Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Cop
yrig
ht:
SIPC
Shell Exploration and Production Europe
Brent Facilities Decommissioning
Project Overview
(Shell is operator of the Brent Field for and on behalf of Shell U.K. Limited and Esso Exploration and Production UK Limited .)
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 2
Context
• The project is at a very early stage.
• Feasibility studies are still being put together.
• The scope is still being defined.
• The strategy is still to be finalised.
• We are seeking input and listening.
• This is an opportunity to influence direction.
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 3
Where is the Brent Field ?
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 4
Overview of Brent Field…
~160 wells4 topsides1 steel jacket3 GBS~36 pipelines2 subsea locations
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 5
Brent Field History…
• License partners – Shell 50% , Esso 50% (1965 Agreement)
• Discovered 1971, 1.96 billion bbls oil and 5.69 trillion cu.ft gas produced (to 1.1.06)
• First production from Brent Bravo in 1976
• Continuous innovation in reservoir management
– Oil recovery with pressure maintenance
– Gas export
– LTFD project (£1.3 bln, 3 platforms) – reservoir depressurisation
– Penguins field development – longest subsea tie-back @ 65kms
– Enhanced Voidage project – increased depressurisation by water production
– Low Pressure Operation project – LP compression
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 6
Brent Alpha – a steel jacket substructure platform… On 5th May 1976 the 13,000 ton Brent `A' jacket was
towed from the construction yard of RedpathDorman Long (North Sea)Ltd., Methil, Fife, Scotland.
Supported on two barges in a catamaran arrangement, the 500 foot high jacket was towed about three miles offshore. Here it was released from the barges and taken in tow under it`s own buoyancy for the journey to Shell/Esso`s Brent oilfield 112 miles northeast of Sheland.
The first three half modules were installed in the deck of Brent `A' during February 1977.
Topsides installed weight is about 16,000te
The platform currently exports all its well production over to the Brent B platform for processing.
The Western Leg and Northern Leg gas pipelines come up onto the platform topsides where they are co-mingledbefore going back down to the seabed where they join the FLAGS pipeline to St Fergus.
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 7
Brent C – a concrete GBS platform...
The Shell/Esso Brent `C' gravity base storage platform has a total concrete weight of 282,000 tons and was constructed at the Sir Robert McAlpine & Sons yard, west coast of Scotland site at ArdynePoint. The base caisson contains 36 storage cells capable of holding 660,000 barrels of oil.
On 4th February 1978 the 6,400 ton deck substructure for the production platform left the Penn and Bauduin yard at Dordrecht for Stavanger in Norway. There it was mated with the submerged Brent `C' substructure.
Some 20 lifts were scheduled to place modules and facilities in position before the platform was due for tow-out to the North Sea at the beginning of June 1978.
Topsides installed weight is about 30,000te.
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 8
Brent B & D – concrete GBS platforms...
Brent ‘B’ and ‘D’ platforms are of the sameCondeep design.
The deck substructures were mated with the concrete substructures in Norway before being towed to the field for final installation.
The 348,000 ton concrete and steel ‘B’platform, was towed by five tugs with a combined horsepower of 70,000. Even with a towing draught of 260 feet the structure towers 420 feet above the water, the height of a 30 storey building.
Additional modules were added to the ‘B’production platform by the derrick barge Hercules - June 1976.
Topsides weights are about 24,000 te.
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 9
End of Field Life...
Status
• The Brent field is currently producing some 26000 bpd oil, 183000 bpd of produced water and 260 MMSCFD gas.
• The platforms are occupied by approx 500 people working in shifts at any one time.
• New developments continue to be pursued ie
– Installation of gaslift facilities and 65km pipeline to Penguins subsea field,
– And drilling of the Barnacle well from Brent ‘D’ platform.
Planning
• A team of SUBSURFACE specialists are developing the final field development plan which will be agreed with DTI and will identify Cessation of Production dates for each platform.
• After CoP is agreed with the DTI, a Decommissioning Programme will be submitted covering all Brent facilities i.e all platforms and subsea facilities.
• Well abandonment will start end 2007, ahead of CoP, as there are a large number of non-producing wells already and activity is covered by different regulations (not OSPAR).
• Decommissioning will occur over many years.
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 10
Early Stages of Decommissioning Studies
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 11
Decommissioning Studies
• What are the issues ?
• What is feasible, what is not feasible ?
• Are risks manageable ?
• How do we minimise impact on the environment ?
• Have we identified all the options ? ?
• How should we compare options ?
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 12
Some Topsides Removal Options
Heavy liftPiece small
Reverse float over Single lift
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 13
Some Jacket Removal Options
Reverse installation
buoyancySingle lift
Heavy lift
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 14
Gravity Base Storage
• GBS refloat risks and feasibility issues
– Reaction of GBS to breaking loose from seabed.
– Structural integrity of GBS under refloat conditions
– Weather during transit
– Landing and Dismantling the GBS
• GBS cell contents
– Determine the contents and inventory
– Access via shaft pipework (10”)
– Sampling
– Remediation methodology – to what degree is sufficient
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 15
Drill Cuttings
• Drill cuttings survey 1997 & 2005
• New survey planned end 2006….(now 2007)
• Focus on chemical analysis, volumetrics, coverage under jacket and on cells
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 16
Brent Pipelines
• There are a large number of pipelines connecting the Brent platforms to each other;
– Gas
– Oil
– Water
– Mixed oil,gas and water
• There are also pipelines connecting Brent platforms to gas and oil gathering systems some of which need to retain their functionality;
– Gas export to St Fergus
– Oil export (via Cormorant Alpha) to Sullom Voe terminal
• Also...
– operational pipelines to Penguins subsea field
– Redundant pipelines to Brent South subsea field, the Brent Spar and Flare.
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 17
Brent Pipelines
Background
• Technical challenge of removal
• Condition of concrete coatings
• Impact on environment and other sea users
Options
• Complete removal
• Lines trenched and buried
• Lines on the seabed.
• Reconfiguration of pipelines for oil and gas transport by others
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 18
Waste Disposal
Background
• Understand and quantify the waste inventory
• Options available under current (and future) legislation
• Impact on the environment
Challenges
• Capacity and availability of existing waste disposal routes
• Transfrontier shipment of waste - in an EU perspective ?
• OSPAR 2008 and subsequent reviews
Brent Decommissioning will be a long term project….
• …how best to develop agreed plans and commitments in a developing regulatory environment ?
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 19
In summary….
• Early days ….still a long road ahead.
• Actively working to promote openness and transparency in our processes.
• We are keen to look for opportunities to extend the technical envelope and apply innovative solutions.
• The scale of Brent Decommissioning may create resource and regulatory challenges. We will work with industry, regulators and stakeholders to address these.
• The project has full management involvement, within Shell and Esso, as befits a billion pound project.
16 &18 January 2007 Stakeholder Engagements, Aberdeen & London 20
Shell Exploration & Production
Cop
yright: Sh
ell E
xploratio
n & Produ
ction Ltd.
Brent Facilities DecommissioningRegulatory Framework & Option Selection Process
January 2007
Shell Exploration & Production
-1-
Regulatory Framework
Decommissioning Regulation
• International
– IMO Guidelines.
• Regional
– OSPAR 98/3.
• UK
– Petroleum Act 1998 enabling Act requires submission of detailed Programme for approval.
– DTI Guidelines (2006)provides framework.
Shell Exploration & Production
-2-
Regulatory Framework
Installations
• OSPAR 98/3 Presumption of Total Removal
• Waste Hierarchy Re-Use/ Recycle/ Dispose
• Right to derogate for certain categories by comparative assessment:
– GBS
– Steel Jacket > 10,000 tonne Footings
– Damage
Shell Exploration & Production
-3-
Regulatory Framework - Experience
Installation Status
• Small/Med Experience: Leman – Odin – Froy
• Some larger ‘Unique’: Spar – Maureen – Hutton tlp
• Ekofisk: First Concrete Tank Derogation accepted Execution Ongoing –15 platforms to be removed (<10,000tn)
• Frigg: Concrete GBS derogation accepted - 4 concrete platforms. 3 steel jackets to be removed (<10,000tn)
• BP NW Hutton: First steel derogation (>10,000tn)– approval to leave lower section
Shell Exploration & Production
-4-
Regulatory Framework - Experience
- NW Hutton Steel Jacket DerogationUK Sector
- Frigg Area 4 Concrete DerogationNorwegian/UK Sector(3 Steel Installations Removed)
- Ekofisk Concrete Tank DerogationNorwegian Sector(15 Steel Installations Fully Removed)
Shell Exploration & Production
-5-
Regulatory Framework
Historic Cuttings Piles
• OSPAR Recommendation 2006
• UK/Norway issue
• Proactive UKOOA R&D programme in conjunction OLF
• Options
– natural attenuation/ cover/ re-inject?/ return to shore & landfill
• Key is good characterisation – need to survey and understand behaviour
– hydrocarbon leaching and persistence key parameters
Shell Exploration & Production
-6-
Regulatory Framework
Pipelines
• DTI Guidance/ Approval
• Case by Case
• Comparative Assessment – balance env/safety/cost/feasibility
• Criteria – cleanliness/ stability/ burial/ other users
Shell Exploration & Production
-7-
Regulatory Framework - Experience
Pipeline Status
• Varied but limited outcomes
– Some left;
– Some lifted where reel-able or short lengths
– Trenched or buried more obvious leave candidates
• Consider as Future Assets?
Shell Exploration & Production
-8-
Regulatory Framework
Wells
• Not part of Decommissioning Programmes
• Approved separately
• National Guidance by UKOOA accepted by regulators as best practice
Shell Exploration & Production
-9-
Comparative Assessment – A Balanced Judgement
TECHNICAL
Feasibility
Complexity
SOCIAL
Sea Users
Community
ECONOMIC
Cost/Benefit
Uncertainty
SAFETY
Risk Assessment
Implementation
ENVIRONMENTAL
Air
Sea
Land
Reputation
TECHNICAL
Feasibility
Complexity
SOCIAL
Sea Users
Community
ECONOMIC
Cost/Benefit
Uncertainty
SAFETY
Risk Assessment
Implementation
ENVIRONMENTAL
Air
Sea
Land
Reputation
Regulatory Framework – Option Selection
Shell Exploration & Production
-10-
Option Selection Process
Technical Development and Stakeholder Engagement in Parallel
I R G I R G
DTI Approval
Current Status Recommend Option Plan Approved
Ongoing Stakeholder Engagement
Challenge & Assurance on Robustness of Technical Basis
Regular Engagement opportunity to listen/share.Identify Issues
Inform decisions
OPEN
TRANSPARENT
INCLUSIVE
INTEGRATED
Shell Exploration & Production
-11-
Independent Review Group
IRG…an Independent group of experts
• Role appreciated by stakeholders on previous projects
• Independent review of technical scope and conclusions, to provide assurance to technical basis of decisions
• Individuals invited to participate by Prof John Shepherd (Chair)–
– Independent experts – international reputations in key fields of scientific and technical activity
• Retain “freedom to publish” findings