1
The “Building Performance What Ifs” project collaborated with Boora Architects to analyze the envelope design performance for three schools in the Portland area. The three selected schools, North Clackamas High School, Rock Creek Middle School, and the Early Learning Center addition to Earl Boyles Elementary School serve as examples of evolving knowledge and strategies in envelope performace design in recent years. Building Performance “What Ifs” Thermographic readings Methodology and Timeline Thermographic readings Thermographic readings Sefaira Strategies Sefaira Strategies Sefaira Strategies Findings For Rock Creek Middle School, significant loss through the exposed slab edge could be seen in the thermographic imaging. The thermographic imaging findings were consistent with predictions made from baseline data. Strategies in air leakage as well as wall R value showed the most significant changes in Sefaira Findings Because the envelope is well designed, Sefaira iterations were less telling in Earl Boyles; however, the thermographic imaging revealed a thermal bridge in the slab that was not forseen. Using a higher performance glazing would actually have a significiant impact on the school’s annual space heating. This is because the rest of the envelope is so tight. Findings Thermographic imaging found obvious heat loss through Clackamas High School’s exposed floor slab. Through Sefaira, improving the building’s air leakage strategy had the biggest effect on the overall performance. Increasing the roof to 60 had a significant impact. Increasing the r-value of wall glazing by a percentage change of ten had a marginal impact on energy use due to overall square footage. Earl Boyles Elementary School Rock Creek Middle School North Clackamas High School Boora Architects: Mike Manzi, Abby Dacey, Jacob Peel, Stephen Endy PSU School of Architecture Graduate Students: Paul Conrad, Alejandra Ruiz, Genevieve Wasser The research consisted of taking thermographic image readings of the building envelope. Data was collected over two separate field visits to each school during times of cold outdoor temperatures in late November and early December. In addition to this, the three schools were modeled and brought into Sefaira to analyse strategies for improved envelope performance. The thermographic images were used to help identify areas where the envelope is underperforming. Location: 10822 SE Bush St, Portland, OR Year of Completion: 2014 Square Footage: 15,000 addition Occupancy: 188 Location: 14897 SE Parklane Dr, Happy Valley, OR Year of Completion: 2010 Square Footage: 129,000 sqft Occupancy: 750 Location: 14486 SE 122nd Ave, Clackamas OR Year of Completion: 2002 Square Footage: 275,000 sqft Occupancy: 2,213 Roof Assembly: R-50 Membrane Roofing 10” Polyiso Roof Insulation Self-adhered Air/Vapor Barrier Roof Assembly: R-38 Membrane Roofing 3” Polyiso Roof Insulation Polyethylene Vapor Barrier Batt Insulation Below Deck Roof Assembly: R-25 Membrane Roofing 5” Polyiso Roof Insulation No Air/Vapor Barrier Wall Assembly: R-30 Metal Panel Cladding Thermally-Broken Framing Assembly 3 1/2” Mineral Wool Insulation Self-Adhered Air Barrier 6” Batt Insulation In Wood Stud Cavity Wall Assembly: R-16 Metal Panel Cladding Continuous Z Supports 1-1/2” Extruded Polystyrene Insulation Building Wrap (Tyvek) 6” Batt Insulation In Stud Cavity Wall Assembly: R-7 Metal Panel Cladding Continuous Z Supports Building Wrap (Tyvek) 6” Batt Insulation In Stud Cavity Glazing System: U-30 Ultra-thermal aluminum frames Double pane, low-e glass Standard spacer Glazing System: U-30 Thermally Broken Aluminum Frames Double-Pane, Low-E Glass Standard Spacer Glazing System: U-41 Thermally Broken Aluminum Frames Double-Pane, Low-E Glass Standard Spacer Air Tightness: 0.13 Measured Value (Cfm/Sf at 1.57 Psf) Air Tightness: No Tested Value Air Tightness: No Tested Value Insulated Slab Edge Measured Value (Cfm/Sf at 1.57 Psf) Exposed Slab Edge Exposed Slab Edge Detail 1. Southeast corner of Northeast wing Detail 1. Roof overhang, Southwest corner of South wing Detail 1. Recess speaker on East Cexterior courtyard wall Detail 2. North face of Northeast wing Detail 2. Slab on southwest corner of South slab Detail 2. North exterior courtyard wall. Leakage through windows, door, and concrete slab Detail 3. South face of Northeast wing Detail 3. Thermal bridging in studs on North face of Media Center Detail 3. Slab of corner of North exterior courtyard wall Section. Wall section of Northeast wing Section Wall section of East facade of courtyard Wall Section at courtyard wall 0 5 10 15 20 25 30 35 40 0 50000 100000 150000 200000 250000 0 2 4 6 8 10 38 202250 8.25 .18 .26 .36 - 10 + 10 .13 40 20 60 70 U-Factor Glazing % Air Leakage Wall R-Value Roof R-Value EUI (kBTU/ft2) Annual Space Heating (kBTU) Heating Capacity (ton) Glazing U-Factor: .36 BTU/h ft2 °F Wall R-Value: 30 BTU/h ft2 °F Air Leakage: .13 cfm/ft2 BASELINES Glazing Percentage: 25.5 Roof R-Value: 50 BTU/h ft2 °F 0 10 20 30 40 50 0 1000000 2000000 3000000 4000000 5000000 6000000 0 50 100 150 200 43 5392466 190.95 .18 .26 .36 - 10 + 10 .13 40 20 50 60 EUI (kBTU/ft2) Annual Space Heating (kBTU) Heating Capacity (ton) U-Factor Glazing % Air Leakage Wall R-Value Roof R-Value Glazing U-Factor: .41 BTU/h ft2 °F Wall R-Value: 7 BTU/h ft2 °F Air Leakage: .50 cfm/ft2 BASELINES Glazing Percentage: 28 Roof R-Value: 25 BTU/h ft2 °F 0 10 20 30 40 50 0 500000 1000000 1500000 2000000 2500000 3000000 0 20 40 60 80 100 47 2473808 92.25 .18 .26 .36 - 10 + 10 .13 40 20 50 60 U-Factor Glazing % Air Leakage Wall R-Value Roof R-Value EUI (kBTU/ft2) Annual Space Heating (kBTU) Heating Capacity (ton) Glazing U-Factor: .40 BTU/h ft2 °F Wall R-Value: 14.5 BTU/h ft2 °F Air Leakage: .50 cfm/ft2 BASELINES Glazing Percentage: 27 Roof R-Value: 39 BTU/h ft2 °F week 1 week 2 week 3 week 4 week 5 week 6 week 7 week 8 week 9 week 10 research parameters school selections and initial research baseline building data provided from firm GOALS model buildings in Sketchup individually CONCLUSIONS IMPROVEMENT STRATEGIES FLIR READINGS SKETCHUP cold weather readings coordinate with occupancy behavior group examine joints, floors, parapets seek professional opinion on Flir camera strategies compare data with photos and wall sections EARL BOYLES ELEMENTARY ROCK CREEK MIDDLESCHOOL CLACKAMAS HIGHSCHOOL SEFAIRA - WEB establish model baselines correct model errors OFFICE DIALOGUE re-examine project goals schedule school visits determine what to examine in thermographic imaging solidify field data collection strategies glazing u value: 0.18 glazing u value: 0.26 glazing u value: 0.36 SHGC: 0.26 S facades only SHGC: 0.26 all facades wall r value: 40 wall r value: 20 floor r value: 10 floor r value 20 roof r value: 50 roof r value: 60 schools lack adequate floor insulation heat loss through joints between classrooms, expansions noteable improvement in EUI with air leakage improvement improvements in EUI when wall insulation increased

Bora | Architecture and Interiors - North Clackamas High School … · 2020. 2. 6. · Year of Completion: 2010 Square Footage: 129,000 sqft Occupancy: 750 Location: 14486 SE 122nd

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Bora | Architecture and Interiors - North Clackamas High School … · 2020. 2. 6. · Year of Completion: 2010 Square Footage: 129,000 sqft Occupancy: 750 Location: 14486 SE 122nd

The “Building Performance What Ifs” project collaborated with Boora Architects to analyze the envelope design performance for three schools in the Portland area. The three selected schools, North Clackamas High School, Rock Creek Middle School, and the Early Learning Center addition to Earl Boyles Elementary School serve as examples of evolving knowledge and strategies in envelope performace design in recent years.

Building Performance “What Ifs”

Thermographic readings

Methodology and Timeline

Thermographic readings Thermographic readings

Sefaira StrategiesSefaira StrategiesSefaira Strategies

FindingsFor Rock Creek Middle School, significant loss through the exposed slab edge could be seen in the thermographic imaging. The thermographic imaging findings were consistent with predictions made from baseline data. Strategies in air leakage as well as wall R value showed the most significant changes in Sefaira

FindingsBecause the envelope is well designed, Sefaira iterations were less telling in Earl Boyles; however, the thermographic imaging revealed a thermal bridge in the slab that was not forseen. Using a higher performance glazing would actually have a significiant impact on the school’s annual space heating. This is because the rest of the envelope is so tight.

FindingsThermographic imaging found obvious heat loss through Clackamas High School’s exposed floor slab. Through Sefaira, improving the building’s air leakage strategy had the biggest effect on the overall performance.Increasing the roof to 60 had a significant impact. Increasing the r-value of wall glazing by a percentage change of ten had a marginal impact on energy use due to overall square footage.

Earl Boyles Elementary SchoolRock Creek Middle SchoolNorth Clackamas High School

Boora Architects:Mike Manzi, Abby Dacey, Jacob Peel, Stephen Endy

PSU School of Architecture Graduate Students: Paul Conrad, Alejandra Ruiz, Genevieve Wasser

The research consisted of taking thermographic image readings of the building envelope. Data was collected over two separate field visits to each school during times of cold outdoor temperatures in late November and early December. In addition to this, the three schools were modeled and brought into Sefaira to analyse strategies for improved envelope performance. The thermographic images were used to help identify areas where the envelope is underperforming.

Location: 10822 SE Bush St, Portland, ORYear of Completion: 2014Square Footage: 15,000 additionOccupancy: 188

Location: 14897 SE Parklane Dr, Happy Valley, ORYear of Completion: 2010Square Footage: 129,000 sqftOccupancy: 750

Location: 14486 SE 122nd Ave, Clackamas ORYear of Completion: 2002Square Footage: 275,000 sqftOccupancy: 2,213

Roof Assembly: R-50Membrane Roofing10” Polyiso Roof InsulationSelf-adhered Air/Vapor Barrier

Roof Assembly: R-38Membrane Roofing3” Polyiso Roof InsulationPolyethylene Vapor BarrierBatt Insulation Below Deck

Roof Assembly: R-25Membrane Roofing5” Polyiso Roof InsulationNo Air/Vapor Barrier

Wall Assembly: R-30Metal Panel CladdingThermally-Broken Framing Assembly3 1/2” Mineral Wool InsulationSelf-Adhered Air Barrier6” Batt Insulation In Wood Stud Cavity

Wall Assembly: R-16Metal Panel CladdingContinuous Z Supports1-1/2” Extruded Polystyrene InsulationBuilding Wrap (Tyvek)6” Batt Insulation In Stud Cavity

Wall Assembly: R-7Metal Panel CladdingContinuous Z SupportsBuilding Wrap (Tyvek)6” Batt Insulation In Stud Cavity

Glazing System: U-30Ultra-thermal aluminum framesDouble pane, low-e glassStandard spacer

Glazing System: U-30Thermally Broken Aluminum FramesDouble-Pane, Low-E GlassStandard Spacer

Glazing System: U-41Thermally Broken Aluminum FramesDouble-Pane, Low-E GlassStandard Spacer

Air Tightness: 0.13Measured Value (Cfm/Sf at 1.57 Psf)

Air Tightness:No Tested Value

Air Tightness:No Tested Value

Insulated Slab EdgeMeasured Value (Cfm/Sf at 1.57 Psf)

Exposed Slab EdgeExposed Slab Edge

Detail 1. Southeast corner of Northeast wing

Detail 1. Roof overhang, Southwest corner of

South wing

Detail 1. Recess speaker on East Cexterior courtyard wall

Detail 2.North face of Northeast wing

Detail 2. Slab on southwest corner of South slab

Detail 2. North exterior courtyard wall. Leakage through windows, door, and

concrete slab

Detail 3. South face of Northeast wing

Detail 3. Thermal bridging in studs on North face

of Media Center

Detail 3. Slab of corner of North exterior

courtyard wall

Section. Wall section of Northeast wing

Section Wall section of East facade of courtyard

Wall Section at courtyard wall

0

5

10

15

20

25

30

35

40

0

50000

100000

150000

200000

250000

0

2

4

6

8

10

38

202250

8.25

.18

.26

.36

- 10

+ 10 .1

3

40

20

60 70

U-Factor Glazing % Air Leakage Wall R-Value Roof R-Value

EUI (

kBTU

/ft2

)A

nnua

l Spa

ce H

eatin

g (k

BTU

)H

eatin

g Ca

paci

ty (t

on)

Glazing U-Factor:.36 BTU/h ft2 °F

Wall R-Value: 30 BTU/h ft2 °F

Air Leakage:.13 cfm/ft2

BASELINES

Glazing Percentage:25.5

Roof R-Value: 50 BTU/h ft2 °F

0

10

20

30

40

50

0

1000000

2000000

3000000

4000000

5000000

6000000

0

50

100

150

200

43

5392466

190.95

.18

.26

.36

- 10

+ 10 .1

3

40

20

50 60

EUI (

kBTU

/ft2

)A

nnua

l Spa

ce H

eatin

g (k

BTU

)H

eatin

g Ca

paci

ty (t

on)

U-Factor Glazing % Air Leakage Wall R-Value Roof R-Value

Glazing U-Factor:.41 BTU/h ft2 °F

Wall R-Value: 7 BTU/h ft2 °F

Air Leakage:.50 cfm/ft2

BASELINES

Glazing Percentage:28

Roof R-Value: 25 BTU/h ft2 °F

0

10

20

30

40

50

0

500000

1000000

1500000

2000000

2500000

3000000

0

20

40

60

80

100

47

2473808

92.25

.18

.26

.36

- 10

+ 10 .1

3

40

20

50 60

U-Factor Glazing % Air Leakage Wall R-Value Roof R-Value

EUI (

kBTU

/ft2

)A

nnua

l Spa

ce H

eatin

g (k

BTU

)H

eatin

g Ca

paci

ty (t

on)

Glazing U-Factor:.40 BTU/h ft2 °F

Wall R-Value: 14.5 BTU/h ft2 °F

Air Leakage:.50 cfm/ft2

BASELINES

Glazing Percentage:27

Roof R-Value: 39 BTU/h ft2 °F

week 1

week 2

week 3

week 4

week 5

week 6

week 7

week 8

week 9

week 10

research parameters

school selections and initial research

baseline building data provided from �rm

GOALS

model buildings in Sketchup individually

CONCLUSIONS

IMPROVEMENT STRATEGIES

FLIR READINGS

SKETCHUP

cold weather readings

coordinate with occupancy behavior group

examine joints, �oors, parapets

seek professional opinion on Flir camera strategies

compare data with photos and wall sections

EARL

BOY

LES

ELEM

ENTA

RY

ROCK

CRE

EK M

IDDL

ESCH

OOL

CLAC

KAM

AS H

IGH

SCH

OOL

SEFAIRA - WEBestablish model baselines

correct model errors

OFFICE DIALOGUE

re-examine project goals

schedule school visits

determine what to examine in thermographic imaging

solidify �eld data collection strategies

glazing u value: 0.18glazing u value: 0.26glazing u value: 0.36SHGC: 0.26 S facades onlySHGC: 0.26 all facadeswall r value: 40

wall r value: 20�oor r value: 10�oor r value 20roof r value: 50roof r value: 60

schools lack adequate �oor insulation

heat loss through joints between classrooms, expansions

noteable improvement in EUI with air leakage improvement

improvements in EUI when wall insulation increased