8/20/2019 Boards from Sept. 17th Admiral Way Project meeting
1/16
SEPTEMBER 2015
WELCOME
Thank you for coming to tonight’s
SW Admiral Way Safety Improvements
Open House.
6:15 PM
Please sign in and browse the informationstations
6:45 PM
Stay for presentation and conversation after
7:15 PM
Continue with the open house
7:45 PM
Open house concludes
8/20/2019 Boards from Sept. 17th Admiral Way Project meeting
2/16
SEPTEMBER 2015
MEETING GUIDELINES
1. Stay on topic
2. Listen while others are talking
3. Give everyone a chance to speak
4. Respect one another even if
you disagree
5. Challenge ideas, not people
6. Avoid repeating comments
7. Please silence your phones
8/20/2019 Boards from Sept. 17th Admiral Way Project meeting
3/16
SEPTEMBER 2015
Seattle’s plan to end traffic deaths
and serious injuries by 2030 using:
Street design
Education Enforcement
8/20/2019 Boards from Sept. 17th Admiral Way Project meeting
4/16
SEPTEMBER 2015
HOW FAST PEOPLE DRIVE
20MPH
HIT BY A VEHICLETRAVELING AT:
9 out of 10 pedestrians survive
30MPH
HIT BY A VEHICLETRAVELING AT:
5 out of 10 pedestrians survive
40MPH
HIT BY A VEHICLETRAVELING AT:
Only 1 out of 10 pedestrians survives
Speed is especially lethal for vulnerable users like pedestrians and people biking. The risk of
injury and death increases as speed increases.
32 32
37 37 3836
33 3331 31
0
10
20
30
40
East of
45th Ave SW
East of
48th Ave SW
East of
51st Ave SW
East of
SW Stevens St
East of
61st Ave SW
Westbound
Eastbound
SW Admiral Way 85th % Speed(February 2015)
Why Speed Matters
8/20/2019 Boards from Sept. 17th Admiral Way Project meeting
5/16
SEPTEMBER 2015
SW ADMIRAL WAY
SAFETY PROJECT
Goals
Encourage slower speeds
Reduce collisions
Provide a comfortable and predictable
bike connection between Alki and
California Ave business district
Accommodate existing maximum
on-street parking occupancy
8/20/2019 Boards from Sept. 17th Admiral Way Project meeting
6/16
SEPTEMBER 2015
HOW MANY PEOPLE TRAVEL
ON SW ADMIRAL WAY?
SW Admiral Way Average Daily Traffic(February 2015)
People Driving
Bicycle Counts Over One Week in April 2015
People Biking
East of61st Ave SW
East ofSW Stevens St
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
East of51st Ave SW
East of48th Ave SW
East of45th Ave SW
7,085
5,9635,340
4,352
7,336
6,013
5,137
4,154
0
1000
2000
3000
4000
5000
6000
7000
8000
55
27
49
13
26
41 39
94
56
81
50
62
69 68
100
90
80
70
60
50
40
30
2010
0
SW Admiral Way - Both Directions(at SW Stevens St)
SW Admiral Way - Both Directions(at 48th Ave SW)
3,471
2,765
Westbound
Eastbound
8/20/2019 Boards from Sept. 17th Admiral Way Project meeting
7/16
SEPTEMBER 2015
SAMPLE CROSS SECTION
(EAST OF SW STEVENS ST)
Before Improvements
After Improvements
Option A Option B
8/20/2019 Boards from Sept. 17th Admiral Way Project meeting
8/16
SEPTEMBER 2015
SCHEDULE
Date Action
April - May Admiral NeighborhoodAssociation and SW DistrictCouncil briefings;Open house #1
Summer Conduct parking study andrevise concept
Sept 8 Admiral NeighborhoodAssociation briefing
Sept 17 Open house #2
Oct 1 Comments due
Fall Final design
Fall/Winter Implementation
2016 Evaluation
8/20/2019 Boards from Sept. 17th Admiral Way Project meeting
9/16
SEPTEMBER 2015
63RD AVE SW TO 60TH AVE SW
Speed: 32 MPH in both directionsAverage number of vehicles (east of 61st Ave SW): 6,2363,471 Westbound
2,765 Eastbound
D r i v e L a n e
D r i v e L a n e
9' 12'
P a
r k i n g
9'
P a r k i n g
southnorth
T w
o - W a y L e f t
T u r n L a n e
12' 12'
D r i v e L a n e
D r i v e L a n e
P a r k i n g
P a r k i n g
southnorth11'11' 5'3' 8'8' 5' 3'
B i k e L a n e
B u f f e r
B i k e L a n e
B u f f e r
Existing Cross Section
Proposed Cross Section
8/20/2019 Boards from Sept. 17th Admiral Way Project meeting
10/16
SEPTEMBER 2015
60TH AVE SW TO SW STEVENS ST
Speed: 37 MPH in both directionsAverage number of vehicles (east of SW Stevens St): 8,5064,154 Westbound
4,352 Eastbound
D r i v e L a n e
D r i v e L a n e
9' 12'
P a
r k i n g
9'
P a r k i n g
southnorth
T w
o - W a y L e f t
T u r n L a n e
12' 12'
Existing Cross Section
Proposed Cross Section
north
D r i v e L a n e
D r i v e L a n e
P a r k i n g
south5' 11'
B i k e L a n e
7'
B i k e L a n e
B u f f e r
9' 3'
B u f f e r
11' 3' 5'
P a r k i n g
8/20/2019 Boards from Sept. 17th Admiral Way Project meeting
11/16
SEPTEMBER 2015
SW STEVENS ST TO SW LANDER ST
Speed: 37 MPH in both directionsAverage number of vehicles (east of SW Stevens St): 8,5064,154 Westbound
4,352 Eastbound
Existing Cross Section
Proposed Cross Section Option A Proposed Cross Section Option B
D r i v e L a n e
D r i v e L a n e
11.5' 10'
P a r k i n g
11.5'
P a r k i n g
southnorth
T w o - W
a y L e f t
T u r n L a n e
9' 9'
D r i v e L a n e
P a r k i n g
southnorth
B i k e L a n e
B i k e L a n e
B u f f e r
P a r k i n g
D r i v e L a n e
5' 10.5'7' 3' 7'10.5' 3' 5'
D r i v e L a n e
D r i v e L a n e
10'
P a r k i n g
southnorth
T w o - W
a y L e f t
T u r n L a n e
9'10' 5' 8'
B i k e L a n e
B i k e L a n e
B u f f e r
6' 3'
8/20/2019 Boards from Sept. 17th Admiral Way Project meeting
12/16
SEPTEMBER 2015
SW LANDER ST TO 47TH AVE SW
Speed: 37 MPH in both directionsAverage number of vehicles (east of 51st Ave SW): 10,4775,137 Westbound
5,340 Eastbound
Existing Cross Section
Proposed Cross Section Option A Proposed Cross Section Option B
D r i v e L a n e
D r i v e L a n e
21' 12'
P a r k i n g
21'
P a r k i n g
southnorth
T w o - W
a y L e f t
T u r n L a n e
north
D r i v e L a n e
D r i v e L a n e
P a r k i n g
south9' 11'
B u f f e r
5'3'
B i k e L a n e
B u f f e r
8'3' 5'
P a r k i n g
B i k e L a n e
11'north
D r i v e L a n e
D r i v e L a n e
P a r k i n g
south
T w o - W
a y L e f t
T u r n L a n e
5' 3' 10' 10' 10'
B i k e L a n e
B u f f e r
5'3'
B i k e L a n e
B u f f e r
8'
8/20/2019 Boards from Sept. 17th Admiral Way Project meeting
13/16
SEPTEMBER 2015
47TH AVE SW TO 44TH AVE SW
Speed: 33 MPH in both directionsAverage number of vehicles (east of 48th Ave SW): 11,9766,013 Westbound
5,963 Eastbound
Existing Cross Section
Proposed Cross Section
D r i v e L a n e
D r i v e L a n e
19' 10'
P a r k i n g
19'
P
a r k i n g
southnorth
T w o - W
a y L e f t
T u r n L a n e
north
D r i v e L a n e
P a r k i n g
11'11'south
7'
P a r k i n g
7'
B i k e L a n e
D r i v e L a n e
6'
B i k e L a n e
6'
8/20/2019 Boards from Sept. 17th Admiral Way Project meeting
14/16
SEPTEMBER 2015
44TH AVE SW TO CALIFORNIA AVE SW
Speed: 31 MPH in both directionsAverage number of vehicles (east of 45th Ave SW): 14,4217,336 Westbound
7,085 Eastbound
No Change - Existing Cross Section
D r i v e L a n e
D r i v e L a n e
10.5' 10'southnorth
D r i v e L a n e
10.5' 10.5' 10.5'
D r i v e L a n e : 1 / 2 b l o c k
P a r k i n g : 1 / 2 b l o c k
L e f t T u r n L a n e
( a t C a l i f o r n i a )
8/20/2019 Boards from Sept. 17th Admiral Way Project meeting
15/16
SEPTEMBER 2015
COLLISION LOCATIONS
(1/1/2011 12/31/2014)
Pedestrian Collision
Cycle Collision
Vehicle Collision
LEGEND 2
5 4
4
2 23 2
3
3
7
2 2
72
4
4
4
1 pedestrian collision (2012)
2 bicycle collisions (both in 2011) 71 vehicle-only collisions
8/20/2019 Boards from Sept. 17th Admiral Way Project meeting
16/16
SW ADMIRAL WAY
SAFETY PROJECT
Option A
Option B
Buffered Bike Lane
Maintain Parking on Both Sides,
Remove Center Turn Lane
A Potential New Crosswalk
Left Turn Pocket
LEGEND
Under Study
Maintain existing
left turn pocket
Westbound radar
feedback sign
Buffered Bike Lane
Maintain Parking on Both Sides,
Remove Center Turn Lane
Maintain Parking on South Side,
Maintain Center Turn Lane
A Potential New Crosswalk
LEGEND
Under Study
Maintain existing
left turn pocket
Westbound radar
feedback sign
North Side: 2 out of 69
Parking Utilization
South Side: 11 out of 65
Parking Utilization