BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
1 | P a g e
2018
BOROUGH OF AVALON
EARLY INTERVENTION PLAN
SPECIAL CONDITIONS REPORT
PARKS, POOL, AND RECREATION
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
2 | P a g e
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
3 | P a g e
TABLE OF CONTENTS
Acknowledgements ............................................................................................................................................. 4
Introduction ........................................................................................................................................................ 5
Background ....................................................................................................................................................... 5
Avalon Pool ....................................................................................................................................................... 13
Financial Evaluation .......................................................................................................................................... 14
Pool Marketing ................................................................................................................................................. 16
Pool Attendance ............................................................................................................................................... 17
Concession Operations ...................................................................................................................................... 18
Program Evaluation .......................................................................................................................................... 19
Area Pool Comparisons ..................................................................................................................................... 20
Building and Grounds Maintenance ..................................................................................................................... 22
Pool System Monitoring ..................................................................................................................................... 23
Avalon Park – Master Site Plan.......................................................................................................................... 24
Phase 1 – Ballfield and Stormwater Improvements ............................................................................................... 25
Phase 2 – Play Equipment and Fitness Stations .................................................................................................... 27
Phase 3 – Pavilion, Riparian Restoration, and Accessible Parking ............................................................................ 29
Phase 4 – New Play Areas and Kitchen ................................................................................................................ 31
Observations ..................................................................................................................................................... 34
Recommendations ............................................................................................................................................. 35
Appendix A – Avalon Community Park Master Plan Estimate of Probable Costs ................................................ 41
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
4 | P a g e
ACKNOWLEDGEMENTS
The Grass Root Solutions (GRS) team would like to thank the Avalon Borough officials, management, and staff for their excellent
cooperation and assistance. Without their support, this project would not have been possible.
ELECTED OFFICIALS
Thomas Lloyd Mayor
Joshua Klicker Council President
Patrick Narcisi Council Vice President
John Crawford Council Member
Victoria Donnelly Council Member
J. P. McFeely Council Member
Shawn McWilliams Council Member
Ruth Lloyd Council Member
Lee Nelson Council Member
William Pascale Council Member
Edward Klicker Tax Collector
STAFF
Lorraine Makatura Borough Manager
Brian O’Malley Assistant Manager
Thomas Kokoski Police Chief
David Haslett Public Works Superintendent
GRS TEAM DCED
Deborah J. Grass Project Manager Michael Foreman, Local Government Policy Specialist
Jennifer Hass Financial Analyst Governor’s Center for Local Government Services
Jason Dailey Operations Consultant
David Soboslay Technology Consultant
John Trant Community Development
HRG Engineering Landscape Architecture
THIS PROJECT WAS PARTIALLY FUNDED THROUGH A
GRANT FROM THE PENNSYLVANIA DEPARTMENT OF
COMMUNITY AND ECONOMIC DEVELOPMENT,
GOVERNOR’S CENTER FOR LOCAL GOVERNMENT
SERVICES UNDER THE EARLY INTERVENTION
PROGRAM.
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
5 | P a g e
INTRODUCTION
As part of the Borough’s Early Intervention Program
study, a special conditions report was included with a
focus on the Borough’s parks and recreation facilities
including the community park and swimming pool
facility. To complete this portion of the report, the GRS
team worked with the Borough Development
Committee of the Borough Council and with Borough
staff and other interested stakeholders. Meetings began in December of 2017 and continued through
April of 2018. The goal was to plan improvements to
the Borough’s parks and recreation systems and to
memorialize the plans and projects in a master site plan
for the Avalon Community Park.
BACKGROUND
Emphasis on outdoor recreation has become the
number one driving force in community living and
neighborhood sustainability. Communities that offer
the best recreational facilities and outdoor recreation
opportunities are attractive to residents of all ages and
become a strong marketing tool for community and
economic development. The 2014 – 2019 PA Statewide Recreation Plan noted that:
“Outdoor recreation is key to helping address some of today’s pressing health care issues. Creating walkable and
bikeable communities and making improvements to the built environment can encourage active living. An increased
focus by the health care community on recreation and opportunities for new partnerships and coordination can
lessen our obesity and chronic disease crises. Getting people of all ages – including the growing population of
active seniors – connected to the outdoors and nature can have a positive effect on the health and wellness of our
citizens.”1
1 PA Statewide Comprehensive Outdoor Recreation Plan 2014-2019, Executive Summary, page 5.
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
6 | P a g e
As part of the development of the state plan, a statewide resident survey was conducted and the results of that survey are shown
in Figure 1. These results are based on the percentage of participation of individuals reported during the past year. Similar to
past surveys, walking is cited as the most popular activity and this mirrors the national outdoor recreation preferences. In every
survey conducted, about half of the population participates in outdoor recreation one or more times a week, and most
Pennsylvania residents use their local parks more frequently than any other facility.
FIGURE 1 – STATEWIDE SURVEY TOP 10 OUTDOOR RECREATION ACTIVITIES
In Avalon, there are recreation assets and opportunities that can be enhanced and expanded for maximum use by residents in
the area. The day to day park and recreation activities are overseen by Borough management staff with the Chairperson of the
0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0%
LAWN GAMES (HORSESHOES, BOCCE)
BIRD WATCHING
VISITING NATURE CENTERS
NIGHT SKY VIEWING
WILDLIFE VIEWING
SWIMMING
SCENIC DRIVING
PICNICKING
VISITING HISTORIC SITES
WALKING (STREETS, SIDEWALKS, TRAILS)
TOP 10 OUDOOR RECREATION ACTIVITIES
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
7 | P a g e
Borough Development Committee providing oversight. The Borough owns the park propertie ,s facilities, and equipment.
The recreation programs and activities are driven by the Borough Council and provided primarily through community volunteers.
The park operations and maintenance rely on the full-time public works employees and the part-time seasonal workers.
THE OPERATING BUDGET
The Parks operation is funded from the general fund revenue. The operation receives funding from time-to-time from fees,
miscellaneous local non-profits, and sports associations. Parks expenses identified in the budgets are primarily for utilities within
each park. Few funds are allocated for supplies, maintenance, or replacement funds for equipment and facilities.
TABLE 1 – GENERAL OPERATING PARKS BUDGET 2012 - 2017
453.000 — CALIFORNIA AVE PARK 2012
ACTUAL
2013
ACTUAL
2014
ACTUAL
2015
ACTUAL
2016
ACTUAL
2017
ACTUAL
453.130 — Salaries Crew 562 1,135 1,095 1,540 1,450 1,510
453.220 — Materials and Supplies 582 1,395 942 49 174 335
453.250 — Repair Maintenance 0 0 549 14,600 10,316 1,000
453.260 — Equipment 0 0 0 0 5,503 0
453.361 — Electricity 414 233 291 226 1,668 108
453.370 — Outside Repairs 812 0 0 0 0 0
453.720 — Improvements to Park 242 66 0 0 0 0
Total 453.000 — CALIFORNIA AVE PARK 2,612 2,829 2,877 16,415 19,111 2,953
454.000 — AVALON PARK 2012
ACTUAL
2013
ACTUAL
2014
ACTUAL
2015
ACTUAL
2016
ACTUAL
2017
ACTUAL
454.220 — Materials and Supplies 4,156 3,461 942 3,591 312 2,338
454.260 — Equipment 25 0 0 0 0 525
454.361 — Electricity 7,084 6,071 6,178 6,739 5,594 7,740
454.370 — Outside Repairs 3,284 85 0 220 1,523 30
454.720 — Improvements to the Park 0 533 11 6,350 217 23,334
Total 454.000 — AVALON PARK 14,549 10,150 7,131 16,900 7,646 33,967
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
8 | P a g e
455.000 — BIRMINGHAM PARK 2012
ACTUAL
2013
ACTUAL
2014
ACTUAL
2015
ACTUAL
2016
ACTUAL
2017
ACTUAL
455.200 — Tot park 0 0 0 19 7 304
Total 455.000 — BIRMINGHAM PARK 0 0 0 19 7 304
456.000 — MAYERNICK BUILDING 2012
ACTUAL
2013
ACTUAL
2014
ACTUAL
2015
ACTUAL
2016
ACTUAL
2017
ACTUAL
456.140 — Cleaning 5,067 4,160 5,828 5,342 4,992 5,038
456.220 — Operating Supplies 545 582 724 310 143 241
456.230 — Elevator Repair & Maintenance 1,794 3,623 2,166 1,941 3,410 2,160
456.250 — Repair and Maintenance 10,053 1,756 1,757 4,313 7,902 4,350
456.364 — Sewage 503 671 407 447 1,253 908
Total 456.000 — MAYERNICK BUILDING 17,963 10,793 10,882 12,435 17,700 12,697
457.000 — CIVIL MILITARY CELEBRATION 2012
ACTUAL
2013
ACTUAL
2014
ACTUAL
2015
ACTUAL
2016
ACTUAL
2017
ACTUAL
457.551 — Easter Egg Hunt 0 0 0 0 1,539 1,068
457.550 — Christmas Decorations 28 139 118 11 276 1,190
457.570 — Community Festival 2,990 3,448 4,176 3,188 3,781 568
457.575 - Fourth of July Celebration
659 3,202
Total 457.000 — CIVIL MILITARY
CELEBRATION
3,543 3,587 4,294 3,198 6,279 6,028
459.000 — AVALON FOOTBALL FIELD 2012
ACTUAL
2013
ACTUAL
2014
ACTUAL
2015
ACTUAL
2016
ACTUAL
2017
ACTUAL
459.361 — Electricity 177 84 183 295 244 882
459.364 — Sewage 84 0 65 79 84 36
459.366 — Water 1,360 96 88 70 79 85
459.370 — Repairs 173 76 0 366 2,750 10,011
Total 459.000 — AVALON FOOTBALL FIELD 1,795 256 336 810 3,157 11,014
There have been relatively few Borough funds and resources invested in the parks in the past. The Borough is fortunate that it
has received grant funds to improve park facilities and to promote activities within its park system. There is a need for long
range maintenance and replacement planning to take place within each of the Borough owned parks and facilities.
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
9 | P a g e
MUNICIPAL COMPARISON
A budget comparison with 10 other boroughs in southwestern Pennsylvania initially identified by this report is shown below. Of
the ten communities, Avalon is about average in its expenditures for Parks & Recreation and Libraries. It should be noted that
those communities that have community pools (i.e. Crafton, Avalon, Glassport and Etna) are expending much more for recreation
than their counterparts in the region. Etna Borough and Crafton Borough spend double what Avalon spends on its parks and
recreation operation while Sharpsburg spends far more than other communities on its library operation.
TABLE 2 - PUBLIC WORKS EXPENDITURES IN COMPARABLE COMMUNITIES
MUNICIPALITY NAME POPULATION EXPENDITURES
CULTURE
AND
RECREATION
LIBRARIES
CRAFTON BORO 5,951 6,063,434 335,605 60,000
CORAOPOLIS BORO 5,677 7,088,410 6,549 95,468
TURTLE CREEK BORO 5,349 3,948,383 10,275 0
BRIDGEVILLE BORO 5,148 4,790,487 78,028 20,000
AVALON BORO 4,705 4,207,925 135,844 70,102
GLASSPORT BORO 4,483 3,332,540 184,277 0
PORT VUE BORO 3,798 5,748,652 24,365 0
MILLVALE BORO 3,744 5,904,900 60,725 15,127
ETNA BORO 3,451 5,520,182 245,939 0
SHARPSBURG BORO 3,446 3,708,885 45,478 401,096
FACILITIES AND SERVICES
The Public Works staff is responsible for the maintenance of the following parks and facilities: California Ave Park, South
Birmingham tot lot, Semple Avenue Park, the Mayernik Library, the Avalon Community Park and Pool and the baseball fields at
Avalon Park.
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
10 | P a g e
AVALON COMMUNITY PARK – At 17 acres of park area, this is the main community park for the Borough. There are two
shelters that are rented to the public: one with water and electric, one that is free but is slated for demolition. There is a larger
playground area that has swings, a play structure, basketball court, full bathroom facility, small ballfield with a backstop. The
community pool and pool building are also located in Avalon Park. Facilities are inspected for utilities on Fridays by Public Works
employees and the Borough pays one employee two hours to setup for Sunday rentals. All facilities and equipment are tired and
outdated.
CALIFORNIA AVENUE – This is a large playground across from the
Borough Building and adjacent to the elementary school.
There are three larger play structures that require regular
inspection, regular tree pruning and fall leaf collection; grass
requiring the need for push mowing and extensive weed eating along
the fence line and hillside; spring animals, rubber safety surface,
fenced asphalt surfaces for tennis and deck hockey; and concrete
walkways and steps and fenced perimeter. A utility building is on
the premise but it is not currently used. There is also some lighting
within the playground. This playground gets a lot of visitors
throughout the day because of its proximity to the school and its
central location within the Borough. Allegheny County manages a
summer lunch program at this park June through August in the
summer months.
SOUTH BIRMINGHAM TOT LOT – This neighborhood parklet is a 40 x 40 lot
that consists of grass and mulch. There is a small child swing set, spring
animals, painted retaining wall, single trash receptacle, wooden picnic
bench with a roof canopy and chain link fencing surrounding the entire
perimeter.
SEMPLE AVE PARK – This smaller neighborhood parklet contains an older
child swing set, smaller wood shelter with integrated benches, one spring
animal, grass and mulch, a cherry blossom tree, and a war memorial
with flag pole and flag.
BASEBALL FIELDS AT AVALON PARK - This facility is the Boroughs primary
sports complex. There is a gravel track around the complex and 3 ball
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
11 | P a g e
fields, one with a grass infield and dugouts. The Bellevue-Avalon Baseball Association and MYTAA Avalon-Bellevue Baseball split
costs of mowing and maintaining the fields from April through June for approximately 8 weeks. No play is permitted on Sundays.
The Borough has discretion on rain day play which resulted in a shut down once in 2017. The Association manages their own
scheduling and owns and operates the concession facility which has an announcer booth on the second floor. The Association
pays all utilities and for lights on fields. Porta Johns are delivered for use throughout the season and these are paid for by BABA,
Borough Avalon and MYTAA
. There are two small storage buildings near the parking lot field area. The baseball association
o swn
one and the other is owned by the storage for it uses company fire volunteer the although Borough . Public Works maintains the
mowing of the fields in the off-season months of April through June. Proper drainage of the field was identified as an ongoing
problem
for the sports play. Parking was also identified as being an issue during seasonal play and for heavy tournament play.
MAYERNIK LIBRARY – The Mayernik Library facility is not only home to the library but also has business office space which is
presently
leased to Building Inspection Underwriters (BIU). There is also general meeting space available for rent. This
facility requires routine maintenance, regular checks of the facility inside and out by the Public Works department.
PARK PROGRAMMING
The Borough does not have a program manager or recreation director for recreation programming so there is no formal
programming regularly scheduled at the parks or within the facilities. The Borough has budgeted for several annual events
including the annual Easter egg hunt, community day festival, and Fourth of July which is a multi-community event. These
activities and events are undertaken by community volunteers and volunteer committees.
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
12 | P a g e
PARK MAINTENANCE
The Borough relies on public works personnel to maintain the various parks and parklets. These facilities require knowledge of
the play equipment installed and how it should be maintained. In older parks, it is not uncommon for park equipment to become
outdated and no longer serviceable. With such a small department, it is important that the Public Works Superintendent have a
good understanding of the latest requirements for playground fall zones and general park safety standards. According to the
Consumer Products Safety Commission, 200,000 children are treated annually for playground accidents. Of these, 70% or
140,000 occurred at public parks and schoolyards.
Each year the PA Recreation and Park Society (PRPS) sponsor a comprehensive training program on playground hazard
identification and risk management. The Certified Playground Safety Inspector (CPSI) course and exam trains individuals to
identify hazards on public playgrounds and playground equipment, how to rank
hazards according to injury potential and how to apply that knowledge and
establish a playground safety program. Upon completion of the reading, course,
and examination, an individual can be certified as a CPSI. A full-time employee
should be required to complete this training and obtain the certification. This will
provide the Borough with the necessary skills for establishing a sound risk
reduction program, a system repair system, retrofit, and removal of hazardous
equipment. It will also help the CPSI to set up a routine inspection system for the
City-owned and leased recreation and park facilities.
Because the parks and facilities were constructed and updated at various times,
there is little continuity to the aesthetics, installation methods, or fixtures
selected. For instance, various styles of benches installed with and without
concrete pads require different levels of maintenance and subsequently vary in
the amount of time it takes to mow and remove weeds around them. Additionally,
the types and styles of fencing at the various parks varies widely and requires special fencing repairs such as split rail versus
cyclone. There is a need for standardization and planning relative to maintenance practices that will limit the need for numerous
styles and special costly fixtures that may not be available. A catalogue of equipment and standardized parks structures and
installation design standards should be developed and implemented.
The use of seasonal labor is essential because of the amount of unskilled or lower skilled labor that the parks require. The
Borough pays a premium skilled labor wage rate for its full-time employees that is commensurate to skilled construction and
facility related projects. The Borough has had success with seasonal labor and should continue to employ them consistently. The
cost benefit of seasonal labor for park maintenance is a much better solution than using full-time skilled labor for these tasks.
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
13 | P a g e
AVALON POOL
The Avalon Community Pool is located in the
Community Park. The facility is owned and
operated by the Borough and seasonal
staffing is hired for lifeguard, concessions
and management duties. The pool is open
for approximately three months each year -
June through the end of August. The hours
of operation are 11:30 am to 7:30pm
Monday through Friday and noon to 6pm on
weekends and holidays. The facility consists
of a bathhouse with changing rooms,
restrooms and showers, a pumphouse and
concession building. The facility is fenced
and there is ample paved parking for the
facility.
Public Works is responsible for the grounds
and facility maintenance of the pumphouse,
changing rooms, and concession building, as
well as the pool itself. The employees
perform heavy cleaning of the facility and
clean mats in changing areas every Monday. The pool is, by far, the largest
expenditure in the Borough’s recreation budget and the most important recreation
asset owned and operated by the Borough.
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
14 | P a g e
FINANCIAL EVALUATION
The Avalon Pool budget consists of major operational items that are typical for pool operations such as wages, supplies, utilities,
repairs, contracted services, and capital improvements. The Avalon Pool, like other public swimming pools, has consistently
struggled to generate enough revenue to cover expenses. It is at the mercy of the weather each season which can expand or
contract the number of business days available. Local officials are often resistant to raising rates enough to cover the actual
operating costs to keep the pool open because it serves an important social purpose for the community. The Avalon pool has run
a deficit of 30-40% nearly every year for the last five years.
TABLE 3 − THE BOROUGH OF AVALON PARKS AND RECREATION BUDGET
452.000 — POOL EXPENSES 2012
ACTUAL 2013
ACTUAL 2014
ACTUAL 2015
ACTUAL 2016
ACTUAL 2017
ACTUAL
452.140 — Pool Salaries 34,193 31,126 25,090 26,672 28,507 28,896
452.141 — Concession Salaries 7,250 6,836 6,516 8,096 10,963 10,703
452.161 — FICA- Boro Share 3,869 3,717 2,961 3,764 4,023 4,139
452.163 — PSAB- Unemployment 2,378 1,356 1,129 1,402 1,499 1,542
452.220 — Materials Supplies 3,979 11,902 7,818 9,013 11,789 19,011
452.229 — Concession Stand Supplies 9,230 6,724 7,264 8,231 9,542 9,932
452.250 — Repair and Maintenance 21,766 1,983 1,300 729 845 848
452.321 — Telephone 303 358 351 359 353 390
452.341 — Advertising 306 446 437 599 638 480
452.361 — Electricity 1,280 965 906 1,764 1,531 1,197
452.362 — Gas 1,999 686 2,748 3,006 1,969 2,435
452.364 — Sewage 2,460 8,002 1,672 9,853 11,320 13,103
452.366 — Water 3,313 5,073 3,753 8,696 7,033 6,657
452.450 — Pool Managers' Salary 9,500 9,500 6,225 12,763 12,089 13,148
452.500 — Guard Uniforms 1,040 1,424 1,485 2,039 2,521 1,642
452.720 — Improvements to Pool 5,948 -4,676 126 716 2,920 0
Total 452.000 — POOL EXPENSES 108,814 85,423 69,780 98,501 107,542 114,123
367.200 — REVENUE Swimming Pool Fee 72,178 58,261 52,503 56,756 61,982 50,071
367.219 – REVENUE Concession 14,932
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
15 | P a g e
The Borough began to track concession revenue separately from pool fees in 2017. Typically, the pool revenue covers about
65% of the cost of running the pool. In the years when the weather is hotter and drier, the revenue covers about 75% of pool
expenses.
There are specific budget lines items that should be added that would provide further detail to identify spending trends and
revenue opportunities. For example, the pool has several different programs that are fee based. The only program tracked for
revenue is the swim lessons program. Other programs like the early swim, late swim, yoga, and movie night swim are not as
closely monitored but have correlating expenditures in lifeguard wages and pumphouse costs. These programs may or may not
be paying for themselves but there is no way to determine their revenue performance. Knowing this information through the
budget document would help the Borough management team identify more opportunities for marketing, program performance,
and continuance. In general, a more detailed financial picture of the pool revenue operations is needed for a clearer picture of
the actual operations of the pool to be determined.
Some enhancements to the pool operation should be considered. The first
relates to the handling of cash. Avalon pool accepts “cash only” for admission
and concessions. This “cash only” approach keeps operating costs down as
it avoids transaction fees and costs associated with equipment rental but is
inconvenient for attendees and has the potential for fraud.
Seasonally placed ATM’s are being installed where cash is the preferred
transaction. These are centrally located to the entrance and concession area.
Fees for the ATM are handled by the ATM vendor and not passed along to the
business hosting the machine since electric and phone service may be
required if the machine is not cellular.
The second trend is accepting credit/debit cards with mobile devices such as
the Square for ipads and iphones. Credit card transactions require equipment
and introduce fees to the user and business alike in most cases. They provide
a level of convenience, reduce the risk for fraud to the business, and are
more likely to result in an increase in concession sales revenue.
Wages for staff are the primary expense of the pool as is the case for all
pools. The primary cost containment tool for wages is time management.
Pools both private and public have begun to implement attendance
requirements in order for their pool to stay open, not just closing for
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
16 | P a g e
inclement weather. While this is unpopular among pass holders, it may
be a necessary step to containing costs. Factors that are used to dictate
closure at some pools include the following:
• Temperature 65 degrees or less on deck
• 20 swimmers or less for one hour
• Amenity use low (slide, lap lanes, etc) results in section closed
POOL MARKETING
Currently, the annual marketing for the pool is handled by Borough
management and staff. Public flyers, newsletter announcements, web
site presence on the Borough’s main web page, and social media
announcements are the primary marketing tools used.
It is difficult to be consistently creative and to come up with new and innovative ways to market the pool. Many pools have
developed a theme for their pool that is then used to for the concession stand and pool programs. Many pools have a theme
associated with their pool that they can build on for, not only concession items, but also the amenities offered at the pool. Below
are some examples of what other community pools have done to promote their programs with an overall theme.
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
17 | P a g e
POOL ATTENDANCE
Paid pool attendance is the primary revenue source for the pool operation. Management has implemented various tiered pricing
plan changes over the years making minor adjustments to annual memberships and daily admission pricing. In 2017, paid
attendance revenue accounted for 66% of the operating revenue. Table 4 provides the rate structure for the Avalon Pool in
2017. Rates are currently $7 for adults and $5 for children ages 4-17, there is no difference for resident or non-resident daily
admission rate. Most pools do have a higher daily rate for non-residents. Daily admission rates accounted for the largest source
of revenue for the pool. Table 5 provides information about the type of revenue that is derived from Pool fees. The pool closes
when there is inclement weather and posts to its social media outlets. There have been a few days announced when the pool
closes due to staffing shortages.
TABLE 4 - 2017 POOL PASS RATES
TABLE 5 – 2017 REVENUE BY TYPE
2018 POOL PASS RATES RESIDENT NON-RESIDENT
Type of Pass Full Rate Early Bird Discount
Full Rate Early Bird Discount
Children 17 and Under $ 65.00 $ 60.00 $ 105.00 $ 100.00
18 Years and Over $ 80.00 $ 75.00 $ 120.00 $ 115.00
62 Years and Over (Individual) $ 70.00 $ 65.00 $ 110.00 $ 105.00
62 Years and Over (2 Adults OR 1 Adult w-1 Child)
$ 85.00 $ 80.00 $ 125.00 $ 120.00
Family of 2 (2 Adults OR 1 Adult w-1 Child)
$ 95.00 $ 90.00 $ 135.00 $ 130.00
Family (2 Adults and 2 Children) $ 140.00 $ 135.00 $ 180.00 $ 175.00
Additional 3-4 Children $ 25.00 $ 25.00
5 or More Children $ 50.00 $ 50.00
REVENUE TYPE DOLLARS % OF
TOTAL
Daily Admissions 24,878.00 40.14%
Passes 16,590.00 26.77%
Concessions 17,989.00 29.02%
Parties 1,050.00 1.69%
Lessons 920.00 1.48%
Wrist Bands 555.00 0.90%
Total Revenue 61,982.00
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
18 | P a g e
CONCESSION OPERATIONS
Concessions are the second largest revenue
generator for the pool operations, generating
nearly 30% of the pools overall revenue. It
is managed separately from the pool
operation and management staff.
The building has two half garage doors for
serving and entry ways. There are four
coolers, a small fryer and microwave. The
equipment is not all commercial grade but
serves the purpose for the small operation.
The inside is poorly lit for serving staff and
for patrons to see the items for sale. There
are various racks and shelves that are used
for both storage and promotion of the
products being sold.
Food items are thoughtfully developed from
one year to the next with only minor changes
being made to the menu offerings each year.
Supplies are bought in bulk and tax exempt
to provide the best pricing and then marked
up. There is not an actual mark-up policy or
procedure so management staff use their
best judgement when establishing pricing on
new items. Management could establish a
mark-up policy to provide consistency.
Pricing was consistent with other pool
concession venues that were evaluated. The
menu selections were also typical with the exception of having less fried items than comparable operations. A fountain soda
system may also be more economical than providing canned and bottled drinks. A fountain system is often provided by the
vendor at no charge. Fountain systems provide more sales opportunities as well as refills, souvenir refillable cups, and uniquely
named drinks and novelties. There is an opportunity for adding retail items such as sunscreen, ear and nose plugs, eye goggles,
swim diapers, soap and shampoo. These are all items that are typically sold through pool concession stands.
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
19 | P a g e
There is a need for a larger concession sign that can showcase the items
and prices to customers as they come up to the serving window. Many of
the items that are for sale are not visible to the customer. There is also an
opportunity for items like ice cream and cold drinks to be put into a shoulder
strap cooler and walked around by a concession staff worker on especially
busy days to be sold.
In addition to adding some retail items, the concession stand may want to
consider purchasing a few chaise lounge chairs and plastic Adirondack chairs
to rent. These chairs are popular at most public pools. Rentals for the day
at area pools are $5 for the lounge chairs and $3 for the Adirondacks. These
chairs are made of hearty plastic, have a 3-5 year life and are relatively
inexpensive to purchase and maintain.
PROGRAM EVALUATION
Pool programming has been developed by the pool operations manager with
input from Borough staff and elected officials that have taken interest in the
pool operations. Over the last few years, the following programs have been
implemented:
• Movie nights
• Evening Swims
• Yoga
• Morning Lap Swims
• Swim Lessons
The revenue and attendance for these various programs varies. According
to staff, the movies at the pool have the largest attendance and are successful. Swim lessons are the second most successful
program offered. Yoga was discontinued after it showed declining interest.
An evaluation of other community pools in the area showed the following programs in place:
• Water polo clubs (evening and early morning games / practice)
• School swim athletics (training and practice)
• Scuba diving training (privately instructed)
• Senior water aerobics (privately instructed)
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
20 | P a g e
The Northgate School District boys swim team are recent WPIAL AA champions. This is an excellent indication that competitive
swimming is valued in the community and it could serve the Avalon Community Pool to make a connection with this program.
AREA POOL COMPARISONS
As part of this study, the team conducted a survey of some public pools in Allegheny County. Table 6 provides this information.
TABLE 6 - COMPARISON OF SELECTED PUBLIC POOLS IN ALLEGHENY COUNTY
Borough Website Pool
Size Amenities Hours
Daily Fee /
Annual Pass
Resident
Daily Fee/
Annual Pass
Non-Resident
Program
Notes
Misc.
Features
Avalon
http://www.bo
roughofavalon
.org/avalonpo
ol.html
8,700 sf
Swim slide
chute,
small child
slide, lap
lanes
11:30-
7:30pm
weekdays
12 to 6pm
weekends
and holidays
$7 adult,
$5 child
$60 / $95
Daily rates are
same
$105/ $130
multiple age
tiers for
single /
senior/ and
family
Bellevue
https://www.b
ellevuepa.org/
memorial-pool
Zero entry;
children’s
feature
12 – 7:30pm
weekdays
12 – 6pm
weekends
and holidays
$6 Adult
$5 Child
$75/ $150
$100/ $225
Pool
parties
$125
Residents/
$175 Non-
Residents
Special
Discount for
Ross
Township
Dormont
http://www.bo
ro.dormont.pa
.us/
60,000 sf
Large
water slide,
in-pool
children’s
water
feature
12 - 8 pm
every day
2 age tiers
$4-$6
$80 / $150
2 age tiers
$5-$7
$130/ $275
Lessons
offered
through
JEM
$100 pool
party
residents/
$125 non-
residents
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
21 | P a g e
Community Website Pool
Size Amenities Hours
Daily Fee /
Annual Pass
Resident
Daily Fee/
Annual Pass
Non-Resident
Program
Notes
Misc.
Features
Etna
http://etnabor
ough.org/swi
mming-
pool.html
6,625 sf
Two tube
slide,
concession
stand
12-7pm
every day
$5
$85/$120
$7
$120/ $190
Water
aerobics
for fee
$2/$3
Baldwin
http://www.ba
ldwinborough.
org/162/Pool
Small slide;
swim lanes
12-6 pm
weekdays
12-8 pm
weekends/h
olidays
$6
$55/$155
$6
$80/$215
2-hour pool
party rental
off hours
$250
Whitehall
https://www.
whitehallboro.
org/recreation
/pool.html
8,000 sf
Separate
baby pool,
painted lap
lanes,
concession
stand
12:30pm-
6:30 pm
every day
$6
$50/ $250
N/A
$30 pp for
group
swim
lessons
Residents
Only; can
purchase a
guest pass
for daily
use
White Oak
http://www.w
oboro.com/rec
reation.htm
11am–7pm
every day
$5
$60
$10 / 100
Children
under 2
free, photo
id issued
and
required or
$10 fee,
free
admission
on
Community
Day
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
22 | P a g e
BUILDING AND GROUNDS MAINTENANCE
The pumphouse building is one of the most important structures that impacts the operation of the pool. The pool filtration system
and
electric supply are all housed in this facility. It is imperative that the building be inspected regularly both externally
and internally for routine maintenance items as well as safety. Items such as disconnected roof drains as well as missing or
disconnected ground connections or splash pads were visible and can cause damage to the buildings foundation.
Staff have developed a good monitoring system for trash and restrooms that
is documented and logged on a simple form with initials. This allows for pool management to quickly spot check the facilities.
Paper products, ground litter, canned trash, and cleaning issues are checked hourly when the pool is open. The documented
performance is effective and should continue to be spot checked by management.
The bathhouse is the most visible and visited building on the premise. It serves as the main entrance, changing room, restroom
and shower for pool visitors. It is the first thing visitors see when they arrive and the last impression they will have when leaving
the pool. The appearance of this structure both inside and out is important to not only attract new visitors to the pool but also
to retain existing memberships. Unfortunately, this structure should be completely renovated. The appearance is institutional,
outdated, and does not meet the needs of the operation with its layout and amenities. There is nothing inviting or encouraging
about the primary bathhouse building.
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
23 | P a g e
The bathhouse has undergone many changes and renovations since its initial
construction. When renovations were in progress, the public works staff got
busy and have moved on to other projects, leaving the removal of the
demolition components. This is a familiar sight within the building that can be
easily remedied. There are disconnected pipes, wires and vents throughout
that can be corrected with little expense.
Along the perimeter fencing it was visible that there are dead ash and dying
oak trees. These trees pose a threat to the bathhouse, fencing and lighting of
the pool and should be addressed with professional removal.
There are various grass areas inside the pool perimeter that should be treated
for weeds and seeded to improve coverage. There were noticeable bare spots
in prime locations that should be repaired to improve the look of the grounds.
Weed and feed products are a low-cost maintenance product that will make a
noticeable improvement.
POOL SYSTEM MONITORING
The pool is electronically monitored with the
PoolComm system. This is a good system that
consists of Oxidation Reduction Potential (ORP)
probes for Ph and chlorine. The system allows for
automatic feed adjustments and has the capability of
alerts when parameters are not met. Public Works
has a trained Certified Pool Operator (CPO) as
required that is proficient in the pool operation. The
Pool Manager is typically trained and certified as a
CPO also. Proper logs are maintained with readings
that are taken at various intervals during the pools
hours of operation.
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
24 | P a g e
AVALON PARK – MASTER SITE PLAN
As part of the work done with the Borough Development Committee, a complete master site plan for the Avalon
Park Community
was developed. The plan assumes at least four (4) phases that would be implemented over time. The overarching
elements are to design for long-term sustainability, return much of the park to natural elements, address storm water
drainage problems, and install play equipment, fitness stations, and pedestrian connections that will encourage increased use
and healthy lifestyles. F IGURE 2 – AVALON COMMUNITY PARK – MASTER PARK PLAN
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
25 | P a g e
PHASE 1 – BALLFIELD AND
STORMWATER IMPROVEMENTS
The existing ballfield area in the community park
requires significant upgrades and improvements.
The most pressing need is to repair the existing
culvert and field as needed, install ADA
components, and address storm water runoff
through repair of the existing culvert. It was
decided that this was the most pressing need
and that it should be completed in the first phase
of the project. Phase 1 encompasses all
improvements to the ballfields and track area
west of New Brighton Road. A PA Department of
Conservation and Natural Resources,
Community Conservation Partnership Program
grant request was submitted on April 18, 2018
to complete these Phase 1 improvements.
A. Stormwater and infrastructure
repair, including the investigation of the
existing drainage structures running
under the baseball field and required repairs. The existing stormwater culvert has been a source of damage to the park.
Necessary drainage improvements to the existing ballfields will be completed.
B. Connectivity and accessibility improvements include additions to Avalon Borough’s pedestrian network of sidewalks
in the surrounding neighborhoods, including crosswalks, to create safe routes for pedestrians to enter the western section
of the park. This includes demolition of an existing stairway above the concrete bleachers that does not meet current
safety requirements and does not end at a safe crossing. Accessible parking and an accessible path to the bleachers is
provided adjacent to the existing track. Directional signs for the ballfields are added at the municipal lot above the fields.
C. Improvements to existing athletic facilities include resurfacing the existing track, top dressing the outfields of all
three ballfields, and renovating infield surfaces as needed. Additionally, this phase would replace antiquated scoreboards,
repair the dugout roofs, and provide additional three-row steel bleachers. Two drinking fountains will be installed, as
requested by stakeholders, along with new waste receptacles.
D. At the park entry, an entrance sign with a small planting bed is proposed in a new location to replace the existing worn,
low-visibility sign. The adjacent existing parking lot is to be striped to improve safety and efficiency. Additionally, security
lighting and cameras are proposed for this lot.
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
26 | P a g e
FIGURE 3 - PHASE 1 BALLFIELD AND STORMWATER IMPROVEMENTS
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
27 | P a g e
PHASE 2 – PLAY EQUIPMENT AND FITNESS STATIONS
Phase 2 includes all improvements from the entrance of the park through the existing playground area.
A. The existing playground is the focus of Phase 2, where outdated and unsafe equipment is to be demolished. Proposed
improvements include a play structure for ages 2-12; a separate area for proposed swings; and a centrally located adult
fitness area with equipment. Poured-in-place rubber safety surface is proposed for longevity and ease of maintenance,
with a concrete perimeter accessible sidewalk connecting to the existing parking area. Shade structures, benches, and
improved landscape border plantings define the area. Additionally, a drinking fountain is proposed in the existing
adjoining patio area.
B. Riparian restoration items include the removal of an existing unsafe
metal pedestrian bridge over Spruce Run; removal of hard structures
and shoring along Spruce Run where it will no longer be needed after
restoration; stabilization of any pipe crossings; and a combination of
native riparian plantings and cost-effective constructed best
management practices to improve flow, mitigate risk, and improve
ecological condition.
C. Connectivity & pedestrian network improvements are proposed
to include additions to the pedestrian network on the east side of New
Brighton Road, providing a safe alternate path for pedestrians that
formerly used the Spruce Run bridge to be removed. Additionally,
crosswalks and a lighted pedestrian crossing sign on New Brighton
Road are proposed to further enhance safety. The proposed sidewalk continues through the large parking area to the
existing bath house to allow separation of pedestrian and vehicle traffic within the park, as well as improve accessibility
(the existing sidewalk behind the pool area is serviceable but not accessible due to stairs).
D. Pool area proposed improvements include a new splash pad, a drinking fountain, and screening vegetation on the slope
between the pool fence and parking area.
The replacement of play equipment and a fitness station will be accessible from the newly installed parking areas. Access ramps
is a priority for the Phase 2 improvements for the Community Park.
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
28 | P a g e
FIGURE 4 - PHASE 2 – PLAY EQUIPMENT AND FITNESS STATIONS
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
29 | P a g e
PHASE 3 – PAVILION, RIPARIAN RESTORATION, AND ACCESSIBLE PARKING
Phase 3 continues from the Phase 2 existing playground to the existing pavilions at the back of the park.
A. Riparian restoration includes the following proposed items: removal of an existing damaged brick pedestrian bridge on
Spruce Run; removal of hard structures and shoring where it will no longer be needed after restoration; stabilization of
any pipe crossings; and native riparian plantings and cost-effective constructed BMPs to improve flow, mitigate risk,
and improve ecological condition on Spruce Run. Demolish the existing, deteriorated Shelter 3 south of Spruce Run; use
the Shelter 3 area for riparian restoration activities as needed.
B. A proposed Shelter 3 area will be installed
north of Spruce Run, removing the need for a
pedestrian bridge and filling the need for a
“free” shelter for park users. The proposed
Shelter 3 area includes an additional accessible
parking area, a shelter with concrete pad, and
a concrete walk to a paved riparian restoration
viewing area with seating and interpretive
signage to acquaint residents with the riparian
restoration project. Also proposed are a fire
ring and small landscape plantings to improve
aesthetics.
C. To improve circulation, safety, and accessibility, asphalt paving is
proposed for the existing driveway leading to the back of the park. The road’s
existing drainage structures will be modified or replaced as necessary. The
proposed accessible concrete sidewalk continues along this road from the Phase
2 playground to the Phase 4 area.
D. Finally, proposed improvements to the existing basketball court
include renovating the court surface and replacing the fence and equipment
which is deteriorating and/or damaged.
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
30 | P a g e
FIGURE 5 - PHASE 3 PAVILION AND RIPARIAN RESTORATION
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
31 | P a g e
PHASE 4 – NEW PLAY AREAS AND KITCHEN
The focus of Phase 4 is a proposed playground attraction to be constructed at the “family” ballfield between Shelters 1 and 2.
There is currently no play attraction in the community park and the proposed installment would be a destination for families in
the area. Also, the addition of pedestrian connections in Phase 3 would make the park markedly more accessible to residents of
all ages and physical abilities.
A. The proposed playground attraction is designed to draw activity from surrounding communities into Avalon park,
and is intended to create a destination within Avalon. The playground will include 2-3 large, all-ages play structures,
poured-in-place rubber safety surface, a perimeter accessible concrete sidewalk, and landscape plantings to define the
new play space and beautify the area.
B. To improve circulation, safety and accessibility, the following improvements are proposed: an additional parking
area with accessible parking to serve the proposed playground attraction; striping the existing parking lots to improve
safety and efficiency; a concrete sidewalk connection to a redesigned accessible ramp serving existing restrooms; and
concrete sidewalks and crosswalk between the playground, parking areas and pavilions.
C. Kitchen improvements for existing shelters are
proposed adjacent to the playground. At existing Shelter 1,
renovate the existing kitchen; adjacent to Shelter 2, construct
a proposed kitchen to serve growing demand from park users.
D. Phase 4 completes riparian restoration. Continue
native riparian plantings and constructed BMPs from Phase III
to the end of the park.
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
32 | P a g e
F IGURE 6 - PHASE 4 PLAYGROUND ATTRACTION AND K ITCHEN
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
33 | P a g e
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
34 | P a g e
OBSERVATIONS
The Borough parks and the pool facility are tremendous assets for the community. The Borough currently provides parks and
recreation facilities and services to over 4,500 residents in Avalon and countless other residents in the region. Parks and
recreational opportunities provide a community gathering place that promotes a healthy lifestyle and an enriched quality of life.
While the funding for the Parks appears to be in line with other communities of similar size, wages and benefits for the public
works employees are not captured in the Parks and Recreation categories. Labor is always a major component of maintenance
along with supplies and equipment replacement. To see a true picture of what it takes to operate and maintain these facilities,
better accountability systems should be put into place to track hours that are associated with parks maintenance and operation.
The Borough owns an abundance of parks and maintains several open green spaces or lots that require an extensive amount of
knowledge of specific equipment and amenities. Safety updates on ADA requirements of walking surfaces and changes to
consumer safety products are important for the Public Works personnel to be aware. The amount of grass to be maintained and
areas to be trimmed requires several days per week for just normal upkeep during the regular growing season and nearly every
day when the growing season is at its peak. Thoughtful planning for any addition to any of the parks should keep maintenance
time and attention, as well as the sustainability of the improvement in mind.
Overall the parks are very well maintained in season. While there are not specific work tasks or check lists prepared, the work
force has good attention to detail and due to the seasoned tenure of the employees, the work to be completed is understood by
the workers. But there is a need for consistent direction and overall development of the work of the parks from a maintenance
perspective. There is plenty of room to improve efficiencies from the type of equipment selected for mowing, to how maintenance
equipment is transported, to painting or removing old and dilapidated play structures. The public works Superintendent and full-
time employees will need to have a better understanding of best programs and practices to support the use and future
improvements to the Borough’s park system.
According to the 2014-2019 Statewide Comprehensive Recreation Plan, it is important to address several initiatives relative to
local parks. These are:
1. Connect citizens to “close-to-home” recreational opportunities and green space.
2. Position local park facilities and recreation programs as essential services.
3. Create and leverage partnerships that expand outdoor recreation opportunities.
4. Coordinate strategic investment in local priorities and respond to emerging trends.
It is important for the future sustainability of the Borough that the resources necessary for parks and recreation projects and
programs are thoughtfully and realistically applied to creating connections for residents of all ages to be stewards of recreation
and nature so that it can have a positive impact on the long-term wellness of Avalon residents.
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
35 | P a g e
RECOMMENDATIONS
RECOMMENDATION NO. 1 - MAXIMIZE THE USE OF BOROUGH PARKS BY ADOPTING THE MASTER SITE PLAN
Strong parks make strong neighborhoods and the Borough is rich in park and greenspace. Avalon is .69 square miles and relies
on the Community Park for most of its recreation needs. The park is not fully maximized in terms of facilities or programming.
Scheduling more programming provides lifestyle enhancement opportunities for all ages. Some action items that should be
considered by the Borough include:
• Implement and pursue funding based on the Avalon Park Master Site Plan included in this study. The plan is shown in
phases so that the logical staging of improvements can be made as funding becomes available.
• Encourage healthy programs like running, walking, biking events in the park and in the central business district to
encourage the use of the park and to create gathering events for residents.
• Consider the creation of a Recreation Board of volunteers to begin to explore possible programming for Borough parks.
About 15% of the Borough population is under 18 and there should be programming for this age group. The Recreation
Board should act as an advisory board to Council and should provide volunteer labor to help support recreation
programming.
• Hire a Recreation Director with an early childhood or recreation
background to develop, coordinate, and oversee summer programming,
especially summer day camp in the parks. Fees can be charged that
would partially cover the salary of the Director.
• Work with senior agencies to include additional programming and
activities for senior citizens. In surveys and crowd sourcing, seniors have
indicated a preference for planned day trips; strength, stretching, fitness
and cardio classes; healthy cooking classes; gardening, movies, yoga,
and dance classes.
RECOMMENDATION NO. 2 – DEVELOP AND ADOPT A PEDESTRIAN AND BIKE TRAIL PLAN.
The Borough should develop and adopt a pedestrian and bike lane plan that creates a local system to link parks, employment
centers, transit facilities, and adjacent municipalities. The “pedestrian oriented” plan would:
• Provide convenient and well illuminated pedestrian walkways throughout California Avenue and within parking
lots.
• Provide pedestrian links between the business district and communities adjacent to the Borough.
• Provide pedestrian improvements and connections between California Avenue and adjacent neighborhoods and
the community park.
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
36 | P a g e
Healthy lifestyles and changes in demographics have created a demand for
more pedestrian oriented activities and the need for more walkable
communities. Enabling safe access for pedestrians and bikers will help
improve the experience and help to make alternatives to car travel more
attractive. Adopting the policy of “complete streets” for the design,
development, or redevelopment of Borough roads should be a priority.
According to the National Complete Streets Coalition
(smartgrowthamerica.org) “Complete Streets are streets for everyone. They
are designed and operated to enable safe access for all users, including
pedestrians, bicyclists, motorists, and transit riders of all ages and abilities.
Complete Streets make it easy to cross the street, walk to shops, and bicycle
to work. They allow buses to run on time and make it safe for people to walk
to and from train stations.” Complete streets can also be important for
creating economic activity for smaller business districts such as California
Avenue. According to the National Complete Streets Coalition: “Building more sidewalks and striping bike lanes has been shown
to create more jobs than traditional car-focused transportation projects.” With the increased demand for bike lanes and pedestrian
connections from the public, and with the goal of increasing the attractiveness of Avalon for the millennial and young professional
class, the Borough would be well advised to consider exploring pedestrian and bike path options.
RECOMMENDATION NO. 3 − CONSIDER USING SUMMER INTERNS OR SEASONAL EMPLOYEES TO DEVELOP RECREATION
PROGRAMMING.
The Borough has a lot to offer in its parks. California Aveenue with its
fenced Dek Hockey area is a prime location for a summer dek hockey
league to play. The ballfields at Avalon Park, while used for the early
part of the season are not used during the later part of the season or in
the fall. Fall league adult softball is still popular and is always looking
for centrally located fields to play through November. The two smaller
parks on Semple and South Birmingham may serve as good craft and
or activity play areas that could serve those neighborhoods with an
organized program. All of these ideas require time to develop and
manage and may be a good opportunity for an intern to research/survey
the community and help develop and manage the activities. Programs
are typically sustainable when a small fee is established based on the
program involvement from staff, this should also be researched. The
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
37 | P a g e
Local Government Academy offers a municipal internship program that pays 50% of the intern’s wages for the year. This may
be a good option for Avalon in future years.
RECOMMENDATION NO. 4 - REVIEW FEES FOR PROGRAMMING AND FACILITIES ON AN ANNUAL BASIS.
The Borough should annually review all fees charged for rentals and facility usage to ensure that the fees partially cover the
recreation expenses. Reviewing the fees on an annual basis during the regular budget adoption process will ensure that adequate
charges are imposed to recoup some of the Borough’s cost of providing programming.
RECOMMENDATION NO. 5 - DEVELOP AND USE WORK CODES ON TIME SHEETS TO TRACK WORK DONE AT PARKS.
A more detailed timesheet and work order system would allow for employees to code work performed at the parks against codes
that would then allow management to evaluate the time spent working in the parks. A true cost of the operation and maintenance
of the parks is essential to see how much of the Borough’s labor is related to park and recreation activities. This would serve as
as a basis for evaluating fees for programs and facility use.
RECOMMENDATION NO. 6 - CONDUCT A PARK SIGN INVENTORY AND ADDRESS FADED AND UNNECESSARY SIGNS
It is important for the public when entering a park to know not only the identity of the park that they are visiting but also to
understand the rules of the park. There are many signs that have been installed at the Avalon parks over the years that should
be reviewed for their use and overall appearance. Avoid sign pollution - a sign inventory should be conducted and evaluated for
sign reduction and replacement. Attractive identification, directional, and rules signs should be installed at every park.
RECOMMENDATION NO. 7- TRAIN AT LEAST ONE CERTIFIED APPLICATOR
THROUGH THE DEPARTMENT OF AGRICULTURE.
The Borough has a need for the spraying of herbicides and pesticides in and around
its public facilities to control vegetation. Public entities are required to have at least
one certified applicator, licensed through the Commonwealth, in order to utilize even
the smallest amount of products like “Roundup.” There are special requirements for
public entities that must be observed in order to perform this activity. Additional
information on the full requirements of certification may be found through the Penn
State Agriculture Extension at this link http://extension.psu.edu/publications/agrs-118
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
38 | P a g e
RECOMMENDATION NO. 8 - ESTABLISH ROUTINE MAINTENANCE AND INSPECTION SCHEDULES TO INCREASE PUBLIC SAFETY
AND REDUCE LIABILITY.
The amount of maintenance needed at the Borough’s parks can be overwhelming for the public works employees. The busiest
time for park maintenance can be demanding because it is also the peak vacation time for workers. For this reason, it is important
to have written check inspection and safety checklists and to have seasonal employees hired and trained before these peak
periods. If the public works Superintendent were to establish a routine maintenance and inspection schedule with sign-off
checklists, employees would understand the duties required and the parks appearance and functionality would rise. Public spaces
must be safe and accessible to all members of the public at all times. Unsafe play equipment, walkways, and debris are not only
unsightly and devalue a community asset but lead to liability issues for the Borough. A full-time employee should be required to
complete the CPSI training and obtain the certification through the PA Recreation and Park Society. This will provide the Borough
with the necessary skills for establishing a sound risk reduction program, a system repair
system, and removal of hazardous equipment. It will also help the CPSI to set up a
routine inspection system for the City-owned and leased recreation and park facilities.
RECOMMENDATION NO. 9 – REGULARLY PERFORM A COMPREHENSIVE ANALYSIS OF
COMPETITIVE FUNDING OPPORTUNITIES AT THE LOCAL, STATE, AND FEDERAL LEVELS
THAT COULD SUPPORT RECREATION PROGRAMS AND CAPITAL PROJECTS.
County, state, and federal funding programs are available to help in funding recreation
programs and projects. The PA DCNR offers grant programs to aid in rehabilitation and
development of parks and recreation facilities, land acquisition to support active or
passive recreation, and planning studies to assess project feasibility and/or plan
comprehensively for the recreation needs. Most competitive grant programs carry local
match requirements, which require applicants to document cash and/or in-kind
contributions (e.g. staff time) proportionate to the requested grant amount. Securing
the required match for a competitive grant is a challenge that requires creative solutions.
In some cases, match can be comprised of several funding sources, from CDBG funds to direct cash contributions to donated
services. The Commonwealth’s programs recognize the appraised value of land as an eligible match when the land will be
incorporated as part of the recreation project. Grant funds represent a one-time cash infusion and should not be utilized to
balance an operating budget. But grant funds can represent a viable source of funding to offset the costs associated with major
capital projects. Some opportunities are provided under the following programs.
PA GREENWAYS, TRAILS, AND RECREATION – There are regional trails not far from Avalon. Trails are desirable to promote healthy,
active lifestyles. Trails also promote economic activities in and around their locations. Act 13 of 2012 establishes the Marcellus
Legacy Fund and allocates funds to the Commonwealth Financing Authority (the “Authority”) through DCED for planning,
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
39 | P a g e
acquisition, development, rehabilitation and repair of greenways, recreational trails, open space, parks and beautification projects.
Connecting neighborhoods and parks within the Borough is also desirable and would be looked at positively for funding in many
cases. Visit the website at: https://dced.pa.gov/programs/greenways-trails-and-recreation-program-gtrp
DEPARTMENT OF CONSERVATION AND NATURAL RESOURCES (DCNR) − COMMUNITY CONSERVATION PARTNERSHIPS PROGRAM (C2P2)
– Parks and Recreation Planning, Development, Land Acquisition, and Partnership Projects. Phase 1 of the Avalon Park Master
Site Plan was submitted to this program for funding on April 18, 2018. Avalon should prepare and submit future applications for
a pool feasibility planning study and Phase 2 of the Avalon Park Master Site Plan. Both are eligible projects for this funding
source. These applications are due in mid-April of each calendar year. Visit the website at:
http://www.dcnr.pa.gov/Communities/Grants/Pages/default.aspx
GAMING ECONOMIC DEVELOPMENT AND TOURISM FUND (GEDF) – The GEDF fund was created for community and economic
development projects in Allegheny County and is funded through gaming revenue. Eligible projects include projects that promote
local economic activity, improve infrastructure, public safety projects, and projects that improve or create civic, cultural, or
recreational activities or facilities. Single applications are submitted through the DCED Single Application program and are
reviewed and approved by the Commonwealth Financing Authority (CFA) which is controlled by the caucuses of the PA General
Assembly. State representatives and senators must be supportive of the project in order for it to advance. These applications
are due before October 1 of each calendar year. Visit the website at: https://dced.pa.gov/download/gaming-economic-
development-tourism-fund-guidelines
COMMUNITY INFRASTRUCTURE AND TOURISM FUND (CITF) – The CITF is an annual allocation of $6.6 million from gaming revenue
for use in Allegheny County for construction, development, improvement and maintenance of infrastructure projects. CITF
provides grants and loans to municipalities to carry out important project for development of key sites for future use. Stormwater
infrastructure and recreation amenities are eligible projects under the CITF. Applications are typically accepted between January
and February of each calendar year. Visit the website at: http://www.county.allegheny.pa.us/economic-
development/authorities/citf-grant.aspx
FISH AND BOAT COMMISSION – BOAT LAUNCH INFRASTRUCTURE GRANTS – The Commission has a number of grant programs that
provide funding in support of fishing, boating and aquatic resource conservation. A list of the major grant programs are available
at the website at: http://www.fishandboat.com/Transact/Grants/Pages/default.aspx
RECOMMENDATION NO. 10 − CONTINUE TO ENGAGE IN STRATEGIC PLANNING THAT TAKES A COMPREHENSIVE VIEW OF THE
BOROUGH'S PARKS AND RECREATION PROGRAMS, FACILITIES, AND PROJECTS.
Th Boroughe Development Committee have taken a proactive approach to parks and recreation planning. Continued strategic
planning for the Borough should include ongoing discussions about:
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
40 | P a g e
• Where are we going? (Mission)
• How do we get there? (Strategies)
• What is our blueprint for action? (Budget,
Goals, and Objectives)
• How do we know if we are on track?
(Control)
Issues for discussion should include:
• Are there any programs or services that
we currently provide that we should stop
providing? If yes, which programs?
• Are there any new programs that the
Borough should start offering?
• What opportunities should the Borough
pursue over the next five years?
• What challenges is the Borough likely to
face over the next five years?
• What are the emerging trends?
It may be helpful to continue to work with an independent consultant who has training in recreation planning to facilitate
discussions between the Borough and the residents. The goal of this strategic planning process should be to establish goals that
can be achieved within a reasonable timeframe.
BOROUGH OF AVALON EARLY INTERVENTION PLAN – PARKS AND RECREATION
41 | P a g e
APPENDIX A – AVALON COMMUNITY PARK MASTER PLAN ESTIMATE OF PROBABLE COSTS
See following pages.