Upload
nelson-p-colo
View
231
Download
0
Embed Size (px)
Citation preview
8/13/2019 Blowing Out Steam Lines
1/8
BLOWING OUT STEAM LINES
INTRODUCTION
The purpose of blowing the steam lines prior to starting up a new unit is to
remove any foreign matter remaining in the equipment (i.e. super heater) andsteam piping after erection is completed. Considerable damage could result if
such foreign matter was allowed to enter the plant steam system during initial
operation.
On older units the need for steam line blowing should be considered
following major pressure parts repairs, where the possibility of introduction
of foreign material into the system exists.
Since prevention of damage to the plant steam system is the prime concern,
the responsibility for determining the effectiveness of the steam line blowing
operation rests with the plant operator. During the steam line blowing process
the unit should be operated in accordance with the vendor recommended
procedures, with all control systems and protective interlocks functioning.
The principle behind steam blowing lines clean is that the thermal cycling
(heating/cooling) and high velocity gas flowing through the line will "shock"
the pipe and tend to break the mill scale and weld slag away from the pipe
wall. Ideally, steam blowing should be done prior to the system being
insulated to maximum the thermal cycling of the equipment. If the system is
insulated, a greater time between blows may be necessary to allow the system
to cool.
Ideally, to obtain optimum cleaning, the flow conditions in the system during
steam line blowing should equal those during normal operation at maximum
load. Since it is impossible to exactly duplicate these conditions when blowing
through the piping to atmosphere, it is desirable to produce equivalent
conditions by using lower pressure steam with a flow rate such that the
product of steam flow times velocity will equal that under normal full load
conditions. The determination of the total obtainable flow quantity must be
based on flow resistance in the entire system, including the temporary piping.
This determination is normally made by the designer of the blowing system.
8/13/2019 Blowing Out Steam Lines
2/8
The temporary piping is normally equipped with a shutoff valve that is used
as a blowing valve. With this arrangement, the superheater and the upstream
portion of the temporary piping are maintained at drum pressure at all times
when not actually blowing.
When a boiler and its associated steam piping have been erected, there is a
possibility that debris, such as welding beads and dirt may have been left in
the tubes and piping. In addition, these parts may have an internal coating of
oxide or mill scale, which will flake off during initial temperature changes.
To avoid any hazard of such material causing obstruction or damage to
machinery, it is recommended that arrangements are made to blow the piping
systems to atmosphere before the final connections are made and steam is
passed to the plant. This blowing through is done with steam which is
exhausted through adequate sized, open ended low pressure temporary
piping. The steam blowing operation cleans the system and provided the
steam of requisite purity for the plant.
This low pressure temporary piping must be connected as near as possible to
the terminal point of the section of the system being purged. In some cases an
appropriate valve cover may be removed and the temporary piping led off the
valve chest. The run should be as short as possible consistent with steam
discharging freely to atmosphere with out causing danger to personnel or
damage to structure and equipment.
If a basket type strainer is installed in the steam piping it must be removed
prior to steam blowing and subsequently replaced.
The precautions listed below must be strictly observed.
REQUIREMENT OF TEMPORARY STEAM LINE FOR BLOWING
The diameter of temporary discharge piping shall not be less than the
diameter of the respective line to be steam blown. The spool pieces should
have an opening equal to the diameter of the respective temporary pipeline.The temporary discharge piping and supports shall be capable to withstand
steam blowing parameters.
PROCEDURE FOR BLOWING
8/13/2019 Blowing Out Steam Lines
3/8
There are two alternative procedures for blowing out the steam lines to the
plant.
One is to raise pressure in the boiler to just below the permissible pressure in
the temporary atmospheric discharge piping, gradually open the boiler stop
valve whilst increasing the firing rate to maintain pressure during the blow,
then gradually close the stop valve whilst reducing the firing rate.
This procedure has the advantage that the blowing period may be as long as
is necessary to clean the steam piping thoroughly.
Usually the waste steam discharged to atmosphere will be dark in colour
when blowing starts, and will become clear as foreign matter is removed from
the system. Several successive bows should be made with an adequate cooling
period between each, as the associated temperature changes will assist inloosening mill scale.
The alternative procedure is the puffing method. The boiler is raised to
around 40kg/cm2g pressure or just below the permissible pressure in the
temporary atmospheric discharge piping. Shut off the firing.
Ensure that the drum water level is at the lowest level.
Open the boiler stop valve quickly; water level in the drum swings upward.
The level may even go beyond visible limit. Permit the boiler pressure to drop
about 10.5 to 14kg/cm2g. The change in steam saturation temperature is kept
less than 42deg.C. Then quickly close the stop valve.
This method has the advantage that the sudden change in steam pressure
produces a sudden change in saturated steam temperature causing a thermal
shock which helps to loosen the adhered scale from the inside of tubes and
piping. The steam expands quickly through the system as the pressure drops.
The scales are than removed by the expanding steam. How ever, all the
pressure parts, including the drum, are subject to thermal shock, and to
prevent excessive stresses and differential expansions, the change insaturation temperature should not exceed 42deg.C.
To ensure thorough cleaning, a number of successive blows must be made
due to the limited blowing period permitted by the allowable pressure
reduction.
8/13/2019 Blowing Out Steam Lines
4/8
8/13/2019 Blowing Out Steam Lines
5/8
8/13/2019 Blowing Out Steam Lines
6/8
8/13/2019 Blowing Out Steam Lines
7/8
3. Remove all control valves, desuperheater nozzles, flow elements, thermowells, pressure gauges, orifice plates, safety valves and instruments that
may be damaged during the steam blow.
4. Insure all vent pipes have adequate drains and that these drains are routedto a safe location.
5. Install temporary pressure gauges as required to monitor the progress ofthe steam blow and make arrangements for to record pressure readings.
6. Establish adequate radio communication between the control room and theoperator at the shutoff valve. Back this up with a system of visual
communication, such as lights or flags, since audio communication may be
difficult due to high noise levels at the steam shutoff valve.
7. Insure personnel traffic is controlled in area during steam blow. Insure thearea near the vent pipe is clear of all personnel during the steam blow.Protect neighbouring equipment from damage due to the steam vents.
8. Individuals operating the steam blow valves (especially near the vent pipe)should wear double ear protection.
General Cleaning Procedure
1. Discontinue all firing and gradually open the temporary blowoff valve, to
blow through the steam system and out the temporary blowoff piping.
Caution: The first blow should always be done at reduced pressure, in order
to check out the temporary piping system, its supports and anchors.
2. When the drum pressure has dropped to the value corresponding with a
100F (56C) saturated steam temperature decrease, close the temporary
blowoff valve and refire the unit to re-establish blowing conditions.
3. Repeat the above cycle until it is considered that cleaning is satisfactory as
indicated by inspection of impact specimens during the final blows.
Post Cleaning Procedures
1. Drain the temporary and permanent piping.2. Remove temporary spools, blind flanges, temporary vent piping, etc., and
reinstall all components removed prior to steam blow.
Cleanliness Criteria
8/13/2019 Blowing Out Steam Lines
8/8
The turbo-generator vendor or the primary end user of the steam will
generally specify the criteria to which the system should be cleaned. If steam
is used in a turbo-generator the following criteria is generally used:
Two successive targets must result in mirror finishes that meet the specifiedcriteria.
After a cooling down period of at least 12 hours, two more successive steamblows must result in mirror surfaces that meet the specified criteria.
Criteria
No indentation exceeding 0.8 mm diameter Indentation exceeding 0.4 mm diameter to number not more than 2 per
2500 mm of the target plate surface
Indentations exceeding 0.2 mm to number not more than 10 per 2500 mmof the target plate surface
Indentations less than 0.2 mm to be well dispersed and nowhere present inconcentration