17
BMA Safe: From 42 BMA Safe: From 42 different tools to 1. different tools to 1. Christian Young Christian Young OHS Principal OHS Principal

BMA Safe: From 42 different tools to 1. Christian Young OHS Principal

Embed Size (px)

Citation preview

BMA Safe: From 42 different BMA Safe: From 42 different tools to 1.tools to 1.

Christian YoungChristian Young

OHS PrincipalOHS Principal

Where are we?Where are we?

BackgroundBackground

2000 – 2003: 2000 – 2003: 7 BMA sites independently developed and implemented their 7 BMA sites independently developed and implemented their

own site specific pre-task risk management tool (e.g. SAM, own site specific pre-task risk management tool (e.g. SAM, Take 5). Take 5).

August 2008: August 2008: Recognised that BMA had 42 different tools. Recognised that BMA had 42 different tools. This situation created a multitude of issues, particularly for This situation created a multitude of issues, particularly for

personnel required to work across multiple BMA sites. personnel required to work across multiple BMA sites.

Current problemsCurrent problems

Inefficiencies in training, printing and supply. Inefficiencies in training, printing and supply. Knowledge gap re. tool purpose and its role in risk mgt.Knowledge gap re. tool purpose and its role in risk mgt. Some tools were too complex in relation to intent.Some tools were too complex in relation to intent. Site tools using different risk matrix’s, consequence and Site tools using different risk matrix’s, consequence and

likelihood definitions.likelihood definitions. Some tools had evolved into a control audit process.Some tools had evolved into a control audit process. Inconsistent link to risk management process.Inconsistent link to risk management process. Hazard checklists not aligned with risk profile.Hazard checklists not aligned with risk profile.

Project Initiation / DeliverablesProject Initiation / Deliverables

Project Initiation:Project Initiation: To align with the One BMA strategy, in September 2008 a To align with the One BMA strategy, in September 2008 a

project was initiated to develop one pre-task risk management project was initiated to develop one pre-task risk management tool for all operations. tool for all operations.

Deliverables:Deliverables: July 2009;July 2009; BMA Safe,BMA Safe, BMA Safe training and assessment package.BMA Safe training and assessment package.

Hazard Checklist – front pageHazard Checklist – front page

Joe Blogs 30/5/09 1.30

Ramp 42 South

Relocate dragline cable

Hazard Checklist – back pageHazard Checklist – back page

1 Check guarding is in place

4 Move loose rocks and tools

9 Put barricading in place

14 Check task with geotech

BMA Safe Booklet contents – hazard prompt list, BMA Safe Booklet contents – hazard prompt list, hazard / near miss form, change management form.hazard / near miss form, change management form.

BMA Safe Booklet contentsBMA Safe Booklet contents

BMA Safe Booklet Innovations (for BMA)BMA Safe Booklet Innovations (for BMA)

The tool aligns with its original intent.The tool aligns with its original intent. Hazard checklist is based on incident taxonomy.Hazard checklist is based on incident taxonomy. Defined link to JSA processDefined link to JSA process Accountability for the person completing the hazard Accountability for the person completing the hazard

checklist.checklist. Use of injury mechanism language.Use of injury mechanism language. repository for ‘on the job’ risk management tools.repository for ‘on the job’ risk management tools.

One BMA & Project MethodologyOne BMA & Project Methodology

One BMAOne BMA From a HSEC perspective is about standardisation of From a HSEC perspective is about standardisation of

processes across the group. processes across the group. Even though a relatively simple project, BMA Safe was the first Even though a relatively simple project, BMA Safe was the first

significant One BMA safety project. significant One BMA safety project.

Project Methodology:Project Methodology: It was critical that all project activities were robust, credible and It was critical that all project activities were robust, credible and

transparent to ensure;transparent to ensure;• Alignment to One BMA guiding principles,Alignment to One BMA guiding principles,• Compliance with Legislative and Corporate requirements, andCompliance with Legislative and Corporate requirements, and• Potential organisational impacts were effectively managed.Potential organisational impacts were effectively managed.

Key Project ActivitiesKey Project Activities

Strong project team structure;Strong project team structure; Site and contractor representatives (Steering Committee), Site and contractor representatives (Steering Committee), BMA SSE (Project Sponsor), BMA SSE (Project Sponsor), BMA OHS Principal (Project Manager). BMA OHS Principal (Project Manager). Minor stakeholder groups (supply personnel, printing Minor stakeholder groups (supply personnel, printing

contractor, site HSEC Managers, training personnel).contractor, site HSEC Managers, training personnel).

Thorough data review to define the problem (site tools / Thorough data review to define the problem (site tools / processes).processes).

Key Project ActivitiesKey Project Activities

Prototype used ‘on the job’ during consultation phase.Prototype used ‘on the job’ during consultation phase.

Site reps performed all site consultation activities.Site reps performed all site consultation activities.

Early and regular formal and informal project Early and regular formal and informal project communicationcommunication

Regular communications to other BMA SSE’s by project Regular communications to other BMA SSE’s by project sponsor.sponsor.

BenefitsBenefits

Realised benefits = elimination of current issues.Realised benefits = elimination of current issues.

Unexpected benefits;Unexpected benefits; One BMA is the right strategy.One BMA is the right strategy. Belief in One BMA projects.Belief in One BMA projects. ‘‘Thin end of the wedge’ for next HSEC projects; Thin end of the wedge’ for next HSEC projects;

• One BMA Job Step Analysis Process, and,One BMA Job Step Analysis Process, and,• One BMA Facilitated Risk Assessment Process.One BMA Facilitated Risk Assessment Process.

Challenged thinking of ‘ours is best’ and ‘it can’t be done’.Challenged thinking of ‘ours is best’ and ‘it can’t be done’. Allowed site representatives to contribute to a strategic safety project.Allowed site representatives to contribute to a strategic safety project. Sites owned deliverables. Sites owned deliverables. Safety Advisor Relationships. Safety Advisor Relationships.

Key Learning’s:Key Learning’s:

Change management: evolving process, requires regular Change management: evolving process, requires regular review.review.

Early involvement of printing organisation Early involvement of printing organisation time and time and effort.effort.

Feedback – single point of accountability, feedback Feedback – single point of accountability, feedback template. template.

Use of prototype and tool feedback = informal project Use of prototype and tool feedback = informal project communication. communication.

Key Learning’s:Key Learning’s:

““It may be different but it won’t be wrong”It may be different but it won’t be wrong” Using the final product during consultation focuses Using the final product during consultation focuses

feedback.feedback. Be willing to concede on deliverable design to obtain final Be willing to concede on deliverable design to obtain final

approval. approval. Powerful question - ‘Is this issue a show stopper?’ Powerful question - ‘Is this issue a show stopper?’ Line management sponsor is critical for success.Line management sponsor is critical for success.

Thank YouThank You

Further information Further information [email protected]@bmacoal.com

Copies of booklet.Copies of booklet.