Marshall Building, London Bespoke formwork delivers unique architectural concrete requirements Key benefits: Formwork designed for multiple reuse Flexible tie positioning Seamless climbing reduced material on ground Formwork Scaffolding Engineering | www.peri.ltd.uk

Bespoke formwork delivers unique architectural concrete ...1bd90837-5f26-409b-a492-cc3736cb98ca/marshall-building...Bespoke formwork delivers unique architectural concrete requirements

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Bespoke formwork delivers unique architectural concrete ...1bd90837-5f26-409b-a492-cc3736cb98ca/marshall-building...Bespoke formwork delivers unique architectural concrete requirements

Marshall Building, London

Bespoke formwork delivers uniquearchitectural concrete requirementsKey benefits: Formwork designed for multiple reuse

Flexible tie positioning

Seamless climbing reduced material on ground

Formwork Scaffolding Engineering | www.peri.ltd.uk

The project at a glance

The Marshall Building at 44 Lincoln Inn Fields will be the newest addition to the London School of Economics and Political Science campus, boasting an exposed concrete façade and concrete interior on the ground floor.

Space has been a challenging factor through-out its construction. However, this has been combated with efficient climbing sequences and prefabricated formwork.

Page 2: Bespoke formwork delivers unique architectural concrete ...1bd90837-5f26-409b-a492-cc3736cb98ca/marshall-building...Bespoke formwork delivers unique architectural concrete requirements

Contact us by email on [email protected] or call 01788 861 600

What was the challenge?

The sloped ground floor slab made reusing the form-work shutters more complex than initially imagined.

In addition, the beams at each intersection had to be poured at the same time. This meant that the tightest possible joints and connections between each panel had to be achieved to avoid any movement.

How did we help?

In partnership with Getjar, we were able to work around the changes in ground conditions. Temporary concrete plinths were supplied by the customer at ground floor level, enabling us to elevate and align our VARIO formwork shutters from one beam to the next.

By supplying additional walers to the back of the formwork shutters, we could strengthen the connec-tion between each one and produce the specified tie pattern.

What did the customer need?

On this project, an architectural finish was important, especially for the concrete trees, which feature on the ground floor and again on the second floor. Due to the unusual shape of the beams on these struc-tures, which taper towards the end, a custom and robust formwork solution had to be designed to take the pressure acting in all directions.

A formwork and climbing solution was also required for the building’s two exposed box cores. The climb-ing solution had to accommodate changes in the geometry of the main core.

Climbing sequences on the main core

We used ply lined TRIO formwork with our CB 240 climbing system and generous working platforms to climb the core’s exterior and deliver a good finish. The TRIO system was ideal, as panels could be rearranged quickly to accommodate the change in geometry that occurs between the lower floors.

Due to the straightforward climbing sequence for the inner core walls, the panels and platforms were cy-cled on RCS-G (gallows). Using this system allowed all of the shutters to be lifted in tandem.

With the material in continuous operation, the core could progress ahead of the floors. This also kept the ground clear of additional material, as the panels did not require reassembly – a huge benefit on an extremely congested site.

Customer: Getjar

Main Contractor: MACE

Developer: LSE

Project type: Private, Non-Housing

Products and Services: VARIO panel formwork, TRIO panel formwork, CB 240 climbing system, RCS-G climbing system