14

Boiler Supporting structure-Steel detailing

Embed Size (px)

Citation preview

Page 1: Boiler Supporting structure-Steel detailing
Page 2: Boiler Supporting structure-Steel detailing

2

Architecture Engineering Construction

Page 3: Boiler Supporting structure-Steel detailing

Index

9/18/2014 3

1. Project Type & Location

2. Client & Project Details

3. Project Process : Challenges & Execution

4. Project Process : Duration, Inputs, Output

5. Quality Process

6. Project Outputs

Page 4: Boiler Supporting structure-Steel detailing

9/18/2014 4

Project : Development of Boiler supporting structure for Cement Industry

Location : UAE

Project Type & Location

Page 5: Boiler Supporting structure-Steel detailing

9/18/2014 5

Client Profile

• Client Company is a leading cement manufacturer’s in emerging markets.

• It is based in Ras Al Khaimah, United Arab Emirates and employs more than 500 people.

• It is the largest cement producer in the United Arab Emirates and a leading regional cement exporter.

• Their principal operating cement plant has an annual production capacity of 2.7 million tons cement

and 3.8 million tons clinker.

Project Detail

• The project was to build up a supporting structure for new boiler in cement industry.

• Hi-Tech’s scope of work was to provide shop drawings for boiler supporting structure.

Client & Project Details

Page 6: Boiler Supporting structure-Steel detailing

9/18/2014 6

Project Process

Challenges

• Their structure design firm of the boiler supporting structure provided Staad pro model as an initial input

for starting the TEKLA model. Further the task was to import the Staad model into TEKLA & work on it.

• The analysis model in Staad is always a center line model, so we need to change all members location

as per the actual input drawings.

• Steel connections were too heavy for TEKLA modeling.

Execution

• After incorporating Staad model provided by their design firm we have to change each member’s

location.

• Even design firm was to design the same structure simultaneously which we were doing in TEKLA. So

there were chances of more revisions from the design team. So to deal with it and to make it finish it in

specific time line was one of the big task.

• Tower height was 55 metre and there was a lump mass at the top of structure in the form of boiler. Such

situation makes stability of structure very instable under earthquake forces and to resist such forces

designer provided us very heavy beam-beam, beam-column, bracing connections. So to do TEKLA

model of such heavy connections was a good experience.

• The detailed shop drawings helped the client to reduce the overall installation time which further

reduced project cost & thus made the execution process smoother.

Page 7: Boiler Supporting structure-Steel detailing

9/18/2014 7

Project Duration

• The project lasted for a period of about 5 months.

Inputs Received

• The Staad working model, Structure drawings & connection sketches from structure engineer.

Outputs Delivered

• General Arrangement drawings

• Assembly drawings

• Part drawings

Software Used

• TEKLA

Project Process

Page 8: Boiler Supporting structure-Steel detailing

9/18/2014 8

Quality Process

Organization Quality Standards, Quality Documents & earlier project reference

Quality Planning for each project

Prepare List of Quality Parameters

Prepare Responsibility Matrix [RACI

Chart]

Prepare Quality Register

Prepare a

Preliminary Quality List

1st Level – Self QC 2nd Level – Peer QC 3rd Level – Random Audit by Quality Manager Update Quality register & if necessary update Quality List/ Quality Parameter List

If any changes recommended by client a. Part of SoW (Scope of Work): Iteration in above process b. Any new changes included in SOW: Start Engineering Change Management Process

Prepare a Final

Quality List

Project In

Quotation

Sample Project

Customer Feedback

Actual Project Execution

Quality Check

Customer Feedback

Final Delivery

Page 9: Boiler Supporting structure-Steel detailing

9/18/2014 9

Project Output

ELEVATION

Page 10: Boiler Supporting structure-Steel detailing

9/18/2014 10

Project Output

COLUMN SPLICE CONNECTION

Page 11: Boiler Supporting structure-Steel detailing

9/18/2014 11

Project Output

BRACING CONNECTION

Page 12: Boiler Supporting structure-Steel detailing

9/18/2014 12

Project Output

BASE PLATE CONNECTION

Page 13: Boiler Supporting structure-Steel detailing

Project Award

TEKLA MODEL COMPETITION

Page 14: Boiler Supporting structure-Steel detailing

9/18/2014 14

T H A N K Y O U

L O C A T I O N S :

Hi-Tech House Nr. Gurukul Tower, Gurukul, A h m e d a b a d, Gujarat, India.

5th Floor, Commerce House – IV, 100 Ft. Road, Prahladnagar, A h m e d a b a d, Gujarat, India.

43-A, E Block, 3rd Floor, Cochin Special Economic Zone Kakkanad, Kochi, Kerala, India.

Bhushan Avsatthi Associate Director Architecture Engineering Construction