IIMB Hostel block. Block 7 ( 16 rooms). Block 8 (40 rooms). Block 6 ( 28 rooms). Block 5 ( 48 rooms). Block 1 ( 48 rooms ). Block 2 (44 rooms). Block 3( 40 rooms). Block 4 ( 36 rooms ). IIMB Hostel block – Major milestones. - PowerPoint PPT Presentation
Citation preview
Going far…..going together
Block 2 (44 rooms)
Block 3( 40 rooms)
Block 4 ( 36 rooms )
Block 5 ( 48 rooms)
Block 6 ( 28 rooms)
Block 7 ( 16 rooms) Block 8 (40
rooms)
IIMB Hostel block
Block 1 ( 48 rooms )
Going far…..going together
IIMB Hostel block – Major milestones
Total completi
on
Basement GF FF SF TF
1 Block 1 48 26/03/09 15/04/09 05/05/09 25/05/09 27/09/09
2 Block 2 44 12/03/09 01/04/09 21/04/09 11/05/2009 31/05/2009 13/09/09
3 Block 3 40 17/03/09 06/04/09 26/04/09 16/05/09 05/06/2009 18/09/09
4 Block 4 36 22/03/09 11/04/09 01/05/09 21/05/09 01/06/09 23/09/09
5 Block 5 48 15/06/09 05/07/09 25/07/09 14/08/09 17/12/09
6 Block 6 28 20/06/09 10/07/09 30/07/09 19/08/09 01/01/10
7 Block 7 16 25/06/09 15/07/09 4/8/2009 24/08/09 27/12/09
8 Block 8 40 30/06/09 20/07/09 9/8/2009 29/08/09 1/1/2010
300
DetailsSl NoRoof slab ConcretingNo. of
rooms
This is for the present scope of works without furnishing works
Going far…..going together
Duplex 1 Duplex 2 Duplex 3
Duplex 4
Duplex 5 Duplex 6
IIMB Faculty Residences
Going far…..going together
IIMB Faculty Residences – Major milestonesTotal
completion
Basement GF Mezzanine FF SF
1Duplex 1 - North
4 10/03/09 15/04/09 06/05/09 27/05/09 17/06/09 08/10/09
2Duplex 2 - North
4 17/03/09 22/04/09 13/05/09 03/06/09 24/06/09 15/10/09
3Duplex 3 - North
4 24/03/09 29/04/09 20/05/09 10/06/09 01/07/09 22/10/09
4Duplex 4 - North
4 31/03/09 08/07/09 29/07/09 19/08/09 09/09/09 31/12/09
5Duplex 5 - South
4 15/07/09 05/08/09 26/08/09 16/09/09 07/01/10
6Duplex 6 - South
4 22/07/09 12/08/09 02/09/09 23/09/09 26/01/10
24
Sl No DetailsNo. of units
Roof slab Concreting
This is for the present scope of works without furnishing works
Going far…..going together
Faculty residence – marking work in progress
Hostel Block – excavation work in progress