Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
BOWIE STATE
UNIVERSITY FINE AND PERFORMING ARTS
CENTER
Final Report
Zack Lippert – Mechanical
Advisor: Steve Treado
Location: Bowie, MD
April 4th, 2012
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
2
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
3
Contents Executive Summary ......................................................................................................................... 5
Building Overview and Existing Conditions .................................................................................... 6
Electrical/Lighting System ........................................................................................................... 6
Structural System ........................................................................................................................ 6
Construction ................................................................................................................................ 7
Sustainability Features ................................................................................................................ 7
Transportation System ................................................................................................................ 7
Existing Mechanical System Summary............................................................................................ 7
Design Objectives ........................................................................................................................ 7
Existing Design ............................................................................................................................. 7
Site and Mechanical Systems Cost .................................................................................................. 8
Design Conditions ........................................................................................................................... 9
Design Requirements ...................................................................................................................... 9
Energy Sources and Rates ............................................................................................................. 10
Environmental Impact ............................................................................................................... 11
Energy Analysis Conclusion ....................................................................................................... 11
Systems Operation and Schematics .............................................................................................. 11
Air Side .................................................................................................................................. 11
Water Side ............................................................................................................................. 12
Existing Mechanical System LEED Analysis ................................................................................... 13
Energy and Atmosphere ....................................................................................................... 14
Indoor Environmental Quality .............................................................................................. 16
Proposed Redesign Overview ....................................................................................................... 19
Depth One: Ground Source Heat Pump ........................................................................................ 21
Soil Type ................................................................................................................................ 21
Calculations ............................................................................................................................... 21
Bore Length ........................................................................................................................... 21
Well Field Layout ................................................................................................................... 23
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
4
Pipe and Pump Sizing ............................................................................................................ 24
Energy Model ........................................................................................................................ 30
Depth Two: Underfloor Air Distribution ....................................................................................... 30
Lighting Breadth ............................................................................................................................ 32
Construction Management Breadth ............................................................................................. 35
Redesign Cost and Energy Analysis ............................................................................................... 37
Ground Source Heat Pump ................................................................................................... 37
References .................................................................................................................................... 41
Appendix A: Illuminance Value ..................................................................................................... 43
Appendix B: Commissioning Prefunctional Tests ......................................................................... 45
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
5
Executive Summary
This report investigates the proposed redesign to the Bowie State University Fine and
Performing Arts Center with a focus on reducing the building’s energy consumption. The
building uses a variable air volume system to supply and distribute air to the various spaces.
The air is conditioned by an air cooled chiller and two gas fired boilers. The building is a mixed
use building that contains offices, classrooms, workshops, recital halls and auditoriums.
The first proposed redesign to the mechanical system was incorporating a ground source heat
pump. A large effort was placed on analyzing whether or not a ground source heat pump would
be an effective way to reduce the use of fossil fuels and lower the yearly utility costs. The
system was sized to be able to completely handle both the heating and cooling loads enabling it
to operate year round.
The second change to the mechanical system was the use of an underfloor air distribution
system for the large volume spaces including the auditoriums and recital halls. The underfloor
air distribution lessens the load on the cooling equipment by allowing the supply air to be
delivered at a warmer temperature. A year round analysis was done to determine if the overall
system was more or less efficient.
A lighting analysis was also done to determine if electricity could be saved by using more
efficient luminaires and lamps. Also, occupancy sensors were investigated to determine if they
would be useful in significantly reducing the building’s electricity consumption. All of these
redesigns added to the complexity of the building during both the construction and operating
phases of the project, therefore the commissioning plan was updated to include the redesigns.
Installation and operating costs were analyzed to determine if the proposed systems would
have a reasonable payback period. The ground source heat pump and the underfloor air
distribution did not save enough energy to recover the additional upfront costs and therefore
were not recommended to be used. The lighting redesign and the occupancy sensors both saw
substantial energy savings and would pay for themselves in a reasonable amount of time.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
6
Building Overview and Existing Conditions
Bowie State University’s new Fine and Performing Arts Center is a 123,000 square foot mixed
use building that contains both a 400 and 200-seat theatre, a recital hall, class rooms, offices,
an art gallery, a large atrium and workshops for creating scenery and costumes. The north side
of the building has a large expanse of glass with different colored panes spaced in a pattern to
look like sheet music. The numerous acoustical considerations have made this a wonderful
building to enjoy musical and theatrical performances. Figure 1 shows the layout of the
building. The north section, highlighted in blue, is three stories filled with classrooms and
administrative offices. The south section, highlighted in red, houses the large performance
spaces.
Figure 1: Building Layout
Electrical/Lighting System
The lighting fixtures use fluorescent lamps for the classroom and office areas, and the theatres
have a mix of metal halides and halogens. The electrical system is fed from the main campus
distribution system into a 3000 kVA main transformer. There is a 250 kW gas-powered
generator that serves the emergency lighting.
Structural System
It is a reinforced concrete building with a mix of one-way and two-way slab systems sitting on
CMU bearing walls. However, the upper-level seating in the large theater is structural steel and
the floor is composite slab on metal deck.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
7
Construction
The construction manager for this project was Holder Construction Company. The project
delivery method was a traditional Design-Bid-Build format. Construction began in October 2009
and finished two years later in October of 2011 at a cost of roughly $79 million.
Sustainability Features
Energy efficient lighting was a large part of this project. Energy efficient luminaires and lamps
were used throughout the building. The large two story atrium uses skylights to bring natural
light into the center of the building. The north side of the buildings has a large expanse of glass
to bring daylight into the class rooms and offices.
Transportation System
There are two elevators that serve all floors of the north half of the building. The main theater
has two small elevators that bring people and scenery from the storage areas to the stage.
Existing Mechanical System Summary
Design Objectives
There were several design objectives for the mechanical systems in this building. All of the
spaces had to be provided with adequate ventilation air as required by ASHRAE standards. Also,
the spaces needed to be kept at a certain temperature and humidity to keep the occupants
comfortable, and a good indoor air quality was important as well. All of these objectives were
to be obtained while minimizing the operating costs of the system. The performing spaces
posed a challenge to occupant comfort because there are two groups of people in the same
space; the performers, who would be moving, and exerting energy and the crowd who would
be stationary for the extent of the performances.
Existing Design
There are 3 MAUs with enthalpy wheels that provide ventilation air to the 16 AHUs, which
provide conditioned air to the building through VAV systems. There are two 1,712 MBH gas-
fired boilers and one 305 ton air cooled chiller on site. Tables 1 and 2 show the size and the
area that each AHU and MAU serves.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
8
Unit Area Served Min OA (CFM) Enthalpy Wheel
MAU-1 AHUs-1, 3, 9 9500 Yes
MAU-2 AHUs-2, 7, 10, 14 9030 Yes
MAU-3 AHUs-8, 11, 12 17400 Yes
Table 1: Mixed Air Units
Unit Area Served CFM Min OA (CFM)
Enthalpy Wheel
AHU-1 Main Theater 7000 4000 No
AHU-2 Recital Hall 4850 3700 No
AHU-3 Main Stage 3750 2900 No
AHU-4 Black Box Theater 6200 3500 Yes
AHU-5 Movement Studio 4200 1800 No
AHU-6 Choral Room 1950 900 No
AHU-7 Instrument Ensemble 2700 2700 No
AHU-8 Art Gallery 4500 2900 No
AHU-9 2nd Floor, East 6185 2600 No
AHU-10 2nd Floor, Lobby & Lounge 5500 2250 No
AHU-11 North Wing 1st Floor 9300 4000 No
AHU-12 North Wing 2nd & 3rd Floor 19800 10500 No
AHU-13 West Offices 1900 475 No
AHU-14 Instructional Offices 800 380 No
AHU-15 1st Floor Electrical Room 1600 30 No
AHU-16 3rd Floor Electrical Room 1700 0 No
Table 2: Air Handling Units
Site and Mechanical Systems Cost
There was no upfront cost for the site in this project because it was already own by the
university and it not being used.
The total cost of the mechanical system for this project was $6,781,479 which represents 8.6%
of the overall project cost. For this project, the cost per square foot for the mechanical system
is $55/SF. The majority of this price came from the installation, labor and materials for the
ducts, pipes and wiring. Table 3 shows a breakdown of the overall cost.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
9
Description of Work
Cost
General $1,370,000.00
Major Equipment $2,039,950.00
Installation, Labor and Materials $2,885,050.00
Change Orders $486,479.00
Total $6,781,479.00
Table 3: Mechanical System Costs
Design Conditions
The outdoor design conditions for the BSU Fine and Performing Arts Center are based off of
climate data in the 2009 ASHRAE Handbook Fundamentals from Baltimore, Maryland which is
only thirty miles away from Bowie. Table 4 shows the design temperatures used.
Design Outside Air Temperatures
Dry Bulb Wet Bulb
Summer 91°F 77 °F
Winter 13°F N/A
Table 4: Design OA Temperatures
Design Requirements Ventilation
The BSU Fine and Performing Arts Center requirements for ventilation are defined by ASHRAE
Standard 62.1. The purpose of Standard 62.1 is to set minimum ventilation standards to ensure
that the HVAC systems provide enough outdoor air to increase occupant comfort and well-
being. The amount of ventilation air that is required is based on occupancy, room type and
room area. All of the AHUs for this building were calculated and found to be providing adequate
CFM of outside air.
Heating and Cooling Loads
A Trane Trace model was created for the second technical report to determine the heating and
cooling loads. The results from the load calculations compared to the actual designed values
are provided in Table 5. The peak heating and cooling loads from the Trace calculations are
both much less than the equipment in the building is sized for. An attempt to get the designer’s
load calculations was made but at the time of the publication, they were unavailable.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
10
Peak Heating (MBH)
Peak Cooling (tons)
Supply Air (cfm)
Ventilation Air (cfm)
BSU Trace Model 749.3 211.3 95,012 23,777
BSU Designed 3424 304.9 81,635 42,635
Table 5: Load Calculation Results vs. Actual Design Conditions
Energy Sources and Rates
The rates that were used for the cost estimate were obtained from Baltimore Gas and Electric
(BGE). The rates were used to determine the monthly energy cost for both gas and electric.
Figure 2 shows the total monthly energy cost broken up into electric and gas. The electric
clearly dominates the total monthly costs.
Rate Demand
Natural Gas $0.20/therm N/A
Electricity $0.0927/kWh $3.95/kW
Table 6: Energy Rates
Figure 2: Monthly Utility Costs
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
11
Environmental Impact
An environmental impact analysis was performed as well. Table 7 has the result, showing the
total value for the entire year. It considers three greenhouse gases; CO2, SO2 and NOX.
Environmental Impact
CO2 1,035,798 lbm/year
SO2 8,840 gm/year
NOX 1,872 gm/year
Table 7: Environmental Impact Analysis
Energy Analysis Conclusion
The total amount of energy that the BSU Fine and Performing Arts building uses is 2.73 million
kBTU/year. The natural gas is mainly used for the boiler which provides hot water to the
heating coils. Therefore the natural gas consumption peaks in the winter when heating is
needed. Likewise, the electricity consumption peaked in the summer when the chiller was
working the hardest. The cost analysis showed that the yearly cost for energy in the building is
just under $68,000. The vast majority of the cost comes from electricity which accounts for not
only cooling, but also the lights, receptacles and equipment.
Systems Operation and Schematics
Air Side
The rooms are conditioned through a VAV system. Ventilation air is brought into the space
through 3 make-up air units (MAUs). The air is preconditioned by enthalpy wheels that in
heating mode take heat and moisture from the return air and transfers it to the supply air.
During cooling mode it takes the heat and moisture from the supply air and rejects it to the
exhaust air. The MAUs have heating and cooling coils to further condition the air. Fans with
variable frequency drives (VFDs) then send the air to the AHUs where it is mixed with the return
air and heated or cooled to needs of the specific spaces that it will be conditioning. The AHUs
also have VFDs which are used to distribute the air to the spaces through VAV boxes. Some
spaces have fan powered VAV boxes while others have damper controlled VAV boxes. All of the
VAV boxes have electric reheat coils to bring the supply air temperatures up to the required
supply temperature. All of the space conditioning is controlled by a direct digital control
system. All of the MAUs, AHUs, and VAVs have numerous sensors including pressure,
temperature and humidity sensors.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
12
Water Side
The chilled water is cooled by an air cooled chiller located on the side of the building. It is then
pumped to the coiling coils in the MAUs and AHUs by four variable speed pumps. Figure 3
shows the chilled water schematic for the building. The heating hot water is provided by two
natural gas fired boilers. The heating hot water is set up in a similar manner to the chilled water
system. Four variable speed pumps provide the AHUs and MAUs with the hot water they need.
A schematic of the heating hot water system can be seen in Figure 4.
Figure 3: Chilled Water Schematic
P-2 P-4
P-3 P-1
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
13
Figure 4: Heating Hot Water Schematic
Existing Mechanical System LEED Analysis
The Bowie State University Fine and Performing Arts Center did not apply for LEED Certification
and therefore there is no LEED Scorecard for the building. However, an analysis of the points
P-10
P-8
P-9
P-7
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
14
relating to the mechanical systems has been provided below. The sections looked at for this
report are “Energy and Atmosphere” and “Indoor Environmental Quality”.
Energy and Atmosphere
EA Prerequisite 1: Fundamental Commissioning of the Building Energy Systems
This prerequisite requires the building to be commissioned by a Commissioning Authority (CxA)
that has at least 2 years of experience, and that the commissioning process be well
documented and reported. This project was commissioned by Eaton Corporation. Therefore
this building meets this prerequisite.
EA Prerequisite 2: Minimum Energy Performance
This prerequisite is included to ensure buildings are using energy efficiently. It requires that the
building complies with ASHRAE 90.1-2004. In Technical Report 1, an in depth analysis of the
building’s compliance with ASHRAE 90.1 was performed and found it to meet all of the
requirements.
EA Prerequisite 3: Fundamental Refrigerant Management
This prerequisite is intended to ensure that buildings do no cause ozone depletion by using CFC-
based refrigerants. The BSU Fine and Performing Arts Center used all new HVAC equipment
that was specified to not have CFC refrigerants.
EA Credit 1: Optimize Energy Performance
This credit is designed to encourage buildings to be increasingly energy efficient. It can earn a
LEED score of 1-10 points and there are 3 options for getting point. The first option is a whole
building energy simulation with the results compared to the baseline building that complies
with ASHRAE Standard 90.1-2004. Option 2 is only for office buildings under 20,000 square feet
which makes it not an option for this building. Option 3 only allows the building to receive 1
point and it requires it to comply with all applicable criteria for the Advanced Buildings
Benchmark for that particular climate zone. A whole building energy simulation was not
performed for this building and therefore the points from this credit cannot be determined at
this time.
EA Credit 2: On-Site Renewable Energy
This credit is intended to reduce the impact associated with fossil fuel energy use. It requires
the building to use on-site renewable energy. The building can be awarded one to three points
based on what percent of the building’s total energy use is offset by renewable energy. The BSU
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
15
Fine and Performing Arts Center does not have any on-site renewable energy systems and
therefore it would receive zero points for this credit.
EA Credit 3: Enhanced Commissioning
The purpose of this credit is to get the Commissioning Authority involved early in the design
process and continue after the performance verification is completed. This credit requires that
a CxA be selected before the construction document phase and that authority continue
reviewing building operation within 10 months after substantial completion with the building
staff. Also, the CxA must review the owner’s project requirements, basis of design and design
documents. The BSU project did not include the CxA until later in the design process and thus
would not receive a point for this credit.
EA Credit 4: Enhanced Refrigerant Management
This credit is intended to reduce the building’s impact on depleting the ozone and minimize
global warming caused by refrigeration chemicals. This credit has two options. The first is
simply, do not use refrigerants. The second option is more complex and has several equations
to determine if a refrigerant meets the necessary requirements. This building uses R-407C from
the ASHRAE Standard 34 code which complies with this credit. This project would receive 1
point for this credit.
EA Credit 5: Measurement & Verification
This credit ensures that the building continues to operate as it was designed for at least a year.
It requires that a measurement and verification (M&V) plan be created in accordance with the
International Performance Measurement & Verification Protocol. An M&V plan was created for
this project and is currently in use. Therefore, this building would receive one point for this
credit.
EA Credit 6: Green Power
The purpose of this credit is to encourage the owners to invest in grid-source renewable energy
technologies. In order to obtain the one point for this credit, 35% of the building’s electricity
must come from renewable resources in at least a two year contract.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
16
Indoor Environmental Quality
EQ Prerequisite 1: Minimum IAQ Performance
This credit is used to establish a minimum indoor air quality (IAQ) for the building. In order to
meet this prerequisite the building must meet the requirements for the ASHRAE 62.1-2004
Standard. Technical Report 1 did an in depth analysis on Standard 62.1 and found the building
to be in compliance with the standard.
EQ Prerequisite 2: Environmental Tobacco Smoke (ETS) Control
Tobacco smoke is terrible for IAQ; therefore this prerequisite is intended to minimize the
amount of smoke in the building. There are two options for commercial buildings to meet this
prerequisite. The first is to prohibit smoking in the building and up to 25 feet away from doors,
operable windows and outdoor air intakes. The second option is to have designated smoking
rooms that are exhausted directly outside. The BSU Fine and Performing Arts Center is in
compliance by prohibiting smoking in and around the building.
EQ Credit 1: Outdoor Air Delivery Monitoring
The purpose of this credit is to ensure the comfort of the occupants in the space by monitoring
the ventilation system. To receive a point for this credit, the building must have permanently
installed monitoring system for ventilation and carbon dioxide detectors. If the levels vary by
10% of what the system was designed for an alarm must signal the building operator. This
building has a BACnet control system with CO2 sensors and ventilation monitoring, therefore it
would get one point for this credit.
EQ Credit 2: Increased Ventilation
This credit is intended improve IAQ by increasing outdoor air ventilation. In order to receive a
point for this credit the building must exceed ASHRAE Standard 62.1-2004 by 30%. The BSU
project did exceed the minimum standards but it did not reach the 30% required and
consequently they would receive no points for this credit.
EQ Credit 3.1: Construction IAQ Management Plan: During Construction
The purpose of this credit is to improve IAQ during construction to keep the construction
workers and occupants safe and comfortable. An IAQ management plan must be developed
and implemented for the construction and pre-occupancy stages. The plan must meet the IAQ
guidelines from the SMACNA control measures. Also, all absorptive materials must be
protected from moisture and all AHUs must have filters with a MERV of 8.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
17
EQ Credit 3.2: Construction IAQ Management Plan: Before Occupancy
The purpose of this credit is to improve IAQ during construction to keep the construction
workers and occupants safe and comfortable. The IAQ management plan must include
measures to make sure the building is good to occupy after construction. To get the point for
this credit the building can either be flushed out or air testing can be done.
EQ Credit 4.1: Low-Emitting Materials: Adhesives & Sealants
This credit is designed to reduce the amount of contaminants in the building and increase the
comfort and well-being of the occupants. This credit requires that all sealants and adhesives
used on the interior of the building have VOC levels lower that the limits specified in the South
Coast Air Quality Management District (SCAQMD) Rule #1168 and Green Seal Standards.
EQ Credit 4.2: Low-Emitting Materials: Paints & Coatings
This credit is designed to reduce the amount of contaminants in the building and increase the
comfort and well-being of the occupants. In order to get the one point for this credit, all paints
and coatings must have a VOC content lower than that allowed by the SCAQMD and Green Seal
Standards.
EQ Credit 4.3: Low-Emitting Materials: Carpet Systems
This credit is designed to reduce the amount of contaminants in the building and increase the
comfort and well-being of the occupants. In order to get the one point for this credit, all carpets
and cushions must meet the requirements of the Carpet and Rug Institute’s Green Label Plus
program.
EQ Credit 4.4: Low-Emitting Materials: Composite Wood & Agrifiber Products
This credit is designed to reduce the amount of contaminants in the building and increase the
comfort and well-being of the occupants. In order to get the one point for this credit, all
composite wood and agrifiber cannot contain added urea-formaldehyde resin.
EQ Credit 5: Indoor Chemical & Pollutant Source Control
The purpose of this credit is to reduce the amount of exposure that the occupants have to
chemical and other potentially hazardous particulates. To get a point for this credit, entryways
must have a system for preventing dirt and particulates from entering the building. Also, areas
with hazardous gases and chemicals must be negatively pressurized so that they cannot spread
to other parts of the building. Lastly, the mechanical system must have a filtration rate of MERV
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
18
13 or better. The BSU Fine and Performing Arts Center meets the first two criteria for this credit
but the filtration system uses MERV 7 filters. Therefore this project would receive no points for
this credit.
EQ Credit 6.1: Controllability of Systems: Lighting
This credit is included to promote productivity and comfort for the occupants of the building. At
least 90% of the building occupants must be able to adjust the lighting in the space to suit their
own needs or the needs of a group. This building has multiple lighting options for group spaces
like classrooms and conference rooms, and the offices have overhead lighting and task lighting
on the desks. Therefore this project meets the requirements for the one point awarded for this
credit.
EQ Credit 6.2: Controllability of Systems: Thermal Comfort
The purpose of this credit is to increase occupant comfort and productivity by providing the
occupants with the ability to control the temperature of the spaces. In order to get the point for
this credit, a minimum of 50% of the building must have comfort controls or operable windows.
The BSU project does not meet these requirements because the offices and large performance
spaces cannot be individually changed by the occupants.
EQ Credit 7.1: Thermal Comfort: Design
This credit is designed to ensure the comfort and well-being of the occupants. To get a point for
this credit, the HVAC system must be designed in accordance with ASHRAE Standard 55-2004.
This building was design to the specifications of this stand and as a result would receive a point
for this credit.
EQ Credit 7.2: Thermal Comfort: Verification
This credit verifies that the system is operating the way it was intended when it was designed.
To receive this point, a thermal comfort survey of building occupants must be given 6-18
months after the building is first occupied. If 20% or more of the occupants are uncomfortable,
corrective action must be taken.
EQ Credit 8.1: Daylight & Views: Daylight 75% of Spaces
This credit is designed to connect the indoor spaces with the outside through daylighting and
views of outside. There are three options for obtaining the one point for this credit. The first
option is calculation based, and it shows that at least 75% of the regularly occupied spaces have
sufficient glazing. The second option is to demonstrate through computer simulation that 75%
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
19
of the building receives 25 footcandles or more from daylight. The third option is measuring the
footcandles over a ten foot grid for all occupied spaces. For 75% of the building 25 footcandles
must be observed. The BSU building has a large glass curtain wall and sky lights throughout the
building. The spaces without windows are performance spaces and not regularly occupied so
they would be excluded from the calculations. Therefore this building would receive this point.
EQ Credit 8.2: Daylight & Views: Views for 90% of Spaces
This credit is designed to connect the indoor spaces with the outside through daylighting and
views of outside. To get this point 90% of all regularly occupied spaces must have a direct line
of site to the outdoor environment via glazing between 2’6” and 7’6” above the finished floor.
The BSU project does not meet these requirements and would not receive a point for this
credit.
Proposed Redesign Overview
In order to reduce the amount of energy that the mechanical system uses, a vertical loop
ground source heat pump and an underfloor air distribution system have been proposed.
The GSHP will reduce the amount of energy that the chiller and boilers need to condition the
building. Depending on the size of the GSHP system, it could replace the chiller and boilers
altogether. The GSHP requires a lot of nearby land to reject and absorb heat from the ground.
The vertical loop proposed requires 250 to 300 sf/ton. The site has plenty of unused land
surrounding the building which could be used for the GSHP as shown in Figure 5. The GSHP will
significantly increase the upfront cost of the project but using it for both cooling and heating
will greatly reduce the monthly utilities cost for both electricity and natural gas.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
20
Figure 5: Aerial View of Site
(Image courtesy of Google Maps)
The UFAD system will allow the occupants of the large volume spaces such as the theaters and
dance studios to be more comfortable and the systems can provide higher temperature air to
the spaces. Since the air needs to be warmer to keep the occupants comfortable the
mechanical system can save energy on conditioning the air for these spaces. Also, since the air
reaches the occupants first, the heat generated by the lighting and other electrical equipment
will have less effect on the space.
The energy model referenced earlier showed that over half of the electricity consumption in
the building is from lighting. The lighting system for the north section of the building will be
redesigned with an emphasis on energy efficiency. The south section will be omitted from the
redesign because the performance spaces need special lighting for artistic and aesthetical
reasons. The redesign will use energy efficient lamps, ballasts and occupancy sensors. After the
design is done, an energy model will be created to determine if the payback period is
acceptable.
The addition of the ground source heat pump and underfloor air distribution system will greatly
affect the testing and commissioning of the building. As a construction breadth, a plan for
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
21
testing and commissioning these systems will be created. Also, the existing testing and
commissioning requirements will be looked at to see if they can be simplified.
Depth One: Ground Source Heat Pump
Soil Type
The objective of this ground source heat pump is to replace both the boilers and chiller in the
existing design. In order to determine the size of the system the ground conditions and soil type
needs to be determined. Normally borehole testing and a thorough analysis of the soil would
be completed. Unfortunately this process is very expensive and therefore was not used for this
report. Instead a geologic map (see Figure 6) of the area was obtained from the Maryland
Geological Survey Program. The site of this project is represented by the gold star in Figure XX
and is located on Cretaceous ground which consists of sand, gravel, silt and clay. Of the soils
listed in the 2011 ASHRAE Handbook--HVAC Applications, cretaceous ground most closely
resembles light sand, 15% water and therefore these values were used. It was also found that
the ground temperature averaged to approximately 55 °F which is the value used for this
report.
Figure 6: Geological Map of Maryland
Calculations
Bore Length
In order to correctly calculate the length of bores needed to condition the building year round,
the process detailed in chapter 34 of the 2011 ASHRAE Handbook—HVAC Applications. The
following equation calculates the necessary length of the bores to achieve the desired heating
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
22
or cooling capacity. The equation was used twice, once to determine the length needed for
cooling and once for the heating. Table XX shows the values used in the equation.
Fsc = short-circuit heat loss factor
L = required bore length [ft]
PLFm = part-load factor during design month
qa = net annual average heat transfer to ground [Btu/h]
ql = building design block load [Btu/h]
Rga = effective thermal resistance of ground (daily pulse) [ft*h*°F/Btu]
Rgd = effective thermal resistance of ground (peak daily pulse) [ft*h*°F/Btu]
Rgm = effective thermal resistance of ground (monthly pulse) [ft*h*°F/Btu]
Rb = thermal resistance of bore [ft*h*°F/Btu] tg = undisturbed ground temperature [°F] tp = temperature penalty for interference of adjacent bores [°F] twi = liquid temperature at heat pump inlet [°F] two = liquid temperature at heat pump outlet [°F] W = system power input at design load [W]
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
23
Variable Value Units
Fsc 1.06
qa 1618500 Btu/h
qlc 2451600 Btu/h
qlh 833100 Btu/h
Rga 0.345 ft*h*°F /Btu
Rgd 0.2 ft*h*°F /Btu
Rgm 0.309 ft*h*°F /Btu
Rb 0.1 ft*h*°F /Btu
tg 55 °F
tp 1.8 °F
twi 55 °F
two 67 °F
Wc 38166 btu/hr
Wh 5089 btu/hr
PLFm 1
Table 8: Values for Bore Length Calculation
Well Field Layout
It was determined that the BSU Fine and Performing Arts Center needs 277,259 ft. to meet the
cooling load. Looking at the space available the best configuration was a grid of seventeen rows
of thirty bores spaced twenty feet apart for a total of 510 bores at a depth of 544 ft. A diagram
of the layout can be seen in Figure 7.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
24
Figure 7: GSHP Well Field Layout
Pipe and Pump Sizing
Before the pipes and pump could be sized several decision about the bores and the system had
to be decided. The U-tube diameter was determined to be 1” and the bore diameter was
selected to be 6” to get a thermal resistance value of .1 which works well for this layout. This
value was taken from table 6 of the 2011 ASHRAE Handbook—HVAC Applications. It was also
decided that there would be one bore per loop and the flow would be 2 gpm/ton. With 2
gpm/ton the total gpm for the system came out to 409 gpm. This number was used in
conjunction with Figure 8 to determine the diameter of the header to be 5”.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
25
Figure 8: Friction Loss Due to Flow of Water
The head loss for the longest run was calculated in order to size the pump. In order to fine the
total head loss, first the total length of the longest run, which was to AHU-12, was calculated
and found to be 2553 ft. The resistance coefficient for each fixture was calculated by
multiplying a constant (based on the type of fitting) by the friction factor (ft) of the pipe size.
The friction factor was found using Figure 9. Five inch pipe was used for the header and one
inch pipe was used for the U-loops in the bores.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
26
Figure 9: Friction Factors for Nominal Size Pipes
The types of fittings needed for this system were 90° elbows, “T” through run and “T” through
branch. For the 5” pipe, the resistance coefficient for the 90° elbow was found to be .48, the
“T” through run is .32 and the “T” through branch is .96. Then the equivalent length for each
fitting was calculated by using Figure 10. (The example shown is for a 90° turn.) The equivalent
length for the 90° turns is 13 ft., the “T” through run is 9 ft. and the “T” through branch is 27 ft.
The equivalent length for each fitting was multiplied by the total number of fittings in each
section and then added to the length of straight pipe to get the total length. Finally it was
multiplied by the head loss per 100 feet found in Figure 8. The results of these calculations for
the 5” pipe can be found in Figure XX. The same calculations were run for the 1” pipe but
because the flow rate is so low the head loss is negligible.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
27
Figure 10: Equivalent Length of Fittings
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
28
Section Length GPM Pipe Head Loss
90° Turn
“T” Run “T” Branch
Total Head Loss
1 1393 408.6 2.8 11 43.008
2 40 394.98 2.6 1 1.274
3 40 381.36 2.2 1 1.078
4 40 367.74 1.8 1 0.882
5 40 354.12 1.6 1 0.784
6 40 340.5 1.5 1 0.735
7 40 326.88 1.3 1 0.637
8 40 313.26 1.2 1 0.588
9 40 299.64 1.1 1 0.539
10 40 286.02 1 1 0.49
11 40 272.4 0.9 1 0.441
12 40 258.78 0.8 1 0.392
13 40 245.16 0.8 1 0.392
14 40 231.54 0.7 1 0.343
15 40 217.92 0.7 1 0.343
16 40 204.3 0.7 1 0.343
17 40 190.68 0.65 1 0.3185
18 40 177.06 0.6 1 0.294
19 40 163.44 0.5 1 0.245
20 40 149.82 0 1 0
21 40 136.2 0 1 0
22 40 122.58 0 1 0
23 40 108.96 0 1 0
24 40 95.34 0 1 0
25 40 81.72 0 1 0
26 40 68.1 0 1 0
27 40 54.48 0 1 0
28 40 40.86 0 1 0
29 40 27.24 0 1 0
30 40 13.62 0 2 0
Total 2553 408.6 11 28 2 53.1265
Table 9: Total Head Loss Calculations for 5” Pipe
The total head loss comes out to 54 ft of water. It was found that the Bell and Gossett series
1510 was capable of operating under the required conditions and so the head loss and system
gpm were plotted on Figure 11 to determine which pump would be used. A 1750 RPM pump
labeled 2½ BB was selected. The total system head and gpm were plotted on the 2½ BB pump
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
29
curve in Figure 12. It was determined that the pump is approximately 63% efficient and a 10
horsepower pump is required.
Figure 11: Bell and Gossett 60 Hertz Performance Curve
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
30
Figure 12: Bell and Gossett Series 1510 Pump 2.5 BB Pump Curve
Energy Model
Earlier in this report the energy consumption and utilities costs of the existing system were
calculated using Trane Trace 700. Therefore, the ground source heat pump was also model in
Trace so that the two could be compared. The weather information, the templates and the
rooms from the existing energy model were reused to start the new model with the GSHP so
that everything was held constant except for the cooling and heating system. The AHUs from
the existing system were changed to water source heat pumps and the heating and cooling
plants were changed to ground source heat pumps with the system values determine above. An
analysis of the results is detailed later in this report in the Redesign Cost and Energy Analysis
section.
Depth Two: Underfloor Air Distribution
An underfloor air distribution (UFAD) system was analyzed to determine possible energy
savings. UFAD system have potential for energy savings because conditioned air is supplied
directly to where the occupants are, therefore it can be provided at a higher temperature and
still keep the occupants comfortable. For this project the supply air is brought to the space at
63°F. Another potential savings comes from the reduced duct length that results in not having
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
31
to run the ducts to the ceiling. The short duct length creates less pressure loss and therefore
the fans can use less energy. Also, less ductwork is less expensive to install.
The system was modeled in Trace and compared to the baseline model of the existing system.
The weather, templates and rooms were all copied from the baseline model to ensure any
energy changes were solely the result of the UFAD system. The AHUs serving the offices,
classrooms and the atrium were also copied from the existing model because those areas are
not being changed. The UFAD system was modeled to replace the overhead air diffusers in the
large volume spaces like the auditorium and recital halls. AHUs 1, 2, 4, 5, 6 and 7 were all
changed from variable air volume with overhead discharge to UFAD with parallel fan powered
VAV’s. A typical UFAD with parallel fan powered VAV’s is diagramed in Figure 13.
Unfortunately where the AHUs for the BSU Fine and Performing Arts Center are located the
duct length needed to be increased in order to run the ducts under the floor. This meant that
the fan would have a higher pressure drop to overcome to supply the space with air.
Nonetheless, a Trace model calculation was run in order to determine if the energy savings
from the increased supply temperature was enough to overcome the higher energy
consumption of the fan.
The energy analysis from Trace revealed that the UFAD system saved minimal energy during the
cooling modes and actually required more energy in heating. As mentioned earlier, the fan
needs more power to overcome the longer duct runs which really makes this distribution less
energy efficient. Also, UFAD systems are more expensive to install because the floor has to be
raised to allow the ductwork to be installed. Combining the fact that this system is more
expensive to operate and install it is obvious to see that the system will never pay for itself and
should not be used in this building.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
32
Figure 13: Typical Schematic of a UFAD System
Lighting Breadth
The lighting system for the classrooms and offices were looked at to find possible energy
savings. More efficient luminaires with T5 High Output fluorescent lamps were selected in an
attempt to provide the same level of lighting with less luminaires. The Lighting Handbook 10th
edition specifies that the illuminance for offices of occupants ages 25-65 require 30 foot-
candles for reading and writing, and classrooms with occupants with an average age of less
than 25 require 15 foot-candles for music rooms. Therefore the intent of this redesign was to
provide sufficient lighting while using fewer watts than the existing design.
First the existing lighting system was analyzed and it was found that the classrooms used
several different types of luminaires that used between one and four 32 watt T8 lamps and the
offices used luminaires that had two 40 watt TT5 lamps. The total number of kilowatts was
calculated and found to be 19.4 for the classrooms and 7.6 for the offices. These values were
then used to obtain the kWh per year by multiplying the kW by the equivalent full load hours
(EFLH) of 2,522 and 2,870 for classrooms and offices respectively. The classrooms used 49,000
kWh and the offices used 22,000 kWh yearly.
The luminaires selected for the redesign of both the classrooms and the offices are direct
indirect pendent fixtures that contain one T5 High Output fluorescent lamp. Offices and
classrooms were then modeled in AGI to determine how many luminaires were required to
obtain the proper illuminance throughout the room. Figures 14 and 15 show renderings of a
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
33
typical classroom and office. Appendix A shows the actual values found from the AGI
calculations. Then the watts per square foot of each room was calculated and averaged to get a
watt/square foot value for classrooms and offices, which was then multiplied by the total
square footage of each type of room. The new classroom design uses 6.6 kilowatts and 16,500
kWh per year, and the new office design uses 3.8 kilowatts and 11,000 kWh per year. Further
break down of savings is discussed in Redesign Cost and Energy Analysis section of this report.
Figure 14: AGI Rendering of a Typical Classroom
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
34
Figure 15: AGI Rendering of a Typical Office
In another attempt to reduce the energy wasted by the lighting system, the redesign calls for
infrared occupancy sensors in the office and ultrasonic occupancy sensors in the classrooms to
reduce the amount of time the lights are on. Infrared sensors were selected for the offices
because they can sense the body heat generated by a person, which is good for offices where
occupants can be stationary for long periods of time. Ultrasonic occupancy sensors were
selected for the classrooms because they detect motion and have a larger range which is
required for the size of the classrooms in the BSU Fine and Performing Arts Center. It is
important to select the right type of sensor and position them correctly based on the type of
room so that the lights aren’t turning off when the room is in use or staying on when it is not.
Throughout the day in university buildings people come and go through rooms, but a lot of the
time the lights are left on when the space is unoccupied. Table 10 shows the percentage of the
time spaces are unoccupied with the lights on. For this report the Electric Power Research
Institute (EPRI) predictions were used to determine the impact of installing occupancy sensors.
The EPRI predictions were subtracted from one to determine the percentage of time that the
lights are on in each space. This value was then multiplied by the EFLH to determine the
number of hours per year that the lights would be on with the occupancy sensors. That value
was then multiplied by the kilowatts used in the classrooms and the offices to calculate the
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
35
actual kWh per year. The classroom value came to 6,900 kWh and the office value came to
6,800 kWh per year. Further analysis of savings is discussed in Redesign Cost and Energy
Analysis section of this report.
Table 10: Percentage of Time Lights Are on in Unoccupied Spaces
Construction Management Breadth
Commissioning is a valuable service that can greatly improve the efficiency and comfort of a
building. An existing commissioning plan was created and implemented for the BSU Fine and
Performing Arts Center. However, with the proposed redesign the commissioning plan will be
edited to incorporate new component and eliminate no longer existing ones. ASHRAE outlines
the different items that need to be checked and what specifically needs tested for ground
source heat pumps. These requirements can be found in Table 11. The heat pump units and
heat pump piping will be located in the AHUs and therefore will be included in the AHU
prefuctional test (PFT). A typical AHU and GSHP prefuctional test report (modified from the
existing reports) can be found in Appendix B.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
36
System Function
Heat Pump Piping Pressure test, clean and fill
Ground Source Piping
Pressure test, clean, fill and purge air
Pumps Inspect, test and start up
Heat recovery unit Inspect, test and start up; provie clean set of filters, staff instruction
Heat pump units Inspect, test and start up; provie clean filters, staff instruction
Chemical treatment Flushing and cleaning, chemical treatment, staff instruction
Balancing Balancing, spot checking, follow-up site visits
Controls Installation/commissioning, staff instruction, performance testing, seasonal testing
Table 11: ASHRAE GSHP Commissioning Process
Since there is so much equipment in a modern building it would be incredibly time consuming
and expensive to individually check every piece of equipment. Therefore, sample testing is done
for some of the smaller and more numerous pieces of equipment. Table 12 shows what fraction
of each piece of equipment must be observed. The boiler equipment and the chiller equipment
have been eliminated from this schedule as they are no longer necessary with the addition of
the ground source heat pump.
Equipment or System Fraction To Be Observed by CxA
Mechanical Equipment
Pumps, VFDs 100%
Air Handlers 100%
Make-Up Air Units 100%
Fan Coil Units 20%
Cabinet Unit Heaters 100%
Terminal Units 20%
Exhaust Fans 100%
Fin Tube 100%
Dust Collection System 100%
Hydrostatic Pressure Test 10%
Pipe Flushing At beginning and end
Building Automation System Observe sub checkout and calibration
TAB Work Sample observation of the TAB process and compare process utilized to the TAB plan
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
37
Equipment or System Fraction To Be Observed by CxA
Plumbing Equipment
Domestic Water Heaters, Mixing Valves, Re-circulators and Booster Pumps
100%
Other Misc. Equipment As necessary
Electrical Equipment
Emergency Generator 100%
Automatic Transfer Switches 100%
Electrical Distribution Switchgear (800A and Larger)
100%
Lighting Controls 100%
Life Safety System (Mechanical interlocks only. No NFPA 72 requirements)
100%
Table 12: Prefunctional Test Sampling
Redesign Cost and Energy Analysis
Ground Source Heat Pump
The ground source heat pump was very expensive to install mainly because of the incredible
amount of labor and material needed for the well field. A breakdown of the cost added to the
mechanical systems from the GSHP can be found in Table 13. The total added cost from the
GSHP comes to just over $2.9 million. The GSHP was designed to replace the air cooled chiller
and the gas fired boiler, which cost $180,000 and $80,000 respectively. However, local power
companies can provide additional assistance, as many provide incentives for the use of energy
efficient equipment. The Baltimore Gas & Electric Company, which is the utility provider for
Bowie State University, has a Commercial Energy Efficiency Program that provides various
utility rebates. Through this program, this ground source heat pump qualifies for up to 75
percent of the system cost since the building is new construction. There is a maximum incentive
of $1 million, which for this project is less than 75 percent of the total cost meaning it would
reach the $1 million max.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
38
Amount Unit Price Total
Pump - 1 - 410 GPM, 10 H.P. VSD 1 $15,000.00 $15,000.00
Pump - 2 - 410 GPM, 10 H.P. Stand-by VSD
1 $15,000.00 $15,000.00
Air Separator 1 $2,500.00 $2,500.00
Water Filter Geothermal 1 $800.00 $800.00
Geo-Manifold/Valves 277258 $9.00 $2,495,322.00
DDC Controls 123000 $3.00 $369,000.00
HPU 16 $2,500.00 $40,000.00
Total
$2,937,622.00
Total With Incentive $1,937,622.00
Table 13: Additional Mechanical Costs from the GSHP
The GSHP is able to draw heating and cooling from the earth and distribute it through the
building. There is a large potential for energy savings when used in the right climates and soil
types. The Trace model provided the results for the existing system and the GSHP. The GSHP
was able to reduce the amount of gas consumed to zero therms by meeting all of the heating
needs. However, the electricity consumption went up most likely due to the increased load on
the pumps that are required to move water throughout a long distance of pipe. Looking at the
current prices for the BSU Fine and Performing Arts Center the GSHP costs roughly $700 more
to operate per year. Table 14 shows the utility cost comparisons. Since the initial cost of the
GSHP system is much greater than that of the existing system, and that it costs more to operate
the system it is recommended not to implement a GSHP.
Existing System GSHP
Electric Consumption (kWh)
619509 634582
Electric Cost $57,428.48 $58,825.75
Gas Consumption (therms) 3660 0
Gas Cost $732.00 $0.00
Total Utility Cost $58,160.48 $58,825.75
Table 14: Utility Cost Comparison
Lighting Redesign
The new high efficiency lighting was very effective in reducing the lighting costs of the building. The existing luminaires cost $212 per fixture and the new luminaires cost $352 per fixture including overhead and profit. Since the new luminaires provide more light, less of them were needed in the building. The original design called for 317 fixtures in the classrooms and office,
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
39
but the redesign has 159 fixtures. Table 15 shows the total cost for both designs. Since there were so many fewer fixtures in the new design, the initial cost is over $11,000 lower for the more efficient design.
No. of
Fixtures Price/Fixture Total Cost
Old Luminaires 317 $212.00 $67,204.00
New Luminaires 159 $352.00 $55,968.00
Savings
$11,236.00
Table 15: Initial Cost Comparison In addition to saving on the initial cost, the new lighting system provides significant savings on the cost of electricity. The redesigned lighting system saves 43,155 kWh each year which amounts to just over $4,000. Table 16 shows the utility savings from the new design.
Classrooms Offices
kW Saved 12.9 3.7
EFLH 2522 2870
kWh Saved per Year 32437 10718
Cost/kWh $0.0927 $0.0927
Money Saved/Year $3006.88 $993.57
Total Savings/Year $4000.45
Table 16: Utility Savings from Lighting Redesign The occupancy sensors that are included in the redesign were selected because they are wireless sensors and are much easier and quicker to install. A quote from an electrical contractor stated that the sensors could be installed for $180 per device. The devices have a large enough range that one can be used per room. That means that 24 ultrasonic sensors and 32 infrared sensors are required for all of the classrooms and offices. Both types of Lutron wireless sensors cost $80 per sensor but the utility company, Baltimore Gas & Electric Company, offers to pay for 75% of the occupancy sensors through their Commercial Energy Efficiency Program. Therefore, the occupancy sensors cost only $20 which greatly reduces the payback period. The total cost of the sensors comes to $11,200 and the energy savings due to the occupancy sensors is $1,275. Therefore, the payback period for the occupancy sensors is 8.8 years. A cost break down can be found in Tables 17 and 18.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
40
Classroom Office
Cost of Sensors $1920 $2560
Cost with Rebate $480 $640
Cost of Installation $4320 $5760
Total Cost $4800 $6400
Total $11,200
Table 17: Cost of Sensors
Classrooms Offices
Cost Without Sensors
$1,531.81 $1,018.73
Cost With Sensor $643.36 $631.61
Utility Savings $888.45 $387.12
Total Savings $1,275.56
Table 18: Utility Cost With and Without Occupancy Sensors Combining the new lighting system with the occupancy sensors there is still an initial savings of $36, but the yearly energy savings comes out to $5,275. Looking at these numbers it is obvious to see that the new energy efficient lighting plan should be implemented because it is less expensive and it saves energy every year. The occupancy sensors are fairly expensive, but save a significant amount of energy each year. With the rebate from the utility company, the payback period is reasonable and considering the money saved from the new lighting installation it is recommended to install the occupancy sensors.
The ground source heat pump and the underfloor air distribution did not save enough energy to recover the additional upfront costs and therefore were not recommended to be used. The lighting redesign and the occupancy sensors both saw substantial energy savings and would pay for themselves in a reasonable amount of time. Therefore, they should both be implemented.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
41
References 2009 ASHRAE Handbook: Heating, Ventilating, and Air-conditioning Fundamentals. Atlanta, GA:
ASHRAE, 2009. Print. 2011 ASHRAE Handbook: Heating, Ventilating, and Air-conditioning Applications. Atlanta, GA:
ASHRAE, 2011. Print. ASHRAE.2007, ANSI/ASHRAE, Standard 62.1-2007, Ventilation for Acceptable Indoor Air Quality.
American Society of Heating Refrigeration and Air-Conditioning Engineer, Inc. Atlanta, GA.
ASHRAE.2007, ANSI/ASHRAE, Standard 90.1-2007, Energy Standard for Building Except Low-Rise
Residential Buildings. American Society of Heating Refrigeration and Air-Conditioning Engineers, Inc. Atlanta, GA.
Bauman, Fred S., and Allan Dally. Underfloor Air Distribution (UFAD) Design Guide. Atlanta, GA:
American Society of Heating Refrigerating and Air-Conditioning Engineers, 2003. Print. Bauman, P.E., Fred, Tom Webster, P.E., and David Lehrer. "Underfloor Technology Design
Guidelines." Center for the Built Environment. University of California, Berkley. Web. 15 Jan. 2012. <http://www.cbe.berkeley.edu/underfloorair/designguidelines_pr.htm>.
Bell and Gossett. Base Mounted Centrifugal Pump Performance Curves. Bell and Gossett. Print. DiLaura, David L. The Lighting Handbook: Reference & Application. New York, NY: Illuminating
Engineering Society of North America, 2011. Print. "DSIRE: DSIRE Home." DSIRE USA. Web. 02 Apr. 2012. <http://www.dsireusa.org/>. Eaton’s EMC Engineers. Commissioning Construction Documents. Eaton’s EMC Engineers,
Washington D.C. EYP Architecture & Engineering, P.C. Architectural Construction Documents. EYP Architecture &
Engineering, Washington D.C. EYP Architecture & Engineering, P.C. Electrical Construction Documents. EYP Architecture &
Engineering, Washington D.C. EYP Architecture & Engineering, P.C. Mechanical Construction Documents. EYP Architecture &
Engineering, Washington D.C. Filler, Mike. "Best Practices for Underfloor Air Systems." ASHRAE Journal October (2004): 39-44.
Print.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
42
Hamilton, Sephir D., Kurt W. Roth, Ph.D., and James Brodrick, PH.D. "Displacement
Ventilation." ASHRAE Journal September (2004): 56-58. Print. Li, Ph.D., Yuguo, Peter V. Nielsen, Ph.D., and Mats Sanberg, Ph.D. "Displacement Ventilation in
Hospital Environments." ASHRAE Journal June (2011): 86-88. Print. "Lutron Radio Powr Saver Wireless Occupancy Sensor Overview." Lutron Radio Powr Saver
Wireless Occupancy Sensor Overview. Lutron. Web. 16 Mar. 2012. <http://www.lutron.com/Products/Sensors/Occupancy-Vacancy/WirelessRadio PowrSavr/Pages/Overview.aspx>.
McDonell, P.Eng., Geoff. "Underfloor and Displacement: Why They're Not the Same."ASHRAE
Journal July (2003): 18-22. Print. McQuay International. "Geothermal Heat Pump Design Manual." (2002). Print. McQuiston, Faye C., Jerald D. Parker, and Jeffrey D. Spitler. Heating, Ventilating, And Air
Conditioning, Analysis And Design. 6th. Wiley, 2005. Print. Montgomery, P.E., Ross D. "UFAD Commissioning for Air Force Base." ASHRAE JournalJune
(2009): 38-44. Print. Stanke, Dennis, and Brenda Bradley. "Turning Air Distribution Up Side Down...Underfloor Air
Distribution." Trane Engineers 30 (2001): 1-5. Trane. 2001. Web. 12 Jan. 2012. <http://www.trane.com/commercial/library/vol30_4/>.
Webster, Jack. "Is UFAD All That It's Cracked Up to Be?" ASHRAE Journal February (2004). Print. Webster, P.E., Tom, Fred Bauman, P.E., and Jim Reese, P.E. "Underfloor Air Distribution:
Thermal Stratification." ASHRAE Journal May (2002). Print.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
43
Appendix A: Illuminance Value
Figure 16: Classroom Lighting Isolines
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
44
Figure 17: Office Lighting Isolines
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
45
Appendix B: Commissioning Prefunctional Tests
Mechanical System Information Name AHU-01 Description Manufacturer:
Volts: CFM:
Building/Phase BSU FPAC Model
Report Date Serial
Mechanical Checklist for AHU-01 Category # Item Performed Initials Date
1 AHU Prefunctional Checklist 44224
AHU Drawing No.
1 AHU Prefunctional Checklist 44225
Specification Section:
1 AHU Prefunctional Checklist 44226
Location (Floor/Room):
1 AHU Prefunctional Checklist 44227
Area Served:
1 AHU Prefunctional Checklist 44228
Supply Fan Manufacturer:
1 AHU Prefunctional Checklist 44229
SF Serial No:
1 AHU Prefunctional Checklist 44230
SF HP:
1 AHU Prefunctional Checklist 44231
SF RPM:
1 AHU Prefunctional Checklist 44232
SF Volts/Hz/Ph
1 AHU Prefunctional Checklist 44233
SF Amps:
1 AHU Prefunctional 44234
SF CFM:
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
46
Checklist
2 Cabinet and General Installation 44235
Permanent label affixed.
2 Cabinet and General Installation 44236
Casing condition good: no dents or leaks.
2 Cabinet and General Installation 44237
Door gaskets installed. Doors close tightly with no leaks.
2 Cabinet and General Installation 44238
Housing piping and duct penetrations sealed.
2 Cabinet and General Installation 44239
Dampers/actuators properly installed and close tightly.
2 Cabinet and General Installation 44240
Vibration isolation equipment installed and released from shipping locks.
2 Cabinet and General Installation 44241
Thermal insulation properly installed.
2 Cabinet and General Installation 44242
Construction filters installed.
2 Cabinet and General Installation 44243
Flex connection at fan installed.
2 Cabinet and General Installation 44244
Manufacturer's required clearances for unit/components maintained.
3 Valves, Piping and Coils 44245
Piping fittings complete. Piping properly supported.
3 Valves, Piping and Coils 44246
Strainer in place and clean.
3 Valves, Piping and Coils 44247
Piping system properly flushed.
3 Valves, Piping and Coils 44248
All coils clean. Fins have been combed.
3 Valves, Piping and Coils 44249
Heat pump unit completed and functioning properly.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
47
3 Valves, Piping and Coils 44250
Heat pump cleaned and filter changed.
3 Valves, Piping and Coils 44251
Condensate piping properly trapped and vented. Condensate drain pans clean and sloped to drain.
3 Valves, Piping and Coils 44252
Pressure/Temperature ports installed as required
3 Valves, Piping and Coils 44253
Chilled water pipe complete and piping properly supported.
3 Valves, Piping and Coils 44254
Chilled water pipe pressure test complete and no leaks.
3 Valves, Piping and Coils 44255
Piping, valves, and clearances accommodate coil removal.
3 Valves, Piping and Coils 44256
Valves properly labeled and tagged.
3 Valves, Piping and Coils 44257
Valves installed in proper direction.
3 Valves, Piping and Coils 44258
Balancing valves installed as required.
3 Valves, Piping and Coils 44259
Isolation valves installed as required.
3 Valves, Piping and Coils 44260
Control valves installed as required.
3 Valves, Piping and Coils 44261
Dirt leg drain valve, hose bib and cap installed.
3 Valves, Piping and Coils 44262
Heat pump pipe complete and piping properly supported.
3 Valves, Piping and Coils 44263
Heat pump pipe pressure test complete and no leaks.
4 Fans 44264
Drive belts matched and tensioned.
4 Fans 44265
Shaft and motor bearing lubricated.
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
48
4 Fans 44266
Motor rotation correct and free fan wheel rotation.
4 Fans 44267
Vibration isolators released and adjusted. Isolators not bottomed out.
4 Fans 44268
Proper starter/VFD installed and labeled.
4 Fans 44269
All bolts, fasteners, and set screws checked and tightened.
5 Start‐up 44270
Vibration Level Satisfactory
5 Start‐up 44271
Noise Level Satisfactory
5 Start‐up 44272
Motor Amps Actual
5 Start‐up 44273
Motor Volts Actual
6 Certificate of Readiness
44274
I certify that all equipment, systems, and controls are now complete and ready for the Functional Performance Testing to begin. Initialing this ensures the functional tests can be completed without the need to redo or perform for the first time, manufacturer's start‐up or commissioning pre‐functional inspections, tests or tasks.
6 Certificate of Readiness
44275
The subcontractor has reviewed the Approved FPT and has no concerns with performing it.
Mechanical Checklist Notes for AHU-01 Item # Note
Mechanical System Information Name GSHP Description Manufacturer:
Volts: CFM:
Building/Phase BSU FPAC Model
Report Date Serial
Mechanical Checklist for GSHP Category # Item Performed Initials Date
1 AHU Prefunctional Checklist 48564
GSHP Drawing No.
1 AHU 48565 Specification Section:
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
49
Prefunctional Checklist
1 AHU Prefunctional Checklist 48566
Location (Floor/Room):
1 AHU Prefunctional Checklist 48567
Area Served:
2 Cabinet and General Installation 48568
Permanent label affixed.
2 Cabinet and General Installation 48569
Casing condition good: no dents or leaks.
2 Cabinet and General Installation 48570
Door gaskets installed. Doors close tightly with no leaks.
2 Cabinet and General Installation 48571
Housing piping and duct penetrations sealed.
2 Cabinet and General Installation 48572
Vibration isolation equipment installed and released from shipping locks.
2 Cabinet and General Installation 48573
Thermal insulation properly installed.
2 Cabinet and General Installation 48574
Chemical treatment devices installed.
2 Cabinet and General Installation 48575
Manufacturer's required clearances for unit/components maintained.
3 Valves, Piping and Coils 48576
Piping fittings complete. Piping properly supported.
3 Valves, Piping and Coils 48577
Strainer in place and clean.
3 Valves, Piping and Coils 48578
Piping system properly flushed.
3 Valves, Piping and Coils 48579
All coils clean. Fins have been combed.
3 Valves, Piping and Coils 48580
Pressure/Temperature ports installed as required
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
50
3 Valves, Piping and Coils 48581
Chilled water pipe complete and piping properly supported.
3 Valves, Piping and Coils 48582
Chilled water pipe pressure test complete and no leaks.
3 Valves, Piping and Coils 48583
Piping, valves, and clearances accommodate coil removal.
3 Valves, Piping and Coils 48584
Valves properly labeled and tagged.
3 Valves, Piping and Coils 48585
Valves installed in proper direction.
3 Valves, Piping and Coils 48586
Balancing valves installed as required.
3 Valves, Piping and Coils 48587
Isolation valves installed as required.
3 Valves, Piping and Coils 48588
Control valves installed as required.
3 Valves, Piping and Coils 48589
Dirt leg drain valve, hose bib and cap installed.
4 Pumps 48590
Drive belts matched and tensioned.
4 Pumps 48591
Shaft and motor bearing lubricated.
4 Pumps 48592
Motor rotation correct and free impeller wheel rotation.
4 Pumps 48593
Vibration isolators released and adjusted. Isolators not bottomed out.
4 Pumps 48594
Proper starter/VFD installed and labeled.
4 Pumps 48595
All bolts, fasteners, and set screws checked and tightened.
5 Start‐up 48596
Vibration Level Satisfactory
5 Start‐up 48597
Noise Level Satisfactory
5 Start‐up 48598
Motor Amps Actual
5 Start‐up 48599 Motor Volts Actual
Bowie State University Fine and Performing Arts Center | Zack Lippert | Mechanical Option
51
6 Certificate of Readiness
48600
I certify that all equipment, systems, and controls are now complete and ready for the Functional Performance Testing to begin. Initialing this ensures the functional tests can be completed without the need to redo or perform for the first time, manufacturer's start‐up or commissioning pre‐functional inspections, tests or tasks.
6 Certificate of Readiness
48601
The subcontractor has reviewed the Approved FPT and has no concerns with performing it.
Mechanical Checklist Notes for GSHP Item # Note