Upload
kesraj77
View
230
Download
0
Embed Size (px)
Citation preview
8/9/2019 Bigiest Power Station
1/15
-----Original Message-----From: Parthasarathy R (Safety)Sent: Wednesday, May 17, 2006 5:58 PMTo: Sugavanam S (Electrical); Natarajan (Electrical); Selvakumar M [Electrical]Subject: FW: Biggest power plant on the Earth
FYI please,Partha.-----Original Message-----From: Ravichandran, Bakthavatcha (B.) [mailto:[email protected]]Sent: Friday, May 12, 2006 11:05 AMTo: Ravichandran, Bakthavatcha (B.)Subject: Biggest power plant on the Earth
Biggest power plant on the Earth
ITAIPU- Largest power plant on the Earth- 12600 MW of Hydro power
Total view of the ITAIPU power plantLeft part shows overflow (spillway), the power station is located in the middle.
8/9/2019 Bigiest Power Station
2/15
At the bottom of the 196 m tall dam, the white tubes are containing the inlets for the
18 turbines (715 MW each).
On top of the 7.6 km dam, a 12 800 000 m of concretewas used for the projectITAIPU.
8/9/2019 Bigiest Power Station
3/15
The lake created by ITAPU dam. Its area reaches 1 350 km2, its length 170 km andits average width 7 km.
One 715 MW electrical generator
The diameter of the rotor is almost 16 m, the rotating mass
8/9/2019 Bigiest Power Station
4/15
Inside the ITAIPU PowerhouseDimensions: length: 986 m, maximum height: 112 m and width: 99m.
The red line on the floor indicates the border of Brazil and Paraguay.
One 715 MW electrical generatorThe diameter of the rotor is almost 16 m, the rotating mass is 2 650 t
8/9/2019 Bigiest Power Station
5/15
The control center of the 18 generators
Left half of it (in Brazil) controls the 60 Hz units, right half (in Paraguay) controlsthe 50 Hz units.
A 18 kV to 525 kV transformator for 825 MVATo increase the voltage To increase the voltage of the generators, transformers with
a capacity of 825 MVA and 768 MV(for 50 and 60 Hz respectively) were specified.
8/9/2019 Bigiest Power Station
6/15
Power switches for high voltages
Power switches at the "Left Bank Substation" (FURNAS).
The AC-DC rectifier
The FURNAS rectifier substation is accomplished by four lines of of 500 kV.Output DC voltages are symmetrical 500 000 Volt SC.
8/9/2019 Bigiest Power Station
7/15
Electricity (AC) leaving ITAPU to Sao Paulo
6 300 MW of electrical power generated by the 60 Hz units is transported by an 891km AC transmission system, formed by three lines of 750 kV.
"Peanuts"- a word often used from so called "economic experts" and representatives
when it comes to Renewable Energies."Not sufficient", "unreliable", "not feasible", are common bias.
ITAIPU shows they are wrong! Having more power than 10 nuclear power stations it
supplies the second largest city on the planet with zero-emission electricity since1984, still being extended until 1991. 26% of the electrical power consumption of
Brazil and 78% of Paraguay are supplied by ITAIPU.
Located at the Brazilian-Paraguaian border and not far from the Argentinian border,
the first step of the initiation was already in 1966 when the Ministers of Foreign
Affairs of Brazil and Paraguay signed a joint statement known as the "Act of Ygazu".By this a study and evaluation of the hydraulic resources of the Parana river (owned
jointly by Brazil and Paraguay) followed.
On April, 26, 1973, the two governments of the states signed a treaty "for thedevelopment of the hydroelectric resources of the Parana River" and founded
"ITAIPU Binacional" (cooperation with the legal, administrative and financialcapacities and technical responsibility to plan, set up and operate the plant) in May,
17, 1974.
The construction work started in 1975, reaching its peak in 1978 with 30 000 peopleat work. Monthly on-site concrete production reached 338 000 m. In total, 15 times
the mass of concrete used for the "Eurotunnel" was supplied. The height of the damreaches 196 m, its length 7.76 km. The lake created by this is 170 km long and
contains 29 billion tons of water.
8/9/2019 Bigiest Power Station
8/15
Unit 1 started to operate in December 1983. Electrical grid connection to Paraguay
was established in March 1984, Brazil was connected 5 months later. In March 1991the last unit (No.18) was put into operation.
The water intake of one single 715 MW Francis-turbine is 700 m/s, its weighted
efficiency is 93.8%.
Each year ITAPU generates 75 TWh of electricity and avoids 67.5 million tons ofcarbon dioxide emissions - compared to coal power plants.
The final cost of ITAIPU amounts to US$ 20 billion, 50% of this value are directinvestments and balance financial charges.
If whole area of the lake - at nominal level - would be covered by solar modules the
power of the would be 135 000 MWp, which would produce 230 TWh a year. For thesame yearly output as ITAIPU a solar PV-plant would cost US$ 132 billion
Technical Data
8/9/2019 Bigiest Power Station
9/15
Powerhouse and Main Dam
Location of the Equipment and Principal Elevations
Powerhouse (18 units including erection bays) - (m)
Length 968
Width 99
Height 112
Roof level 148
Generator hall floor level 108
Spacing between units 34
01 - El 40 - Foundation of the dam
02 - El 92,4 - Access to turbine pit
03 - El 98,5 - Unit auxiliary service - Pure water system
04 - El 98,5 - Excitation system, access to generator housing and speed governo
05 - El 108 - Step-up transformers06 - El 108 - Generator hall floor and local control rooms
07 - El 122 - Ventilation system
08 - El 127,6 - Cable gallery
09 - El 128,2 - GIS - SF6
10 - El 133,2 - Principal panels of AC auxiliary service and diesel generator hall
11 - El 144 - Dam auxiliary service
12 - El 214 - Gate hydraulic pump group
Rolling track of gantry crane
8/9/2019 Bigiest Power Station
10/15
Rolling track (m) Span 10,00
Total length 857,6
Rail-top elevation 225
Penstocks
Quantity 18
Weight each penstock (t) 883
Internal diameter (m) 10,5
Developed length (m) 142,2
Rated flow (m / s) 690
Water Intake Trashracks
Quantity 18
Rack panels per intake 24 (m) 4,7 x 5,5
Trashrack Cleaning Machine
Quantity 2
Jib crane capacity (kN) 200
Vertical lift of rake (m) 61,5
Rake capacity (m / kN) 2/2,5
Service Gates (Fixed wheel type)
Quantity 18
Span (m) 8,2
Total height (m) 19,3
Sill beam elevation (m) 177,6
Maximum flow through gate (m/s) 750
Stop-logs
Sill beam elevation (m) 177,2
Span (m) 7,5
Height (m) 17,5
Quantity 7
Gantry cranes
Quantity 2
Capacity (kN) 1.100/400
Max. hoisting speed 50/60 Hz (m/min.) 4,6/5,5
Min. hoisting speed 50/60 Hz (m/min.) 1,7/2,0
Rated travel speed 50/60 Hz (m/min.) 25/30
8/9/2019 Bigiest Power Station
11/15
Generator
Quantity 18
Frequency 60 Hz (9 un.) / 50 Hz (9 un.)
Rated power 50 / 60 Hz (MVA) 823,6 / 737,0Rated voltage (kV) 18
Number of poles 50 / 60 Hz 66 / 78
Moment of inertia - GD2 (t.m) 320.000
Power factor 50 / 60 Hz 0,85 / 0,95
Heaviest component - rotor (t) 1.760
Weight of each unit 50 / 60 Hz (t) 3.343 / 3.242
Turbine
Quantity 18
Type Francis
Rated power (MW) 715
8/9/2019 Bigiest Power Station
12/15
Design speed - 50 / 60 Hz (rpm) 90,9 /92,3
Net design head (m) 118,4
Rated flow (m/s) 645
Heaviest component - rotor (t) 296
Weight of each unit (t) 3.360
Bank of Single-Phase Transformers
50 Hz 9 + 2 Reserve Units60 Hz 9 + 2 Reserve Units
Rated Power of Each Bank
50 / 60 Hz (MVA) 825/768
Impulse Level (Phase/Neutral)
High Voltage (kV) 1.550/110
Low Voltage (kV) 125
Type of connection - Y
Weight of each transformer (kg)
217 x 103 (50 Hz)
189 x 103 (60 Hz)Cooling forced oil and water
SF6 Gas Insulated Substation
Maximum Rated Voltage (kV) 550
Rated Current (A) 4.000
Rated Break Current (kA) 63
8/9/2019 Bigiest Power Station
13/15
Quantity of Circuit Breakers 52
Length of Enclosed Busbars Isolated by SF6 Gas (m) 7.500
SF6 Pressure in the Circuit Breakers (kPa) 620
Quantity of Isolation Switches 124
Quantity of Current Transformers 396
Quantity of Potential Transformers 24
Quantity of Surge Arresters 126
Mass of SF6 Gas (kg) 108 x 103
SCADA - Supervisory Control and Data Acquisition
The SCADA System, is a means of supervision and control based on computers. The general purpose of thisSystem is to provide the Plant Operators with detailed and automatic information in a centralized form - at presentbeing distributed over more that 1,500 panels in the diverse galleries along the length of the power plant - andorganized in real time (that is, at the instant of occurrence) concerning the electrical, mechanical, thermal andhydraulic conditions of the equipment and the installations. This will permit the operators in the Central ControlRoom to exercise a permanent analysis of the situation and facilitate taking the correct and appropriate decisionswithin the time limits necessary to maintain the generation of energy.
Its operation is based on the installation of electronic devices in the diverse units of equipment in the Power Plant(generators, turbines, transformers, etc.) for the automatic acquisition of operational information. This informationwill be transferred to a central computer, where it will be processed by specific software. When the softwareidentifies abnormal conditions, the Operators will be instantly informed by signals on the computer monitors. Therequired corrective actions or commands can be taken through these same computers.
The SCADA System is scheduled to be installed by the middle of 2002 and will provide the Operators withsupervision over approximately 18,000 points, significantly improving the operating conditions of the Plant andpermitting, in many cases, the prevention of disconnections, as well as allowing greater speed of recovery from theoperational problems that may occur.
8/9/2019 Bigiest Power Station
14/15
Transmission system
***********************************************************************
*********"This e-Mail may contain proprietary and confidential information and is sent for the
intended recipient(s) only. If, by an addressing or transmission error, this mail has been
misdirected to you, you are requested to delete this mail immediately.You are also hereby
notified that any use, any form of reproduction,dissemination, copying, disclosure,modification,distribution and/or publication of this e-mail message, contents or its
attachment other than by its intended recipients is strictly prohibited. Any opinions
expressed in this email are those of the individual and not necessarily the organization.Before opening attachments, please scan for viruses."
***********************************************************************
*********
---DISCLAIMER-------------------------------------------------
The contents of this E-mail (including the contents of the
enclosure/(s) or attachment/(s) if any) are privileged and
confidential material of Mahindra and Mahindra Limited (M&M)
and should not be disclosed to, used by or copied in any
manner by anyone other than the intended addressee/(s). If
this E-mail (including the enclosure/(s) or attachment/(s)
if any ) has been received in error, please advise the
sender immediately and delete it from your system. The views
8/9/2019 Bigiest Power Station
15/15
expressed in this E-mail message (including the enclosure/(s)
or attachment/(s) if any) are those of the individual sender.
--------------------------------------------------------------