Turner Innovation Series ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company
Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.
1
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
TURNER INNOVATION SERIESMay 2012
BIM for Design, Preconstruction, & Construction
Brian Krause Manager, Integrated Building [email protected]
Dan Gramer Manager, Integrated Building [email protected]
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
SupportActivity
57% Waste
Construction Industry Institute 2004
Value Added 62% Waste
26%
SupportActivity
Value Added 10%
Why BIM? Excessive Re-Work and Waste
Value Added 62% Waste
26%
SupportActivity
SupportActivity
57% Waste
Value Added 10%
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Why BIM? Construction Productivity is Declining
0.00%
50.00%
100.00%
150.00%
200.00%
250.00%
Inde
x
Construction Productivity Index (1964 = 100%)Cumulative Non-Farm Productivity Index (1964 = 100%)
Construction & Non-Farm Labor Productivity Index (1964 - 2004)Stanford University CIFE 2004
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
BIM for Design, Preconstruction, & Construction
Define
Create
Plan
Build
Measure
Educate
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Why BIM? Try to visualize this section
Pike Place Market – Seattle, Washington
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Why BIM? Does this make more sense?
Pike Place Market – Seattle, Washington
Turner Innovation Series ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company
Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.
2
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
BIM is…
Hand Drawing 2D CAD 3D CAD
evolution
BIM
BIM – Building Information Modeling(Yapi Bilgi Modellemesinin)
Intelligent 3D model Central platform for information
exchange Collaborative work environment Better communication
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
LOD 100 200 300 400 500
Example
DescriptionLine work, areas,
volume zones and text
Generic 3D elements,
maximum size, purpose
Specific 3D elements with
actual dimensions, capacities, and
connections
Shop/Fabrication 3D model, actual
dimensions with manufacture details
As Built 3D model, actual
Purpose2D
Drawing(CAD)Coordination
General Reference for
Fabrication
Detailed Plan for Fabrication and
InstallationDefined by Owner
Level of Detail
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
What we are trying to avoid…
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
BIM for Design, Preconstruction, & Construction
Define
Create
Plan
Build
Measure
Educate
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Documentation Advantages – Rapid Visualization
• Integrated visualization and documentation process
• Changes to model automatically updates project documentation
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Documentation Advantages – Integrated Information
• Inherent Information in model objects create quick automatic schedules
Turner Innovation Series ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company
Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.
3
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Model Based Code Checking
Space 1.6: STAFF TOILET(2039) has insufficient room for wheelchair turning space…
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Program Design Validation
Too small OFFICE spaces. Area of the spaces is 95.48 sq ft, when the required minimum area is 125.00 sq ft.
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Visualization of Scope
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Visualization of Scope
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Visualization of Scope
Turner Innovation Series – BIM Conference Istanbul – Swissotel Meeting Space
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
BIM for Design, Preconstruction, & Construction
Define
Create
Plan
Build
Measure
Educate
Turner Innovation Series ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company
Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.
4
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
BIM Project Execution Plan
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
BIM Project Execution Plan – Content Plan
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
OPTION 1
PRECAST 6’
OPTION 2
PRECAST 7’
OPTION 3
BRICK 6”
OPTION 4
CURTAINWALL
OPTION 5
CURTAIN WALL W/ SUN SHADE
Window Surface Area Glass
185,600 156,800 185,600 339,000 339,900
Wall Surface Area Hard Surface
156,800 185,600 156,800 2,500 2,500
Cost per SF Contact Area
$68.55 $66.45 $66.26 $124.49 $174.12
Total Exterior Wall Cost
$23,472,000 $22,752,000 $22,688,000 $42,625,000 $59,620,000
Model Based Estimation – 5D
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Riverside Doctor’s Hospital
Model Based Estimation – 5D
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Voxel iStudio Quantify – Model Based Estimation
Voxel iStudio Quantify – Takeoff, quantify, model, and report using traditional 2D takeoff methods, but in a 3D environment.
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Voxel iStudio Attribute – Content Management
Voxel iStudio Attribute – Intelligent building information content management in a model based environment.
Turner Innovation Series ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company
Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.
5
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Total Cost of Ownership
Land, Planning & Design
7%
Construction Costs31%
Construction Management
3%Medical Equip./FF&E
12%
Energy9%
Operations & Staff9%
Maintenance & Repair14%
Business Impact12%
Financing Costs2%
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Total Cost of Ownership
Lifecycle Studies – Daylight Simulations – Energy Analysis
Existing
Option #1
Option #2
Option #3
Option #4
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Visualization of Scope
Bid Package Scope
Scope by Discipline
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Detailed Concrete Formwork Planning
Detailed Concrete Formwork Planning
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Schedule Simulation – 4D
Sacramento Airport – Sacramento, CA
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Permit Submission & Review
NYU Dentistry – Department of Buildings Submission in .dwfxfor site safety
Turner Innovation Series ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company
Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.
6
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
BIM for Design, Preconstruction, & Construction
Define
Create
Plan
Build
Measure
Educate
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Approach
Transparent, collaborative environment
Best results if owner, designers, and subcontractors are involved
Guide, support , and enable project participants to work in 3D
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Architectural Design
Structural Design Structural Model
Architectural Model
Revision of Shop drawings
Coordination Meeting
Mechanical 3D Shop DWGs
Plumbing 3D Shop DWGs
Electrical 3D Shop DWGs
Other Shop DWGs Other Model
Subcontractors (contractual requirement)
Integrated Model
Clash Report
Automated Clash Detection
Turner
3D Trade Coordination
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
3D Trade Coordination
Electrical J-Box
Access space for J-Box
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
3D Trade Coordination
Architectural & Structural Models
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
3D Trade Coordination
Ductwork & Piping Models
Turner Innovation Series ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company
Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.
7
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
3D Trade Coordination
Plumbing & Other Piping Models
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
3D Trade Coordination
Electrical Power & Lighting Models
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
3D Trade Coordination
Fire Protection Models
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
3D Trade Coordination
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Capture Existing Conditions
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Capture Existing Conditions
Turner Innovation Series ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company
Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.
8
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Capture Existing Conditions
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Capture Existing Conditions
Madison Square Garden – New York, NY
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
2D versus 3D Coordination
The Old Way… 2D The New Way… 3D
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Turner Model Coordinator
Electrical Coordinator
Ductwork Coordinator
Fire Sprinkler Coordinator Mech Pipe Coordinator
Plumbing Coordinator
Turner MEP Manager
iRoom Coordination Environment
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Seattle, WA Sacramento, CA New York, NY
Salem, OR Gaithersburg, MD
iRoom Coordination Environment
Butler, PA
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Virtual Coordination Environment
Teleconference
Webinar
Collaborative Digital Whiteboard
Remote Desktop
Smartboards
Desktop/Laptop
iPad
Turner Innovation Series ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company
Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.
9
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Model Based Layout
Combined model reviewed with structural engineer, layout team, and detailers.
Points exported from model to total station for layout.
As-built information overlaid for verification prior to concrete pour.
Early field verification to accelerate release to fabrication
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Model Based Layout
Trades: Mechanical, Plumbing, Electrical, Fire Protection
Labor Savings: > 50 % Accuracy: > 96%
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Digital Document Management
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
AR via Turner iPad/iPhone app
VOXEL iSTUDIO
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Visual Production Control
Percent Plan Complete (PPC)
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Visual Production Control
Work in Place Tracking
Visual RACS
Turner Innovation Series ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company
Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.
10
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
MEP Systems Prefabrication
Just in time delivery = Less waste
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
MEP Systems Prefabrication
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
BIM for Design, Preconstruction, & Construction
Define
Create
Plan
Build
Measure
Educate
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
0
50
100
150
200
250
300
8/18/2008 8/25/2008 9/2/2008 9/9/2008 9/15/2008 9/17/2008 9/19/2008 9/22/2008 9/23/2008 9/30/2008 1/14/2009 1/20/2009 1/21/2009 1/26/2009 1/28/2009 1/29/2009
0-CELLAR
Weekly Coordination Meetings
Number of Clashes
Spike 3 – Change to LEED project, MEP systems changed
Spike 2 – Clashes with Fire Protection
Spike 1 – Structure, Sheet Metal, & Plumbing Clashes
MEP Process Performance
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
MEP Process Performance
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Coordination Tracking
World Trade Center Tower 2
Turner Innovation Series ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company
Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.
11
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Results – Increased Productivity
0.05.0
10.015.020.025.030.035.040.0
Mechanical Electr ical Fire Protection
$K
/Ma
n M
on
th
Trade
Average Productivity Metrics
BIM AVG PRODUCTIVITY
NON BIM AVG PRODUCTIVITY
143% Increase in Mechanical Productivity
BIM Average Productivity vs. Non-BIM Average Productivity
67% Increase in Electrical Productivity
36% Increase in Fire Protection Productivity
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Nintendo of America, Corporate Headquarters- Location: Redmond, WA - Completed Spring 2010
- Seattle Business Unit - Architect: ZGF
- 4-story, 380k sf Office Building - Volume: $136M
- Significant BIM & Lean Strategies - LEED Gold
Project Case Study
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
- 3D Virtual Trade Coordination of MEP - Model Based Constructability Reviews- 4D Schedule Simulations & Logistics Planning - Model Based Curtain Wall Studies- 5D Quantity Extraction - Model Based Steel Sequencing Planning- Field Layout from BIM- Collaborative onsite iRoom
Project Case Study
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Results
Accelerated schedule 3 months
On-site labor 37% less than estimated
Productivity 42% higher than average Business Unit Avg. 33.91 ($K WIP/MM):
Project Avg. 48.36 ($K WIP/MM):
7% of total budget returned as savings
Project Case Study
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
BIM for Design, Preconstruction, & Construction
Define
Create
Plan
Build
Measure
Educate
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Implementation at Turner
Senior level support & engagement
National/Regional talent & support for standards, procedures, education, training, & consistency
Local talent for project support
Subcontractor talent for implementation
Turner Innovation Series ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company
Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.
12
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Turner Sharepoint – VDC Internal• BIM Job Metrics• BIM Staff Metrics• BIM Examples
• Recorded Webinar Wednesday Videos• Streaming Training Videos
Socialcast – Turner VDC Social Networking Site – www.socialcast.com
BIM at Turner: Network of Resources
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Turner Metrics
• Ranked #1 BIM Implementer in BD&C Magazine in 2010• Total Number of BIM Projects - 387• Total BIM Project Estimated Volume - $29.1 Billion• Total MEP Clash Projects - 307
• Total Constructability Review Projects - 136• Total Quantity Take-Off/Cost Estimating Projects - 114• Total Scheduling/4D Modeling Projects - 128• Total Laser Scanning Projects – 33• Total iRoom Setups in Use – 109
0
20
40
60
80
100
120
140
2004 2005 2006 2007 2008 2009 2010 2011
Total Turner BIM Projects By Year
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Turner BIM University
2010 – 11 new BIM recruits
2011 – 25 new BIM recruits
8-weeks centralized VDC/BIM training
Weekly topics – Visualization, BIM & 4D, Model Based Scheduling, Model Based Estimating, Coordination, Lean Integration & Optimization
Weekly Flow: Operations – Tools – Practice
Advanced BIM Training
BU/Project Specific Training
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Turner BIM University
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Next Steps – Think Big, Start Small, Move Fast
Think Big Identify current inefficiencies in the process
Identify potential project issues
Identify where technology can help inefficiencies, solve issues, or improve current processes
Select the appropriate technology
Start Small Learn a 3D Model or Analysis Software
Free Software Available Google Sketchup – Modeling
Autodesk Design Review – Review & Analysis
Autodesk Navisworks Freedom – Review & Analysis
Solibri Model Viewer – Review & Analysis
Tekla BIMSight – Review, Analysis, & Clash Detection
TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012
Questions?
Brian Krause
Manager, Integrated Building Solutions
Dan Gramer
Manager, Integrated Building Solutions