Bond Construction Update Citizen’s Oversight Committee. Long Beach Community College District April 20, 2009. EDUCATE ENGAGE EMPOWER. Agenda. Completed Construction Projects LAC Central Plant LAC Learning Resource Center Building Q and R Roof Replacement - PowerPoint PPT Presentation
Citation preview
Bond Construction Bond Construction UpdateUpdate
Citizen’s Oversight Citizen’s Oversight CommitteeCommittee
Bond Construction Bond Construction UpdateUpdate
Citizen’s Oversight Citizen’s Oversight CommitteeCommittee
Long Beach Community College District April 20, 2009
EDUCATE ENGAGE EMPOWER 1
Agenda Completed Construction Projects
LAC Central Plant LAC Learning Resource Center Building Q and R Roof Replacement Building P Faculty Restroom Upgrade
Current & Upcoming Construction Projects LAC South Quad Complex LAC Building A, Student Services Retrofit LAC Math Technology Building LAC Parking Structure LAC Building O Complex LAC Infrastructure Improvements – Phase 3 LAC Q & R ADA/HVAC UpgradesLAC Q & R ADA/HVAC Upgrades PCC Industrial Tech Phase 1 PCC MDAB (Multi-Disciplinary Academic Building) PCC Building CC Retrofit District Wide - Master Landscape Plan District Wide - Marquee Signage Plan District Wide - Energy RetrofitsDistrict Wide - Energy Retrofits Los Coyotes Property Upcoming Projects Planned Phasing of Future Projects
Q & A
2
Construction Complete Adds 10,000 ASF to existing
building Substantial Completion Anticipated
April 2009 Ribbon cutting scheduled April
24th, 2009
LAC/Learning Resource Center – Measure E 2002LAC/Learning Resource Center – Measure E 2002
3
Completed Construction Projects
Completed Construction Projects
Central Plant equipment, Public Safety, & Field House for Athletics
Final FF&E installation underway Plant ready for operation and
awaiting completion of LRC & SQC Construction Complete Anticipated startup 12/05/08
LAC Central Plant – Measure E 2002LAC Central Plant – Measure E 2002
4
Completed Construction Projects
Completed Construction Projects
5
Construction completed Replaced existing roof with
modified bitumen roof system. Existing skylights were removed
and installed new skylights. All broken tiles were replaced on all perimeter edging of both buildings.
Building Q and R Roof ReplacementBuilding Q and R Roof ReplacementMeasure E 2008Measure E 2008
Completed Construction Projects
6
Provides two new ADA compliant restrooms in lieu of the existing staff restrooms.
Installation of new wall and framing, redesign layout, finishes, fixtures and doors.
New fixtures and restroom accessories have been installed throughout. Finishes will match existing building décor.
Building P Faculty Restroom UpgradeBuilding P Faculty Restroom Upgrade Measure E 2008Measure E 2008
Current and UpcomingConstruction Projects
Construction approx. 93% Complete
Space includes Approx. 68,000 ASF 32 modern classrooms and labs 38 faculty offices Executive office suites Multipurpose room State of the art Board Room
Substantial completion anticipated Summer 2009
South Quad Complex – Measure E 2002South Quad Complex – Measure E 2002
7
Current and UpcomingConstruction Projects
Design Development phase completed Adds 4,000 ASF to existing building Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. Estimated start of construction end of Spring 2010
LAC Building A – Student Services RetrofitLAC Building A – Student Services Retrofit
Measure E 2008Measure E 2008
8
Current and UpcomingConstruction Projects
Completed Schematic Design Will house Math and Culinary Arts instructional
program as well as Reprographics Estimated start of construction 2012
LAC Math Technology Building – Measure E 2008LAC Math Technology Building – Measure E 2008
9
Current and UpcomingConstruction Projects
LAC Parking Structure – Measure E 2008LAC Parking Structure – Measure E 2008
10
Planning initiated for approximately 900 Vehicles
To be procured under “Design Build Delivery” method
Final Design Criteria completed To be located Southeast corner
of Lot J adjacent to the Verizon building
Photovoltaic Electrical Generation Array on top level of structure
Anticipated start of construction 2010
Current and UpcomingConstruction Projects
LAC Building O Complex – Measure E 2008LAC Building O Complex – Measure E 2008
11
Property acquired December 2008
Two structures totaling 87,000 square feet
Potential occupants to be ACIT, District Warehouse Facility, ERD, and Foundation Office
Warehouse temporarily located in building 2
Foundation Offices under Design Development
Current and UpcomingConstruction Projects
LAC Infrastructure Improvement ProjectsLAC Infrastructure Improvement Projects
Measure E 2008Measure E 2008
12
Planning underway with engineers 75% of Design Phase completed Completes chilled water lines to
North side of campus Includes other major utility
upgrades; Reclaimed Water, Domestic Water, Data, etc.
Existing building HVAC systems to be upgraded in synch with infrastructure improvements
Coordinated with modernization, quick start projects, and Master Landscape Project
Current and UpcomingConstruction Projects
13
Whole building ADA upgrade: includes restrooms, stairlift (Bldg. R)
All new infrastructure: new piping, etc. (Bldg. R) Minor renovations to offices (Bldg. R) Total renovations of locker/training room (Bldg. R) HVAC upgrade: includes new air handlers, ductwork, etc.
(Bldg. Q & R) Update fire alarm system (Bldg. Q & R) Construction will be done in phases so as to minimize
disruption of classes Final construction documents to be submitted to DSA May
2009 Estimated start of construction Spring 2010
LAC Q & R ADA/HVAC - Measure E 2008LAC Q & R ADA/HVAC - Measure E 2008
Current and UpcomingConstruction Projects
Modern facility houses Welding Department and other trade programs
Construction is 60% complete Replaces existing antiquated
structures New Northern face of the
campus Completion anticipated late
summer 2009
PCC Industrial Technology Center Phase 1PCC Industrial Technology Center Phase 1
Measure E 2002Measure E 2002
14
Current and UpcomingConstruction Projects
90% construction documents submitted Swing space planning completed 9/2008, construction of swing space starts
Summer 2009 Anticipated start of MDAB construction Fall 2009 To be completed in two phases
PCC MDAB PCC MDAB (Multi-Disciplinary Academic Building) Measure E 2002(Multi-Disciplinary Academic Building) Measure E 2002
15
Current and UpcomingConstruction Projects
PCC Building CC Retrofit - Measure E 2008PCC Building CC Retrofit - Measure E 2008
16
To be designed by Hill Partnership Architects Houses the Fitness Center, Gymnasium, Weight Room, and
Faculty and Staff Offices Swing space to be located on PCC Campus (Bldg. FF) To be completed concurrently with MDAB project Anticipated start of construction Spring 2010
Current and UpcomingConstruction Projects
District Wide – Master Landscape PlanDistrict Wide – Master Landscape Plan Measure E 2008Measure E 2008
17
Planning completed December 2008 Plan to be implemented concurrently as each Bond construction
project finalizes Designed for long term sustainability of campus and neighborhood
Current and UpcomingConstruction Projects
District Wide – Marquee Signage PlanDistrict Wide – Marquee Signage Plan Measure E 2008Measure E 2008
18
District Wide Signage Plan complete Currently in construction document phase Final site location determined Securing city permits at this time Planned completion late Fall 2009
Current and UpcomingConstruction Projects
19
Phase 1 – Construction of Central Plants The chillers at the Central Plants were selected to achieve maximum
efficiencies both at part load and full load conditions. The plant not only reduces the peak electrical demand at the campus but also offers lower emissions thus reducing the impact on the environment. Received rebates from Southern California Edison
LAC Central Plant Designed to have (2) 600 ton centrifugal chillers and (1) 300 ton
chiller with space for a future 600 ton chiller. The Central Plant is designed to serve most of the existing buildings and all the new buildings at the campus.
PCC Central Plant Designed to have (2) 300 ton centrifugal chillers and (1) 300 ton
multi-stack chiller. The Central Plant is designed to serve most of the existing buildings and approximately three new buildings at the campus.
District Wide Energy Retrofits - Measure E 2008District Wide Energy Retrofits - Measure E 2008
Current and UpcomingConstruction Projects
20
Phase 2A (99% Complete)
Lighting upgrades HVAC upgrades Controls upgrades Pool upgrades Water systems upgrades Hot water system upgrades Re-roofing
Phase 2B (Design Phase)
HVAC upgrades (Air Handlers, Zone upgrades, tie to Central plant, etc.)
Controls upgrades Lighting Upgrades (Interior/Exterior/Lighting controls)
Hot water system upgrades Irrigation Controls Window film addition
District Wide Energy Retrofits - Measure E 2008District Wide Energy Retrofits - Measure E 2008
Current and UpcomingConstruction Projects
21
Re-design current dirt lot to have 80 parking stalls with new lighting and drainage. (Awaiting City feedback)
Re-slurry and re-stripe existing asphalt parking lot. (Done)
Retrofit hand rails and courtyard entry fencing/gates. (Done) Replace elevator controls to bring them up to new current
standards. (In process) Installation of new automated front door. (In process) Building/Monument Signage & Interior Signage upgrade with
Tenant/Suite names. (In process) Refinish exterior aluminum mullions. (In process) Building exterior wood/stucco repairs and painting. (In process) 2nd floor deck repair/resurfacing. (Bids received) Building perimeter landscape upgrade. (In process) Replacement of gutters. (Done)
Los Coyotes Property - Measure E 2008Los Coyotes Property - Measure E 2008
Current and UpcomingConstruction Projects
22
LAC Carson Street Median Fence Replacement (Construction starts April 2009) Pool boiler upgrade (In process)
Replace current heating system with energy efficient boilers. Bldg. F - Conversions of rooms F104 and F106 to new classroom space.
(Awaiting structural calculations) Expansion of Building I (In Design Phase)
Bookstore to be relocated here Relocate Bond Management Team Offices to O Building Complex and
removal of W trailers (December 2009)
Increase parking at Faculty and Lew Davis St. PCC
MM (FPP) Exterior renovation (In Process)
Paint, windows, replacement of all exterior doors Restroom ADA upgrade (In Process)
Upcoming ProjectsUpcoming Projects
Planned Phasing of Future Projects
23
Currently Planned ScheduleCurrently Planned Schedule
2008-09 Parking Structure – Design/Build concept
Anticipate awarding bid Summer 2009 Moving Warehouse from PCC to Building O at LAC – (Done) LAC/PCC Building Needs Assessment Projects
Bathroom Improvement Projects Quick-Start Projects Lighting Projects Classroom Improvement Projects Infrastructure Projects
Submit FPP for M/N Project at LAC and MM Project at PCC and submit IPP for P Building at LAC and MM Project at PCC
Planned Phasing of Future Projects
24
2009-10 Install portables at PCC for Swing Space – Summer 2009 Master Landscaping and Signage plans complete
Marquee signage anticipated to be installed Fall 2009 Moving LAC Building A into Swing Space – Spring 2010 Begin construction of Building A at LAC
Anticipating start at end of Summer 2010 Begin construction of Buildings CC, DD, and EE at PCC
Anticipating Fall 2009 start
Begin Schematic Design for Buildings C and F at LAC
Submit plans to DSA no later than March 2010
Begin Master Landscaping and Signage Initiatives
Continue District Wide Energy Efficiency Improvements Phase IIA (99% complete)
Lighting Upgrades, HVAC Upgrades, Control upgrades, Pool Cover, Roof replacement, etc
Phase IIB (In Design Phase) Upcoming advancements include connecting current buildings to
Central Plant infrastructure
Currently Planned ScheduleCurrently Planned Schedule
Planned Phasing of Future Projects
25
2010-11 Anticipated Construction completion of Building A
at LAC – Fall 2011 Submit plans to DSA for Math/Technology Building
at LAC Move Buildings C and F programs into Swing
Space (M/N Building) and begin construction – late Fall 2011
Construction completion of Buildings CC, DD and EE at PCC
Begin construction of Buildings AA and BB at PCC Anticipating Spring 2011 start
Currently Planned ScheduleCurrently Planned Schedule
Planned Phasing of Future Projects
26
2011-12 Begin construction of Math/Technology Building at LAC Submit plans to DSA for M/N Building at LAC
2012-13 Anticipated Construction completion of Buildings C and
F at LAC – December 2012
Anticipated Construction completion of Math/Technology Building at LAC – December 2012
Begin construction of Buildings M/N at LAC – January 2013
Anticipated Construction completion of Buildings AA and BB at PCC – June 2013
Currently Planned ScheduleCurrently Planned Schedule
QUESTIONS&
ANSWERS