Bill of Materials on Site

Embed Size (px)

Citation preview

  • 7/30/2019 Bill of Materials on Site

    1/23

    PROJECT : PROPOSED 3-STOREY APARTMENT

    OWNER : MR. & MRS. VICTOR FRANCISCO

    LOCATION : NO.39 NATIB ST., CUBAO, QUEZON CITY

    SUBJECT : BILL OF MATERIALS

    CODE

    NO. U. Cost Amount

    I MOBILIZATION / SITE lot 1.00 50,000.00 50,000.00

    II EARTHWORKS

    Excavation cu m 50.98 - -

    Backfilling cu m 65.14 756.00 49,245.84

    Soil Treatment sq m 164.40 35.00 5,754.00

    III FORMWORKS:

    Footings sq m 9.28 85.00 788.80

    Slab on grade and Garage sq m 5.17 85.00 439.45

    Columns sq m 244.16 170.00 41,507.20Beams 2/F sq m 133.02 170.00 22,613.40

    Beams 3/F sq m 133.02 170.00 22,613.40

    Roof Beams sq m 104.97 170.00 17,844.90

    Sloping Roof Beams sq m 47.85 170.00 8,134.50

    Suspended Slab 2/F sq m 134.79 170.00 22,914.30

    Suspended Slab 3/F sq m 134.79 170.00 22,914.30

    IV REBAR WORKS

    Footings (16mm) kg 545.48 29.45 16,064.39

    Slab on grade and Garage (12mm) kg 771.57 29.45 22,722.74

    Columns (16mm) kg 3,030.40 29.45 89,245.28Beams 2/F (16mm) kg 1,679.50 29.45 49,461.28

    Beams 3/F (16mm) kg 1,679.50 29.45 49,461.28

    Roof Beams (16mm) kg 1,054.23 29.45 31,047.07

    Sloping Roof Beams kg 453.14 29.45 13,344.97

    Suspended Slab 2/F (12mm) kg 3,040.09 29.45 89,530.65

    Suspended Slab 3/F (12mm) kg 3,040.09 29.45 89,530.65

    Wall Footing (10mm) kg 297.71 29.45 8,767.56

    V CONCRETE WORKS

    Footings cu m 9.28 3,600.00 33,408.00

    Slab on grade and Garage cu m 16.40 3,600.00 59,040.00

    Columns cu m 13.96 3,600.00 50,256.00Beams 2/F cu m 10.88 9,500.00 103,360.00

    Beams 3/F cu m 10.88 9,500.00 103,360.00

    Roof Beams cu m 7.64 3,600.00 27,504.00

    Sloping Roof Beams cu m 3.48 3,600.00 12,528.00

    Suspended Slab 2/F cu m 13.08 9,500.00 124,260.00

    Suspended Slab 3/F cu m 13.08 9,500.00 124,260.00

    Wall Footing cu m 7.78 3,600.00 28,008.00

    UNITSCOPE OF WORK QTY

    MATERIAL COST (PHP)

  • 7/30/2019 Bill of Materials on Site

    2/23

    VI MASONRY WORKS

    6" CHB (400psi) sq m 742.65 420.00 311,913.00

    4" CHB (400psi) sq m 317.88 273.00 86,781.24

    Cement Plaster Walls sq m 1,815.96 70.00 127,117.20

    VII STEEL WORKS

    TRUSSES

    2"x5"x1.2mm thick Purlins pc 49.00 650.00 31,850.00

    12mm Sag Rods pc 11.00 175.00 1,925.00

    Red oxide primer gal 4.50 450.00 2,025.00

    Welding rod kg 10.00 185.00 1,850.00

    VIII ARCHITECTURAL FINISHES

    ROOFING WORKS

    Longspan Tri Rib Type Roof sq m 145.48 350.00 50,918.00

    Including All Bended Parts and

    Accessories

    DOORS and JAMBSD1 0.80x2.10m Panel Type & 2"x6" Jamb set 3.00 8,951.00 26,853.00

    D2 0.60x2.10m PVC Type & Jamb set 16.00 1,600.00 25,600.00

    D3 0.60x2.10m Flush Type & 2"x5" Jamb set 18.00 3,090.00 55,620.00

    D4 0.70x2.10m Flush Type & 2"x5" Jamb set 3.00 3,090.00 9,270.00

    D5 0.80x2.10m Flush Type & 2"x5" Jamb set 3.00

    Door knobs set 40.00 383.00 15,320.00

    FLOOR & WALLS FINISHES

    Plain cement ( garage, laundry

    open area)

    (living,dining,kitchen)

    .60mx.60m China tiles sq m 45.90 831.00 38,142.90T&B (floor)

    12x12" china/mariwasa tiles sq m 25.20 375.00 9,450.00

    T&B (walls)

    12x12" china/mariwasa tiles sq m 77.58 321.60 24,949.73

    Entry,roofdeck

    12"x12" china/mariwasa tiles sq m

    Granite Countertop sq m 5.94 1,800.00 10,692.00

    Under kitchen countertop

    .20x.20m floor & walls tiles sq m 3.60 364.00 1,310.40

    All Bedrooms, Den/study rm.

    Hornitex floor laminated sq m 207.36 750.00 155,520.00

    Vinyl tile 12"x12"(storage)

    .20x.20cm tiles (laundry counter) sq m 4.83 364.00 1,758.12

    Cement

    Tile Grout

    Tile Trim

    Muriatic Acid

    IX WINDOWS (Powder coated fin.)

    Powder coated Frame with

    1/4" thk & screen

  • 7/30/2019 Bill of Materials on Site

    3/23

    W1 2.00mx1.20m ht. set 3.00 9,037.00 27,111.00

    W2 1.00mx.1.20m ht. set 9.00 4,519.00 40,671.00

    W3 1.40mx1.20m ht. set 12.00 6,326.00 75,912.00

    W4 .40mx.60m ht. set 6.00 903.85 5,423.10

    W5 set 6.00 6,326.00 37,956.00

    SD 2.40mx2.10m ht. set 3.00

    DR .80mx2.10m ht set 3.00

    X CARPENTRY WORKS

    CEILING sq m 418.84 205.00 85,862.20

    1/2" Gypsum Board

    1x2x20' metal furring

    1 1/2"x 1 1/2"x8' wall angle

    Metal clip

    Carrying channel

    Ceiling accessories

    STAIRS,HANDRAIL

    2x12x8 steps pc 45.00 1,568.00 70,560.00

    2x2x12 handrail pc 15.00 368.00 5,520.00

    MOULDINGS

    4" baseboard/casing lot 1.00 7,500.00 7,500.00

    CABINETS,CLOSETS set 21.00 5,250.00 110,250.00

    3/4" plyboard

    1/4" plywood

    1/2x2x8" KD

    Concealed hinges

    Drawer guide

    Chrome rod 1"

    Handles

    HARDWARE lot 1.00 10,000.00 10,000.00Gypsum screw

    Common nail 2

    Finishing nail 1 1/2

    Finishing nail 1

    Stickwell

    XI PLUMBING WORKS

    FIXTURES

    Package HCG set 9.00 37,990.00 341,910.00

    Watercloset

    Walltype lavatory with faucet

    Tissue & soap holder

    Shower head & valve

    Kitchen sink with Drain & faucet set 3.00 16,730.00 50,190.00

    Floor drain 4x4 pc 9.00 245.00 2,205.00

    Faucet pc 15.00 175.00 2,625.00

    Hosebib pc 3.00 439.75 1,319.25

    Pipes & Fittings (Water Line-Rehau) each 3.00 18,000.00 54,000.00

    Septic tanks & Basin each 3.00 9,240.00 27,720.00

    Overhead Tank 400gls(stainless) set 3.00 23,000.00 69,000.00

    SANITARY & STORM DRAIN LINE

  • 7/30/2019 Bill of Materials on Site

    4/23

    PVC Pipe 4" (Neltex) lm 120.00 230.00 27,600.00

    PVC Pipe 3" (Neltex) lm 75.00 173.33 12,999.75

    PVC Pipe 2" (Neltex) lm 74.10 80.00 5,928.00

    Soil Pipe 6" lm 6.00 350.00 2,100.00

    Pipe Fittings & Bracket each 3.00 5,000.00 15,000.00

    Consumables each 3.00 5,000.00 15,000.00

    XII ELECTRICAL WORKS

    FIXTURES

    Pinlight set 102.00 300.00 30,600.00

    Duplex outlet set 78.00 269.75 21,040.50

    1 gang switch set 12.00 100.25 1,203.00

    2 gang switch set 21.00 156.75 3,291.75

    3 gang switch set 15.00 213.25 3,198.75

    3 way switch set 9.00 111.25 1,001.25

    Range outlet set 3.00 165.00 495.00

    AC outlet set 18.00 153.25 2,758.50

    Tel outlet set 9.00 270.00 2,430.00

    Cable outlet set 9.00 339.25 3,053.25

    Panel Board (12 branches) set 3.00 1,250.00 3,750.00

    Wires,pipes & fittings each 3.00 25,000.00 75,000.00

    XIII PAINTING WORKS

    Exterior & Interior walls-painted fin. sq m 1,815.96 98.00 177,964.08

    Ceiling- flat enamel finish and Eaves sq m 418.84 65.00 27,224.60

    Cabinets- duco finish lot 1.00 10,000.00 10,000.00

    Stairs - Varnish finish lot 1.00 2,250.00 2,250.00

    Baseboard - varnish finish lot 1.00 2,250.00 2,250.00

    XIV WATER PROOFING

    Sahara bag 16.00 35.00 560.00

    Black Coaltar gal 3.00 640.00 1,920.00

    XV GRILLEWORKS

    Stair railing kg 852.00 29.45 25,091.40

    Stair railing ( entry ) kg 113.64 29.45 3,346.70

    Gate with pedestrian each 3.00 6,500.00 19,500.00

    Garage grill each 3.00 4,500.00 13,500.00

    Grill ( open area - airwell ) kg 95.94 29.45 2,825.43

    Trellis ( roofdeck )

    Aircon grill kg 47.97 29.45 1,412.72

    XVI TOTAL AMOUNT 3,918,824.77

    XVII SUPERVISION, MARK-UP,

    TAX & CONTINGENCY

    XVIII TOTAL COST OF CONSTRUCTION

  • 7/30/2019 Bill of Materials on Site

    5/23

    Prepared by:

    ERNIE RUGAYAN, CE

    334.72

  • 7/30/2019 Bill of Materials on Site

    6/23

    DIRECT

    U. Cost Amount TOTAL (PHP)

    - - 50,000.00

    750.00 38,235.00 38,235.00

    75.60 4,924.58 54,170.42

    10.50 1,726.20 7,480.20

    8.50 78.88 867.68

    8.50 43.95 483.40

    17.00 4,150.72 45,657.9217.00 2,261.34 24,874.74

    17.00 2,261.34 24,874.74

    17.00 1,784.49 19,629.39

    17.00 813.45 8,947.95

    17.00 2,291.43 25,205.73

    17.00 2,291.43 25,205.73

    8.84 4,819.32 20,883.70

    8.84 6,816.82 29,539.56

    8.84 26,773.58 116,018.868.84 14,838.38 64,299.66

    8.84 14,838.38 64,299.66

    8.84 9,314.12 40,361.20

    8.84 4,003.49 17,348.46

    8.84 26,859.20 116,389.85

    8.84 26,859.20 116,389.85

    8.84 2,630.27 11,397.83

    1,080.00 10,022.40 43,430.40

    1,080.00 17,712.00 76,752.00

    1,080.00 15,076.80 65,332.802,850.00 31,008.00 134,368.00

    2,850.00 31,008.00 134,368.00

    1,080.00 8,251.20 35,755.20

    1,080.00 3,758.40 16,286.40

    2,850.00 37,278.00 161,538.00

    2,850.00 37,278.00 161,538.00

    1,080.00 8,402.40 36,410.40

    LABOR COST (PHP)

  • 7/30/2019 Bill of Materials on Site

    7/23

    126.00 93,573.90 405,486.90

    81.90 26,034.37 112,815.61

    21.00 38,135.16 165,252.36

    195.00 9,555.00 41,405.00

    52.50 577.50 2,502.50

    135.00 607.50 2,632.50

    55.50 555.00 2,405.00

    105.00 15,275.40 66,193.40

    2,685.30 8,055.90 34,908.90

    480.00 7,680.00 33,280.00

    927.00 16,686.00 72,306.00

    927.00 2,781.00 12,051.00

    0.00

    114.90 4,596.00 19,916.00

    249.30 11,442.87 49,585.77

    112.50 2,835.00 12,285.00

    96.48 7,484.92 32,434.65

    540.00 3,207.60 13,899.60

    109.20 393.12 1,703.52

    225.00 46,656.00 202,176.00

    109.20 527.44 2,285.56

  • 7/30/2019 Bill of Materials on Site

    8/23

    903.70 2,711.10 29,822.10

    451.90 4,067.10 44,738.10

    632.60 7,591.20 83,503.20

    90.39 542.31 5,965.41

    632.60 3,795.60 41,751.60

    61.50 25,758.66 111,620.86

    470.40 21,168.00 91,728.00

    110.40 1,656.00 7,176.00

    2,250.00 2,250.00 9,750.00

    1,575.00 33,075.00 143,325.00

    3,000.00 3,000.00 13,000.00

    11,397.00 102,573.00 444,483.00

    5,019.00 15,057.00 65,247.00

    73.50 661.50 2,866.50

    52.50 787.50 3,412.50

    131.93 395.78 1,715.03

    5,400.00 16,200.00 70,200.00

    2,772.00 8,316.00 36,036.00

    6,900.00 20,700.00 89,700.00

  • 7/30/2019 Bill of Materials on Site

    9/23

    69.00 8,280.00 35,880.00

    52.00 3,899.93 16,899.68

    24.00 1,778.40 7,706.40

    105.00 630.00 2,730.00

    1,500.00 4,500.00 19,500.00

    - 15,000.00

    90.00 9,180.00 39,780.00

    80.93 6,312.15 27,352.65

    30.08 360.90 1,563.90

    47.03 987.53 4,279.28

    63.98 959.63 4,158.38

    33.38 300.38 1,301.63

    49.50 148.50 643.50

    45.98 827.55 3,586.05

    81.00 729.00 3,159.00

    101.78 915.98 3,969.23

    375.00 1,125.00 4,875.00

    7,500.00 22,500.00 97,500.00

    29.40 53,389.22 231,353.30

    19.50 8,167.38 35,391.98

    3,000.00 3,000.00 13,000.00

    675.00 675.00 2,925.00

    675.00 675.00 2,925.00

    10.50 168.00 728.00

    192.00 576.00 2,496.00

    8.84 7,527.42 32,618.82

    8.84 1,004.01 4,350.71

    1,950.00 5,850.00 25,350.00

    1,350.00 4,050.00 17,550.00

    8.84 847.63 3,673.06

    8.84 423.81 1,836.53

    1,115,164.59 5,033,989.36

    1,761,896.27

    Php6,795,885.63

  • 7/30/2019 Bill of Materials on Site

    10/23

  • 7/30/2019 Bill of Materials on Site

    11/23

    PROJECT : PROPOSED 3-STOREY APARTMENT

    OWNER : MR. & MRS. VICTOR FRANCISCO

    LOCATION : NO.39 NATIB ST., CUBAO, QUEZON CITY

    SUBJECT : PROGAMME OF WORKS

    MONTH

    WEEK

    XVII TOTAL COST OF CONSTRUCTION 6,795,885.63 100.0000%

    Prepared by:

    ERNIE RUGAYAN, CE

    334.72

    CUMULATIVE ACTUAL ACC.

    3,224.00

    85,379.12

    1,761,896.27

    PROJECTED ACC.

    CUMULATIVE PROJECTED ACC.

    ACTUAL ACC.

    1.25634%

    25.92593%

    0.04744%

    285,595.28

    2.82772%

    4.20247%

    0.73574%

    1.46980%

    553,025.39

    205,780.41

    376,599.86

    811,376.10

    192,168.60

    175,747.28

    SUPERVISION, MARK-UP, TAX & CONT.XVI

    596,928.62

    865,779.20

    683,554.87

    48,945.00

    XIII PAINTING WORKS

    XIV WATER PROOFING

    GRILLEWORKSXV

    PLUMBING WORKS

    IX

    X

    XI

    XII ELECTRICAL WORKS

    CARPENTRY WORKS

    VII STEEL WORKS

    VIII ARCHITECTURAL FINISHES

    WINDOWS (Powder coated fin.)

    IV REBAR WORKS

    V CONCRETE WORKS

    MASONRY WORKSVI

    3.02801%

    5.54159%

    11.93923%

    2.58608%

    8.78368%

    12.73976%

    10.05836%

    0.72022%

    8.13765%

    SCOPE OF WORK AMOUNT %WTCODE NO.

    IIIFORMWORKS:

    I MOBILIZATION / SITE

    II EARTHWORKS

    50,000.00

    99,885.62

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

  • 7/30/2019 Bill of Materials on Site

    12/23

  • 7/30/2019 Bill of Materials on Site

    13/23

  • 7/30/2019 Bill of Materials on Site

    14/23

    1 2 3 4 5 6 7 8 9 10 1

    0.73574%

    0.20997% 0.20997% 0.20997% 0.20997% 0.20997% 0.20997% 0.20997%

    0.18472% 0.18472% 0.18472% 0.18472% 0.18472% 0.18472% 0.18472

    0.67567% 0.67567% 0.67567% 0.67567% 0.67567% 0.67567% 0.67567% 0.67567

    0.97998% 0.97998% 0.97998% 0.97998% 0.97998

    0.59167% 0.59167% 0.59167% 0.59167% 0.59167% 0.59167

    0.99494% 0.99494% 0.99494% 0.99494% 0.99494

    0.25707% 0.25707% 0.25707% 0.25707% 0.25707

    0.92593% 0.92593% 0.92593% 0.92593% 0.92593% 0.92593% 0.92593% 0.92593% 0.92593% 0.92593% 0.92593

    1.6617% 1.1359% 1.1359% 1.8116% 1.9963% 2.5880% 4.8199% 4.8199% 4.6100% 4.6100% 4.6100%

    1.66% 2.80% 3.93% 5.75% 7.74% 10.33% 15.15% 19.97% 24.58% 29.19% 33.80%

    0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    1 2 3

    1 2 3 4 5 6 7 8 9 10 11

    PROJECTED

    ACTUAL

  • 7/30/2019 Bill of Materials on Site

    15/23

  • 7/30/2019 Bill of Materials on Site

    16/23

  • 7/30/2019 Bill of Materials on Site

    17/23

    12 13 14 15 16 17 18 19 20 21

    0.18472% 0.18472% 0.18472% 0.18472% 0.18472% 0.18472% 0.18472%

    0.67567% 0.67567% 0.67567% 0.67567% 0.67567%

    0.97998% 0.97998% 0.97998% 0.97998% 0.97998% 0.97998% 0.97998% 0.97998%

    0.59167% 0.59167% 0.59167% 0.59167% 0.59167% 0.59167% 0.59167% 0.59167% 0.59167% 0.59167% 0.5916

    0.14404% 0.14404% 0.14404% 0.1440

    0.67814% 0.67814% 0.67814% 0.67814% 0.67814% 0.67814% 0.67814% 0.6781

    0.50467% 0.50467% 0.5046

    0.42628% 0.42628% 0.42628% 0.42628% 0.42628% 0.42628% 0.42628% 0.42628% 0.42628% 0.42628% 0.4262

    0.99494% 0.99494% 0.99494% 0.9949

    0.25707% 0.2570

    0.26265% 0.26265% 0.26265% 0.26265% 0.26265% 0.26265% 0.26265% 0.26265% 0.26265% 0.2626

    0.01581% 0.01581% 0.01581%

    0.12563% 0.12563% 0.12563% 0.12563% 0.12563% 0.1256

    0.92593% 0.92593% 0.92593% 0.92593% 0.92593% 0.92593% 0.92593% 0.92593% 0.92593% 0.92593% 0.9259

    5.0362% 4.0469% 4.0627% 4.7408% 4.7408% 4.1750% 4.1750% 4.1343% 4.6539% 4.6539% 4.911

    38.84% 42.88% 46.94% 51.69% 56.43% 60.60% 64.78% 68.91% 73.56% 78.22% 83.1

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    54

    12 13 14 15 16 17 18 19 20 21 22

  • 7/30/2019 Bill of Materials on Site

    18/23

  • 7/30/2019 Bill of Materials on Site

    19/23

  • 7/30/2019 Bill of Materials on Site

    20/23

    23 24 25 26 27 28 29 30 31 32

    0.73574%

    1.46980%

    2.58608%

    8.78368%

    12.73976%

    10.05836%

    0.14404% 0.72022%

    0.67814% 0.67814% 0.67814% 0.67814% 8.13765%

    0.50467% 0.50467% 0.50467% 3.02801%

    0.42628% 0.42628% 5.54159%

    0.99494% 0.99494% 0.99494% 11.93923%

    0.25707% 0.25707% 0.25707% 0.25707% 2.82772%

    0.26265% 0.26265% 0.26265% 0.26265% 0.26265% 0.26265% 4.20247%

    0.04744%

    0.12563% 0.12563% 0.12563% 0.12563% 1.25634%

    0.92593% 0.92593% 0.92593% 0.92593% 0.92593% 0.92593% 25.92593%

    100.00002%

    4.3193% 4.1753% 3.7490% 2.2494% 1.1886% 1.1886% 0.0000% 0.0000% 0.0000% 0.0000%

    87.45% 91.62% 95.37% 97.62% 98.81% 100.00% 100.00% 100.00% 100.00% 100.00%

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    7 8

    23 24 25 26 27 28 29 30 31 32

  • 7/30/2019 Bill of Materials on Site

    21/23

  • 7/30/2019 Bill of Materials on Site

    22/23

  • 7/30/2019 Bill of Materials on Site

    23/23

    -0.0000034%

    0.0000000%

    -0.0000047%

    0.0000000%

    0.0000034%

    0.0000000%

    -0.0000048%

    0.0000000%

    0.0000001%

    0.0000000%

    0.0000046%

    0.0000000%

    -0.0000038%

    0.0000000%

    -0.0000046%

    0.0000000%

    -0.0000003%

    0.0000000%

    0.0000034%

    0.0000000%

    0.0000005%

    0.0000000%

    -0.0000045%

    0.0000000%

    -0.0000041%