Boq Dan Jadwal Pelaksanaan

Embed Size (px)

Citation preview

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    1/31

    NO URAIAN PEKERJAAN JUMLAH HARGA

    1 2 3

    1 PEKERJAAN PERSIAPAN 14.311.375,00Rp.

    2 PEKERJAAN TANAH DAN PONDASI 29.516.318,48Rp.

    3 PEKERJAAN BETON BERTULANG 79.523.764,14Rp.

    4 PEKERJAAN PASANGAN DAN PLESTERAN 54.729.952,73Rp.

    5 PEKERJAAN LANTAI 20.432.478,41Rp.

    6 PEKERJAAN ATAP DAN PLAFOND 184.362.102,30Rp.

    7 PEKERJAAN KOSEN. PINTU DAN JENDELA 41.250.719,13Rp.

    8 PEKERJAAN PENGECATAN 23.041.378,88Rp.

    9 PEKERJAAN INSTALASI LISTRIK 5.418.000,00Rp.

    10 PEKERJAAN NON STANDAR 6.142.547,50Rp.

    11 PEKERJAAN PAVING BLOK 17.868.339,22Rp.

    Rp. 476.596.975,79

    Rp. 47.659.697,58

    Rp. 524.256.673,37

    524 257 000 00Rp

    REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)

    PEKERJAAN : PENYELESAIAN PEMBANGUNAN 3 RKB SDN LAWE SERAKUT

    SUMBER DANA : MIGAS

    TAHUN ANGGARAN : 2016

    LOKASI : KABUPATEN ACEH TENGGARA

    TOTAL

    PPN 10% JUMLAH TOTAL

    DIBULATKAN

    JUMLAH TOTAL

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    2/31

    524 257 000 00RpDIBULATKAN

    No. JENIS PEKERJAAN VOLUME SAT. ANALISA HARGA SATUAN JUMLAH HARGA

    1 2 3 4 5 6 7

    A

    1 Mobilisasi Bahan 1,00 Ls Taksir 7.500.000,00 7.500.000,00

    1 Papan Nama Proyek 1,00 Ls Taksir 500.000,00 500.000,00

    2 Pembersihan Lapangan 299,88 M2 6.8 RSNI-T-12-2002 9.375,00 2.811.375,00

    2 Pengukuran dan Pemasangan Bowplank 1,00 Ls Taksir 2.500.000,00 2.500.000,00

    3 Dokumentasi Photo dan Pelaporan 1,00 Ls Taksir 1.000.000,00 1.000.000,00

    14.311.375,00

    B PEKERJAAN TANAH DAN PONDASI

    1 Galian Tanah Pondasi menerus 70,20 M3 PT. 06 - SNI 2835:2008 48.437,50 3.400.312,50

    2 Urugan Kembali Bekas Galian 17,55 M3 PT. 09 - SNI 2835:2008 16.145,83 283.359,38

    3 Urugan Pasir Alas Pondasi 4,68 M3 PT. 11 - SNI 2835:2008 132.000,00 617.760,00

    4 Pasangan Batu Kosong 9,36 M3 PP. 09 - SNI 2836:2008 224.160,00 2.098.137,60

    5 Pasangan Pondasi batu belah 36,86 M3 PP. 02 - SNI 2836:2008 627.150,00 23.116.749,00

    29.516.318,48

    C PEKERJAAN BETON BERTULANG

    1 Sloof Beton 20/25 cm 6,90 M3 PB. 39 - SNI. SUPLEMEN 4.663.029,95 32.174.906,662 Kolom Beton C1 25/25 cm 0,95 M3 PB. 45 - SNI. SUPLEMEN 5.866.752,23 5.573.414,61

    3 Kolom Beton C2 20/20 cm 1,20 M3 PB. 43 - SNI. SUPLEMEN 4.513.744,87 5.416.493,84

    4 Kolom Beton C3 13/13 cm 0,26 M3 PB. 43 - SNI. SUPLEMEN 6.560.394,62 1.705.702,60

    5 Ring balok 15/20 cm' 3,39 M3 PB. 51 - SNI. SUPLEMEN 6.090.913,87 20.648.198,02

    6 Balok latai 15/13 cm' 1,33 M3 PB. 50 - SNI. SUPLEMEN 7.529.595,92 10.014.362,57

    7 Balok top gevel 15/13 0,53 M3 PB. 50 - SNI. SUPLEMEN 7.529.595,92 3.990.685,84

    79.523.764,14

    D PEKERJAAN PASANGAN DAN PLESTERAN

    1 Pasangan Bata 1Pc:2PP 9,30 M2 PD. 07 - SNI 6897:2008 105.347,50 979.731,75

    2 Plesteran Bata 1Pc:2PP 18,60 M2 PPL. 02 - SNI 2837:2008 186.210,00 3.463.506,00

    3 Pasangan Dinding Bata 1 PC : 4 PP 258,59 M2 PD. 09 - SNI 6897:2008 94.772,50 24.507.220,78

    4 Plesteran Dinding Bata 1PC : 4 PP 517,18 M2 PPL. 04 - SNI 2837:2008 42.690,00 22.078.414,20

    5 Plesteran beton bertulang 53,60 M2 PPL. 27 - SNI 2837:2008 69.050,00 3.701.080,00

    54.729.952,73

    TOTAL C

    TOTAL B

    TOTAL A

    RENCANA ANGGARAN BIAYA (RAB)

    PEKERJAAN : PENYELESAIAN PEMBANGUNAN 3 RKB SDN LAWE SERAKUT SUMBER DANA

    : MIGAS

    TAHUN ANGGARAN : 2016

    LOKASI : KABUPATEN ACEH TENGGARA

    TOTAL D

    PEKERJAAN PERSIAPAN

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    3/31

    No. JENIS PEKERJAAN VOLUME SAT. ANALISA HARGA SATUAN JUMLAH HARGA

    1 2 3 4 5 6 7

    E PEKERJAAN LANTAI

    1 Timbunan Pasir Bawah Lantai Ruangan dan Selasar 31,59 M3 PT. 11 - SNI 2835:2008 151.375,00 4.781.936,25

    2 Timbunan Tanah Bawah Lantai Ruangan dan Selasar 85,05 M3 PT. 15 - SNI 2835:2008 77.187,50 6.564.796,88

    3 Lantai Beton Tumbuk 11,64 M3 PB. 04 - SNI 7394:2008 613.425,31 7.140.270,61

    4 Lantai keramik 40x40 cm pada ruangan 9,45 M2 PLD. 34 - SNI 7395:2008 167.137,00 1.579.444,65

    5 Lantai keramik 40x40 cm pada Selasar 2,19 M2 PLD. 34 - SNI 7395:2008 167.137,00 366.030,03

    20.432.478,41

    F PEKERJAAN ATAP DAN PLAFOND

    1 Rangka kuda-kuda dan gording baja ringan Multytruss 396,90 m2 PBA. 21 SUPL. SNI 298.226,00 118.365.899,402 Atap Seng BJLS 396,90 M2 PA. 09 SNI-03-3436-2002 72.040,00 28.592.676,00

    3 Rabung seng BJLS 29,40 M' PA. 10 SNI-03-3436-2002 29.060,00 854.364,00

    4 Lesplang Kayu 3/20 cm 81,00 M' PK. 21 - SNI 3434:2008 50.792,50 4.114.192,50

    5 Plafond teriplek 4mm 302,40 M2 PLL. 05 - SNI 2839:2008 46.152,50 13.956.516,00

    6 Rangka plafond 302,40 M2 PK. 20 - SNI 3434:2008 41.106,00 12.430.454,40

    7 Kayu lisPlafon 604,80 m' Taksir 10.000,00 6.048.000,00

    184.362.102,30

    G PEKERJAAN KOSEN. PINTU DAN JENDELA

    1 Pintu Type P1 (3 Unit)

    - Kosen Kayu 6/13 0,15 M3 PK. 02 - SNI 3434:2008 4.847.750,00 727.162,50

    - Daun Pintu Panel Ukuran 60 x 210 cm 7,56 M2 PK. 05 - SNI 3434:2008 394.875,00 2.985.255,00

    - Ventilasi Jalusi 2,13 M2 PK. 10 - SNI 3434:2008 365.012,50 777.476,63

    - Kunci Tanam 2 Slaag 3,00 Buah 02. KK. SNI 164.112,50 492.337,50

    - Engsel Pintu 6,00 Buah 04. KK. SNI 41.750,00 250.500,00

    2 Jendela Type J1 (6 Unit)

    - Kosen Kayu 6/13 0,59 M3 PK. 02 - SNI 3434:2008 4.847.750,00 2.860.172,50

    - Daun Jendela Ukuran 60 x 90 cm 12,96 M2 PK. 06 - SNI 3434:2008 293.100,00 3.798.576,00

    - Ventilasi kaca 60 x 42 cm 6,05 M2 PK. 06 - SNI 3434:2008 293.100,00 1.773.255,00

    - Engsel Jendela 96,00 Buah 05. KK. SNI 35.831,25 3.439.800,00

    - Hak Penahan Angin Jendela 96,00 Buah 06. KK. SNI 31.750,00 3.048.000,00

    - Kaca 5 mm 10,60 M2 11. KK. SNI 113.500,00 1.203.100,00

    3 Jendela Type J1 (6 Unit)

    - Kosen Kayu 6/13 0,69 M3 PK. 02 - SNI 3434:2008 4.847.750,00 3.344.947,50

    - Daun Jendela Ukuran 78 x 80 cm 14,58 M2 PK. 06 - SNI 3434:2008 293.100,00 4.273.398,00

    - Ventilasi kaca 60 x 42 cm 6,80 M2 PK. 06 - SNI 3434:2008 293.100,00 1.993.080,00

    - Engsel Jendela 108,00 Buah 05. KK. SNI 35.831,25 3.869.775,00

    - Hak Penahan Angin Jendela 108,00 Buah 06. KK. SNI 31.750,00 3.429.000,00

    - Kaca 5 mm 7,58 M2 11. KK. SNI 113.500,00 860.330,00

    4 Ventilasi Jalusi pada top gevel

    - Kosen Kayu 6/13 0,09 M3 PK. 02 - SNI 3434:2008 4.847.750,00 436.297,50

    - Ventilasi Jalusi 5,76 M2 PK. 06 - SNI 3434:2008 293.100,00 1.688.256,0041.250.719,13TOTAL G

    TOTAL F

    TOTAL E

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    4/31

    No. JENIS PEKERJAAN VOLUME SAT. ANALISA HARGA SATUAN JUMLAH HARGA

    1 2 3 4 5 6 7

    H PEKERJAAN PENGECATAN

    1 Cat Tembok 3 x (L/D) 517,18 M2 08. CAT SNI 18.826,50 9.736.689,27

    2 Cat Plafond dan List Plafond 302,40 M2 08. CAT SNI 18.826,50 5.693.133,60

    3 Cat Mengkilat Lesplang Kayu 20,25 M2 03. CAT SNI 44.271,25 896.492,81

    4 Cat Mengkilat Kosen Pintu/Jendela 90,12 M2 03. CAT SNI 44.271,25 3.989.725,05

    5 Cat Mengkilat Daun Pintu/Jendela/Jalusi 61,56 M2 03. CAT SNI 44.271,25 2.725.338,15

    23.041.378,88

    I PEKERJAAN INSTALASI LISTRIK

    1 Armatur- Lampu Hemat Energi 26,00 Buah Taksir 30.000,00 780.000,00

    2 Saklar lampu Merk Broco 2 seri

    - Sakalar 2 Seri setara Broco 4,00 Buah Taksir 16.000,00 64.000,00

    3 Stop Kontak 3,00 Buah Taksir 18.000,00 54.000,00

    4 Instlasi titik penerangan. instalasi termasuk kabel NYA 2.5

    mm dalam pipa PVC fitting lampu dan kelengkapan instalasi

    terpasang 26,00 Titik Taksir 110.000,00 2.860.000,00

    5 Instalasi titik Stop kontak. instalasi termasuk kabel NYA

    2.5 mm dalam pip a PVC. kotak kontak dan kelengkapan

    instalasi terpasang. 7,00 Titik Taksir 130.000,00 910.000,00

    6 Box Panel Distribusi 1,00 Buah Taksir 750.000,00 750.000,00

    5.418.000,00

    J PEKERJAAN NON STANDAR

    1 Relief Tiang Teras 10,00 Units Taksir 250.000,00 2.500.000,00

    2 Pasangan Batu Tempel Hitam 19,26 M2 PLD. 58 - SNI 7395:2008 189.125,00 3.642.547,50

    6.142.547,50

    TOTAL H

    TOTAL I

    TOTAL J

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    5/31

    No. JENIS PEKERJAAN VOLUME SAT. ANALISA HARGA SATUAN JUMLAH HARGA

    1 2 3 4 5 6 7

    K PEKERJAAN PAVING BLOK

    1 Paving Blok 102,90 M2 Taksir 130.350,00 13.413.015,00

    2 Pasir Urug Paving Blok 4 cm 20,58 M3 PT. 11 - SNI 2835:2008 132.000,00 2.716.560,00

    3 Dinding Pembatas Paving Blok 7,20 M2 PD. 09 - SNI 6897:2008 94.772,50 682.362,00

    4 Plasteran Dinding Pembatas Paving blok 14,40 M2 PPL. 04 - SNI 2837:2008 42.690,00 614.736,00

    5 Beton Cor pondasi 0,72 M3 PB. 04 - SNI 7394:2008 613.425,31 441.666,22

    17.868.339,22

    476.596.975,79

    47.659.697,58524.256.673,37

    524.257.000,00

    TOTAL K

      Kutacane, 11 April 2016

      CV. TUNAS MUDA

    ZULKARNAIN. SKD

      Direktur

    DIBULATKAN

    TOTAL A s/d N

    PPN 10%JUMLAH TOTAL

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    6/31

    Pekerja 0,750 OH 62.500@Rp. 46.875Rp

    Mandor 0,025 OH 62.500@Rp. 1.563Rp

    48.438Rp

    48.438Rp

    16.146Rp

    Pasir Urug 1,200 M3 110.000@Rp. 132.000Rp

    132.000Rp

    Pekerja 0,300 OH 62.500@Rp. 18.750Rp

    Mandor 0,010 OH 62.500@Rp. 625Rp

    19.375Rp

    151.375Rp

    151 375R

    Jumlah A

    B. Tenaga Kerja

    Jumlah B

    Jumlah (A + B)

    J l h H P S t P k j

    1 M3 Mengurug kembali galian

    Mengurug kembali 1 M3 galian dihitung dari 1/3 kali dari indeks pekerjaan galian

    Jumlah Harga Per Satuan Pekerjaan

    PT. 11 - SNI 2835:2008

    1 M3 Mengurug pasir urug

    A. Bahan

    DAFTAR ANALISA HARGA

    PT. 01 - SNI 2835:20081 M3 Galian tanah biasa sedalam 1 meter

    A. Tenaga Kerja

    Jumlah Harga Per Satuan Pekerjaan

    PT. 09 - SNI 2835:2008

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    7/31

    Batu Kali 1,200 M3 140.000@Rp. 168.000Rp

    Portland Cement 163,000 Kg 1.500@Rp. 244.500Rp

    Pasir Pasang 0,520 M3 120.000@Rp. 62.400Rp

    474.900Rp

    Pekerja 1,500 OH 62.500@Rp. 93.750Rp

    Tukang Batu 0,750 OH 65.000@Rp. 48.750Rp

    Kepala Tukang 0,075 OH 67.500@Rp. 5.063Rp

    Mandor 0,075 OH 62.500@Rp. 4.688Rp

    152.250Rp

    627.150Rp

    627.150Rp

    Batu Kali 1,200 M3 140.000@Rp. 168.000Rp

    Pasir Cor 0,432 M2 130.000@Rp. 56.160Rp

    224.160Rp

    A. Bahan

    Jumlah A

    B T K j

    B. Tenaga Kerja

    Jumlah B

    Jumlah (A + B)

    Jumlah Harga Per Satuan Pekerjaan

    PP. 09 - SNI 2836:2008

    1 M3 Memasang batu kosong (anstamping)

    DAFTAR ANALISA HARGA

    PP. 02 - SNI 2836:20081 M3 Memasang pondasi batu kali. campuran 1 PC : 4 PP

    A. Bahan

    Jumlah A

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    8/31

    Batu Bata 70,000 Bh 650@Rp. 45.500Rp

    Portland Cement 11,500 Kg 1.500@Rp. 17.250Rp

    Pasir Pasang 0,043 M3 120.000@Rp. 5.160Rp

    67.910Rp

    Pekerja 0,300 OH 62.500@Rp. 18.750Rp

    Tukang Batu 0,100 OH 65.000@Rp. 6.500Rp

    Kepala Tukang 0,010 OH 67.500@Rp. 675Rp

    Mandor 0,015 OH 62.500@Rp. 938Rp

    26.863Rp

    94.773Rp

    94.773Rp

    Portland Cement 102,240 kg 1.500@Rp. 153.360Rp

    Pasir Pasang 0,020 M3 120.000@Rp. 2.400Rp

    155.760Rp

    1 M2 Membuat plesteran 1 PC : 2 PP. tebal 15 mm

    A. Bahan

    Jumlah A

    B T K j

    Jumlah A

    B. Tenaga Kerja

    Jumlah B

    Jumlah (A + B)

    Jumlah Harga Per Satuan Pekerjaan

    PPL. 02 - SNI 2837:2008

    DAFTAR ANALISA HARGA

    PD. 09 - SNI 6897:20081 M2 Memasang dinding batu bata tebal 1/2 bata. camp. spesi 1 PC : 4 PP

    A. Bahan

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    9/31

    Portland Cement 32,500 Kg 1.500@Rp. 48.750Rp

    48.750Rp

    Pekerja 0,200 OH 62.500@Rp. 12.500Rp

    Tukang Batu 0,100 OH 65.000@Rp. 6.500Rp

    Kepala Tukang 0,010 OH 67.500@Rp. 675Rp

    Mandor 0,010 OH 62.500@Rp. 625Rp

    20.300Rp

    69.050Rp

    69.050Rp

    Balok Kayu 1,200 M3 2.600.000@Rp. 3.120.000Rp

    Paku 10 cm 1,250 Kg 18.000@Rp. 22.500Rp

    Lem Kayu 1,000 Kg 20.000@Rp. 20.000Rp

    3.162.500Rp

    k j 6 000 OH 62 500@Rp 375 000Rp

    PK. 02 - SNI 3434:2008

    1 M3 Membuat dan memasang kusen pintu dan kusen jendela.A. Bahan

    Jumlah A

    B. Tenaga Kerja

    A. Bahan

    Jumlah A

    B. Tenaga Kerja

    Jumlah B

    Jumlah (A + B)

    Jumlah Harga Per Satuan Pekerjaan

    DAFTAR ANALISA HARGA

    PPL. 27 - SNI 2837:2008

    1 M2 Membuat acian

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    10/31

    Kayu Rangka Plafond 0,016 M3 120.000@Rp. 1.956Rp

    Paku 7 cm - 10 cm 0,250 Kg 18.000@Rp. 4.500Rp

    6.456Rp

    Pekerja 0,200 OH 62.500@Rp. 12.500Rp

    Tukang Kayu 0,300 OH 65.000@Rp. 19.500Rp

    Kepala Tukang 0,030 OH 67.500@Rp. 2.025Rp

    Mandor 0,010 OH 62.500@Rp. 625Rp

    34.650Rp

    41.106Rp

    41.106Rp

    Papan Kayu 0,011 M3 2.600.000@Rp. 28.080Rp

    Paku 5 cm dan 7 cm 0,100 Kg 18.000@Rp. 1.800Rp

    29.880Rp

    Pekerja 0 100 OH 62 500@Rp 6 250Rp

    Jumlah Harga Per Satuan Pekerjaan

    PK. 21 - SNI 3434:2008

    1 M' Memasang lisplank ukuran (3 x 20) cm. kayu kelas I atau kelas IIA. Bahan

    Jumlah A

    B. Tenaga Kerja

    1 M2 Memasang rangka langit-langit (60 x 60) cm.A. Bahan

    Jumlah A

    B. Tenaga Kerja

    Jumlah B

    Jumlah (A + B)

    DAFTAR ANALISA HARGA

    PK. 20 - SNI 3434:2008

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    11/31

    Portland Cement 230,000 Kg 1.500@Rp. 345.000Rp

    Pasir Beton 893,000 Kg 78@Rp. 69.475Rp

    Kerikil (maks. 30 mm) 1027,000 Kg 93@Rp. 95.850Rp

    Air 200,000 Ltr 50@Rp. 10.000Rp

    520.325Rp

    Pekerja 1,200 OH 62.500@Rp. 75.000Rp

    Tukang Batu 0,200 OH 65.000@Rp. 13.000Rp

    Kepala Tukang 0,020 OH 67.500@Rp. 1.350Rp

    Mandor 0,060 OH 62.500@Rp. 3.750Rp

    93.100Rp

    613.425Rp

    613.425Rp

    Portland Cement 326,000 Kg 1.500@Rp. 489.000Rp

    Pasir Beton 760,000 Kg 78@Rp. 59.113Rp

    Kerikil (maks 30 mm) 1029 000 Kg 93@Rp 96 037Rp

    Jumlah (A + B)

    Jumlah Harga Per Satuan Pekerjaan

    PB. 05 - SNI 7394:2008

    1 M3 Membuat beton mutu f'c = 14.5 Mpa (K 175).A. Bahan

    PB. 04 - SNI 7394:20081 M3 Membuat lantai kerja beton mutu f'c = 7.4 Mpa (K 100).

    A. Bahan

    Jumlah A

    B. Tenaga Kerja

    Jumlah B

    DAFTAR ANALISA HARGA

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    12/31

    Portland Cement 371,000 Kg 1.500@Rp. 556.500Rp

    Pasir Beton 698,000 Kg 78@Rp. 54.290Rp

    Kerikil (maks. 30 mm) 1047,000 Kg 93@Rp. 97.717Rp

    Air 215,000 Ltr 50@Rp. 10.750Rp

    719.257Rp

    Pekerja 1,650 OH 62.500@Rp. 103.125Rp

    Tukang Batu 0,275 OH 65.000@Rp. 17.875Rp

    Kepala Tukang 0,028 OH 67.500@Rp. 1.890Rp

    Mandor 0,083 OH 62.500@Rp. 5.188Rp

    128.078Rp

    847.334Rp

    847.334Rp

    Besi Beton (Polos/Ulir) 10,500 Kg 16.000@Rp. 168.000Rp

    Kawat Beton 0,150 Kg 16.000@Rp. 2.400Rp

    170 400R

    Jumlah Harga Per Satuan Pekerjaan

    PB. 17 - SNI 7394:2008

    10 Kg Pembesian dengan besi polosA. Bahan

    J l h A

    1 M3 Membuat beton mutu f'c = 19.3 Mpa (K 225).A. Bahan

    Jumlah A

    B. Tenaga Kerja

    Jumlah B

    Jumlah (A + B)

    DAFTAR ANALISA HARGA

    PB. 07 - SNI 7394:2008

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    13/31

    Kayu Kelas III 0,040 M3 2.400.000@Rp. 96.000Rp

    Paku 5 cm - 10 cm 0,300 Kg 18.000@Rp. 5.400Rp

    Minyak Bekisting 0,100 Ltr 2.000@Rp. 200Rp

    101.600Rp

    Pekerja 0,520 OH 62.500@Rp. 32.500Rp

    Tukang Kayu 0,260 OH 65.000@Rp. 16.900Rp

    Kepala Tukang 0,026 OH 67.500@Rp. 1.755Rp

    Mandor 0,026 OH 62.500@Rp. 1.625Rp

    52.780Rp

    154.380Rp

    154.380Rp

    Kayu Kelas III 0,045 M3 2.400.000@Rp. 108.000Rp

    Paku 5 cm - 10 cm 0,300 Kg 18.000@Rp. 5.400Rp

    Minyak Bekisting 0,100 Ltr 2.000@Rp. 200Rp

    113 600R

    Jumlah Harga Per Satuan Pekerjaan

    PB. 21 - SNI 7394:2008

    1 M2 Memasang bekisting untuk sloof A. Bahan

    J l h A

    1 M2 Memasang bekisting untuk pondasiA. Bahan

    Jumlah A

    B. Tenaga Kerja

    Jumlah B

    Jumlah (A + B)

    DAFTAR ANALISA HARGA

    PB. 20 - SNI 7394:2008

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    14/31

    Kayu Kelas III 0,040 M3 2.400.000@Rp. 96.000Rp

    Paku 5 cm - 12 cm 0,400 Kg 18.000@Rp. 7.200Rp

    Minyak Bekisting 0,200 Ltr 2.000@Rp. 400Rp

    Balok Kayu Kelas II 0,015 M3 2.600.000@Rp. 39.000Rp

    Plywood tebal 9 mm 0,350 Lbr 120.000@Rp. 42.000Rp

    Dolken Kayu Galam.

    φ (8 - 10) cm. panjang 4 m

    2,000 Btg @Rp. 8.500 17.000Rp

    201.600Rp

    Pekerja 0,660 OH 62.500@Rp. 41.250Rp

    Tukang Kayu 0,330 OH 65.000@Rp. 21.450Rp

    Kepala Tukang 0,033 OH 67.500@Rp. 2.228Rp

    Mandor 0,033 OH 62.500@Rp. 2.063Rp

    66.990Rp

    268.590Rp

    268.590Rp

    PB. 23 - SNI 7394:2008

    1 M2 Memasang bekisting untuk balokA. Bahan

    A. Bahan

    Jumlah A

    B. Tenaga Kerja

    Jumlah B

    Jumlah (A + B)

    Jumlah Harga Per Satuan Pekerjaan

    DAFTAR ANALISA HARGA

    PB. 22 - SNI 7394:20081 M2 Memasang bekisting untuk kolom

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    15/31

    Kayu Kelas III 0,040 M3 2.400.000@Rp. 96.000Rp

    Paku 5 cm - 12 cm 0,400 Kg 18.000@Rp. 7.200Rp

    Minyak Bekisting 0,200 Ltr 2.000@Rp. 400Rp

    Balok Kayu Kelas II 0,015 M3 2.600.000@Rp. 39.000Rp

    Plywood tebal 9 mm 0,350 Lbr 120.000@Rp. 42.000Rp

    Dolken Kayu Galam.

    φ (8 - 10) cm. panjang 4 m 6,000 Btg 8.500@Rp. 51.000Rp

    235.600Rp

    Pekerja 0,660 OH 62.500@Rp. 41.250Rp

    Tukang Kayu 0,330 OH 65.000@Rp. 21.450Rp

    Kepala Tukang 0,033 OH 67.500@Rp. 2.228Rp

    Mandor 0,033 OH 62.500@Rp. 2.063Rp

    66.990Rp

    302.590Rp

    302.590Rp

    P k B t K 225 1 000 M3 847 334@R 847 334R

    1 M3 Membuat pondasi tapak (beton K-225. 111.88 kg besi polos)

    Jumlah A

    B. Tenaga Kerja

    Jumlah B

    Jumlah (A + B)

    Jumlah Harga Per Satuan Pekerjaan

    PB. 37 - SNI. SUPLEMEN

    DAFTAR ANALISA HARGA

    PB. 24 - SNI 7394:20081 M2 Memasang bekisting untuk plat lantai

    A. Bahan

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    16/31

    Pek. Beton K-225 1,000 M3 847.334@Rp. 847.334Rp

    Pek. Besi Beton Polos 166,900 Kg 18.005@Rp. 3.004.993Rp

    Pek. Bekisting Kolom 7,500 M2 268.590@Rp. 2.014.425Rp

    5.866.752Rp

    Pek. Beton K-175 1,000 M3 782.977@Rp. 782.977Rp

    Pek. Besi Beton Polos 94,660 Kg 18.005@Rp. 1.704.330Rp

    Pek. Bekisting Balok 6444,000 M2 276.390@Rp. 1.781.057.160Rp

    1.783.544.467Rp

    Pek. Beton K-225 1,000 M3 847.334@Rp. 847.334Rp

    Pek. Besi Beton Polos 155,480 Kg 18.005@Rp. 2.799.379Rp

    Pek. Bekisting Balok 11026,000 M2 276.390@Rp. 3.047.476.140Rp

    3.051.122.853Rp

    1 3 b l l i 10 (b K 22 164 k b i l )

    Jumlah

    PB. 65 - SNI. SUPLEMEN

    1 M3 Membuat balok 13/15 (beton K-225. 155.48 kg besi polos)

    Jumlah

    PB. 76 - SNI. SUPLEMEN

    PB. 53 - SNI. SUPLEMEN1 M3 Membuat kolom 20/40 (beton K-225. 166.9 kg besi polos)

    Jumlah

    PB. 61 - SNI. SUPLEMEN1 M3 Membuat ring balok 18/25 (beton K-175. 94.66 kg besi polos)

    DAFTAR ANALISA HARGA

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    17/31

    Pek. Beton K-175 1,000 M3 @Rp. 782.977 Rp 782.977

    Pek. Besi Beton Polos 209,000 Kg @Rp. 18.005 Rp 3.762.993

    Pek. Bekisting Kolom 7,500 M2 @Rp. 268.590 Rp 2.014.425

     Jumlah Rp 6.560.395

    Pek. Beton K-175 1,000 M3 @Rp. 782.977 Rp 782.977

    Pek. Besi Beton Polos 64,000 Kg @Rp. 18.005 Rp 1.152.304

    Pek. Bekisting Kolom 9,600 M2 @Rp. 268.590 Rp 2.578.464

     Jumlah Rp 4.513.745

    Pek. Beton K-175 1,000 M3 @Rp. 782.977 Rp 782.977

    Pek. Besi Beton Polos 159,800 Kg @Rp. 18.005 Rp 2.877.159

    Pek. Bekisting Balok 14,000 M2 @Rp. 276.390 Rp 3.869.460

     Jumlah Rp 7.529.596

    DAFTAR ANALISA HARGA

    PB. 50 - SNI. SUPLEMEN

    1 M3 Membuat ring balok 13/15 (beton K-175. 185 kg besi polos)

    PB. 43 - SNI. SUPLEMEN

    1 M3 Membuat kolom praktis 13/13 (beton K-175. 209 kg besi polos)

    PB. 43 - SNI. SUPLEMEN

    1 M3 Membuat kolom 20/20 (beton K-175. 65 kg besi polos)

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    18/31

    Genteng Metal 1,200 m2 80.000@Rp. 96.000Rp

    Baut (screw driver) 12,000 bh 1.500@Rp. 18.000Rp

    114.000Rp

    Pekerja 0,200 OH

    62.500@Rp. 12.500Rp

    Tukang Kayu 0,010 OH 65.000@Rp. 650Rp

    Kepala Tukang 0,010 OH 67.500@Rp. 675Rp

    Mandor 0,010 OH 62.500@Rp. 625Rp

    14.450Rp

    128.450Rp

    128.450Rp

    Bubung Genteng Metal 11,500 lbr 45.000@Rp. 517.500Rp

    Paku asbes 0,035 Kg 18.000@Rp. 630Rp

    518.130Rp

    P k j 0 050 OH 62 500@R 3 125R

    B. Tenaga Kerja

    Jumlah (A + B)

    Jumlah Harga Per Satuan Pekerjaan

    PA. 20 SUPL. SNI

    1 M Memasang bubungan genteng metalA. Bahan

    Jumlah A

    PA. 19 SUPL. SNI1 M2 Memasang atap genteng metal

    A. Bahan

    Jumlah A

    B. Tenaga Kerja

    Jumlah B

    DAFTAR ANALISA HARGA

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    19/31

    List Kayu Profil 1,050 M' 12.500@Rp. 13.125Rp

    Paku 0,010 Kg 18.000@Rp. 180Rp

    13.305Rp

    Pekerja 0,050 OH 62.500@Rp. 3.125Rp

    Tukang Kayu 0,050 OH 65.000@Rp. 3.250Rp

    Kepala Tukang 0,005 OH 67.500@Rp. 338Rp

    Mandor 0,003 OH 62.500@Rp. 188Rp

    6.900Rp

    20.205Rp

    20.205Rp

    C-100 . 0.7 1,488 m' 27.000@Rp. 40.176Rp

    C-75 . 0.7 2,232 m' 20.000@Rp. 44.640Rp

    Baut (screw driver) 38,000 bh 1.500@Rp. 57.000Rp

    Dynabolt 1,600 bh 650@Rp. 1.040Rp

    R 5 400 ' 18 500@R 99 900R

    Jumlah B

    Jumlah (A + B)

    Jumlah Harga Per Satuan Pekerjaan

    PBA. 21 SUPL. SNI

    1 M2 Pasang Kuda-kuda baja ringan + reng untuk atap genteng biasa/metalA. Bahan

    DAFTAR ANALISA HARGA

    PLL. 10 - SNI 2839:20081 M' Memasang list langit-langit kayu profil

    A. Bahan

    Jumlah A

    B. Tenaga Kerja

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    20/31

    Ubin Keramik 6,250 Bh 12.000@Rp. 75.000Rp

    Portland Cement 8,190 Kg 1.500@Rp. 12.285Rp

    Pasir Pasang 0,045 M3 120.000@Rp. 5.400Rp

    Semen Warna 1,620 Kg 2.100@Rp. 3.402Rp

    96.087Rp

    Pekerja 0,700 OH 62.500@Rp. 43.750Rp

    Tukang Batu 0,350 OH 65.000@Rp. 22.750Rp

    Kepala Tukang 0,035 OH 67.500@Rp. 2.363Rp

    Mandor 0,035 OH 62.500@Rp. 2.188Rp

    71.050Rp

    167.137Rp

    167.137Rp

    Cat Meni 0,200 kg 40.000@Rp. 8.000Rp

    Plamir 0,150 kg 18.000@Rp. 2.700Rp

    C 0 1 0 k 3 000@ 9 0

    Jumlah (A + B)

    Jumlah Harga Per Satuan Pekerjaan

    03. CAT SNI

    1 M2 Mengecat bidang kayu baru (1 lps plamir. 1 lps cat dsr.A. Bahan

    PLD. 34 - SNI 7395:20081 M2 Memasang lantai keramik ukuran (40 x 40) cm

    A. Bahan

    Jumlah A

    B. Tenaga Kerja

    Jumlah B

    DAFTAR ANALISA HARGA

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    21/31

    Plamir 0,100 Kg 18.000@Rp. 1.800Rp

    Cat Dasar 0,100 kg 20.000@Rp. 2.000Rp

    Cat Penutup 0,260 kg 35.000@Rp. 9.100Rp

    12.900Rp

    Pekerja 0,020 OH 62.500@Rp. 1.250Rp

    Tukang Cat 0,063 OH 65.000@Rp. 4.095Rp

    Kepala Tukang 0,006 OH 67.500@Rp. 425Rp

    Mandor 0,003 OH 62.500@Rp. 156Rp

    5.927Rp

    18.827Rp

    18.827Rp

    Kunci Tanam Biasa 1,000 bh 130.000@Rp. 130.000Rp

    130.000Rp

    k

    Jumlah Harga Per Satuan Pekerjaan

    02. KK. SNI

    1 BH Memasang kunci tanam biasa

    A. Bahan

    Jumlah A

    B. Tenaga Kerja

    1 M2 Mengecat bidang tembok baru (1 lps plamir. 1 lps cat dsr.A. Bahan

    Jumlah A

    B. Tenaga Kerja

    Jumlah B

    Jumlah (A + B)

    DAFTAR ANALISA HARGA

    08. CAT SNI

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    22/31

    Engsel Kuningan 2" 1,000 bh 28.000@Rp. 28.000Rp

    28.000Rp

    Pekerja 0,010 OH 62.500@Rp. 625Rp

    Tukang Kayu 0,100 OH 65.000@Rp. 6.500Rp

    Kepala Tukang 0,010 OH 67.500@Rp. 675Rp

    Mandor 0,001 OH 62.500@Rp. 31Rp

    7.831Rp

    35.831Rp

    35.831Rp

    Kait Angin 1,000 bh 20.000@Rp. 20.000Rp

    20.000Rp

    Pekerja 0,015 OH 62.500@Rp. 938Rp

    Tukang Kayu 0,150 OH 65.000@Rp. 9.750Rp

    l k

    B. Tenaga Kerja

    Jumlah (A + B)

    Jumlah Harga Per Satuan Pekerjaan

    06. KK. SNI

    1 BH Memasang kait anginA. Bahan

    Jumlah A

    05. KK. SNI

    1 BH Memasang engsel jendela kupu-kupu

    A. Bahan

    Jumlah A

    B. Tenaga Kerja

    Jumlah B

    DAFTAR ANALISA HARGA

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    23/31

    Kunci Selot / Gerendel 1,000 bh 14.500@Rp. 14.500Rp

    14.500Rp

    Pekerja 0,020 OH 62.500@Rp. 1.250Rp

    Tukang Kayu 0,200 OH

    65.000@Rp. 13.000Rp

    Kepala Tukang 0,020 OH 67.500@Rp. 1.350Rp

    Mandor 0,001 OH 62.500@Rp. 63Rp

    15.663Rp

    30.163Rp

    30.163Rp

    Seng Plat 3' - 6' BJLS 28 0,300 lbr @Rp. 45.000 Rp 13.500

    Paku ½" - 1" 0,040 kg @Rp. 18.000 Rp 720

     Rp 14.220

    PA. 10 SNI-03-3436-2002

    1 M2 Memasang atap nok seng

    A. Bahan

    Jumlah A

    Jumlah Harga Per Satuan Pekerjaan

    1 BH Memasang Gerendel Pintu Dan JendelaA. Bahan

    Jumlah A

    B. Tenaga Kerja

    Jumlah B

    Jumlah (A + B)

    DAFTAR ANALISA HARGA

    07. KK. SNI

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    24/31

    Papan Kayu 0,060 M3 @Rp. 2.600.000 Rp 156.000

    Paku 1 cm - 2.5 cm 0,150 KG @Rp. 18.000 Rp 2.700

     Rp 158.700

    Pekerja 0,670 OH 62.500@Rp. 41.875Rp

    Tukang Kayu 2,000 OH 65.000@Rp. 130.000Rp

    Kepala Tukang 0,200 OH 67.500@Rp. 13.500Rp

    Mandor 0,335 OH 62.500@Rp. 20.938Rp

    206.313Rp

     Rp 365.013

    Dolken Kayu Ǿ 8 p = 4 m 1,700 Btg @Rp. 8.500 Rp 14.450

    DAFTAR ANALISA HARGA

    6.6 RSNI-T-12-2002

    1 M2 Pembuatan gudang semen dan alat-alat

    A. Bahan

    B. Tenaga Kerja

    Jumlah A

    Jumlah B

    Jumlah (A + B)

    PK. 10 - SNI 3434:20081 M2 Membuat jalusi kusen. kayu kelas I atau kelas II

    A. Bahan

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    25/31

    Kaca 1,100 m2 92.500@Rp. 101.750Rp

     Rp 101.750

    Pekerja 0,015 OH 62.500@Rp. 938Rp

    Tukang Kayu 0,15 OH 65.000@Rp. 9.750Rp

    Kepala Tukang 0,015 OH 67.500@Rp. 1.013Rp

    Mandor 0,0008 OH 62.500@Rp. 50Rp

    11.750Rp

     Rp 113.500

    Pekerja 0,1 OH 62.500@Rp. Rp. 6.250

    Mandor 0,05 OH 62.500@Rp. Rp. 3.125

     Rp 9.375

    DAFTAR ANALISA HARGA

    A. Bahan

    Jumlah

    6.8 RSNI-T-12-2002

    1 M2 Membersihkan lapangan dan perataan

    PLD. 58 - SNI 7395:2008

    A. Bahan

    Jumlah A

    B. Tenaga Kerja

    Jumlah B

    Jumlah (A + B)

    11. KK. SNI1 M2 Memasang kaca; tebal 5 mm

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    26/31

    paving block 1,000 M3 @Rp. 90.000 Rp 90.000

    abu batu 0,080 KG @Rp. 200.000 Rp 16.000

     Rp 106.000

    Pekerja 0,150 OH 62.500@Rp. 9.375Rp

    Tukang Kayu 0,200 OH 65.000@Rp. 13.000Rp

    Kepala Tukang 0,020 OH 67.500@Rp. 1.350Rp

    Mandor 0,010 OH 62.500@Rp. 625Rp

    24.350Rp

     Rp 130.350

      Kutacane, 11 April 2016

      CV. TUNAS MUDA

    DAFTAR ANALISA HARGA

    Jumlah (A + B)

    taksirPaving Blok 

    A. Bahan

    Jumlah A

    B. Tenaga Kerja

    Jumlah B

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    27/31

    No. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

    1 2 3 4

    I UPAH

    1 Mandor Orang 62.500Rp.

    2 Kepala Tukang Kayu/Batu/Besi/Cat Orang 67.500Rp.

    3 Tukang Kayu/Batu/Besi/Cat Orang 65.000Rp.

    4 Pekerja Orang 62.500Rp.

    7 Mekanik Orang 65.000Rp.

    8 Pembantu Mekanik Orang 62.500Rp.

    A KELOMPOK MATERIAL ALAM

    1 Air Bersih Liter 50Rp.2 Batu Bata Bh 650Rp.

    3 Batu Kali/Batu Gunung M3 140.000Rp.

    4 Kerikil (berat jenis = 1350 Kg/m3) Kg 140.000Rp.

    5 Pasir Beton (berat jenis = 1400 Kg/m3) Kg 140.000Rp.

    6 Pasir Beton / Kerikil M3 140.000Rp.

    7 Pasir Cor M3 130.000Rp.

      DAFTAR HARGA SATUAN UPAH DAN BAHAN KABUPATEN ACEH TENGGARA

    PEKERJAAN : PENYELESAIAN PEMBANGUNAN 3 RKB SDN LAWE SERAKUT

    SUMBER DANA : MIGASTAHUN ANGGARAN : 2016

    LOKASI : KABUPATEN ACEH TENGGARA

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    28/31

    33 engsel kuningan 4" buah 30.000Rp.

    34 engsel kuningan 2" buah 28.000Rp.

    35 kait angin buah 20.000Rp.

    36 Seng Gel. 3'-6' BJLS 28 lembar 85.000Rp.37 Seng Plat 3' - 6' BJLS 28 lembar 45.000Rp.

    38 lem kayu kg 20.000Rp.

    39 batu tempel hitam m2 87.500Rp.

    40 paving block m3 90.000Rp.

    41 abu batu kg 200.000Rp.

    42 paku 1" - 20" kg 18.000Rp.

    43 kaca 5mm m2 92.500Rp.

      Kutacane, 11 April 2016

     CV. TUNAS MUDA

     ZULKARNAIN. SKD

      Direktur

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    29/31

    I II III IV I II III IV I II III IV I II III IV

    A PEKERJAAN PERSIAPAN

    1 Mobilisasi Bahan 1,00 Ls 7.500.000,00 7.500.000,00 1,57 1,57

    1 Papan Nama Proyek 1,00 Ls 500.000,00 500.000,00 0,10 0,10

    2 Pembersihan Lapangan 299,88 M2 9.375,00 2.811.375,00 0,59 0,59

    2 Pengukuran dan Pemasangan Bowplank 1,00 Ls 2.500.000,00 2.500.000,00 0,52 0,52

    3 Dokumentasi Photo dan Pelaporan 1,00 Ls 1.000.000,00 1.000.000,00 0,21 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01

    14.311.375,00

    B PEKERJAAN TANAH DAN PONDASI

    1 Galian Tanah Pondasi menerus 70,20 M3 48.437,50 3.400.312,50 0,71 0,36 0,36

    2 Urugan Kembali Bekas Galian 17,55 M3 16.145,83 283.359,38 0,06 0,03 0,03

    3 Urugan Pasir Alas Pondasi 4,68 M3 132.000,00 617.760,00 0,13 0,13

    4 Pasangan Batu Kosong 9,36 M3 224.160,00 2.098.137,60 0,44 0,22 0,22

    5 Pasangan Pondasi batu belah 36,86 M3 627.150,00 23.116.749,00 4,85 2,43 2,43

    29.516.318,48

    C PEKERJAAN BETON BERTULANG

    1 Sloof Beton 20/25 cm 6,90 M3 4.663.029,95 32.174.906,66 6,75 2,25 2,25 2,25

    2 Kolom Beton C1 25/25 cm 0,95 M3 5.866.752,23 5.573.414,61 1,17 0,58 0,58

    3 Kolom Beton C2 20/20 cm 1,20 M3 4.513.744,87 5.416.493,84 1,14 0,57 0,57

    4 Kolom Beton C3 13/13 cm 0,26 M3 6.560.394,62 1.705.702,60 0,36 0,18 0,18

    5 Ring balok 15/20 cm' 3,39 M3 6.090.913,87 20.648.198,02 4,33 2,17 2,17

    6 Balok latai 15/13 cm' 1,33 M3 7.529.595,92 10.014.362,57 2,10 1,05 1,05

    7 Balok top gevel 15/13 0,53 M3 7.529.595,92 3.990.685,84 0,84 0,84

    79.523.764,14

    D PEKERJAAN PASANGAN DAN PLESTERAN

    1 Pasangan Bata 1Pc:2PP 9,30 M2 105.347,50 979.731,75 0,21 0,10 0,10

    2 Plesteran Bata 1Pc:2PP 18,60 M2 186.210,00 3.463.506,00 0,73 0,73

    3 Pasangan Dinding Bata 1 PC : 4 PP 258,59 M2 94.772,50 24.507.220,78 5,14 2,57 2,574 Plesteran Dinding Bata 1PC : 4 PP 517,18 M2 42.690,00 22.078.414,20 4,63 2,32 2,32

    5 Plesteran beton bertulang 53,60 M2 69.050,00 3.701.080,00 0,78 0,39 0,39

    54.729.952,73

    E PEKERJAAN LANTAI

    1 Timbunan Pasir Bawah Lantai Ruangan dan Selasar 31,59 M3 151.375,00 4.781.936,25 1,00 1,00

    2 Timbunan Tanah Bawah Lantai Ruangan dan Selasar 85,05 M3 77.187,50 6.564.796,88 1,38 1,38

    3 Lantai Beton Tumbuk 11,64 M3 613.425,31 7.140.270,61 1,50 1,50

    4 Lantai keramik 40x40 cm pada ruangan 9,45 M2 167.137,00 1.579.444,65 0,33 0,33

    BULAN PERTAMA BULAN KEDUA BULAN KETIGA

    JADWAL PELAKSANAAN PEKERJAAN

    BULAN KEEMPATNO. URAIAN PEKERJAAN VOLUME SATUAN  HARGA

    SATUAN (Rp.)

    JUMLAH

    HARGA (Rp.)bobot (%)

     KURVA SPEKERJAAN : PENYELESAIAN PEMBANGUNAN 3 RKB SDN LAWE SERAKUT

    SUMBER DANA : MIGAS

    TAHUN ANGGARAN : 2016

    LOKASI : KABUPATEN ACEH TENGGARA

    TOTAL A

    TOTAL B

    TOTAL C

    TOTAL D

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    30/31

    5 Lantai keramik 40x40 cm pada Selasar 2,19 M2 167.137,00 366.030,03 0,08 0,08

    20.432.478,41

    F PEKERJAAN ATAP DAN PLAFOND

    1 Rangka kuda- kuda dan gording baj a r ingan Mul tytruss 396, 90 m2 298.226,00 118.365.899,40 24,84 12,42 12,42

    2 Atap Seng BJLS 396,90 M2 72.040,00 28.592.676,00 6,00 6,00

    3 Rabung seng BJLS 29,40 M' 29.060,00 854.364,00 0,18 0,18

    4 Lesplang Kayu 3/20 cm 81,00 M' 50.792,50 4.114.192,50 0,86 0,86

    5 Plafond teriplek 4mm 302,40 M2 46.152,50 13.956.516,00 2,93 2,93

    6 Rangka plafond 302,40 M2 41.106,00 12.430.454,40 2,61 2,61

    7 Kayu lisPlafon 604,80 m' 10.000,00 6.048.000,00 1,27 1,27184.362.102,30

    G PEKERJAAN KOSEN. PINTU DAN JENDELA

    1 Pintu Type P1 (3 Unit)

    - Kosen Kayu 6/13 0,15 M3 4.847.750,00 727.162,50 0,15 0,15

    - Daun Pintu Panel Ukuran 60 x 210 cm 7,56 M2 394.875,00 2.985.255,00 0,63 0,63

    - Ventilasi Jalusi 2,13 M2 365.012,50 777.476,63 0,16 0,16

    - Kunci Tanam 2 Slaag 3,00 Buah 164.112,50 492.337,50 0,10 0,10

    - Engsel Pintu 6,00 Buah 41.750,00 250.500,00 0,05 0,05

    2 Jendela Type J1 (6 Unit)

    - Kosen Kayu 6/13 0,59 M3 4.847.750,00 2.860.172,50 0,60 0,60

    - Daun Jendela Ukuran 60 x 90 cm 12,96 M2 293.100,00 3.798.576,00 0,80 0,80

    - Ventilasi kaca 60 x 42 cm 6,05 M2 293.100,00 1.773.255,00 0,37 0,37

    - Engsel Jendela 96,00 Buah 35.831,25 3.439.800,00 0,72 0,72

    - Hak Penahan Angin Jendela 96,00 Buah 31.750,00 3.048.000,00 0,64 0,64

    - Kaca 5 mm 10,60 M2 113.500,00 1.203.100,00 0,25 0,25

    3 Jendela Type J1 (6 Unit)

    - Kosen Kayu 6/13 0,69 M3 4.847.750,00 3.344.947,50 0,70 0,70

    - Daun Jendela Ukuran 78 x 80 cm 14,58 M2 293.100,00 4.273.398,00 0,90 0,90

    - Ventilasi kaca 60 x 42 cm 6,80 M2 293.100,00 1.993.080,00 0,42 0,42

    - Engsel Jendela 108,00 Buah 35.831,25 3.869.775,00 0,81 0,81

    - Hak Penahan Angin Jendela 108,00 Buah 31.750,00 3.429.000,00 0,72 0,72

    - Kaca 5 mm 7,58 M2 113.500,00 860.330,00 0,18 0,18

    4 Ventilasi Jalusi pada top gevel

    - Kosen Kayu 6/13 0,09 M3 4.847.750,00 436.297,50 0,09 0,09

    - Ventilasi Jalusi 5,76 M2 293.100,00 1.688.256,00 0,35 0,35

    41.250.719,13

    H PEKERJAAN PENGECATAN

    1 Cat Tembok 3 x (L/D) 517,18 M2 18.826,50 9.736.689,27 2,04 2,04

    2 Cat Plafond dan List Plafond 302,40 M2 18.826,50 5.693.133,60 1,19 1,19

    3 Cat Mengkilat Lesplang Kayu 20,25 M2 44.271,25 896.492,81 0,19 0,19

    4 Cat Mengkilat Kosen Pintu/Jendela 90,12 M2 44.271,25 3.989.725,05 0,84 0,84

    5 Cat Mengkilat Daun Pintu/Jendela/Jalusi 61,56 M2 44.271,25 2.725.338,15 0,57 0,57

    23.041.378,88

    I PEKERJAAN INSTALASI LISTRIK

    1 Armatur

    - Lampu Hemat Energi 26,00 Buah 30.000,00 780.000,00 0,16 0,16

    2 Saklar lampu Merk Broco 2 seri

    - Sakalar 2 Seri setara Broco 4,00 Buah 16.000,00 64.000,00 0,01 0,01

    TOTAL E

    TOTAL F

    TOTAL G

    TOTAL H

  • 8/17/2019 Boq Dan Jadwal Pelaksanaan

    31/31

    3 Stop Kontak 3,00 Buah 18.000,00 54.000,00 0,01 0,01

    4 Instlasi titik penerangan. instalasi termasuk kabel NYA 2.5

    mm dalam pipa PVC fitting lampu dan kelengkapan instalasi

    terpasang 26,00 Titik 110.000,00 2.860.000,00 0,60 0,60

    5 Instalasi titik Stop kontak. instalasi termasuk kabel NYA

    2.5 mm dalam pipa PVC. kotak kontak dan kelengkapan

    instalasi terpasang. 7,00 Titik 130.000,00 910.000,00 0,19 0,19

    6 Box Panel Distribusi 1,00 Buah 750.000,00 750.000,00 0,16 0,16

    5.418.000,00

    J PEKERJAAN NON STANDAR1 Relief Tiang Teras 10,00 Units 250.000,00 2.500.000,00 0,52 0,52

    2 Pasangan Batu Tempel Hitam 19,26 M2 189.125,00 3.642.547,50 0,76 0,76

    TOTAL J 6.142.547,50

    K PEKERJAAN PAVING BLOK

    1 Paving Blok 102,90 M2 130.350,00 13.413.015,00 2,81 1,41 1,41

    2 Pasir Urug Paving Blok 4 cm 20,58 M3 132.000,00 2.716.560,00 0,57 0,57

    3 Dinding Pembatas Paving Blok 7,20 M2 94.772,50 682.362,00 0,14 0,14

    4 Plasteran Dinding Pembatas Paving blok 14,40 M2 42.690,00 614.736,00 0,13 0,13

    5 Beton Cor pondasi 0,72 M3 613.425,31 441.666,22 0,09 0,09

    17.868.339,22

    476.596.975,79 100,00

    3,19 3,17 4,91 4,65 4,56 10,51 20,31 23,26 7,46 7,87 1,30 0,68 1,42 1,56 0,31 4,85

    3,19 6,37 11,28 15,92 20,48 30,99 51,30 74,56 82,01 89,89 91,19 91,86 93,28 94,85 95,15 100,00

    TOTAL A s/d N

    RENCANA KEMAJUAN PEKERJAAN MINGGUAN

      Kutacane, 11 April 2016

    CV. TUNAS MUDA

    ZULKARNAIN. SKD

      Direktur

    RENCANA KEMAJUAN PEKERJAAN KOMULATIF

    TOTAL I