

    Location/Survey

    Wilderness Trail Bridges

  • 8/3/2019 Bridge Module

    80/88

    R1 Trails Project Preparation

    Wilderness Trail Bridges

    Minimum Tool analysis.

    Use of helicopters

    Force Account or Contract. Logistics!!

    Wilderness bridges are the most complicatedand expensive. Need special attention.

    Helicopter Usage

  • 8/3/2019 Bridge Module

    81/88

    R1 Trails Project Preparation

    Helicopter Usage

    Helicopter contracts

    Type I (Heavy) Sky cranes, etc

    Can pick up to 25,000 lbs.

    On call contract $9000/hour

    Must come out of West Coast. Mob costs prohibitive.

    Type II (Medium)

    5000 to 12,000 lbs.

    On call contract $4500/hour

    Several in Montana, but not readily available.

    Helicopter Usage

  • 8/3/2019 Bridge Module

    82/88

    R1 Trails Project Preparation

    Helicopter Usage

    Helicopter contractsType III( Light)

    Can pick up to 5000lbs.

    On call contract $1800/hour For up to 3000 lbs, readily available.

    Need to plan ahead and try to coordinate

    with other work in the area to lower costs.

    Helicopter Usage

  • 8/3/2019 Bridge Module

    83/88

    R1 Trails Project Preparation

    Helicopter Usage

    Helicopter Use - best value?

    Small helicopter

    More trips More on-site labor (fly one stringer at a time)

    Big Helicopter

    Less trips.

    Less on site labor (fly in entire bridgesuperstructure)

    Preservative Treatments

  • 8/3/2019 Bridge Module

    84/88

    R1 Trails Project Preparation

    Preservative Treatments

    What is lifeexpectancy ofpermanent bridge?

    Life of untreatedmaterial?

    15 to 20 years

    Life of treatedmaterial?

    50 + years

    Preservative Treatments

  • 8/3/2019 Bridge Module

    85/88

    R1 Trails Project Preparation

    Preservative Treatments

    Treated vs Untreated. Manual Direction fpr

    permanent structures

    design life of 50 yrs

    However, exceptions aremade.

    Who decides?

    Forest

    Treated material isstrongly recommended.

    Papoose Creek on Clwt NF

    Preservative Treatments

  • 8/3/2019 Bridge Module

    86/88

    R1 Trails Project Preparation

    Preservative Treatments

    Protect the integrity ofTreatment. Cutting ends, drilling

    holes, all ruins treatment.

    Field treatments havelimited success.

    To apply fieldtreatments, person

    needs training andcertification. Hassle!Blue Sky Bridge on Ktn NF

  • 8/3/2019 Bridge Module

    87/88

    Preservative Treatment

  • 8/3/2019 Bridge Module

    88/88

    Preservative Treatment Options

    Substructure,stringers, deck,curbs Penta, Copper

    Naphthenate

    Handrail Treated many

    choices

    Untreatedredwood or RedCedar

    Changing constantlyIron Springs - DPGL