Upload
mr29ricardo
View
241
Download
0
Embed Size (px)
Citation preview
8/10/2019 BRADKEN MOLINOS
1/26
September 3-5, 2008. Santiago, Chile
to Improve the Wear Life in SAGto Improve the Wear Life in SAGMill Feed End LinersMill Feed End Liners
Craig FaulknerBradken, Australia
8/10/2019 BRADKEN MOLINOS
2/26
Contents Introduction
SAG Mill - FE Liner Optimisation and Design
Summary
Conclusion
September 3-5, 2008. Santiago, Chile 2
8/10/2019 BRADKEN MOLINOS
3/26
Introduction Cadia Valley Operations (CVO) consists of two
distinct processing plants
Cadia Hill - Low Grade Plant
Ridgeway - High Grade Plant
September 3-5, 2008. Santiago, Chile 3
16,300 tpd @ 2.4g/t Au and 0.8% Cu
Annual Production:
35,000 t Cu
290,000 oz Au
8/10/2019 BRADKEN MOLINOS
4/26
Ridgeway Operation Semi-Augeounous Grinding
32ft Dia. x 16ft Long SAG Mill
700 t/h new feed
6500 kW
14.5 EGL
September 3-5, 2008. Santiago, Chile 4
. .
62.6 78.6% critical
28% Mill volume
13% Ball charge
125mm Dia. Balls 50mm grate aperture
15mm trommel aperture
Steel liners ( 417 tonne)
8/10/2019 BRADKEN MOLINOS
5/26
FE Liner Optimisation & Design The Drivers
Liner life
Combat excessive wear
Reduce reline times per annum
Improve profitability
September 3-5, 2008. Santiago, Chile 5
8/10/2019 BRADKEN MOLINOS
6/26
Feed End Liner Design Original Design
Typical lifter liner (OEM) design
Three row setup (throat, middle & outer)*Note Throat liner missing from image
September 3-5, 2008. Santiago, Chile 6
8/10/2019 BRADKEN MOLINOS
7/26
Feed End Liner Design Original Design
High wear through joint
Both parts changed-out together
Liner life 120 days (avg.)
2.0 Mt processed
September 3-5, 2008. Santiago, Chile 7
8/10/2019 BRADKEN MOLINOS
8/26
Feed End Liner Design Intermediate Design change
Reduce the length of middle liner
Extend outer to cover full charge volume Increase lifter thickness (40mm) to improve wear life
Reduction in liner bolts from 160 to 128 per reline (20%)
September 3-5, 2008. Santiago, Chile 8
8/10/2019 BRADKEN MOLINOS
9/26
Feed End Liner Design Intermediate Design change
Liner life - 4.4 months & 2,122,801 tonnes
Extra thickness to lifter bar (25mm) Change in CTR bolt position
Extra liner mass
September 3-5, 2008. Santiago, Chile 9
8/10/2019 BRADKEN MOLINOS
10/26
Composite Liner Design Design Criteria
CAD Modeling incorporating DEM output
Achieve 6 month liner life Review alternative wear materials
Safe and Easy to install
September 3-5, 2008. Santiago, Chile 10
Survive SAG milling environment
Manufacturability
8/10/2019 BRADKEN MOLINOS
11/26
Composite Liner Design White-iron insert Chrome Moly liner
September 3-5, 2008. Santiago, Chile 11
8/10/2019 BRADKEN MOLINOS
12/26
Composite Liner Design Implementation
Risk
Trial installation 13-03-07 Inspection & Wear monitoring
September 3-5, 2008. Santiago, Chile 12
8/10/2019 BRADKEN MOLINOS
13/26
Composite Liner Design Liner Inspection
Wear monitoring 31-05-07
Liner predictions
September 3-5, 2008. Santiago, Chile 13
8/10/2019 BRADKEN MOLINOS
14/26
8/10/2019 BRADKEN MOLINOS
15/26
Composite Liner Design Full Implementation
Set installed 13-11-07
White-iron performance Liner results
September 3-5, 2008. Santiago, Chile 15
8/10/2019 BRADKEN MOLINOS
16/26
Composite Liner Design Full Implementation
Liner Inspections
September 3-5, 2008. Santiago, Chile 16
18-02-08 (3.0 months) 30-04-08 (5.5 months)
8/10/2019 BRADKEN MOLINOS
17/26
Composite Liner Design Full Implementation
Liners removed 20-05-08
6.2 months life (189 days) 2,985,348 tonnes milled
September 3-5, 2008. Santiago, Chile 17
8/10/2019 BRADKEN MOLINOS
18/26
Composite Liner Analysis Wear Analysis Chrome-moly liner
Laser scanning
Mass reduction Rate of wear
September 3-5, 2008. Santiago, Chile 18
Part No. Material Installed Removed
Life
(Days)
Life
(Months)
Installed
Tonnes
Removed
Tonnes
Period
Tonnes
Tonnes
per Day
BK53212A Chrome-moly 24/07/2007 13/11/2007 112 3.7 29,184,335 30,973,378 1,789,043 15,974
8/10/2019 BRADKEN MOLINOS
19/26
Composite Liner Analysis Wear Analysis Chrome-moly liner
Mass New 1974
Worn 1420
Mass Reduction Kg's 554
% 28%
Installed Height mm 395
Removed Height mm 150
Material Worn mm 245
mm per MT 136.94
September 3-5, 2008. Santiago, Chile 19
.
8/10/2019 BRADKEN MOLINOS
20/26
8/10/2019 BRADKEN MOLINOS
21/26
8/10/2019 BRADKEN MOLINOS
22/26
Composite Liner Analysis Wear Analysis
Feed End Liner Analysis
300
350
400
450
ss
2500000
3000000
3500000
d
September 3-5, 2008. Santiago, Chile 22
0
50
100
150
200
250
0 112 189
Days in Service
LinerThickn
0
500000
1000000
1500000
2000000
TonnesM
ill
CrMo WI Composite CrMo - Tonnes WI Composite - Tonnes
8/10/2019 BRADKEN MOLINOS
23/26
Summary Results
Achieved 6 month relines
Reduction in one reline per year Reduced overall annualised reline times by 24 hours
Increased wear life by 68.75%
September 3-5, 2008. Santiago, Chile 23
Liner Description uan y
Per Set
ner ass
Per Set (kg's)
ange-ou me
Per Set (Hours)
ear e
(Months)
nnua se
Change-out Time (Hours)Feed End
Middle Liner 16 24,000 4.53 3.8 14.3
Outer Liner 32 44,880 9.07 3.8 28.668,880 43
REVISION 2
Liner Description uant ty
Per Set
ner ass
Per Set (kg's)
ange-out me
Per Set (Hours)
ear e
(Months)
nnua se
Change-out Time (Hours)
Feed End
Middle Liner 16 10,816 4.53 42.7 1.3
Composite Outer Liner 32 62,080 9.07 6 18.172,896 19
8/10/2019 BRADKEN MOLINOS
24/26
Conclusion
September 3-5, 2008. Santiago, Chile 24
8/10/2019 BRADKEN MOLINOS
25/26
8/10/2019 BRADKEN MOLINOS
26/26
Acknowledgements Bradken
Newcrest Mining Cadia Valley Operations
September 3-5, 2008. Santiago, Chile 26
Notice:The Design and Technical information as detailed in this document is the exclusive property of the Bradken Pty. Ltd. and its relatedentities. It is issued on the strict condition that except with our written permission it must not be reproduced, copied or communicated toany third party nor be used for any purpose other than that stated in the particular enquiry or contract with which it is issued.
THANK YOUTHANK YOU