Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
2016 BOND OVERSIGHT COMMITTEE
RECOMMENDATIONS FOR NEW PROJECTS TO FUND FROM BOND PREMIUM
Board RecommendationsFebruary 19, 2019
1
BACKGROUND AND CONTEXT
2
• When the Board of Education approved the 2016 Bond in August 2016, all of the $572 million was allocated directly to projects, or designated contingency/reserve buckets.
• When the bonds were sold following voter approval in November 2016, original issue premium was obtained and used to establish a $96 million reserve to ensure committed projects could be delivered:
• Of this amount, $25 million was allocated to the purchase and renovations of the Samsonite facility (High Tech Early College)
• Our citizen’s Bond Oversight Committee is responsible for making recommendations regarding the use of any bond savings/premium funds, in addition to oversight of the implementation of 2016 bond projects.
• Note: Bond funds are one-time and can only be used on capital investments such as critical maintenance and facility improvements. Bond funds cannot be used for on-going operating expenses.
PRIORITIZATION PROCESS
3
Committee members:
Luchia Brown
Diana Romero Campbell
Tony Curcio
Kim Desmond (Co-Chair)
Al Habercorn
Colleen Kazemi
Tom Migaki
Rocio Perez
Melissa Rosas
Andrea Steffanich
Halisi Vinson
Russell Welch (Co-Chair)
Board of Education Representative:
Anne Rowe, District 1
Since June, the Oversight Committee has been working through a deliberative, open process to arrive upon recommended uses for a premium reserve release
June2018
• Committee Discussion of Premium Reserve Process and Review of Past Prioritization Criteria
September 2018
• Committee Discussion of Premium Reserve Process and Discussion of Prioritization Criteria
October 2018
• Hypothetical Prioritization Exercise to Refine Prioritization Approach
November 2018
• Review Project List and DPS Recommendation• Prioritization Criteria and Decision Making Rubric
Finalized
December 2018
• Special Public Comment• Committee Deliberation and Recommendation
Finalized
January 2019 • Recommendation to Board of Education
BOND OVERSIGHT PRIORITIZATION CRITERIA
4
As a key milestone in the Oversight Committee’s process, we developed these 4 prioritization categories to help us in reviewing potential projects and staff recommendations in order to arrive at our own recommendation
The Committee recommendations are based on projects aligning with these following key priorities:
• Life/safety and the ability of a school to operate safely• Alignment to instructional priorities• Supporting the value of equity• Time sensitivity
APPROACH TO EQUITY
5
Equity Index
Student Equity- Giving all students the same chance for success. For measuring student equity, we used the following index:
School % High Poverty + %ELL + %SPED +%VolatilityDistrict Average % High Poverty + %ELL + %SPED +%Volatility
This is in line with how DPS allocates student-based funding.
What is the Data?• District average Equity Index (EI) is 1.0 • You can read an EI of 1.1 as that school having 10% above average population of harder-to-serve students. An EI
of 0.7 indicates that school has 30% smaller than average population of harder-to-serve students.
Equity Index:
As prioritization was evaluated, we considered a method to evaluate district-wide equity and equality through anEquity Index that defines a baseline for ALL schools/programs with more rigor than just looking at student poverty.
BOND OVERSIGHT PRIORITIZATION RUBRIC
6
Each committee member used the following rubric to score all projects prior to deliberation. Categories are weighted based on the committee’s discussion of priorities.
Category Weight 0 1 2 3
Life / Safety – Ability for School to Safely Operate
3x Critical Maintenance/ Facility Does not impact safety
Addresses a life / safety concern that is low priority and does not impact the school’s ability to operate
Addresses a life / safety concern that is a medium priority due to the risk of impacting a school’s ability to operate
Addresses critical safetyviolation that directly risks a school’s ability to operate
Code or ADADoes not impact code or ADA
Addresses a low priority code or ADA issue under which DPS has no obligations and presents no negative impacts to students
Addresses a low or medium priority code or ADA issue under which DPS has no obligations but remedying would present a positive student impact
Addresses a high priority code or ADA issue in which DPS has an obligation to remedy the issue and/or would significantly improve the student experience
Student SafetyDoes not impact student safety
The project improves student safety (Nice to have)
Project expands existing student safety investment that is workingand/or invests in piloting new work
Project will bring DPS facilities into compliance with evolving standards for student safety
Supporting Value of Equity
2x The school has an equity index <0.5
Equity index between0.5-1.0
Equity index between 1.0-1.5 Equity index > 1.5
Aligned with Instructional Priorities
2x The project does not impact instruction and academics
The project will improve the student learning environment
The project improves the learning environment and supports new/different instruction
The project directly supports instruction and will support student learning
Time Sensitivity
1x The project can wait for a future capital request without negatively impacting student experience
The project can wait for a future capital request but would positively impact student experience
The project would enhance thestudent experience in the near term and/or there is a risk of future cost being significantly higher beyond the rate of construction inflation
The project cannot wait for future funding and the district will fund elsewhere if not from premium to the detriment of other district funded programs
GETTING TO COMMITTEE RECOMMENDATION
7
To frame these recommendations, staff shared information and their recommendation on over $130M of priority need in the district, although the overall need is much greater
PRIORITIES FROM SCHOOL OPPORTUNITY DATABASE
(INCLUDES SCHOOL LEADER AND FACILITY MANAGERREQUESTS)
PROJECT SCOPES THAT COULD NOT BE COMPLETED
(E.G., INNOVATIVE CLASSROOM PROJECT THAT WASNOT WITHIN BUDGET)
PROJECTS NOT FUNDED DURING 2016 BONDPLANNING
ASSESSMENT OF NEWLY EVOLVED NEEDS
(E.G., DEPARTMENT OF SAFETY, NEW CAPACITY)
Today’s Project Recommendations
OPPORTUNITIES FOR SCHOOL ENGAGEMENT
The committee has participated in many school site visits and, most recently, a MyTech school tour at Bruce Randolph.
In November, all 56 schools with a project on the potential premium list were contacted and provided with information about the project up for consideration.
- Special Public Comment information was included in the communication
The Bond Oversight Committee heard public comment from students, teachers, administrators and parents from 18 schools.
In the future, our aim is to engage more school communities earlier in the process and increase the number of schools who provide public comment.
8
BOND OVERSIGHT COMMITTEE RECOMMENDATIONS
9
Based upon the prioritization criteria, the committee reviewed staff recommendations along with a range of public input to arrive upon the following recommendations
Category Bond Oversight Committee Recommendation
Critical Maintenance/ADA $19.6M
Quality Learning Environments $13.9M
Capacity $5.9M
Technology $4.9M
Safety and Security $1.5M
Total $45.8M*
*Note: DPS staff originally recommended a reserve release amount of $35.5 million. Through the committee’s prioritization of recommended options, the cost increased to approximately $45.8 million. DPS staff responded that they would support up to $45 million in fund release. The final recommendation voted on by the BOC is slightly above that amount.
COMMITTEE RECOMMENDATIONCritical Maintenance/ADA
10
Priority Building Names Category Description Equity Index Score
Recommended Allocation
1 Holm Emergency Maintenance
Sewer and water pipe repair due to leak which is causing sewer gases to filter into the school
1.32 $1,830,000
2 Ashley Critical Maintenance Provide critical elevator maintenance due to high risk of failure and obsolete components
1.16 $106,600
3 Hallett ADA Add an elevator; school has some common areas that are only accessible via stairs - cafeteria is in the basement, library is on the 2nd floor.
1.01 $856,400
4 Beach Court Critical Maintenance Replace gym windows; single pane and a risk to shatter in another hail storm
1.1 $190,300
5 Beach Court ADA Address identified ADA issues in the facility: elevator, ADA restroom access, main entrance ADA access.
1.1 $1,778,800
6 Manual (Manual High School, McAuliffe Manual)
Critical Maintenance Repaint pool area due to deteriorating paint and potential for paint to fall into pool
1.49 $317,200
7 Cole (Cole Arts and Sciences; DSST:ColeHS)
Critical Maintenance Replace water heater due to high risk of failure 1.32 $63,400
8 Beach Court; Garden Place
Heat Mitigation Continue Heat Mitigation efforts for two of the hottest schools based on recent temperature studies
1.19 $6,914,196
9 Mitchell (DSST:ColeMS)
Critical Maintenance Rebuild cooling tower due to high risk of failure 1.47 $46,100
10 CEC Early College Critical Maintenance Replace water heater due to high risk of failure 1.12 $95,200
COMMITTEE RECOMMENDATIONCritical Maintenance/ADA
11
Priority Building Names Category Description Equity Index Score
Recommended Allocation
11 District Wide Fire Suppression Complete testing of District Wide facilities, identify and fix deficiencies
1 $2,918,200
12 Gilpin (DenverLanguage School)
ADA Add an elevator; school has some common areas that are only accessible via stairs.
0.25 $724,700
13 East Critical Maintenance Provide critical elevator maintenance due to high risk of failure and obsolete components
0.44 $101,500
14 Edison Critical Maintenance Provide critical elevator maintenance due to high risk of failure and obsolete components
0.32 $106,600
15 District Wide Critical Maintenance City ordinance requires sidewalks to meet a minimum threshold for safety. Anticipate that DPS will have significant repairs/replacements after City inspections.
1 $1,000,000
16 NE Bus Cooling Tower Critical Maintenance Rebuild cooling tower due to high risk of failure 1 $203,000
17 South HS Critical Maintenance Repair main entry doors due to deteriorating panels and weakened structure; historic building will require specialized repair
0.91 $101,500
18 South HS ADA Build an ADA ramp from the parking lot to the South HS baseball field.
0.91 $197,600
19 Smiley (McAuliffe International)
Critical Maintenance Replace water heater due to high risk of failure 0.25 $63,400
20 District Wide Facility Condition Assessment
Provide additional funding to complete FCA 1 $2,000,000
Total Recommended Critical Maintenance/ADA
$19,614,696
COMMITTEE RECOMMENDATIONQuality Learning Environments
12
Priority Building Names Category Description Equity Index Score
Recommended Allocation
1 West, John F. Kennedy, Bruce Randolph,North, George Washington, Thomas Jefferson, Sandoval
Field Lights Install field lights 1.16 $3,228,100
2 Castro Learning Landscape Upgrades for older learning landscapes 1.58 $362,300
3 District Wide Center Based Program Updates
Updates (furniture, carpet, paint, lighting, etc) for 50 Center Program rooms ($30k of renovations); and renovations to 5 High School rooms with Life Skills ($150k)
2.05 $3,261,100
4 Montbello(DCIS MontbelloHS/MS, Noel Community Arts HS/MS, Strive Prep Montbello MS)
Renovation Renovate cafeteria space to improve queuing to the kitchen, create a more open and modern environment, and provide more flexibility in uses for the campus.
1.44 $2,536,100
5 Munroe Learning Landscape Upgrades for older learning landscapes 1.65 $362,300
6 Smith Learning Landscape Upgrades for older learning landscapes 1.3 $362,300
7 Greenwood Learning Landscape Upgrades for older learning landscapes 1.39 $362,300
8 Eagleton Learning Landscape Upgrades for older learning landscapes 1.42 $362,300
COMMITTEE RECOMMENDATIONQuality Learning Environments
13
Priority Building Names Category Description Equity Index Score
Recommended Allocation
9 Greenlee Learning Landscape Upgrades for older learning landscapes 1.3 $362,300
10 Harrington Learning Landscape Upgrades for older learning landscapes 1.45 $362,300
11 Ruben Valdez (Strive Prep Ruby Hill)
Learning Landscape New learning landscape 1.44 $362,300
12 Garden Place Learning Landscape Upgrades for older learning landscapes 1.26 $362,300
13 Archuleta Learning Landscape Upgrades for older learning landscapes 1.18 $362,300
14 Manual (Manual High School, McAuliffe Manual)
Painting Paint hallways on 1st and 2nd floors. 1.49 $45,300
15 Columbian Learning Landscape Upgrades for older learning landscapes 0.98 $362,300
16 Crofton (UniversityPrep-Arapahoe Street)
Learning Landscape Upgrades for older learning landscapes 0.9 $362,300
17 District Wide Learning Landscape-Contingency
Provide funds to cover items such as drainage if needed to support Learning Landscape updates
1.0 $434,800
Total Recommended Quality Learning Environments $13,853,000
COMMITTEE RECOMMENDATIONCapacity
14
Priority Building Names Category Description Equity Index Score
Recommended Allocation
1 Far North East Land purchase for future school development
Purchase/secure land for future capacity needs in FNE/Gateway.
1.21 $5,880,600
Total Recommended Capacity $5,880,600
COMMITTEE RECOMMENDATIONTechnology
15
Priority Building Names Category Description Equity Index Score
Recommended Allocation
1 District Wide Technology Expand MyTech 1:1 Chromebook program to 4,000 additional HS student. MyTech works with schools to assign Chromebooks directly to students as take-home devices for the entire school year. Funding would cover a three-year implementation at selected schools, and target High Schools that have feeder Middle Schools currently participating in MyTech.
*Greaterthan 1.0
$4,952,300
Total Recommended Technology
$4,952,300
*Note: The committee recommends funding the MyTech expansion with the expectation that schools with an equity index score of greater than 1.0 will receive priority in the application process.
COMMITTEE RECOMMENDATIONSafety and Security
16
Priority Building Names Category Description Equity Index Score
Recommended Allocation
1 District Wide Emergency Notification
Add 400 strobes (2 per school) that go off when a lock down is initiated to alert nearby personnel. Add 400 speakers (2 per school) to notify of lockdown and other emergencies.
1.0 $1,500,000
Total Recommended Technology
$1,500,000
APPENDIX
Geographic Overview of Recommendation Additional Capacity (FNE Land Purchase) Detail
17
18
CAPACITY (FNE LAND PURCHASE)
19
CapacityFar Northeast Development Overview
Map showing all proposed masterplans and other proposals currently in permitting process
CAPACITY (FNE LAND PURCHASE)
20
• Based on forecasts, expect DPS will need to build 3 new schools in the FNE region within next 10 years• Most pressing need for capacity is for elementary seats east of Chambers Rd. We are projected to have more enrollment
than capacity in this region in 2022.• Land currently available in areas needed for school enrollment; risk that size of site and location will be available when
construction would need to start• There will be 2,000-3,000 additional units constructed in the Gateway and Tower regions, yielding a forecasted 1000
elementary students, nearly 500 middle school students and 500 high school students • The elementary need is most pressing as highlighted in the chart below, however projections call for the need for
additional capacity across all grades by 2025
62 101168
312
548 578659
741848
9471,042
1,099 1,132 1,132
0
200
400
600
800
1,000
1,200
2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
FNE ES Enrollment Growth vs. Available Seats, Considering Constant Choice Rates
~500 available seats east of Chambers
Decrease choice in seats available by ~50 students to delay build until 2022
The demand assumes a steady state of choice-out and choice-in rates.