Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
This addendum consists of three (3) pages and one attachment. 00 91 15-1
BIDDING AND CONTRACT REQUIREMENTS Document 00 91 15 - Addendum No. 1
DATE: April 5, 2015 Design Architects, Inc. #5 Bank Square East St. Louis, IL 62203
TO: PROSPECTIVE BIDDERS SUBJECT: ADDENDUM NO. 1 TO THE REQUEST FOR PROPOSAL FOR
Illinois Eastern Community Colleges
Public Health & Safety Improvements Frontier College
Lincoln Trail College Olney Central College
Wabash Valley College
This addendum forms a part of the proposal request and contract documents and modifies the original documents dated March 20, 2015. Acknowledge receipt of this addendum in the space
provided on the Bid Form. FAILURE TO DO SO MAY SUBJECT BIDDER TO
DISQUALIFICATION.
****************************************************************************************************
Upon receipt of this addendum, please sign below and e-mail to Hurst-Rosche
Engineers, at [email protected]
Clarifications:
1. Sheets C-101-F, C-101-L, C-101-O, C-101-W – Sidewalk Detail, control joints shall be located 5’-0” o.c. and expansion joints 30’-0” o.c..
2. All new hollow metal door frames receive paint per section 09 90 00. 3. Double door and frame as shown in A-101-L receives paint per section 09 90 00. 4. The list of existing Mammoth Rooftop Units being replaced is provided in the
attachment. 5. Where window glazing is required for doors provide insulated glass with a total
thickness of 1”. The glass panels shall be a minimum of ¼” tempered glass.
RECEIVED BY:
Company Name/Authorized Representative
DATE:
This addendum consists of three (3) pages and one attachment. 00 91 15-2
Specifications: 6. Section 08 41 13 – 2.1, A – Manko Series 150 is an approved substitution. 7. Section 08 71 00, 2.4, A – Brass finish for door hardware for door hardware replaced as
part of Alternate #1, Wabash Valley College, Science Building and Bauer Media Center. 8. Section 08 71 00, 2.2, C – Revise the locksets for the individual Colleges as: Frontier
College – CORBIN-RUSSWIN, Lincoln Trail College – SCHLAGE PRIMUS, Olney Central College – BEST, Wabash Valley College – CORBIN RUSSWIN.
9. Section 08 71 00, 2.5, J – Add Horton Automatic as an approved provider of the power assist operators with wireless activator.
10. Section 09 90 00, 2.1, A – Add Pittsburgh Paints as an approved provider for paint.
Drawings:
11. Sheet C-101-W: Remove and Replace entire sheet with attached sheet RC-101-W.
12. Sheet A-101-O: Door Schedule. Materials for the new door and frames are hollow metal.
13. Sheet A-103-F: Add a concrete stoop outside of door #2. See detail #1, sheet A-103-F.
14. Sheet A-103-F: Provide new hollow metal door frames for doors #2, 3 and 4.
15. Sheet AD-101-L: Remove and Replace entire sheet with attached sheet RAD-101-L.
16. Sheet A-102-L: Remove and Replace entire sheet with attached sheet RA-102-L.
17. Sheet A-101-W: Remove and Replace entire sheet with attached sheet RA-101-W.
18. Sheet A-102-W: Remove and Replace entire sheet with attached sheet RA-102-W.
19. Sheet M-101-L: REVISE Natatorium Partial Mech. Demo Plan and Natatorium Partial New Work Plan shall be removed. Existing water heater and storage tank to remain but be completely re-piped per Sheet RM-01.
20. Sheet M-101-L: Remove all Circle keyed notes 1 thru 10.
21. Sheet M-102-L: Replace entire sheet with attached sheet M-102-LR
22. Sheet M-102-O: Existing aggregate surfaced modified bitumen roof system is manufactured by Garland Company and covered under manufacturer’s warranty. Prior to any alteration, addition, tie-in, construction or repairs on or to any existing roofing materials to remain, the contractor shall certify approval of applicator and maintain any pre-existing manufacturer’s warranty in the form of an affidavit written and submitted by the roof system manufacturer. Remove area of existing roof assembly including modified bitumen roof system, tapered rigid insulation and cover board substrate, and steel bar joist and metal deck structural system of penthouse as necessary for installation of new HVAC equipment. Patch and repair roof assembly to match existing construction after installation of new equipment. Remove and reinstall all existing roof mounted equipment and accessories to remain as necessary to complete the work. New roof materials and accessories including flashing of all drains, conduits, and piping penetrations in areas affected by the work shall be as recommended and approved by the roof system manufacturer and installed in accordance with the roof manufacturer’s published installation instructions. Field verify existing construction including size, quantity, and location of all roof penetrations, equipment and accessories in areas to receive work.
23. Sheet M-103-L: Replace entire sheet with attached sheet M-103-LR
24. Sheet M-103-W: Applied Arts/Natatorium Partial Mech. Plan: Add to Keyed note 1 as follows: “ Provide new Thermostatic mixing valve on hot water outlet. Mixing valve shall be Lawler model 802 (86006) or equal by Leonard or Watts. Valve shall be capable of 66 GPM at 30 psi drop, with minimum flow rate of 2 GPM. Valve shall be provided in surface mounted stainless steel cabinet with lock. Remove existing inoperable water heater recirculating pump and replace with new. Provide all required fittings and adapters for complete install. Disconnect and reconnect electrical power. New recirculating pump shall be TACO model 008BF, bronze volute with bronze flanged fittings, ¾” connection. Pump shall be 1/25 HP. Equivalent pump by Bell & Gossett or Grundfos shall be acceptable.”
This addendum consists of three (3) pages and one attachment. 00 91 15-3
25. Sheet M-103-W: (David L. Hart Student Center Roof Plan) – REVISE Sheet number to M-104A-W. ADD General Note:” All removed condensing units shall be turned over to owner after removal.”
26. Sheet M-106-W: Replace sheet metal cover of the boiler vent with pre-finished porcelain panels by Mapes. See attached specification 07 42 43.
27. Sheet M-107-W: (Partial Spencer Sports Center- Dryer Vent Plan) REVISE sheet number to M-108-W.
28. Sheet M-109-W: ADD General Note:” All removed condensing units shall be turned over to owner after removal.”
29. Sheet M-110-W: #6 and #7 ADD General Note:” All removed condensing units shall be turned over to owner after removal.”
30. ADD Sheet M-116: Mechanical Equipment Schedules - in its entirety.
31. Sheet E-101-F: The legend shows DAST. This is an error. The abbreviation should be DACT.
32. Sheet E-101-L: CLARIFICATION: All existing light fixtures in gymnasium are to be removed and replaced with new fixtures. All new fixtures shall be Fixture D. See Light Fixture Schedule RE-601.
33. Sheet E-102-L: Remove and Replace entire sheet with attached sheet RE-102-L.
34. Sheet RE-601: ADD Exterior Light Fixture Schedule per attached RE-601. Also includes lighting schedule for Lincoln Trail Gymnasium and panel schedule for Wabash Valley Main Building.
35. Sheet E-102-W: Clarification: Indicated fire alarm devices shall be added and incorporated into the existing fire alarm system.
36. Sheet E-104-W: REVISE – All Equipment circuits to fan coil units and branch selector boxes shall extend to new panel AC in mechanical penthouse, not the existing panel in boiler room. See panel schedule.
37. Sheet E-105-W: ADD Panel Schedule per Sheet RE-601.
38. Sheet E-105-W: REVISE – Heat Recovery Unit 1 shall have 3 electrical connection, not 2 as shown. Each connection shall have MCA of 43, MOP of 50 per equipment schedule and Main Hall Panel Schedule AC.
This addendum alters date. Bids will be opened on April 14, 2015, 2:00 p.m., Illinois
Eastern Community Colleges, 233 East Chestnut Street, Olney, Illinois.
Sincerely, DESIGN ARCHITECTS, INC. Randy Mitchell, AIA
cc: All planholders
430-3644 Composite Wall Panels
Public Health and Safety Improvements 07 42 43 - 1
SECTION 07 42 43 - COMPOSITE WALL PANELS
PART 1 GENERAL
1.1 SUMMARY
A. Section includes preformed metal panel system for walls with insulation, related flashings
and accessory components.
1.2 REFERENCES
A. Aluminum Association:
1. AA ADM 1 - Aluminum Design Manual.
2. AA ASM 35 - Aluminum Sheet Metal Work in Building Construction.
B. American Society of Civil Engineers:
1. ASCE 7 - Minimum Design Loads for Buildings and Other Structures.
C. ASTM International:
1. ASTM A666 - Standard Specification for Austenitic Stainless Steel Sheet, Strip,
Plate, and Flat Bar.
2. ASTM A755/A755M - Standard Specification for Steel Sheet, Metallic Coated by
the Hot-Dip Process and Prepainted by the Coil-Coating Process for Exterior
Exposed Building Products.
3. ASTM B209 - Standard Specification for Aluminum and Aluminum-Alloy Sheet
and Plate.
4. ASTM C177 - Standard Test Method for Steady-State Heat Flux Measurements and
Thermal Transmission Properties by Means of the Guarded-Hot-Plate Apparatus.
5. ASTM C665 - Standard Specification for Mineral-Fiber Blanket Thermal Insulation
for Light Frame Construction and Manufactured Housing.
6. ASTM D1621 - Standard Test Method for Compressive Properties of Rigid Cellular
Plastics.
7. ASTM D1622 - Standard Test Method for Apparent Density of Rigid Cellular
Plastics.
8. ASTM D2842 - Standard Test Method for Water Absorption of Rigid Cellular
Plastics.
9. ASTM E84 - Standard Test Method for Surface Burning Characteristics of Building
Materials.
10. ASTM E96/E96M - Standard Test Methods for Water Vapor Transmission of
Materials.
11. ASTM E119 - Standard Test Methods for Fire Tests of Building Construction and
Materials.
12. ASTM E330 - Standard Test Method for Structural Performance of Exterior
Windows, Curtain Walls, and Doors by Uniform Static Air Pressure Difference.
13. ASTM E413 - Classification for Rating Sound Insulation.
D. National Fire Protection Association:
430-3644 Composite Wall Panels
Public Health and Safety Improvements 07 42 43 - 2
1. NFPA 285 - Standard Method of Test for the Evaluation of Flammability
Characteristics of Exterior Non-Load-Bearing Wall Assemblies Containing
Combustible Components Using the Intermediate-Scale, Multistory Test Apparatus.
1.3 SYSTEM DESCRIPTION
A. System: Preformed and prefinished composite metal building panel system of horizontal and
vertical profile; with subgirt framing assembly; with integral rigid board insulation core;
with concealed fasteners.
1.4 PERFORMANCE REQUIREMENTS
A. Components: Design and size components to withstand dead and live loads caused by
positive and negative wind pressure acting normal to plane of wall as calculated in
accordance with applicable code.
1. Design Pressure: Minimum 40 lb/sq ft.
B. Maximum Allowable Deflection of Panel: 1/180.
C. Movement: Accommodate movement within system without damage to system, components,
or deterioration of seals; movement between system and perimeter components when subject
to seasonal temperature cycling; dynamic loading and release of loads; and deflection of
structural support framing.
D. Drainage: Provide positive drainage to exterior for moisture entering or condensation
occurring within panel system.
E. Tolerances: Accommodate tolerances of building structural framing.
F. Thermal Resistance of System: R of 8 or greater.
G. Products: Provide continuity of thermal barrier at building enclosure elements in conjunction
with adjacent thermal insulating materials.
1.5 SUBMITTALS
A. Section 01 33 23 – Shop Drawings, Product Data, & Samples Schedule.
B. Shop Drawings: Signed and sealed by professional engineer.
1. Indicate dimensions, panel profile and layout, spans, joints, expansion joints,
construction details, methods of anchorage, method and sequence of installation and
interface with adjacent materials.
2. Include design calculations.
C. Product Data:
1. Submit panel profile characteristics and dimensions, and structural properties.
2. Submit data on assembled panel structural capabilities.
430-3644 Composite Wall Panels
Public Health and Safety Improvements 07 42 43 - 3
D. Samples: Submit two samples of panel and panel finish, 12 x 12 inch in size illustrating
finish color, sheen, and texture.
E. Manufacturer's Installation Instructions: Submit special handling criteria, installation
sequence, and cleaning procedures.
1.6 QUALITY ASSURANCE
A. Perform Work in accordance with AISI.
1.7 QUALIFICATIONS
A. Manufacturer: Company specializing in manufacturing products specified in this section
with minimum three years documented experience.
B. Installer: Company specializing in performing Work of this section with minimum three
years documented experience approved by manufacturer.
C. Design metal panels under direct supervision of a licensed Professional Engineer
experienced in design of this Work.
1.8 DELIVERY, STORAGE, AND HANDLING
A. Section 01 66 00 - Product Requirements: Product storage and handling requirements.
B. Protect panels from accelerated weathering by removing or venting sheet plastic shipping
wrap.
C. Store pre-finished material off ground with weather protection to prevent twisting, bending,
or abrasion, and to provide ventilation. Slope metal sheets to ensure drainage.
D. Prevent contact with materials capable of causing discoloration or staining.
1.9 COORDINATION
A. Section 01 31 00 - Administrative Requirements: Coordination and project conditions.
B. Coordinate Work with placement of anchors.
C. Coordinate Work for installation of vapor retarder seals.
D. Coordinate Work with installation of windows and adjacent components and materials.
1.10 WARRANTY
A. Section 01 78 36 – Extended Warranties & Bonds Schedule: Product warranties and product
bonds.
B. Furnish five year manufacturer warranty for composite panels.
430-3644 Composite Wall Panels
Public Health and Safety Improvements 07 42 43 - 4
PART 2 PRODUCTS
2.1 COMPOSITE METAL BUILDING PANELS
A. Manufacturers:
1. Mapes Industries, Inc.
2. Citadel Architectural Products, Inc.
3. Laminators, Inc.
2.2 COMPONENTS
A. Exterior Panel: Minimum 0.050 inch pre-finished porcelain stock; as indicated on Drawings;
fitted with continuous gaskets, and filled with sealant.
1. Exposed Exterior Openings where louvers are being removed: Color as selected by
Architect from manufacturer's standard range.
B. Insulated Core: Polyisocyanurate type thermal resistance R of 8 or greater.
C. Thickness as required to support specified loads within specified deflection limitations.
D. Internal and External Corners: Same material, thickness, and finish as exterior sheets; profile
to suit system; shop cut and factory mitered to required angles. Mitered internal corners to be
back braced with pre-coated sheet stock to maintain continuity of profile.
E. Trim, Closure Pieces, Caps, Flashings, Infills: Same material, thickness and finish as exterior
sheets; brake formed to required profiles.
F. Anchors: Manufacturer recommended.
2.3 ACCESSORIES
A. Gaskets: Manufacturer's standard type suitable for use with panel system, permanently
resilient; color as selected by Owner.
B. Sealants: Specified in Section 07 90 00. Manufacturer's standard type suitable for use with
installation of panel system; non-staining, and non-sagging; color as selected.
C. Fasteners: Manufacturer's standard type to suit application; fastener cap same color as
exterior panel.
D. Field Touch-up Paint: As recommended by panel manufacturer.
E. Bituminous Paint: Asphalt base.
430-3644 Composite Wall Panels
Public Health and Safety Improvements 07 42 43 - 5
2.4 FABRICATION
A. Fabrication of component profiles on site is not permitted.
B. Form sections to shape indicated on Drawings, accurate in size, square, and free from
distortion or defects.
C. Panel Profile: Manufacturer’s standard profile as indicated on Drawings.
D. Fabricate corners in one continuous piece with minimum 18 inch returns.
PART 3 EXECUTION
3.1 EXAMINATION
A. Section 01 31 00 - Coordination: Coordination and project conditions.
B. Verify building framing members are ready to receive panel system.
3.2 INSTALLATION
A. Protect panel surfaces in contact with cementitious materials and dissimilar metals with
bituminous paint. Allow to dry prior to installation.
B. Permanently fasten panel system to structural supports; aligned, level, and plumb, within
specified tolerances.
C. Use concealed fasteners wherever possible.
D. Seal and place gaskets to prevent weather penetration. Maintain neat appearance.
3.3 ERECTION TOLERANCES
A. Section 01 35 16 – Remodeling Project Procedures: Tolerances.
B. Maximum Offset From Indicated Alignment Between Adjacent Members Butting or In Line:
1/16 inch.
C. Maximum Variation from Plane or Location Indicated on Drawings: 1/8 inch.
3.4 CLEANING
A. Section 01 74 23 – Final Cleaning: Final cleaning.
B. Remove site cuttings from finish surfaces.
C. Clean and wash prefinished surfaces with mild soap and water; rinse with clean water.
430-3644 Composite Wall Panels
Public Health and Safety Improvements 07 42 43 - 6
END OF SECTION
430-3644 Testing, Adjusting, and Balancing for HVAC
Public Health and Safety Improvements 23 05 93 - 1
SECTION 23 05 93 - TESTING, ADJUSTING, AND BALANCING FOR HVAC
PART 1 GENERAL
1.1 SUMMARY
A. Section Includes:
1. Testing, adjusting and balancing of air systems.
2. Measurement of final operating condition of HVAC systems.
1.2 REFERENCES
A. Associated Air Balance Council:
1. AABC MN-1 - National Standards for Testing and Balancing Heating, Ventilating, and Air
Conditioning Systems.
B. American Society of Heating, Refrigerating and Air-Conditioning Engineers:
1. ASHRAE 111 - Practices for Measurement, Testing, Adjusting and Balancing of Building
Heating, Ventilation, Air-Conditioning and Refrigeration Systems.
C. Natural Environmental Balancing Bureau:
1. NEBB - Procedural Standards for Testing, Adjusting, and Balancing of Environmental
Systems.
D. Testing Adjusting and Balancing Bureau:
1. TABB - International Standards for Environmental Systems Balance.
1.3 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Submittal procedures.
B. Prior to commencing Work, submit proof of latest calibration date of each instrument.
C. Test Reports: Indicate data on forms containing information indicated in Schedules.
D. Field Reports: Indicate deficiencies preventing proper testing, adjusting, and balancing of systems
and equipment to achieve specified performance.
E. Prior to commencing Work, submit report forms or outlines indicating adjusting, balancing, and
equipment data required. Include detailed procedures, agenda, sample report forms.
F. Submit draft copies of report for review prior to final acceptance of Project.
G. Furnish reports in 3-ring binder manuals, complete with table of contents page and indexing tabs,
with cover identification at front and side. Include set of reduced drawings with air outlets and
equipment identified to correspond with data sheets, and indicating thermostat locations.
430-3644 Testing, Adjusting, and Balancing for HVAC
Public Health and Safety Improvements 23 05 93 - 2
1.4 CLOSEOUT SUBMITTALS
A. Section 01 70 00 - Execution and Closeout Requirements: Closeout procedures.
B. Project Record Documents: Record actual locations of flow measuring stations, balancing valves
and rough setting.
C. Operation and Maintenance Data: Furnish final copy of testing, adjusting, and balancing report
inclusion in operating and maintenance manuals.
1.5 QUALITY ASSURANCE
A. Perform Work in accordance with AABC MN-1 National Standards for Field Measurement and
Instrumentation, Total System Balance.
1.6 QUALIFICATIONS
A. Agency: Company specializing in testing, adjusting, and balancing of systems specified in this
section with minimum three years documented experience.
B. Perform Work under supervision of AABC Certified Test and Balance Engineer and registered
professional engineer experienced in performance of this Work and licensed in State of Illinois.
1.7 SEQUENCING
A. Section 01 10 00 - Summary: Work sequence.
B. Sequence balancing between completion of systems tested and Date of Substantial Completion.
1.8 SCHEDULING
A. Section 01 30 00 - Administrative Requirements: Coordination and project conditions.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.1 EXAMINATION
A. Section 01 30 00 - Administrative Requirements: Coordination and project conditions.
B. Verify systems are complete and operable before commencing work. Verify the following:
1. Systems are started and operating in safe and normal condition.
2. HVAC control systems are installed complete and operable.
3. Proper thermal overload protection is in place for electrical equipment.
430-3644 Testing, Adjusting, and Balancing for HVAC
Public Health and Safety Improvements 23 05 93 - 3
4. Final filters are clean and in place. If required, install temporary media in addition to final
filters.
5. Duct systems are clean of debris.
6. Fans are rotating correctly.
7. Fire and volume dampers are in place and open.
8. Air coil fins are cleaned and combed.
9. Access doors are closed and duct end caps are in place.
10. Air outlets are installed and connected.
11. Duct system leakage is minimized.
12. Hydronic systems are flushed, filled, and vented.
13. Pumps are rotating correctly.
14. Proper strainer baskets are clean and in place or in normal position.
15. Service and balancing valves are open.
3.2 PREPARATION
A. Furnish instruments required for testing, adjusting, and balancing operations.
B. Make instruments available to Architect/Engineer to facilitate spot checks during testing.
3.3 INSTALLATION TOLERANCES
A. Air Handling Systems: Adjust to within plus 10% or minus 0% of design.
B. Air Outlets and Inlets: Adjust total to within plus 10% or minus 0% of design to space. Adjust
outlets and inlets in space to within plus 10% or minus 0% of design.
C. Hydronic Systems: Adjust to within plus or minus 10 percent of design.
3.4 ADJUSTING
A. Section 01 70 00 - Execution and Closeout Requirements: Testing, adjusting, and balancing.
B. Verify recorded data represents actual measured or observed conditions.
C. Permanently mark settings of valves, dampers, and other adjustment devices allowing settings to
be restored. Set and lock memory stops.
D. After adjustment, take measurements to verify balance has not been disrupted. If disrupted, verify
correcting adjustments have been made.
E. Report defects and deficiencies noted during performance of services, preventing system balance.
F. Leave systems in proper working order, replacing belt guards, closing access doors, closing doors
to electrical switch boxes, and restoring thermostats to specified settings.
430-3644 Testing, Adjusting, and Balancing for HVAC
Public Health and Safety Improvements 23 05 93 - 4
3.5 AIR SYSTEM PROCEDURE
A. Adjust air handling and distribution systems to obtain required or design supply, return, and
exhaust air quantities.
B. Make air flow rate measurements in main ducts by Pitot tube traverse of entire cross sectional
area of duct.
C. Measure air quantities at air inlets and outlets.
D. Adjust distribution system to obtain uniform space temperatures free from objectionable drafts.
E. Use volume control devices to regulate air quantities only to extent adjustments do not create
objectionable air motion or sound levels. Effect volume control by using volume dampers located
in ducts.
F. Vary total system air quantities by adjustment of fan speeds. Provide sheave drive changes to
vary fan speed. Vary branch air quantities by damper regulation.
G. Provide system schematic with required and actual air quantities recorded at each outlet or inlet.
H. Measure static air pressure conditions on air supply units, including filter and coil pressure drops,
and total pressure across fan. Make allowances for 50 percent loading of filters.
I. Adjust outside air automatic dampers, outside air, return air, and exhaust dampers for design
conditions.
J. Measure temperature conditions across outside air, return air, and exhaust dampers to check
leakage.
K. At modulating damper locations, take measurements and balance at extreme conditions.
L. Measure building static pressure and adjust supply, return, and exhaust air systems to obtain
required relationship between each to maintain approximately 0.05 inches positive static pressure
near building entries.
M. Check multi-zone units for motorized damper leakage. Adjust air quantities with mixing dampers
set first for cooling, then heating, then modulating.
N. For variable air volume system powered units set volume controller to airflow setting indicated.
Confirm connections properly made and confirm proper operation for automatic variable-air-
volume temperature control.
3.6 SCHEDULES
A. Equipment Requiring Testing, Adjusting, and Balancing:
1. Packaged Roof Top Heating/Cooling Units.
2. Air Handling Units.
3. Air Inlets and Outlets.
430-3644 Testing, Adjusting, and Balancing for HVAC
Public Health and Safety Improvements 23 05 93 - 5
4. Variable Refrigerant Flow Units.
B. Report Forms
1. Title Page:
a. Name of Testing, Adjusting, and Balancing Agency
b. Address of Testing, Adjusting, and Balancing Agency
c. Telephone and facsimile numbers of Testing, Adjusting, and Balancing Agency
d. Project name
e. Project location
f. Project Architect
g. Project Engineer
h. Project Contractor
i. Project altitude
j. Report date
2. Summary Comments:
a. Design versus final performance
b. Notable characteristics of system
c. Description of systems operation sequence
d. Summary of outdoor and exhaust flows to indicate building pressurization
e. Nomenclature used throughout report
f. Test conditions
3. Instrument List:
a. Instrument
b. Manufacturer
c. Model number
d. Serial number
e. Range
f. Calibration date
4. Electric Motors:
a. Manufacturer
b. Model/Frame
c. HP/BHP and kW
d. Phase, voltage, amperage; nameplate, actual, no load
e. RPM
f. Service factor
g. Starter size, rating, heater elements
h. Sheave Make/Size/Bore
5. V-Belt Drive:
a. Identification/location
b. Required driven RPM
c. Driven sheave, diameter and RPM
d. Belt, size and quantity
e. Motor sheave diameter and RPM
f. Center to center distance, maximum, minimum, and actual
6. Air Cooled Condenser:
a. Identification/number
b. Location
c. Manufacturer
d. Model number
430-3644 Testing, Adjusting, and Balancing for HVAC
Public Health and Safety Improvements 23 05 93 - 6
e. Serial number
f. Entering DB air temperature, design and actual
g. Leaving DB air temperature, design and actual
h. Number of compressors
7. Cooling Coil Data:
a. Identification/number
b. Location
c. Service
d. Manufacturer
e. Air flow, design and actual
f. Entering air DB temperature, design and actual
g. Entering air WB temperature, design and actual
h. Leaving air DB temperature, design and actual
i. Leaving air WB temperature, design and actual
j. Water flow, design and actual
k. Water pressure drop, design and actual
l. Entering water temperature, design and actual
m. Leaving water temperature, design and actual
n. Saturated suction temperature, design and actual
o. Air pressure drop, design and actual
8. Heating Coil Data:
a. Identification/number
b. Location
c. Service
d. Manufacturer
e. Air flow, design and actual
f. Water flow, design and actual
g. Water pressure drop, design and actual
h. Entering water temperature, design and actual
i. Leaving water temperature, design and actual
j. Entering air temperature, design and actual
k. Leaving air temperature, design and actual
l. Air pressure drop, design and actual
9. Air Moving Equipment:
a. Location
b. Manufacturer
c. Model number
d. Serial number
e. Arrangement/Class/Discharge
f. Air flow, specified and actual
g. Return air flow, specified and actual
h. Outside air flow, specified and actual
i. Total static pressure (total external), specified and actual
j. Inlet pressure
k. Discharge pressure
l. Sheave Make/Size/Bore
m. Number of Belts/Make/Size
n. Fan RPM
430-3644 Testing, Adjusting, and Balancing for HVAC
Public Health and Safety Improvements 23 05 93 - 7
10. Return Air/Outside Air Data:
a. Identification/location
b. Design air flow
c. Actual air flow
d. Design return air flow
e. Actual return air flow
f. Design outside air flow
g. Actual outside air flow
h. Return air temperature
i. Outside air temperature
j. Required mixed air temperature
k. Actual mixed air temperature
l. Design outside/return air ratio
m. Actual outside/return air ratio
11. Duct Traverse:
a. System zone/branch
b. Duct size
c. Area
d. Design velocity
e. Design air flow
f. Test velocity
g. Test air flow
h. Duct static pressure
i. Air temperature
j. Air correction factor
12. Duct Leak Test:
a. Description of ductwork under test
b. Duct design operating pressure
c. Duct design test static pressure
d. Duct capacity, air flow
e. Maximum allowable leakage duct capacity times leak factor
f. Test apparatus
1) Blower
2) Orifice, tube size
3) Orifice size
4) Calibrated
g. Test static pressure
h. Test orifice differential pressure
i. Leakage
13. Air Distribution Test Sheet:
a. Air terminal number
b. Room number/location
c. Terminal type
d. Terminal size
e. Area factor
f. Design velocity
g. Design air flow
h. Test (final) velocity
430-3644 Testing, Adjusting, and Balancing for HVAC
Public Health and Safety Improvements 23 05 93 - 8
i. Test (final) air flow
j. Percent of design air flow
14. Variable Refrigerant Flow Unit:
a. Identification/number
b. Location
c. Service
d. Manufacturer
e. Air flow, design and actual
f. Entering air DB temperature, design and actual
g. Entering air WB temperature, design and actual
h. Leaving air DB temperature, design and actual
i. Leaving air WB temperature, design and actual
j. Refrigerant flow, design and actual
k. Air pressure drop, design and actual
l. Check both Heating and Cooling Modes
END OF SECTION
List of Existing Mammoth Rooftop Units being Replaced.
The replacement units for these ten RTUs are being pre-purchased by the College.
Lincoln Trail Mammoth Units
Williams Hall #1
Serial Number Illegible
CDHEBFP-422-G640-N395-MZ9
Williams Hall #2
SN 11386-02-01
CDHEBFP-422-G640-N395-MZ7
Williams Hall #3
16439-01-01
CDHEBFP-422-G640-N395-MZ7
Williams Hall #4
16439-02-01
CDHEBFP-422-G640-N395-MZ10
Williams Hall #5
Makeup Air Unit
16439-03-01
CEHB-162-G235-325
Olney Mammoth Units
Wattleworth Unit 2
16441-01-01
CLHBP-622-G800-MZ9-2060
Wattleworth Unit 4
16441-02-01
CEHBP-622-G700-MZ7-2060
Wattleworth Unit 5
16441-03-01
CEHBP-622-G800-MZ9-2060
Fitness Center Unit (OC-9)
16441-04-01
DHEBFR-G400-N395-MZ4
Wabash Valley Mammoth Units
Cadaver Unit (WV2)
42625-01
DHEBFRC-131-G256-N100-MUA
2015 DESIGN ARCHITECTS, INC.
F: 618.998.0076
MARION, ILLINOIS
SPRINGFIELD, IL
PH: 618.998.0075
EAST ST. LOUIS, IL
HILLSBORO, IL
ARNOLD, MO
NEOSHO, MO
200 NORTH MARKET ST.
FD FD
2015 DESIGN ARCHITECTS, INC.
F: 618.998.0076
MARION, ILLINOIS
SPRINGFIELD, IL
PH: 618.998.0075
EAST ST. LOUIS, IL
HILLSBORO, IL
ARNOLD, MO
NEOSHO, MO
200 NORTH MARKET ST.
2015 DESIGN ARCHITECTS, INC.
F: 618.998.0076
MARION, ILLINOIS
SPRINGFIELD, IL
PH: 618.998.0075
EAST ST. LOUIS, IL
HILLSBORO, IL
ARNOLD, MO
NEOSHO, MO
200 NORTH MARKET ST.
SEE SECTION 08 80 00
2015 DESIGN ARCHITECTS, INC.
F: 618.998.0076
MARION, ILLINOIS
SPRINGFIELD, IL
PH: 618.998.0075
EAST ST. LOUIS, IL
HILLSBORO, IL
ARNOLD, MO
NEOSHO, MO
200 NORTH MARKET ST.
2015 DESIGN ARCHITECTS, INC.
F: 618.998.0076
MARION, ILLINOIS
SPRINGFIELD, IL
PH: 618.998.0075
EAST ST. LOUIS, IL
HILLSBORO, IL
ARNOLD, MO
NEOSHO, MO
200 NORTH MARKET ST.
2015 DESIGN ARCHITECTS, INC.
F: 618.998.0076
MARION, ILLINOIS
SPRINGFIELD, IL
PH: 618.998.0075
EAST ST. LOUIS, IL
HILLSBORO, IL
ARNOLD, MO
NEOSHO, MO
200 NORTH MARKET ST.
FD FD
2015 DESIGN ARCHITECTS, INC.
F: 618.998.0076
MARION, ILLINOIS
SPRINGFIELD, IL
PH: 618.998.0075
EAST ST. LOUIS, IL
HILLSBORO, IL
ARNOLD, MO
NEOSHO, MO
200 NORTH MARKET ST.
FACILITIES IN THE EXISTING BUILDING AND
INDICATED ON THE DRAWINGS HAVE BEEN TAKEN
FROM EXISTING BUILDING DRAWINGS AND FIELD
INSPECTIONS AT THE PROJECT, BUT ITS
COMPLETE ACCURACY IS NOT GUARANTEED.
CONTRACTOR SHALL VERIFY AND/ OR DETERMINE
EXISTING CONDITIONS INVOLVING HIS WORK IN
THE FIELD
2015 DESIGN ARCHITECTS, INC.
F: 618.998.0076
MARION, ILLINOIS
SPRINGFIELD, IL
PH: 618.998.0075
EAST ST. LOUIS, IL
HILLSBORO, IL
ARNOLD, MO
NEOSHO, MO
200 NORTH MARKET ST.
BALL VALVE
TANK TEMPERATURE
PRESSURE RELIEF
PRESSURE RELIEF
CIRCULATING PUMP
TEMPERATURE &
VALVE
VALVE
FULL PORT
DRAIN
CONTROL
LEGEND
SWITCH
WATER FLOW
TEMPERATURE
GAGE
CHECK VALVE
De-Liming
Tee
EXPANSION
TANK
CO
LD
W
AT
ER
S
UP
PL
Y
HOT WATER
TO FIXTURES
ST
OR
AG
E T
AN
K
AO
S
NOTES:
SY
ST
EM
R
ET
UR
N
TEMPERED
WATER HEATER AND
STORAGE TANK
WALL SEPARATING
1. CONTRACTOR SHALL REMOVE ALL EXISTING PIPING BETWEEN WATER HEATER AND STORAGE
TANK, ALL RECIRCULATING WATER CONNECTIONS AND THERMOSTATIC MIXING VALVE.
2. CONTRACTOR SHALL PROVIDE ALL NEW HOT AND COLD WATER PIPING FROM COLD WATER ENTRY
INTO MECHANICAL CLOSET TO TEMPERED WATER OUTLET FROM THERMOSTATIC MIXING VALVE.
3. ALL NEW PIPING SHALL BE INSULATED WITH 1" CLOSED CELL FOAM PIPE INSULATION.
4. ALL HOT AND COLD WATER PIPING SHALL BE 1-1/2". CONTRACTOR SHALL PROVIDE
REQUIRED FITTINGS TO ADAPT TO EXISTING PIPE SIZES.
5. ALL NEW RECIRCULATED WATER PIPING SHALL BE 3/4".
6. NEW THERMOSTATIC MIXING VALVE SHALL BE LAWLER 802 OR APPROVED EQUAL BY LEONARD OR
WATTS.
7. WATER HEATER AND STORAGE TANK ARE EXISTING AND ARE TO REMAIN.
8. EXPANSION TANK SHALL BE WATTS DETA-30 OR EQUAL BY TACO OR AMTROL.
DATE: 04-01-15
ATTACHMENT
NUMBER:
NUMBER:
ADDENDUM
HR-DA # 430-3644
PROTECTION HEALTH & SAFETY
IMPROVEMENTS 2015
HVAC REPAIR/REPLACEMENT AND OTHER MISC.
GENERAL WORK.
ILLINOIS EASTERN COMMUNITY COLLEGES
2015
LINCOLN TRAIL GYMNASIUM
--
RM-01
FD FD
RS
RL
RS
RL
FACILITIES IN THE EXISTING BUILDING AND
INDICATED ON THE DRAWINGS HAVE BEEN
TAKEN FROM EXISTING BUILDING DRAWINGS
AND FIELD INSPECTIONS AT THE PROJECT, BUT
ITS COMPLETE ACCURACY IS NOT
GUARANTEED. CONTRACTOR SHALL VERIFY
AND/ OR DETERMINE EXISTING CONDITIONS
INVOLVING HIS WORK IN THE FIELD
2015 DESIGN ARCHITECTS, INC.
F: 618.998.0076
MARION, ILLINOIS
SPRINGFIELD, IL
PH: 618.998.0075
EAST ST. LOUIS, IL
HILLSBORO, IL
ARNOLD, MO
NEOSHO, MO
200 NORTH MARKET ST.
FACILITIES IN THE EXISTING BUILDING AND
INDICATED ON THE DRAWINGS HAVE BEEN TAKEN
FROM EXISTING BUILDING DRAWINGS AND FIELD
INSPECTIONS AT THE PROJECT, BUT ITS
COMPLETE ACCURACY IS NOT GUARANTEED.
CONTRACTOR SHALL VERIFY AND/ OR DETERMINE
EXISTING CONDITIONS INVOLVING HIS WORK IN
THE FIELD
2015 DESIGN ARCHITECTS, INC.
F: 618.998.0076
MARION, ILLINOIS
SPRINGFIELD, IL
PH: 618.998.0075
EAST ST. LOUIS, IL
HILLSBORO, IL
ARNOLD, MO
NEOSHO, MO
200 NORTH MARKET ST.
2015 DESIGN ARCHITECTS, INC.
F: 618.998.0076
MARION, ILLINOIS
SPRINGFIELD, IL
PH: 618.998.0075
EAST ST. LOUIS, IL
HILLSBORO, IL
ARNOLD, MO
NEOSHO, MO
200 NORTH MARKET ST.
2015 DESIGN ARCHITECTS, INC.
F: 618.998.0076
MARION, ILLINOIS
SPRINGFIELD, IL
PH: 618.998.0075
EAST ST. LOUIS, IL
HILLSBORO, IL
ARNOLD, MO
NEOSHO, MO
200 NORTH MARKET ST.
TWS TWS
/ / / / / / / / / / / / / / / / / / / / /
ST ST
ST ST
2015 DESIGN ARCHITECTS, INC.
F: 618.998.0076
MARION, ILLINOIS
SPRINGFIELD, IL
PH: 618.998.0075
EAST ST. LOUIS, IL
HILLSBORO, IL
ARNOLD, MO
NEOSHO, MO
200 NORTH MARKET ST.
RP-001
STORAGE
107
UTILITY
108
MEN'S
RESTROOM
109
WOMEN'S
RESTROOM
105
UTILITY
110
ENTRY
104
MULTI-PURPOSE
103
MULTI-PURPOSE
102
2015 DESIGN ARCHITECTS, INC.
F: 618.998.0076
MARION, ILLINOIS
SPRINGFIELD, IL
PH: 618.998.0075
EAST ST. LOUIS, IL
HILLSBORO, IL
ARNOLD, MO
NEOSHO, MO
200 NORTH MARKET ST.
RP-101
SCALE:
NORTH
1/4" = 1'-0"
PLUMBING PLAN
GENERAL NOTES:
2015 DESIGN ARCHITECTS, INC.
F: 618.998.0076
MARION, ILLINOIS
SPRINGFIELD, IL
PH: 618.998.0075
EAST ST. LOUIS, IL
HILLSBORO, IL
ARNOLD, MO
NEOSHO, MO
200 NORTH MARKET ST.
SCALE:
NORTH
1/4" = 1'-0"
PLUMBING DEMOLITION PLAN
GENERAL NOTES: