Turner Innovation Series BIM Conference Istanbul – May 2012 BIM for Design, Preconstruction, & Construction Brian Krause, Dan Gramer, Turner Construction Company Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author. 1 TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012 TURNER INNOVATION SERIES May 2012 BIM for Design, Preconstruction, & Construction Brian Krause Manager, Integrated Building Solutions [email protected] Dan Gramer Manager, Integrated Building Solutions [email protected] TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012 Support Activity 57% Waste Construction Industry Institute 2004 Value Added 62% Waste 26% Support Activity Value Added 10% Why BIM? Excessive Re-Work and Waste Value Added 62% Waste 26% Support Activity Support Activity 57% Waste Value Added 10% TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012 Why BIM? Construction Productivity is Declining 0.00% 50.00% 100.00% 150.00% 200.00% 250.00% Index Construction Productivity Index (1964 = 100%) Cumulative Non-Farm Productivity Index (1964 = 100%) Construction & Non-Farm Labor Productivity Index (1964 - 2004) Stanford University CIFE 2004 TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012 BIM for Design, Preconstruction, & Construction Define Create Plan Build Measure Educate TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012 Why BIM? Try to visualize this section Pike Place Market – Seattle, Washington TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012 Why BIM? Does this make more sense? Pike Place Market – Seattle, Washington

BIM for Design, Preconstruction, & Construction

Embed Size (px)

Citation preview

Page 1: BIM for Design, Preconstruction, & Construction

Turner Innovation Series  ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company

Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.

1

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

TURNER INNOVATION SERIESMay 2012

BIM for Design, Preconstruction, & Construction

Brian Krause Manager, Integrated Building [email protected]

Dan Gramer Manager, Integrated Building [email protected]

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

SupportActivity

57% Waste

Construction Industry Institute 2004

Value Added 62% Waste

26%

SupportActivity

Value Added 10%

Why BIM? Excessive Re-Work and Waste

Value Added 62% Waste

26%

SupportActivity

SupportActivity

57% Waste

Value Added 10%

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Why BIM? Construction Productivity is Declining

0.00%

50.00%

100.00%

150.00%

200.00%

250.00%

Inde

x

Construction Productivity Index (1964 = 100%)Cumulative Non-Farm Productivity Index (1964 = 100%)

Construction & Non-Farm Labor Productivity Index (1964 - 2004)Stanford University CIFE 2004

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

BIM for Design, Preconstruction, & Construction

Define

Create

Plan

Build

Measure

Educate

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Why BIM? Try to visualize this section

Pike Place Market – Seattle, Washington

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Why BIM? Does this make more sense?

Pike Place Market – Seattle, Washington

Page 2: BIM for Design, Preconstruction, & Construction

Turner Innovation Series  ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company

Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.

2

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

BIM is…

Hand Drawing 2D CAD 3D CAD

evolution

BIM

BIM – Building Information Modeling(Yapi Bilgi Modellemesinin)

Intelligent 3D model Central platform for information

exchange Collaborative work environment Better communication

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

LOD 100 200 300 400 500

Example

DescriptionLine work, areas,

volume zones and text

Generic 3D elements,

maximum size, purpose

Specific 3D elements with

actual dimensions, capacities, and

connections

Shop/Fabrication 3D model, actual

dimensions with manufacture details

As Built 3D model, actual

Purpose2D

Drawing(CAD)Coordination

General Reference for

Fabrication

Detailed Plan for Fabrication and

InstallationDefined by Owner

Level of Detail

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

What we are trying to avoid…

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

BIM for Design, Preconstruction, & Construction

Define

Create

Plan

Build

Measure

Educate

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Documentation Advantages – Rapid Visualization

• Integrated visualization and documentation process

• Changes to model automatically updates project documentation

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Documentation Advantages – Integrated Information

• Inherent Information in model objects create quick automatic schedules

Page 3: BIM for Design, Preconstruction, & Construction

Turner Innovation Series  ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company

Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.

3

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Model Based Code Checking

Space 1.6: STAFF TOILET(2039) has insufficient room for wheelchair turning space…

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Program Design Validation

Too small OFFICE spaces. Area of the spaces is 95.48 sq ft, when the required minimum area is 125.00 sq ft.

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Visualization of Scope

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Visualization of Scope

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Visualization of Scope

Turner Innovation Series – BIM Conference Istanbul – Swissotel Meeting Space

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

BIM for Design, Preconstruction, & Construction

Define

Create

Plan

Build

Measure

Educate

Page 4: BIM for Design, Preconstruction, & Construction

Turner Innovation Series  ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company

Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.

4

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

BIM Project Execution Plan

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

BIM Project Execution Plan – Content Plan

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

OPTION 1

PRECAST 6’

OPTION 2

PRECAST 7’

OPTION 3

BRICK 6”

OPTION 4

CURTAINWALL

OPTION 5

CURTAIN WALL W/ SUN SHADE

Window Surface Area Glass

185,600 156,800 185,600 339,000 339,900

Wall Surface Area Hard Surface

156,800 185,600 156,800 2,500 2,500

Cost per SF Contact Area

$68.55 $66.45 $66.26 $124.49 $174.12

Total Exterior Wall Cost

$23,472,000 $22,752,000 $22,688,000 $42,625,000 $59,620,000

Model Based Estimation – 5D

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Riverside Doctor’s Hospital

Model Based Estimation – 5D

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Voxel iStudio Quantify – Model Based Estimation

Voxel iStudio Quantify – Takeoff, quantify, model, and report using traditional 2D takeoff methods, but in a 3D environment.

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Voxel iStudio Attribute – Content Management

Voxel iStudio Attribute – Intelligent building information content management in a model based environment.

Page 5: BIM for Design, Preconstruction, & Construction

Turner Innovation Series  ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company

Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.

5

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Total Cost of Ownership

Land, Planning & Design

7%

Construction Costs31%

Construction Management

3%Medical Equip./FF&E

12%

Energy9%

Operations & Staff9%

Maintenance & Repair14%

Business Impact12%

Financing Costs2%

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Total Cost of Ownership

Lifecycle Studies – Daylight Simulations – Energy Analysis

Existing

Option #1

Option #2

Option #3

Option #4

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Visualization of Scope

Bid Package Scope

Scope by Discipline

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Detailed Concrete Formwork Planning

Detailed Concrete Formwork Planning

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Schedule Simulation – 4D

Sacramento Airport – Sacramento, CA

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Permit Submission & Review

NYU Dentistry – Department of Buildings Submission in .dwfxfor site safety

Page 6: BIM for Design, Preconstruction, & Construction

Turner Innovation Series  ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company

Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.

6

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

BIM for Design, Preconstruction, & Construction

Define

Create

Plan

Build

Measure

Educate

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Approach

Transparent, collaborative environment

Best results if owner, designers, and subcontractors are involved

Guide, support , and enable project participants to work in 3D

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Architectural Design

Structural Design Structural Model

Architectural Model

Revision of Shop drawings

Coordination Meeting

Mechanical 3D Shop DWGs

Plumbing 3D Shop DWGs

Electrical 3D Shop DWGs

Other Shop DWGs Other Model

Subcontractors (contractual requirement)

Integrated Model

Clash Report

Automated Clash Detection

Turner

3D Trade Coordination

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

3D Trade Coordination

Electrical J-Box

Access space for J-Box

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

3D Trade Coordination

Architectural & Structural Models

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

3D Trade Coordination

Ductwork & Piping Models

Page 7: BIM for Design, Preconstruction, & Construction

Turner Innovation Series  ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company

Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.

7

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

3D Trade Coordination

Plumbing & Other Piping Models

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

3D Trade Coordination

Electrical Power & Lighting Models

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

3D Trade Coordination

Fire Protection Models

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

3D Trade Coordination

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Capture Existing Conditions

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Capture Existing Conditions

Page 8: BIM for Design, Preconstruction, & Construction

Turner Innovation Series  ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company

Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.

8

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Capture Existing Conditions

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Capture Existing Conditions

Madison Square Garden – New York, NY

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

2D versus 3D Coordination

The Old Way… 2D The New Way… 3D

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Turner Model Coordinator

Electrical Coordinator

Ductwork Coordinator

Fire Sprinkler Coordinator Mech Pipe Coordinator

Plumbing Coordinator

Turner MEP Manager

iRoom Coordination Environment

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Seattle, WA Sacramento, CA New York, NY

Salem, OR Gaithersburg, MD

iRoom Coordination Environment

Butler, PA

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Virtual Coordination Environment

Teleconference

Webinar

Collaborative Digital Whiteboard

Remote Desktop

Smartboards

Desktop/Laptop

iPad

Page 9: BIM for Design, Preconstruction, & Construction

Turner Innovation Series  ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company

Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.

9

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Model Based Layout

Combined model reviewed with structural engineer, layout team, and detailers.

Points exported from model to total station for layout.

As-built information overlaid for verification prior to concrete pour.

Early field verification to accelerate release to fabrication

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Model Based Layout

Trades: Mechanical, Plumbing, Electrical, Fire Protection

Labor Savings: > 50 % Accuracy: > 96%

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Digital Document Management

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

AR via Turner iPad/iPhone app

VOXEL iSTUDIO

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Visual Production Control

Percent Plan Complete (PPC)

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Visual Production Control

Work in Place Tracking

Visual RACS

Page 10: BIM for Design, Preconstruction, & Construction

Turner Innovation Series  ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company

Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.

10

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

MEP Systems Prefabrication

Just in time delivery = Less waste

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

MEP Systems Prefabrication

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

BIM for Design, Preconstruction, & Construction

Define

Create

Plan

Build

Measure

Educate

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

0

50

100

150

200

250

300

8/18/2008 8/25/2008 9/2/2008 9/9/2008 9/15/2008 9/17/2008 9/19/2008 9/22/2008 9/23/2008 9/30/2008 1/14/2009 1/20/2009 1/21/2009 1/26/2009 1/28/2009 1/29/2009

0-CELLAR

Weekly Coordination Meetings

Number of Clashes

Spike 3 – Change to LEED project, MEP systems changed

Spike 2 – Clashes with Fire Protection

Spike 1 – Structure, Sheet Metal, & Plumbing Clashes

MEP Process Performance

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

MEP Process Performance

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Coordination Tracking

World Trade Center Tower 2

Page 11: BIM for Design, Preconstruction, & Construction

Turner Innovation Series  ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company

Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.

11

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Results – Increased Productivity

0.05.0

10.015.020.025.030.035.040.0

Mechanical Electr ical Fire Protection

$K

/Ma

n M

on

th

Trade

Average Productivity Metrics

BIM AVG PRODUCTIVITY

NON BIM AVG PRODUCTIVITY

143% Increase in Mechanical Productivity

BIM Average Productivity vs. Non-BIM Average Productivity

67% Increase in Electrical Productivity

36% Increase in Fire Protection Productivity

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Nintendo of America, Corporate Headquarters- Location: Redmond, WA - Completed Spring 2010

- Seattle Business Unit - Architect: ZGF

- 4-story, 380k sf Office Building - Volume: $136M

- Significant BIM & Lean Strategies - LEED Gold

Project Case Study

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

- 3D Virtual Trade Coordination of MEP - Model Based Constructability Reviews- 4D Schedule Simulations & Logistics Planning - Model Based Curtain Wall Studies- 5D Quantity Extraction - Model Based Steel Sequencing Planning- Field Layout from BIM- Collaborative onsite iRoom

Project Case Study

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Results

Accelerated schedule 3 months

On-site labor 37% less than estimated

Productivity 42% higher than average Business Unit Avg. 33.91 ($K WIP/MM):

Project Avg. 48.36 ($K WIP/MM):

7% of total budget returned as savings

Project Case Study

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

BIM for Design, Preconstruction, & Construction

Define

Create

Plan

Build

Measure

Educate

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Implementation at Turner

Senior level support & engagement

National/Regional talent & support for standards, procedures, education, training, & consistency

Local talent for project support

Subcontractor talent for implementation

Page 12: BIM for Design, Preconstruction, & Construction

Turner Innovation Series  ‐ BIM Conference Istanbul – May 2012BIM for Design, Preconstruction, & ConstructionBrian Krause, Dan Gramer, Turner Construction Company

Copyright © Turner Construction Company 2012 All Rights Reserved. No part of this document may be reproduced without written consent from the author.

12

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Turner Sharepoint – VDC Internal• BIM Job Metrics• BIM Staff Metrics• BIM Examples

• Recorded Webinar Wednesday Videos• Streaming Training Videos

Socialcast – Turner VDC Social Networking Site – www.socialcast.com

BIM at Turner: Network of Resources

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Turner Metrics

• Ranked #1 BIM Implementer in BD&C Magazine in 2010• Total Number of BIM Projects - 387• Total BIM Project Estimated Volume - $29.1 Billion• Total MEP Clash Projects - 307

• Total Constructability Review Projects - 136• Total Quantity Take-Off/Cost Estimating Projects - 114• Total Scheduling/4D Modeling Projects - 128• Total Laser Scanning Projects – 33• Total iRoom Setups in Use – 109

0

20

40

60

80

100

120

140

2004 2005 2006 2007 2008 2009 2010 2011

Total Turner BIM Projects By Year

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Turner BIM University

2010 – 11 new BIM recruits

2011 – 25 new BIM recruits

8-weeks centralized VDC/BIM training

Weekly topics – Visualization, BIM & 4D, Model Based Scheduling, Model Based Estimating, Coordination, Lean Integration & Optimization

Weekly Flow: Operations – Tools – Practice

Advanced BIM Training

BU/Project Specific Training

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Turner BIM University

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Next Steps – Think Big, Start Small, Move Fast

Think Big Identify current inefficiencies in the process

Identify potential project issues

Identify where technology can help inefficiencies, solve issues, or improve current processes

Select the appropriate technology

Start Small Learn a 3D Model or Analysis Software

Free Software Available Google Sketchup – Modeling

Autodesk Design Review – Review & Analysis

Autodesk Navisworks Freedom – Review & Analysis

Solibri Model Viewer – Review & Analysis

Tekla BIMSight – Review, Analysis, & Clash Detection

TURNER INNOVATION SERIES | BIM CONFERENCE | ISTANBUL | May 2012

Questions?

Brian Krause

Manager, Integrated Building Solutions

[email protected]

Dan Gramer

Manager, Integrated Building Solutions

[email protected]