Upload
trinhbao
View
215
Download
1
Embed Size (px)
Citation preview
1
SMP-SOLAR-22/2014-SKP
Bihar Electricity Regulatory CommissionVidyutBhawan-II, J.L.NehruMarg, Patna 800 021
-----------------------------------------------------------------------------------------------------------Suo-Motu Proceedings No. 22/2014
IN THE MATTER OF:Determination of Generic Levelised Generation Tariff for FY2014-15 for Power Generated from Solar Power PV Projectsincluding Rooftop Solar PV and Small Power Projects andSolar Thermal Power Projects.
Coram:1. Sri U. N. Panjiar- Chairman2. Sri S. C. Jha- Member
Appearance :1. Sri J. K. Bhanu, ESE (Com.)
On behalf of North Bihar PowerDistribution Co. Ltd.
2. Sri J. K. Dubey, EEE (Com.)3. Shri Manish Sakya, AEE (Com.)4. Shri Anand Suman, AEE/IS On behalf of Bihar State Power (Holding)
Co. Ltd.5. Shri Kumar Deepak, AEE/IS6. Shri Abhishek Raj, AEE (Com.)
On behalf of South Bihar PowerDistribution Co. Ltd.
7. Miss Julie Kumari, AEE (Com.)8. Shri Atul A. Singh, Consultant9. Shri Sant Prasad, G.M.
On behalf of M/s Response RenewableEnergy Ltd.10 Shri Suraj Kumar, Management
Trainee11. Shri Devjeet Deogharia, Sr. Manager
On behalf of M/s Hindustan Power12. Shri Ashish Nandan, Manager(Regulatory Affairs)
13. Shri Chandan Kumar On behalf Glatt Solutions Pvt. Ltd.14. Shri Dewaki Nandan Pandey, Project
EngineerOn behalf of M/s Avantika Contractors (I)Ltd.
15. Shri Amrendra Kumar Amar, ProjectEngineer
On behalf of M/s Alex Green Energy Pvt.Ltd.
16. Shri Alok Verma, Manager BusinessDev. On behalf of Sun Edison Energy India
Pvt. Ltd.17. Shri Jay Prakash Sinha, Asst.Manager
Dates of Hearing:21.10.2014, 27.11.2014 and 05.01.2015 - Order reserved .Order
Dated :09.04.2015
1. The Bihar Electricity Regulatory Commission (BERC) (Terms and Conditions for
Tariff Determination from Solar Energy Sources) Regulations, 2010, hereinafter
called Regulations, 2010, were approved by the Commission in exercise of powers
2
SMP-SOLAR-22/2014-SKP
conferred to it under section 61 read with section 181 (2) (zd) of the Electricity Act,
2003 and were issued on 2nd August, 2010. Three years control period specified in
the Regulations ended on 31.3.2013. During the 1st year of subsequent control
period from FY2013-14 to FY2015-16,based on revised norms considering
CERC(Terms and Conditions for Tariff determination from Renewable Energy
sources)Regulations,2012, generic tariff for FY2013-14 for solar PV power projects
and solar thermal power projects were determined in suo-motu proceedings
no.09/2013 dated14.06.2013.
2. The Commission is empowered to specify the terms and conditions for
determination of tariff under section 61 of the Act. Section 62 (1) (a) of the Act
stipulates that the appropriate Commission shall determine the tariff for supply of
electricity by a generating company to a distribution licensee. The Commission has
to determine the tariff for generation, supply, transmission and wheeling of
electricity, wholesale, bulk or retail, as the case may be, within the State under
section 86 (1) (a) of the Act.
3. Regulation 39 of the Regulations, 2010 empowers the Commission to amend any
provision ofthe Regulations, 2010and may from time to time add, vary, alter,
modify or amend any provisions of the Regulations, 2010 on its own motion or on
any application made before it by an interested person.
4. The Commission decided to initiate a suo-motu proceedings no.22/2014 under
Regulation 8 of the BERC (Terms and Conditions for Tariff Determination from
Solar Energy Sources) Regulations, 2010 pursuant to revised capital cost
benchmarkapproved by CERCfor determination of tariff for electricity generated
from Solar PV and Solar Thermal Power Projects for Fy2014-15 and issued a
consultative paperto obtain views from general public and stakeholders for
determination of generic levellised tariff for FY 2014-15 for Solar PV Projects
including Rooftop Solar PV and small Power Projects which are to be commissioned
up to 31.03.2016 and for Solar Thermal Projects which are to be commissioned
upto 31.03.2017 and for which PPA is signed upto 31.03.2015.
5. The consultative paper was put on the website of the Commission and a public
notice was issued on 30.09.2014 inviting objections/suggestions/comments from
general public and all stakeholders latest by 20.10.2014. The notice was published
in Hindustan Times dated 1st October, 2014 (daily newspaper in English) and
Danik Jagran dated 1stOctober, 2014 (daily newspaper in Hindi). A copy of the
3
SMP-SOLAR-22/2014-SKP
proposed draft was also sent to Bihar State Power (Holding) Co. Ltd., South Bihar
Power Distribution Co. Ltd., North Bihar Power Distribution Co. Ltd.,Bihar State
Power Transmission Co. Ltd.,M/s Kumar Tech-Bio products Pvt Ltd, HPCL Biofuels
Ltd., Response Renewable Energy Ltd, Ruchi Soya Industries Ltd, Glatt Solutions
Pvt. Ltd., Claro Energy Pvt. Ltd, Alex Green Energy Pvt. Ltd,Moser Baer Clean
Energy Ltd, Awantika ContractorsPvt Ltd Vaishali vidyut upvoka sangh, Bihar
Chamber of Commerce, Bihar Industries Association, Bihar Steel Manufacturers
Association and Mr. Binay kumar singh ,Advocate etc inviting
objections/suggestions/comments so as to reach Secretary of the Commission by
20.10.2014.
6. Hearings:-Public hearing was held on 21.10.2014 and comments/suggestions/objections
were received from :-
(i) M/s EPC Company Ltd, New Delhi
(ii) Sri Binay Kumar Singh, Advocate,Barh.
Representatives of SBPDCL prayed for 10 days time to submit their
comments/suggestions on the matter. Similarly representatives of M/s Response
renewable Energy ltd and M/s Glatt Solutions Pvt Ltd also prayed for 10 days time to
submit their comments/suggestions. Commission allowed their prayers.
Matter was put up for hearing on 06.11.2014 but stake holders were not present on
date due to Guru Nanak Jayanti holiday and the case was posted for hearing on
20.11.2014.Due to some other occupation of the Commission,hearing couldnot take
place on the scheduled date and matter was fixed for hearing on 27.11.2014.
Representatives of M/s Hindustan Power and M/s Response Renewable Energy
Pvt.Ltd made their argument/oral submissions in support of written submissions filed
by them on 20.10.2014 and 3.11.2014 respectively. Representatives of NBPDCL and
SBPDCL prayed for further 10 days time to file reply. Commission allowed their prayer
and 05.01.2015 was fixed for hearing.On 05.01.2015 the matter was finally heard and
in course of hearing, the following stakeholders submitted their written
comments/suggestions:-
1.M/s Acme Solar Energy private Ltd, Gurgaon
2.M/s Response Renewable energy Ltd, Kolkata(additional submission)
3.M/s SunEdision Energy India Pvt. Ltd,Chennai
4
SMP-SOLAR-22/2014-SKP
Representatives of M/s SunEdision Energy India Pvt.Ltd and M/s Response
Renewable Energy Ltd made their oral submissions in support of their written
comments/suggestions/objections. SBPDCL also submitted its comments vide its
letter no.12dated03.01.2015. Representatives of NBPDCL prayed for another 15 days
time to submit their comments. Commission allowed theirprayer.
Order was reserved.
7. COMMENT/SUGGESTIONS/OBJECTIONS :-
7.1 ACIRA Solar Pvt. Ltd., New Delhi:-
Acira Solar Pvt. Ltd has submitted that alongwith German partners, M/s
Vispiron EPC GmbH & KG, they are currently in the process of implementing two
projects in Bihar at sites about 100 KM from Patna. They have submitted the
following:-:-
I. Sites suitable for MW scale PV projects in Bihar have a solar radiation not
exceeding 1850 Kwh/m2/year.
II. The estimated yield of typical plants with German engineering (Tier-1 PV
modules and world renowned German inverters, the most important
components in the performance of the project) is around 1517 KWh/KWp.
Supporting evidence is attached for your ready reference.
A yield of 1517 KWh/Kwp leads to a Capacity utilization Factor of 17.3% lower
than projected 19% in the Consultative paper presented by the Commission.
The Capacity Utilization factor determined by CERC is a national average and
the central regulator expects the State Regulator to bear local factors in mind when
recommending tariffs for their State. This implies that the Capacity Utilization factor
should be commensurate with the prevalent solar radiation in the State.
It is, therefore, suggested thatCapacity Utilization Factor may be determined
according to the solar radiation prevailing in the State and it may be reduced to 17%
for projects in the State and the generic levellized tariff may be computed accordingly.
7.2 RESPONCE RENEWABLE ENERGY LTD., KOLKATA:-Response Renewable Energy Ltd. has submitted the following
comments/suggestions on the proposed norms for determining the Generic
Levelized Tariff for FY 2014-15 for Power generated from Solar Power Projects:-
(i) That CERC vide its order dated 15th May 2014 has notified benchmark
capital cost Rs. 691 lakhs/MW for solar PV project for FY 2014-15
considering parameters like modules cost, cost of land, civil work etc.
5
SMP-SOLAR-22/2014-SKP
(ii) That based on the MVR notified by the Government of Bihar for ekfasla/un-
irrigated type of land in different parts of the State, the Commission has
considered Rs. 5 Lakhs/Acre as cost of land for the Solar PV Projects in the
capital cost of Rs. 691 lakhs/MW. However, for those projects where the cost
of land is higher, a project specific determination of tariff may be considered
on case to case basis.
(iii) That if we look at the land use profile of Bihar more than 60% of land is
utilized for agriculture purpose, Bihar economy is primarily based on
agriculture. There is less than 4% of barren land in Bihar which is shrinking
with rising population. There is hardly any land available which are barren,
rocky and not used for farming, pasture of real estate.
(iv) That solar plants are proposed only where it is adjacent to grid. Areas
adjacent to grid have access to electricity in general for irrigation purpose.
Such irrigated areas have in general three harvests in a yeaf. (i) Bhadai,
dominated by corn that is sown from May to June and gathered in
August and September (ii) Aghani, consisting primarily of rice sown in mid-
June and gathered in December (iii) Rabi, made up largely of wheat that
ripens in the plains in the spring (March to May.)
(v) That there are mainly small and marginal farmers in the state & buying
large chunk of land requires sorting out of several issues associated with
large number of sellers & land acquisition process which result in extra cost
both in terms of brokerage, time and in sorting out litigations which do come
as large number of sellers are involved.
(vi) CERC has proposed the land requirement of 5 Acres/ MW for crystalline
modules. As mentioned in the order of CERC dated 15th May 2014, out of
29, 28 stakeholder who have participated in the hearing (including NTPC,
IL&FS, Tata Power, Federation of India Chamber of Commerce & Industries)
have suggested land cost in the range of 25 to 67 Lakhs/MW. In north
Bihar, more than 2300 people reside in one Sq km area. There are large
barren land/ ekfasli area/ Unirrigated area in MP, Gujrat, Rajasthan &
other states, Jharkhand have three times less population with land area of
three times compared to Bihar. The Commission should consider the cost of
land as Rs 50Lakhs/MW.
6
SMP-SOLAR-22/2014-SKP
(vii) As explained in the above para, Bihar has altogether a different scenario. No
grid connected solar power project has so far come up in the state & the
contention of Commission to consider at this stage the MVR notified by the
Government of Bihar for ekfasla/ un irrigated type of land in different parts
of the State as base land price at the rate of Rs. 5 lakhss/ acre (Rs 25
Lakhs/ MW) is totally unjustified and not based on realistic parameters &
ground reality. This will further prove determinental to the Growth &
promotion of solar power generation in the State.
(viii) That unfortunately the banks/financial institutions are also showing
reluctance to provide finance to solar projects in Bihar. First annual
integrated rating for State Power Distribution Utilities under the integrated
rating methodology formulated by Ministry of power was carried out by
independent agencies ICRA & CRISIL. Bihar Distribution companies has
been awarded "B: grade which shows below average operational and
financial performance capability of BSPHCL and this has added to our woo.
This matter was raised before the Energy Secretary cum CMD of Bihar State
Power Distribution Company Ltd. A meeting of Bankers and developer was
also called by BSPHCL but this has not taken place so far.
(ix) That there are 2 kinds of financing mechanisms for solar project- (i)
Recourse Financing and (ii) Non-Recourse Financing. Recourse Financing is
the prevalent mechanics,. The typical Debt-Equity Ratio (Loan to Investment
Ratio) for Solar Power plants is 70:30. And the typical collaterals required
for 10 MW solar Project at 70% dept could by nearly 60 Crs. The
Commission will agree that collaterals requirement is very high. More-so
there is lack of confidence of Bankers in Bihar particularly in financing solar
projects. Lowering of capital cost will add one more negative parameter in
appraisal of projects for funding by banks and other financial institutions..
(x) That as stated in Para-9 major public sector banks consider Solar Energy
Project more risky as compared to infrastructure projects. Hence Solar
Projects developer relies on foreign lenders which invite lending rate plus
hedging risks. As such we pray Commission consider higher interest rate for
determination of tariff.
(xi) Regulation 59 of RE Tariff Regulations provides that the normative O&M
expenses for solar PV projects for the Year 2012-13 shall be 11 lakhs per
7
SMP-SOLAR-22/2014-SKP
MW which shall be escalated at the rate of 5.72% per annum over the tariff
period for determination of the levellised tariff.
Accordingly, O&M expense norm for solar PV power project for FY 2014-15
should be considered as 11X5.72X2 (FY 2013-14 & FY 2014-15) =Rs12.60
Lakhs should be considered instead of Rs 12.30 lakhs.
(xii) The performance (Capacity utilization factor)CUF depends on several factor
including the solar radiation, temperature, air velocity apart from the
module type and quality, angle of tilt (or Tracking) design parameters to
avoid cable losses and efficiencies of inverters and transformers. There are
some inherent losses which can be reduced through proper designing but
not completely avoided. The estimated capacity utilization factor varies form
16 to 20 % in various parts of the country. The Solar radiation available at
Nawada where we are setting up 10 MW solar plant is on annual average
4.89 kwh/m2/day.
District:
(xiii) With this solar radiation, the actual CUF would be around 17% CERC has
adopted average CUF of 19% taking all India Average. As per solar radiation
map attached, solar radiation varies in different zones of the county
considerable and CERC should have notified varying solar irradiation across
the different State varying form 15% 16% 17% 18% 19% and 20%. But
because of lack of available resource analysis decided all India average.
Commission should arrive at actual CUF & in the mean time, keeping in
view totally unsatisfactory states of solar power generation project in Bihar;
Commission should take a lenient view in the larger interest of promotion of
solar project in the state of Bihar and adopt CUF in between 17-18%
(xiv) That the Commission will agree that power scenario in the State is far from
satisfactory. It has the lowest annual per capita consumption of electricity in
country at 140 kwh, against the national average of about 800kwh. The
state is facing increasingly acute power shortage not only for peak load but
also for base load requirement. A number of projects have been approved by
the state government to enhance the availability of power under the Public-
Private Partnership mode but hardly things have moved up in the last five
years. The total installed capacity of 525 MW in the state has hardly any
relevance as these thermal power plant are either closed or operating at de
8
SMP-SOLAR-22/2014-SKP
related capacity. With major share of NTPC, State Government has hardly
any control over KantiBijleeUtpadan Nigam Limited. Thus the State has to
depend largely upon power purchase for short & long term form central
pool, private sector, and PTC or power exchange, There is hardly any
industrial growth in the state & adding primarily domestic & agriculture
load is going to create a lot of problems on the financial health of the
distribution companies besides creating instability of the power system.
(xv) That keeping in view immense potential of solar power generation in the
state, Distributed Generation needs to be promoted on large scale. Solar
Power industry in India is gaining more and more prominence with each
passing day. The domestic/off-grid industry is picking up speed too.
(xvi) But unfortunately the state is yet to commission a single grid connected
solar project.
(xvii) Seven developer have been recommended by Energy Department for signing
PPA with Bihar State Po0wer Holding Company Ltd for a total installed
Capacity of 50 MW so far, These projects are to be commissioned before 31st
March 2014 but only 5 have signed PPA & rest two are in litigation.
(xviii) That the State Commission is mandated to promote RE power in the state of
Bihar. We have no solar plant installed in the state. The state still needs to
operate in promotional mode. Solar project needs to be promoted keeping in
view the actual base level parameters which is not comparable with most of
the states. Therefore, there is need to be state specific not project specific
approach till developers finds interest in setting up solar projects in state of
Bihar and it gets initial momentum.
(xix) In the past five years the Commission has revised the tariff three times but
not even a single lproject has come up. We therefore, humble request
Commission in the larger interest of power starved state of Bihar to allow the
existing tariff to continue till at least one or two grid connected Solar PV
generating Project come/Set up in the State.
7.4 Sun Edision Energy India Pvt. Ltd., Chennai-
SunEdison has submitted following comments on the proposed
determinationof tariff:-
9
SMP-SOLAR-22/2014-SKP
Capacity Utilization Factor:-Paper has adopted the CUF of 19% in the present draft. We understand that said CUF
has been adopted from the current CERC RE tariff regulation, 2012. Here it is to be
noted that 19% CUF is achievable in only few states such as Gujarat, Rajasthan,
Madhya Pradesh etc. However, in Bihar, Said adopted value of CUF is impossible to
achieve as the state has lesser solar irradiation. CERC in its suo-moto order dated 15th
May, 2014 (petition no. 353/2014) has recognized this issue and directed staff to come
out with the suitable amendments in the RE tariff regulations, 2012 with different
CUF for different GHI bands across the country. In addition, the Central Commission
has also recognized comments received from the Ministry of New & Renewable Energy
(MNRE) advocating zone wise classification of the country. MNRE has also conveyed its
opinion of solar tariff with respect to the CUF (Table-1).
Solar Zone
GHI(kWh/Sq.m./day
Estimated ElectricityGeneration (MU) Year CUF (%)
Tariff(Rs./kWh)for Solar
PV
Greaterthan
Lessthan orequal to
Greaterthan
Lessthanor
equalto
Avg. Greaterthan
Lessthanor
equalto
Avg.
Solar Zone-I 4.5 1.28 14.58 9.11Solar Zone-II 4.5 5.0 1.28 1.46 1.37 14.58 16.67 15.63 8.50Solar Zone-III 5.0 5.5 1.46 1.64 1.55 16.67 18.72 17.69 7.51
1.66* 19.0* 6.99*Solar Zone-IV 5.5 6.0 1.64 1.83 1.74 18.72 20.89 19.81 6.71Solar Zone-V 6.0 6.5 1.83 2.01 1.92 20.89 22.95 21.92 6.06Solar Zone-VI(if any)
6.5 2.01 22.95 5.79
*As per present Draft Tariff Order(Ministry of New and Renewable Energy)
As per the study conducted by CERC in 2010, Commission has arrived on average
CUF of 19% for whole country based on GHI data received from "IMD" and
"Meteronam" for 51 sites across the country which also includes Bihar. According to
the same report, Bihar has a GHI of 4.83 kWH/sq.m which leads to maximum CUF of
17.24% with crystalline and 18.22% with thin film technology.
Considering the fact, proposed CUF should be reduced to 17% to present the realistic
scenario and accordingly tariff should be increased to provide the comfortable returns
to the developers.
Further, degradation in CUF of 1% should also be considered as mentioned in earlier,
being the degradation prescribed by the OEM.
10
SMP-SOLAR-22/2014-SKP
Capital Cost for MW Solar PV Plants:-Commission has considered the capital cost of INR 6.91 Cr/MW for FY 2014-15. The
proposed cost and assumed parameters do not reflect the true cost of a solar PV
project in the current market scenario. This is mainly due to increase in the module
price and unfavorable INR/ USD fluctuation. At present, prices of modules are going
through a rationalization and stabilization phase leading to a reversal of the hitherto
seen downtrend. Rapid absorption to the overcapacity of previous years amidst
accelerating demand from China, Japan, Europe and other parts of the world has led
to a stall in Module Price trends.
By the time when balance in demand supply is achieved, prices are likely to have risen
further. This is also in line with other forecasts about the industry. It had been
projected in earlier forecasts as well that price drop will be stall and reverse in first
quarter of 2015.
Concurrently, the variation in USD-INR exchange rates and price increment of steel,
copper, aluminum etc;, which are the fundamental elements of the mounting
structure and rest of the system, is pushing system costs to higher levels.
A look at various project components confirms the same:Module Cost:As already highlighted, industry is witnessing a sudden increase in module prices.
This is due to the increased demand of solar modules in China and Japan and refining
of project economics in European countries.
At present weekly spot price of silicon and thin film modules is USD 0.621/Watt and
USD 0.641/Watt respectively. in addition, there is an incremental cost of insurance
and freight which comes to USD 0.07/watt. Therefore, resultant cost turns out to be
USD 0.691/Watt and USD 0.771/Watt respectively. Given the present rupee-dollar
exchange rate of INR 62/USD modules prices are INR 43/Watt for silicon and INR
548/Watt for thin film. As a result, for one megawatt utility scale solar PV plant,
module cost would come to INR 430 Lakh/MW and INR 480 Lakh/MW for silicon and
thin film based systems respectively.
Item High Low AverageSilicon Solar
Module0.88 0.54 0.621
Thin Film SolarModule
0.84 0.50 0.641
Unit: USD/Watt
11
SMP-SOLAR-22/2014-SKP
Last update:29-01-2014; Source: PV insights.com
In the light of above submitted facts we request you to consider module cost as INR
455 Lakh/MW.
Power Conditioning Unit (Inverter):-Power conditioning unit is an important component of the balance-of system; the
unit's conditioners process the DC power produced by a photovoltaic system to AC
power and match the same with utility's power. In its order, CERC has considered the
invertor cost as INR 50 Lakh/MW. Please note that as per the current Indian
Electricity Grid Code, solar plants are required to adhere to the scheduling mechanism
and such set up requires an additional cost of INR 15 Lakhs/MW towards the setting
up of SCADA and monitoring instruments. Therefore, we request you to consider PCU
cost as INR 65 Lakhs/MW.
based on our analysis; we propose to adopt the following project cost:-
Sr. No. Components Value1 Module Cost (INR Lakh/MW) 4552 Degradation (INR Lakh/MW) 11.293 Land Cost 254 Civil and General Works 605 Mounting Structure 506 Power Conditioning Unit 607 Cables and Transformer 608 Preliminary and Operative
Expanses, IDC etd69
Total Cost (INR Lakh/MW) 790Auxiliary Consumption:-
Commission has not considered the auxiliary consumption in its paper. However,
other states like Gujarat and Rajasthan has considered the auxiliary consumption of
0.25%. CERC has also acknowledged this aspect has directed the staff to incorporate
the suitable amendment in the regulations. We also submit to Commission to consider
the auxiliary consumption in its tariff order and
review and finalise the benchmark capital cost of the Solar PV project for FY14-15.revise and declare the tariff for Solar PV prject as INR 9.45/kWh for FY 14-15.
7.5 ACME SolarEnergyPvt. Ltd. , Haryana:-ACME Solar Energy Private Ltd. has submitted as under:-
12
SMP-SOLAR-22/2014-SKP
(i) Capital cost considered under the consultative paper is Rs.
6.91Crore/MW, which is very low and it would be tough and even
impossible for a solar developer to consider such a low cost of the power
plant. In order to highlight this low capital cost, some of the facts have
been provided below:
(a) The land cost in Bihar is very high in comparison to other states.
(b) The modules cost have increased.
(c) The cost for Civil, Mounting Structure, etc has increased.
(ii) GHI: The average GHI in Bihar is in the range of 4.482 to 5.066 which is
very low in comparison other states of India.
(iii) Interest on Loan : Major public sector banks are drying up with
infrastructure funds, projects now rely on foreign lenders which invites
lending rate plus hedging risk.
(iv) Auxiliary Power Consumption: There is no consideration of auxiliary
consumption in the consultative paper. Auxiliary consumption is the
quantum of energy consumed by auxiliary equipment of the generating
station and transformer losses within the generating station, expressed
as a percentage of the sum of gross energy generated at generator
terminals of all the units, and hence are significant enough to be
considered. Auxiliary power is required for air conditioning in inverter
room and control room & lighting in night. We propose the Commission
to consider 1% as auxiliary consumption.
(v) Assumption for Solar PV Power Projects parameters: Module Degradation
loss, Grid Unavailability Loss need to be considered/assumed suitably as
it impacts the generation/sale of energy of the plant. Linear Degradation
based on module supplier warranty need to be considered.
7.6 HINDUSTAN EPC CO. LTD. (formerly MOSER BAER Engineering &Construction Ltd) has submitted the following Comments/suggestions:-(i) Preliminary Submission-
Commission has initiated the present suo-motu proceedings under
BERC (Terms and Conditions for Tariff Determination from Solar Energy
Sources) Regulations, 2010 (2010 Regulations). Further, the said 2010
Regulations first control period has ended with the end of FY 2012-13
and Commission initiated the suo-motu proceedings for the second year,
13
SMP-SOLAR-22/2014-SKP
i.e. 2014-15 of the next control period of three years starting FY 2013-14.
In this regard we would humbly submit that the present exercise of tariff
determination needs to be carried out strictly as per the provisions of
2010 Regulations.
(ii) Interest Rate-As per 2010 Regulations Commission had allowed interest rate as LTPLR
of SBI prevalent during the previous year plus 150 basis points. The
relevant extract reads as under:
"(b) For the purpose of computation of tariff, the normative interest rate
shall be considered as average long term prime lending rate (LTPLR) of
State Bank of India (SBI) prevalent during the previous year plus 150
basis points. In case of change of SBI policy as regard LTPLR the
Commission may SuoMotu amended this rate of basis points over and
above the bank interest rate".
However, Commission has proposed to adopt the interest rate i.e. Base
Rate plus 300 basis points as taken by CERC. It may be noted that
although there is Policy shift from PLR to Base Rate as per RBI
guidelines for commercial banks, however, SBI still notifies the PLR from
time to time. Therefore, PLR is history till date is still available and there
is no difficulty in implementing the provisions of 2010 Regulations as far
as Interest Rate is concerned.
However, even if Commission wishes to adopt the Base Rate linked
Interest Rate then the equivalent percentage of the allowed interest rate
may be taken. It may be seen from the historic data of SBI that the
difference between PLR and corresponding Base Rate is a fixed no. of
4.75% (Detailed data enclosed as Annexure-I). Thus, LTPLR plus 150
basis points translate to SBI Base Rate plus 625 basis points. So the
current allowed interest rate of Base Rate Plus 300 basis points is not
equitable compared to the principles provided in Commission's 2010
Regulations. Therefore, in all equity and fairness the interest rate (cost of
debt) be allowed as LTPLR of previous year of SBI plus 150 basis points
as provided in the Regulations or its equivalence of SBI Base Rate during
the previous year plus 625 basis points.
(iii) Interest on Working Capital-
14
SMP-SOLAR-22/2014-SKP
As per 2010 Regulations stipulate interest on working capital as LTPLR
of SBI prevalent during the previous year plus 100 basis points. The
relevant extract of Regulation reads as under:
"(2) Interest on working capital shall be at interest rate equivalent to
average State Bank of India short terms Prime Lending Rate (STPLR)
during the previous year plus 100 basis points. In case of change of SBI
Policy as regard STPLR the Commission may Suo-motu amend this rate of
basis points over and above the bank interest rate."
However, Commission has proposed to adopt the interest rate i.e. Base
Rate plus 350 basis points as taken by CERC. Further, the principle of
interest on working capital has been 50 basis points higher than the
proposed Interest Rate unlike provision of 2010 Regulations wherein
Commission has allowed 50 basis points lower interest on working
capital compared to interest rate for long term. However, for the reasons
mentioned above the Interest on Working Capital, in all fairness, may be
considered as LTPLR of SBI prevalent during the previous year plus 100
basis points as provided in the Regulations or its equivalence as SBI
Base Rate prevalent during first six months of the previous year plus 575
basis points.
(iv) Capital Cost of Solar PV Plants-The break-up of Capital Cost under various heads as considered by
CERC while determining the Capital Cost for Solar PV projects and our
submissions for FY 2014-15 are given below for kind consideration of
Commission:Cost in Rs. Lakh/MW
Sl.No.
Project Cost Head 2014-15 OurProposals
1. PV Modules 365.80 3912. Additional module cost as against
Degradation11.29 …..
3. Land Cost 25 254. Civil and General Works 60 955. Mounting Structures 50 1056. Power Conditioning Unit 50 607. Evacuation Cost up to Inter-connection Pint
(Cables & Transformers)60 105
8. Preliminary and Pre-operative Expensesincluding IDC & contingency
69 86
Total Project Cost (1 to 8 ) per MW 691.09* 863* Hon'ble CERC rounded it off to Rs. 691 Lakh/MW
15
SMP-SOLAR-22/2014-SKP
In light of the above, the total capital cost of Rs. 8.63 Crore/MW (i.e.
module cost of Rs. 3.91 + non-module cost of Rs. 4.72 Crore/MW) may
kindly be considered for FY 2014-15 for Solar PV Projects.
(v) Capacity Utilisation Factor (CUF):Commission in Regulation 26 of Solar Tariff Regulations, 2010 has
allowed CUF of Solar PV projects as 19%, which presumably seems to be
based on the PAN India norms specified by CERC, whereas, the Global
Horizontal Irradiation (GHI) data from four different sources (enclosed as
Annexure-II) suggests a much lower CUF of around 15.5% based on the
given data may kindly be considered by relaxing the norms by exercising
its power under Regulation 37 of Solar Tariff Regulations, 2010. Detailed
submissions in justification thereof are given in the following paras.
The Capacity Utilisation Factor (CUF) specified by Commission is
19% for Solar PV Projects. In this regard, it is submitted that 19% CUF
was specified by CERC based on the maximum value of radiation data
(5.8 kWh/m2/day) considered for entire country (kindly refer Annexure-
III-PP 8-9 of CERC's Explanatory Memorandum for Solar Tariff 2009).
This maximum value is 5.83 kWh/m2/day for the station Bhavnagar
located in Gujrat. For Patna, the radiation level is only 4.79
kWh/m2/day. Accordingly, the expected CUF in Bihar would be
proportionally lower and should be around 15.6% (19% x 4.79/5.83) as
per the said data.
The solar radiation data of from four different sources for the entire State
of biharalongwith Gujarat, the most successful Solar State in the country
(enclosed at Annexure-II) wherein it may be seen that the Global
Horizontal Irradiance (GHI) i.e. Solar Insolation of Bihar is lower than
that of Gujarat. The average insolation data of Bihar and Gujrat have
been complied as below-
16
SMP-SOLAR-22/2014-SKP
State GHIMeteonorm-7.1.2
GHINASA
GHIMNRE
GHISolar-GIS
Average
Gujarat Maximum 5.71 6.07 5.79 5.68 5.856
Minimum 5.30 5.79 5.55 5.23 5.546
Average 5.549 5.332 5.731 5.470 5.521
Bihar Maximum 5.00 5.28 5.34 5.06 5.206
Minimum 4.59 4.88 4.99 4.43 4.820
Average 4.796 5.120 5.183 4.788 4.972
* (All figures in kWh/m2/Day)
The average solar insolation of the above referred data sources is 5.521
kWh/m2/Day and 4.972 kWh/m2/Day for the States of Gujarat and Bihar
respectively. Considering the CUF of 18% as allowed by CERC at the average
solar radiation in Gujarat (5.521kWh/m2/Day), the CUF for Bihar works out to
be 16.21%. However, even at the average maximum and minimum solar
radiation of Bihar, with respective average maximum and minimum solar
radiation of Bihar, with respective average maximum and minimum of Gujarat,
are taken the CUF works out to be 16.00% (18% x 5.206/5.856) and 15.64%
(18% x 4.82/5.546) respectively. It may also be seen from enclosed Annexure-IV
that the average CUF of four three plants in the State of Gujarat is around 18-
18.5%, which also substantiates the allowed CUF of 18% in Gujarat for all
locations in Gujarat. Therefore, it is requested that while determining the tariff
for solar PV Project, the Capacity Utilisation Factor (CUF) @ 15.5% or a
maximum 16% may kindly be considered by Commission by invoking
Regulation 37 (Power to Relax) and Regulation 38 (Power to remove difficulties)
of the Solar Tariff Regulations, 2010.
(vi) O&M Expenses :
Commission in its 2010 Regulations has fixed O&M Expenses for Solar
PV Projects as Rs. 9.51 Lakh/MW for first year (2010-11) and escalated
@ 5.72% per annum, which works out to be Rs. 11.88 Lakh/MW for FY
2014-15. Whereas, Commission in the proposed order has taken the
O&M Expenses as Rs. 12.30 Lakh/MW for FY 2014-15 which is being
taken by CERC for same year. In this regard, it is humbly submitted
17
SMP-SOLAR-22/2014-SKP
that Commission may kindly take the O&M Expenses for Solar PV
projects as Rs. 11.88 Lakh/MW for the FY 2014-15 (instead of Rs. 12.30
Lakh/MW) and escalated @ 5.72% per annum as per the provision of
2010 Regulations.
(vii) Auxiliary Consumption in Solar PV Power Plants :
It is submitted that Commission's Solar Tariff Regulations, 2010 and
CERC's RE Regulations, 2012 neither specifically provide any norm for
degradation nor deny allowing the same. Although, CERC has not
considered Auxiliary Consumption for Solar PV Plants whereas there is
an Auxiliary Consumption at Solar PV Power Plants too, which is not
negligible and, hence needs to be considered for tariff determination.
With our reasonably enough experience of successfully running the Solar
PV Power Plants we have found that Auxiliary Consumption is as high as
2% in MW capacity plant with smaller size, say 5 MW plant.
Commission may kindly exercise Power to relax as provided under Solar
Tariff Regulation, 2010 to factor in a normative Auxiliary Consumption of
at least 0.25% as is being done by GERC, RERC, KERC & MPERC.
(viii) Degradation of Solar Modules :
The annual degradation is also not captured by the average performance
(CUF of 19%) for the entire period 25 years, as that is the expected
average of solar insolation in the State over this period and does not
consider reduction in efficiency due to module degradation effect, which
has been separately considered by CERC and other State Commission.
Therefore separate dispensation for degradation needs to be done. Also,
both Commission's Solar Tariff Regulations, 2010 and CERC's RE
Regulations, 2012, neither specifically provide any norm for degradation
nor deny allowing the same for Solar PV Projects. Hence, Commission
may allow degradation by exercising its power under Regulation 37
(Power to relax) of the 2010 Tariff Regulations for Solar Energy to capture
the same.
It is, therefore, submitted that Commission may kindly consider
degradation/derating @ 0.5% per annum 4th year onwards for
determining the tariff for Solar PV plant.
18
SMP-SOLAR-22/2014-SKP
(ix) Computation of Tariff :
Discount Factor Correction Required:
Commission in BERC (Terms and Conditions for Tariff Determination
from Solar Energy Sources) Regulations, 2010 dated 02.10.2010
(hereafter "Solar Tariff Regulations") has provided provision for discount
rate at pre-tax WACC. The relevant extract of the Regulation 10 (2) reads
as under:
" (2) For the purpose of levellised tariff computation, the discount factor
equivalent to weighted average cost of capital shall be considered"
However, in the present proceeding Commission has proposed to
adopt post-tax WACC as taken by CERC. Commission while determining
the first solar Tariff Order (for FY 2010-11) during the first control period
(2010-13) has computed the pre-tax WACC as mandated under 2010
Regulations, whereas in the present proceeding Commission has not
computed the same as per the Regulations. It is, therefore, requested
that commission may kindly compute discount factor as pre-tax WACC
as mandated under 2010 Regulations.
15. Levellised Tariff is calculated by carrying out levellisation for 'useful life'
of each technology considering the discount factor for time value of money.
16. The discount factor considered for this purpose is equal to the Post Tax
weighted average cost of the capital on the basis of normative debt: equity ratio
(70:30) specified in the Regulations. Considering the normative debt equity ratio
and weighted average of the post tax rates for interest and equity component,
the discount factor is calculated. Interest Rate considered for the loan
component (i.e. 70%) of Capital Cost is 12.70% (as explained later). For equity
component (ie. 30%) rate of Return on Equity (ROE) considered at Post Tax RoE
of 16% considered. The discount factor derived by this method for all
technology is 10.67% ( (12.70% x 0.70 x (1-33.99%) + (16.0% x 0.30))."
It may be seen that the shift from taking discount factor as pre-tax
WACC to post-tax WACC is due to change in Regulations. However, the present
discount factor (i.e. post-tax WACC) taken by CERC does not ensure the
assured return on equity in Regulations. However, this issue is not being
19
SMP-SOLAR-22/2014-SKP
highlighted as it does not relate to the present proceeding considering the
provisions of 2010 Regulations of Commission.
Since Commission has not modified its regulations to state that discount
factor shall be post tax WACC. Commission is, accordingly, requested to correct
the discount factor from post-tax WACC to pre-tax WACC as mandated under
the provisions of 2010 Regulations.
It is, therefore, submitted that Commission while arriving at the generic
levellised tariff for solar PV plant levelisation from the revenue stream may
kindly be done.
7.7 SOUTH BIHAR POWER DISTRIBUTION CO. LTD , PATNA:-South Bihar Power Distribution Company Ltd. has submitted its
comments/suggestions/objections vide letter no. SBC-215/2014/12 dt.
03.01.2015. The detailed comments/suggestions/objections are hereunder-
(i) Section 7 (IV)-Loan Tenure- For the purpose of determination of tariff, loan tenure of 10
years shall be considered and no change is proposed.
Comment 1- In the wake of prevailing tight liquidity conditions and
impact on cash flows of the loan disbursement period, loan tenure of 12
years may be considered as per CERC for determination of generic tariff
order for FY 15 (Petition No. SM/354/2013 (Suo-Motu).
(ii) Section 7 (VI)-Depreciation- It shall be 7 percent for the first 10 years of the tariff
period and remaining depreciation shall be spread over the remaining
useful life of the project from 11th year onwards.
Comment 2- With the proposed revision in loan tenure, it is proposed to
revise the depreciation at the rate of 5.83 percent for the first 12 years
and remaining depreciation should be spread over the remaining useful
life of the project from 13th year onwards. The same treatment has been
done by CERC for determination of generic tariff order for FY 15 (Petition
No. SM/354/2013 (Suo-Motu).
Other Comments(iii) Auxiliary Consumption-
No auxiliary consumption has been considered for Solar PV projects.
20
SMP-SOLAR-22/2014-SKP
Comment 3- Suitable auxiliary consumption should be considered for
auxiliary power requirements of various peripheral systems such as
inverter room and control room air conditioning.
(iv) Module Degradation-The Commission has not considered the loss of power generation due to
module degradation.
Comment 4- An annual performance degradation of 0.5% from second
year onwards should be considered to capture the impact of degradation
process on reduction in generation over the life of project.
7.8 BIHAR STATE POWER HOLDING CO. LTD , PATNA:-Bihar State Power Holding Company Ltd. has submitted following parawise
comments vide letter no. 24 dt. 12.03.2015-
(1) Para 7 (i) : Control period or Review Period- No comment.
(2) Para 7 (ii) : Tariff Period- No comment.
(3) Para 7 (iii) : Debt Equity Ratio- No comment.
(4) Para 7 (iv) : Loan Tenure- No comment.
(5) Para 7 (v):Interest Rate-The project developer obtain loan for the project corresponding to 70% of the
project cost at the SBI base rate, whereas, Commission in the tariff for 2014-15
has proposed interest rate on the loan component as SBI Base Rate + 300 basis
point. The consideration of the additional interest rate i.e. 300 basis point over
and above the SBI base rate coupled with high rate of return proposed by the
Commission on equity to be employed by the developer will be an additional
income to the developer and at the same time it may have considerable impact
on the tariff to be paid by the Distribution licensee and ultimately by the end
consumers.
The reason behind considering the interest rate as SBI Base Rate + 300 basis
points is mainly on account of the high profile risk involved in the Renewable
energy projects in comparison to the conventional energy projects. The
evacuation system is also being provided free of cost to the project developers if
it qualify the provisions of Clause 4.2.3 of the "State NRE Policy 2011". Further,
payment against monthly power supply to DISCOMs from Solar Power PV
projects including Rooftop Solar PV project including Rooftop Solar PV and
Small Power Projects and Soar Thermal Power Projects based generation plant
is also secured in the form of LC to be maintained by the Distribution licensee
21
SMP-SOLAR-22/2014-SKP
in favour of the Solar Power PV/Small thermal project developers under
payment security mechanism in case of default in payment by DISCOMs.
The interest rate considered by the Commission 300 basis point over SBI Base
Rate is very high and not in line with the Monetary Policy Statement of RBI for
2014-15.
It is also relevant to mention that the norms decided by the CERC is the ceiling
norms and State Commissions are free to determine better norms by striking
balance between the cost of generation & Cost of supply in accordance with
section 61 © & 61 (d) of EA-2003. The project developers in the State are being
given various incentive / special concession under provisions of Clause 5 & 6 of
the State NRE Policy, 2011, which is also required to be consider by the
Commission for determination of tariff solar PV including rooftop.
In view of the position explained above, it is prayed that for computation of
interest on loan component in respect of Solar Power PV / Small thermal
project the interest rate be considered as Bank Rate of RBI (i.e. 9 % w.e.f.
28.01.2014) + 200 basis point only for project to be Commissioned in 2014-15.
Para6 (vi) : DepreciationCapital cost of the Solar PV & Rooftop Solar PV Generation Plant shall be
apportioned on Machinery and Land and civil works is the rate at 85% and 15%
respectively. Therefore Depreciation shall be calculated with the reference value of
85% of the cost of Plant and Machinery and accumulated depreciation shall be limited
to 90% of the cost of Plant and Machinery.
Para 7 (vii) : Return of EquityThe normative Return on equity be considered 16 % (pre-tax) for the useful life of
the plant.
Para 7 (viii) : Interest on Working CapitalInterest on working capital should be equivalent to RBIU Bank Rate (9%)+200
basis point (equivalent to 11.0%) only.
Para 7 (ix) : Discount FactorDiscount factor should be increased in the interest of beneficiaries or distribution
licensee to promote the solar power PV /small thermal projects in Bihar.
In the light of the position explained above, it humbly prayed before the
Commission for kind consideration of the followings:
22
SMP-SOLAR-22/2014-SKP
a. Interest rate on loan in case of Solar Power PV/Solar thermal based Generation
Plants be equal to RBI Bank Rate (9%) + 200 basis point i.e. 11%.
b. Return on equity shall be 16% (pre-tax) for the useful life of the plant.
c. Interest on Working Capital shall be equal to Bank Rate (9%) + + 200 basis
point i.e. 11%.
d. Capital cost on Machinery, Land and civil works shall be apportioned in the
ratio 85%:15% and depreciation shall be computed on 85% cost of the plant
and machinery and accumulated depreciation shall be limited to 90% of the
cost of plant and machinery.
8 Commission’s Observation and Views:-(i) Commission has examined the comments /submissions made in respect of
norms considered by the Commission in the consultative paperfor
determination of generic levellised tariff for FY2014-15 for Solar PV Projects
and Solar Thermal Power Projects.
The norms for determination of tariff specified in the Regulations remain valid
during the control period and benchmark capital cost for these projects may be
reviewed annually by the Commission.
(ii) Commission has considered norms of Tariff period, Loan Tenure, Debt Equity
Ratio, Depreciation, O&M expenses and CUF etc. as provided in the
Regulations,2010. Other parameters such as Return on Equity, Interest Rate
and Interest on working capital etc. are as per norms decided by the
Commission during 1stYear of the Control period while determining generic tariff
for FY2013-14 for Power Generated from Solar PV Projects and Solar Thermal
Projects in suo-motu proceeding no.9/2013 dated 14.06.2013.The Commission
has amended respective Regulations 14(2)(b),16(2)(a), 17(2),27(1)and 31(1) of
the Regulations,2010 in para32 of the aforesaid order.
(iii) Capital cost, Capacity Utilization Factorand provision for auxiliary consumption
for Solar PV projects etc have been main issues raised in the comments
/suggestions submitted by M/s Hindustan Power(Moser Baer), Response
Energy, ACIRA solar, Welspun,Sun Edision and SBPDCL.Commission has
considered the following aspects while making decisions on the issues:- :-
23
SMP-SOLAR-22/2014-SKP
(a)Capital Cost:The CERC vide its order dated 15th May 2014 has notified benchmark capital
cost of Rs. 691 Lakh/MW for Solar PV Projects for FY 2014-15 considering parameters
like module cost, cost of land, cost of module degradation and civil & mounting
structures etc. In the submissions,it has been suggested to consider higher capital
cost in view of higher costs of module, module degradation, land and Civil and
mounting structure, etc.
CERC in its order in petition no.SM/353/2013 has observed in para 8.2.4 that
though, average module price is around 0.67USD/Wp, prevailing module price offered
in the country by the leading manufacturers (world top 10 manufacturers) are on
lower side. CERC has considered the module cost of O.59USD/Wp after considering
the suggestions of MNRE and the stakeholders which is inclusive of custom clearing
charges, transportation and unloading. Cost component for module degradation have
also been considered and an amount of Rs11.29 lakhs/MW has been provided.
M/s Response Energy, Welspun and others have suggested higher cost of land
and has mentioned that there is less than 4% of barren land in Bihar and it is
shrinking with rising population. In north Bihar, more than 2300 people reside in one
sq.km area.
It has been submitted that consideration of the MVR notified by Government of
Bihar for ek fasla/un-irrigated type of land in different parts of the State as base land
price at the rate of Rs.5 lakhs/acre(Rs.25lakh/MW) is totally unjustified and not
based on realistic parameters.
Commission has examined the MVR rates prevailing in the different parts of the
state and it was found that average rate for Ek fasla/un-irrigated land is less than
Rs5000/decimal and therefore, has considered Rs25lakhs/MW as cost of Land for
Solar PV projects. However for those projects where the cost of land is higher, a project
specific determination of Tariff may be considered on case to case basis.
(b)Capacity Utilization Factor:SBPDCL, Response Energy, SunEdision, Hindustan Power and others in their
submissions have suggested todetermine CUF according to the solar radiation
prevailing in the State andaccordingly reduce the CUF in between 17-18% for Solar PV
Projects.CERC in its suo-moto order dated 15th May, 2014 (petition no. 353/2014) has
recognized this issue and directed staff to come out with the suitable amendments in
24
SMP-SOLAR-22/2014-SKP
the RE tariff regulations, 2012 with different CUF for different GHI bands across the
country.
Commission has also observed that a study carried out by the CREC ( at page
no. 103-statement of Objects and reasons, RE Tariff Regulations,2012) has noted that
average CUF at more than 80% locations works out to be more than 19% for solar PV
plant based on thin film technology. Similarly, the average CUF at more than 50%
locations work out to be more than 19% for solar PV plant based on crystalline
technology. M/s SunEdision has mailed on 10.1.2015, a copy of report on
performance of Solar Power Plant submitted to CERC in Feb.2011 wherein at page
no.35,table:9 , CUF at 52 various locations in the country have been indicated. As per
the report, CUF for Patna is 17.24% for crystalline technology and 18.22% for thin film
technology.
However, in absence of Zone wise/state wise/location wise data for CUF level,
in its order in SM/353/2013 dated 15.5.2014,while determining the benchmark
capital cost norms for Solar PV power projects and solar thermal projects applicable
during FY 2014-15, the CERC has considered CUF of 19 % for Solar PV power
projects. In suo-motu proceeding no.9/2013 dated 14.06.2013 during 1st year of the
control period, Commission considered to retain the CUF of 19% for Solar PV projects
while determining generic tariff for FY2013-14 for Power Generated from Solar PV
Projects. The Commission, therefore, retains the same for FY 2014-15 also.
(c) Auxiliary Consumption: -SBPDCL and other stake holders have suggested to consider auxiliary
consumption for various peripheral systems such as inverter room and control room
air conditioning of the solar PV power projects.
Commission has not provided any auxiliary consumption in the
Regulation for Solar PV Projects .
CERC has also has not provided auxiliary consumption in RE Regulations,
2012 or in its tariff order for FY2014-15.
9. Common norms for both Solar PV and Solar Thermal ProjectsControl Period or Review Period : The following Common norms for Solar PV and
Solar Thermal Projects are considered for determination of generic levellised tariff for
FY2014-15 :-
(a) Control period or Review Period :- The control period is for three years as per
provisions in the BERC(Terms and Conditions for determination of Tariff from
25
SMP-SOLAR-22/2014-SKP
Solar energy sources)Regulations,2010 i.e for the period from FY 2013-14 to FY
2015-16.
(b) Tariff Period :- It is 25 (twenty five) years for both Solar PV and Solar Thermal
Power Projects as per provision of the Regulations.
(c) Debt Equity Ratio :- For generic tariff to be determined based on suo-motu
petition, the debt equity ratio shall be 70:30 and no change is proposed.
(d) Loan Tenure :- For the purpose of determination of tariff, loan tenure of 10
years has been considered as per provisions in the BERCRegulations,2010
SBPDCL and Moser Bear have suggested Loan Tenure of 12 years as considered
by the CERC for determination of generic Tariff Order in for FY2014-15 for
Solar PV projects and Solar Thermal Projects.
(e) Interest Rate :- The BERC(Terms and conditions for determination of tariff for
solar energy sources)Regulations, 2010 provides that the interest rate shall be
average long term prime lending rate (LTPLR) of State Bank of India (SBI)
prevalent during the previous year plus 150 basis points. As per CERC
Regulations, 2012, the interest rate shall be SBI Base Rate during first six
months of the previous year plus 300 basis points. In view of significant policy
shift from Prime Lending Rate (PLR) to Base Rate for banks as per RBI
guidelines, interest rate on the basis of average State Bank of India (SBI) Base
Rate prevalent during the first six months of the previous year plus 300 basis
has been considered by the Commission in FY2013-14 while determining
generic Tariff for Solar PV projects and Solar thermal power projects. Base Rate
prevalent in SBI during the first six months in FY 2013-14 is 9.70%. As such
interest rate of 9.70% plus 300 basis points equivalent to 12.70% is considered
for FY2014-15 .
(f) Depreciation: It shall be 7 percent for the first 10 years of the tariff period and
remaining depreciation shall be spread over the remaining useful life of the
project from 11th year onwards as provided in theBERC Terms and conditions
for determination of tariff for solar energy sources)Regulations, 2010.
SBPDCL and Hindustan Power have suggested revision of depreciation at the
rate of 5.83% for 1st12 years as done by the CERC for determination of generic
tariff order for FY2014-15.
(g) Return on Equity :-The normative return on equity shall be 20% per
annum(pre –tax) for the first 10 years and 24% per annum(pre-tax) from the
26
SMP-SOLAR-22/2014-SKP
11th years onwards. It is in conformity with the CERC (Terms and Conditions
for Tariff Determination from Renewable Energy Sources) Regulations, 2012
and has been adopted while determining the generic tariff for FY 2013-14 for
power generated from Solar PV and Solar Thermal Power projects in the order of
the Commission in suo-motu proceedings no.09/2013 dated 14.6.2013.
(h) Interest on Working Capital :- The BERC(Terms and conditions for
determination of tariff for solar energy sources)Regulations, 2010 provides that
Interest on working capital shall be at interest rate equivalent to average State
Bank of India Short Term Prime Lending Rate (STPLR) during the previous year
plus 100 basis points. As per CERC Regulations, 2012, the interest rate on
working capital shall be at interest rate equivalent to the average State Bank of
India Base Rate prevalent during the first six months of the previous year plus
350 basis points. In view of policy shift from Prime Lending Rate (PLR) to Base
Rate for Banks as per RBI guidelines, interest Rate on the basis of average State
Bank of India (SBI) Base rate prevalent during the first six months of the
previous year plus 350 basis points has been considered and adoptedby the
Commission while determining generic tariff. for the FY2013-14. Average Base
Rate for the first six months prevalent in SBI in FY 2013-14 is 9.70%. As such
interest rate on working capital shall be 9.70% plus 350 basis points equivalent
to interest rate of 13.2% forFY2014-15.
(i) Discount Factor :- No change is proposed in discount factor which is
equivalent to weighted average cost of capital as per Regulation 22(ii). At
12.70% interest rate for loan component and 16% post tax ROE the discount
factor is { 12.7% x.7 (1-33.990%) + (16% x 0.30)}, which comes to 10.67%.
(10).Following parameters have been considered for Solar PV Power Projects :-
(a) Capital Cost :- The benchmark capital cost for projects may be reviewed
annually by the Commission. The CERC vide its order dated 15th May 2014
has notified benchmark capital cost of Rs. 691 Lakh/MW for Solar PV Projects
for FY 2014-15 considering parameters like module cost, cost of land, cost of
module degradation and civil works etc. The Commission considers this
benchmark capital cost as capital cost of Rs. 691 Lakh/MW for FY 2014-15 for
Solar PV Projects.However for those projects where the cost of land is higher, a
project specific determination of Tariff may be considered on case to case basis.
27
SMP-SOLAR-22/2014-SKP
(b) Capacity Utilisation Factor :- No change in existing 19% of CUF for Solar PV
and other small Solar Power Projects has been made for FY2014-15.
(c)Operation and Maintenance Expenses :- O&M expenses of Rs. 11.00
Lakh/MW for the first year of operation for FY 2012-13 with an escalation of
5.72% per annum was fixed by the CERC. Accordingly, Commission has
considered Rs. 12.30 Lakh/MW as O&M expenses for the period FY 2014-15
considering escalation rate of 5.72% per annum as provided by the CERC and
BERC Regulations.
11. Following parameters have been considered for Solar Thermal PowerProjects :-
(i) Capital Cost :- The CERC vide its order dated 15.05.2014 has fixed
benchmark capital cost of Rs. 1200 Lakh/MW for Solar Thermal Projects
for FY 2014-15. The Commission considers this benchmark capital cost
as normative capital cost of Rs. 1200 Lakh/MW for Solar Thermal Power
Projects for FY 2014-15.
(iii) Capacity Utilisation Factor :- No comment has been received from any
stake holder and Commission has not considered any change in the
existing 23% CUF for Solar Thermal Power Projects.
(iv) Operation and Maintenance Expenses :- O&M expenses of Rs. 15
Lakh/MT for the first year of operation for FY 2012-13 with an escalation
of 5.72% per annum was fixed by the CERC. The Commission considers
Rs. 16.77 Lakh/MW as O&M expenses for FY 2014-15 based on
escalation rate of 5.72% per annum as provided in the Regulations,
2010
(v) Auxiliary Consumption :- No comment has been received and existing
auxiliary consumption of 10% for Solar Thermal Projects has been
retained as provided under the Regulations,2010
12. For availing the benefit of accelerated depreciation applicable income tax rate @
33.990% (30% IT rate + 10% surcharge + 3% education cess)has been considered for
the purpose of determining net depreciation benefit. Depreciation @ 5.28% as per
straight line method (Book depreciation as per Companies Act, 1956) has been
compared with depreciation as per Income Tax Rate i.e. 80% of the written down
value method. Additional 20% depreciation in the initial year is proposed to be
28
SMP-SOLAR-22/2014-SKP
extended to new assets acquired by power generation companies vide amendment in
section 32, sub-section (1) clause (ii a) of the Income Tax Act.
Depreciation for the first year has been calculated at the rate of 50% of
accelerated depreciation 80% and 50% of additional depreciation 20% (as project is
capitalized during the second half of the financial year as per proviso (ii) to Regulation
22). Income Tax benefit of accelerated depreciation and additional depreciation has
been worked out as per normal tax rate on the net depreciation benefit. Per unit
levellised accelerated depreciation benefit has been computed taking discount factor
into account.
13. The generic levellised tariff determined on the basis of above common parameters and
parameters for Solar PV Power Projects shall be applicable for such projects which are
commissioned up to 31.03.2016 and for which PPA is signed up to
31.03.2015.However,till such time new tariff is determined,tariff determined in this
order shall remain applicable.
14. The said tariff shall be valid for 25 years from the date of commissioning of project.
15. The tariff has been determined for the projects for which PPA was to be signed up to
31.03.2015 and the project was to be commissioned before 31.03.2016. However, the
financial year 2014-15 is already over and the process of fresh determination of tariff
for the year 2015-16 may take some time. Therefore, this tariff shall be valid till a
new tariff order for the year 2015-16 is issued by the Commission. This tariff will also
be applicable to projects for which PPA is signed after 31.03.2015 and before the
issue of the next tariff order and the project is commissioned within one year from
the signing of the PPA.
16. The generic levellised tariff for Solar PV including Rooftop PV determined on the
basis of above common parameters and parameters for Solar PV Projects shall be as
hereunder :
Particulars LevelisedTariffRs./KWh
Levelised benefit ofaccelerateddepreciation, ifavailable Rs./KWh
Net levelised Tariffafter adjustment foraccelerateddepreciationRs./KWh
Solar PV PowerProjects includingRooftop Solar PV andSmall Power Projects
7.69 0.76 6.93
29
SMP-SOLAR-22/2014-SKP
17.The generic levelised tariff determined on the basis of above common parameters and
parameters for Solar Thermal Power Projects shall be applicable for such projects
which are commissioned upto 31.03.2017 and for which PPA is signed upto
31.03.2015. However,till such time new tariff is determined, tariff determined in this
order shall continue.
The tariff shall be valid for 25 years from the commercial operation date (COD).
This tariff will also apply to Projects for which PPA is signed after 31.03.2015
and before issue of a new tariff order for the year 2015-16 and the Project is
commissioned within two years of signing of the PPA.
18.The generic levelised tariff determined on the basis of above common parameters for
Solar Thermal Power Projects for Solar Thermal shall be as hereunder:
Particulars LevelisedTariffRs./KWh
Levelised benefit ofaccelerateddepreciation,if available
Rs./KWh
Net levelised Tariff afteradjustment foraccelerateddepreciation
Solar ThermalPower Projects
11.84 1.23 10.61
17.The detailed computations of the generic levelised tariff are shown in Annexure I for
Solar PV Projects and Annexure II for Solar Thermal Projects.
18.Other terms and conditions will remain the same as stipulated in Regulations, 2010.
Sd/-(S. C. Jha)Member
Sd/(U. N. Panjiar)
Chairman
30
SMP-SOLAR-22/2014-SKP
Annexure-1Template for Solar PV Power Projects
Sl.No.
AssessmentHead
Sub-Head (1) Sub- Head (2) Unit Assumptions
1. PowerGeneration
Capacity Installed PowerGenerationCapacityUtilization factorAuxiliaryConsumptionUseful life
MW
%%
Year
1
19.00.0
252. Power Cost Capital
Cost/MWPower Plant Rs.
Lac/MW691
3. FinancialAssumptions Debt :Equity
DebtComponent
EquityComponent
Depreciation
Tariff PeriodDebtEquityTotal DebtAmountTotal EquityAmountLoan AmountMoratoriumPeriodRepaymentPeriodInterest rateEquity AmountReturn onEquity first 10yearsROE 11th yearonwardsdiscount rateDepreciationrate first 10yearsDepreciationrate 11th yearonwardsIncome Tax
Year%%Rs. Lakh
Rs. Lakh
Rs. LakhYear
Year
%Rs. Lakh% p.a.
% p.a.
%
%
%
%
257030483.70
207.30
483.700
10
12.7207.3020
24
10.67
7
1.33
33.9904. Operation &
MaintenanceO&Mexpensesp.a.Escalationfor O&M
Rs. Lakh
%
12.30
5.725. Working O&M Month 1
31
SMP-SOLAR-22/2014-SKP
capital expensesMaintenanceSpareReceivablesInterest onworkingcapital
(%O&Mexpenses)
%
Month
%
15
2
13.2
32
SMP-SOLAR-22/2014-SKP
Annexure-II
Solar Thermal Power Projects
Sl.No.
Assessment Head Sub-Head (1) Sub- Head (2) Unit Assumptions
Installed PowerGeneration Capacity
MW 1
1 Utilization factor % 232 Auxiliary consumption % 10
useful life Year 25
3 Project Cost CapitalCost/MW
Power Plant cost Rs. Lakh/MW 1200
4 FinancialAssumptions
Tariff Period Year 25
Debt :Equity Debt % 70Equity % 30Total Debt Amount Rs. Lakh 840Total Equity Amount 360
DebtComponent
Loan Amount Rs. Lakh 840
Moratorium Period Year 0Repayment Period Year 10
Interest rate % 12.70EquityComponent
Equity Amount Rs. Lakh 360
Return on Equity first10 years
% p.a. 20
ROE 11th year onwards
discount rate
%
%
24
10.67Income tax % 33.90
Depreciation Depreciation rate first10 years
% 7
Depreciation rate 11th
year onwards% p.a. 1.33
4 Operation &Maintenance
O&Mexpenses(2014-15)
Rs. Lakh 16.77
Escalation forO&M
% p.a. 5.72
33
SMP-SOLAR-22/2014-SKP
expenses
O&Mexpenses(2013-14)
Rs. Lakh 15.86
5 Working capital O&Mexpenses
Month 1
MaintenanceSpare
% of O&M expenses % 15
Receivables Month 2Interest onworkingcapital
% 13.2
34
SMP-SOLAR-22/2014-SKP
34
SMP-SOLAR-22/2014-SKP
34
SMP-SOLAR-22/2014-SKP
35
SMP-SOLAR-22/2014-SKP
35
SMP-SOLAR-22/2014-SKP
35
SMP-SOLAR-22/2014-SKP
36
SMP-SOLAR-22/2014-SKP
36
SMP-SOLAR-22/2014-SKP
36
SMP-SOLAR-22/2014-SKP
37
SMP-SOLAR-22/2014-SKP
37
SMP-SOLAR-22/2014-SKP
37
SMP-SOLAR-22/2014-SKP