18
Booster L12/Noker-L13/Absorber Update PIP Update Talk August 15, 2012 Salah Chaurize

Booster L12/Noker-L13/Absorber Update

  • Upload
    marcy

  • View
    47

  • Download
    0

Embed Size (px)

DESCRIPTION

Booster L12/Noker-L13/Absorber Update. PIP Update Talk August 15, 2012 Salah Chaurize. Current Status L12 Noker Systems. Tunnel Prep work 85% Complete - PowerPoint PPT Presentation

Citation preview

Page 1: Booster L12/Noker-L13/Absorber Update

BoosterL12/Noker-L13/Absorber Update

PIP Update TalkAugust 15, 2012Salah Chaurize

Page 2: Booster L12/Noker-L13/Absorber Update

Current StatusL12 Noker Systems

• Tunnel Prep work 85% Complete• Two of three Noker kicker magnets have been rotated using

new magnet angle brackets and end plates. Third magnet will be rotated this week.

• Maintenance work in progress on kicker load resistors.• Charging resistor module need component fabrication.• L12 Noker power supply systems controls migration

completed and tested.• Working on timing/trigger module installation for Noker

Thyratron firing.• New Thyratron cabinet construction in progress.

Page 3: Booster L12/Noker-L13/Absorber Update

Before After

Noker and MKS04 Racks

Page 4: Booster L12/Noker-L13/Absorber Update

East Gallery Thyratron Cabinets

Page 5: Booster L12/Noker-L13/Absorber Update

Load Resistors AndCharging Resistor Box

Page 6: Booster L12/Noker-L13/Absorber Update

Rotated Magnet support plates.

Page 7: Booster L12/Noker-L13/Absorber Update
Page 8: Booster L12/Noker-L13/Absorber Update

Current StatusL13 Absorber Systems

• Tunnel prep work 90% Complete• Floor and wall marking to be laid out to show foot print of K

and L Blocks and wall shielding support section locations. • Small concrete blocks have been painted by AD Techs. • Machined Beam tube and liner components in hand at Meson

Assembly Building. Preassemble of components in progress. • V. Sidorov is refining design details for aisle side beam kick

configuration. • V. Sidorov is overseeing preassembly efforts by PPD Techs. So

far parts are going together as planned. Liner parts are heavy precision milled components.

Page 9: Booster L12/Noker-L13/Absorber Update

Vacuum Liner

Page 10: Booster L12/Noker-L13/Absorber Update

Vacuum Liner

Page 11: Booster L12/Noker-L13/Absorber Update

Moving block support plates.

Page 12: Booster L12/Noker-L13/Absorber Update

Moving block assembly parts

Page 13: Booster L12/Noker-L13/Absorber Update

Preassembly process at MAB

Page 14: Booster L12/Noker-L13/Absorber Update

Preassembly process at MAB

Page 15: Booster L12/Noker-L13/Absorber Update

Preassembly process at MAB

Page 16: Booster L12/Noker-L13/Absorber Update

Preassembly process at MAB

Page 17: Booster L12/Noker-L13/Absorber Update

Booster Long 13

Page 18: Booster L12/Noker-L13/Absorber Update

Illustration of Wall shielding and blocks in tunnel