BPVC I Interp Stnd 62 2012 Jul

Embed Size (px)

Citation preview

  • 7/30/2019 BPVC I Interp Stnd 62 2012 Jul

    1/3

    SECTION I

    Subject Interpretation File No.PG-67.2.6, Isolable Economizer Pressure Relief Valve

    Capacity Requirements (2010 Edition) .................................................... I-10-26 11-514

    PW-11, PW-40.1, PW-52, PFT-11.4, NondestructiveExamination of Butt Welds (2010 Edition) .............................................. I-10-27 11-557

    PG-109 and PG-112.2.5, Certification and Stampingof Power Piping (2010 Edition) .............................................................. I-10-28 11-1961

  • 7/30/2019 BPVC I Interp Stnd 62 2012 Jul

    2/3

    Interpretation: I-10-26

    Subject: PG-67.2.6, Isolable Economizer Pressure Relief Valve Capacity Requirements (2010 Edition)

    Date Issued: July 18, 2011

    File No.: 11-514

    Question: If the Manufacturer predicts that the fluid relieved from an economizer during overpressure conditions

    will be water, does the last sentence of PG-67.2.6 allow the Manufacturer to select relieving capacity based on water

    service only, in lieu of maximum expected heat absorption in Btu/hr (W) divided by 1,000 (646), as long as this is

    sufficient to prevent the pressure from exceeding the limits of PG-67.2?

    Reply: No, the relieving capacity shall be selected to satisfy both conditions.

    Interpretation: I-10-27

    Subject: PW-11, PW-40.1, PW-52, PFT-11.4, Nondestructive Examination of Butt Welds (2010 Edition)

    Date Issued: July 18, 2011

    File No.: 11-557

    Question (1): Do the UT acceptance/rejection criteria of PW-52.3.1 and PW-52.3.2 apply only to those butt welds

    identified in PW-11 and Table PW-11?

    Reply (1): Yes.

    Question (2): Does Section I classify weld joints meeting the requirements of PFT-11.4 as butt joints?

    Reply (2): No.

    Question (3): Does Section I have rules establishing when a visual examination such as that mentioned in

    PW-40.1 is to be performed?

    Reply (3): No.

    Question (4): Does Section I classify the hydrostatic test required by PG-99 as a nondestructive examination?

    Reply (4): No.

  • 7/30/2019 BPVC I Interp Stnd 62 2012 Jul

    3/3

    Interpretation: I-10-28

    Subject: PG-109 and PG-112.2.5, Certification and Stamping of Power Piping (2010 Edition)

    Date Issued: November 17, 2011

    File No.: 11-1961

    Background: Portions of a pressure piping system were shop fabricated and documented on P-4A Manufacturers

    Data Report for Fabricated Piping. A portion of the pressure piping system had been field installed by one certificate

    holder. A second certificate holder completed the installation of the piping system.

    Question (1): For the scenario above, if the first certificate holder has certified his work on a P-4A

    Manufacturers Data Report, may the second certificate holder issue a P-4A Manufacturers Data Report,

    referencing the P-4A forms from the first certificate holder and the P-4A forms for the shop fabrication, certifying

    the pressure piping system and apply the Certification Mark to the piping system?

    Reply (1): Yes.

    Question (2): For the scenario above, if the first certificate holder has not certified his work on a P-4AManufacturers Data Report, may the Authorized Inspector for the first certificate holder issue a P-4A certifying the

    certificate holders work?

    Reply (2): No.

    Question (3): For the scenario above, if the first certificate holder has not certified his work on a P-4A

    Manufacturers Data Report, may the second certificate holder issue a P-4A Manufacturers Data Report,

    referencing the P-4A forms for the shop fabrication, certifying the pressure piping system and apply the Certification

    Mark to the piping system?

    Reply (3): No.