Booster L12/Noker-L13/Absorber Update. PIP Update Talk August 15, 2012 Salah Chaurize. Current Status L12 Noker Systems. Tunnel Prep work 85% Complete - PowerPoint PPT Presentation
Citation preview
BoosterL12/Noker-L13/Absorber Update
PIP Update TalkAugust 15, 2012Salah Chaurize
Current StatusL12 Noker Systems
• Tunnel Prep work 85% Complete• Two of three Noker kicker magnets have been rotated using
new magnet angle brackets and end plates. Third magnet will be rotated this week.
• Maintenance work in progress on kicker load resistors.• Charging resistor module need component fabrication.• L12 Noker power supply systems controls migration
completed and tested.• Working on timing/trigger module installation for Noker
Thyratron firing.• New Thyratron cabinet construction in progress.
Before After
Noker and MKS04 Racks
East Gallery Thyratron Cabinets
Load Resistors AndCharging Resistor Box
Rotated Magnet support plates.
Current StatusL13 Absorber Systems
• Tunnel prep work 90% Complete• Floor and wall marking to be laid out to show foot print of K
and L Blocks and wall shielding support section locations. • Small concrete blocks have been painted by AD Techs. • Machined Beam tube and liner components in hand at Meson
Assembly Building. Preassemble of components in progress. • V. Sidorov is refining design details for aisle side beam kick
configuration. • V. Sidorov is overseeing preassembly efforts by PPD Techs. So
far parts are going together as planned. Liner parts are heavy precision milled components.
Vacuum Liner
Vacuum Liner
Moving block support plates.
Moving block assembly parts
Preassembly process at MAB
Preassembly process at MAB
Preassembly process at MAB
Preassembly process at MAB
Booster Long 13
Illustration of Wall shielding and blocks in tunnel