Design Thinking | Learning Module | Dept. of Architecture | Universitas Islam Indonesia| Ilya F Maharika
BERPIKIR PERANCANGANDESIGN THINKING
DESIGN PROCESSDESIGN MAP
DO WE REALLY NEED DESIGN
MAP?
WEEK 3
Thursday, October 7, 2010
7/24/2019 BERPERAN.week3.DesignProcess.small
2/42
Design Thinking | Learning Module | Dept. of Architecture | Universitas Islam Indonesia| Ilya F Maharika
BERPIKIR PERANCANGANDESIGN THINKING
Apakah yang dimaksuddengan proses disain?
Thursday, October 7, 2010
7/24/2019 BERPERAN.week3.DesignProcess.small
3/42
Design Thinking | Learning Module | Dept. of Architecture | Universitas Islam Indonesia| Ilya F Maharika
BERPIKIR PERANCANGANCLASS WORKSHOP
! Presentasikan proses perancangan para disainer yang telahdilakukan!
! Gambarkan peta disain proses itu! Bagaimana dengan
! Beri gambaran proses perancangan yang sudah pernah andalakukan dan bandingkan dengan peta disain proses itu!
! Apakah proses disain sama dengan gambaran peta disain?
Thursday, October 7, 2010
7/24/2019 BERPERAN.week3.DesignProcess.small
4/42
Design Thinking | Learning Module | Dept. of Architecture | Universitas Islam Indonesia| Ilya F Maharika
BERPIKIR PERANCANGANDESIGN THINKING
Apakah yang dimaksuddengan peta proses disain?
Thursday, October 7, 2010
7/24/2019 BERPERAN.week3.DesignProcess.small
5/42
http://www.hku.hk/bse/interdisciplinary/bs-designprocess.pdf
DESIGN PROCESSDESIGN PROCESS AND DESIGN MAP
Thursday, October 7, 2010
http://www.hku.hk/bse/interdisciplinary/bs-designprocess.pdfhttp://www.hku.hk/bse/interdisciplinary/bs-designprocess.pdf7/24/2019 BERPERAN.week3.DesignProcess.small
6/42
DESIGN PROCESSDESIGN PROCESS AND DESIGN MAP
Thursday, October 7, 2010
7/24/2019 BERPERAN.week3.DesignProcess.small
7/42
DESIGN PROCESSDESIGN PROCESS AND DESIGN MAP
INTERNATIONAL CONFERENCE ON ENGINEERING DESIGN ICED 99MUNICH, AUGUST 24-26, 1999
MAPPING THE EARLY STAGES OF THE DESIGN PROCESS - A COMPARISON
BETWEEN ENGINEERING AND CONSTRUCTIONSebastian Macmillan, John Steele, Simon Austin, Robin Spence, Paul Kirby
available at http://www.eclipse-research.co.uk/Conference%20papers/MDP_ICED
%2099.pdf
Thursday, October 7, 2010
http://www.eclipse-research.co.uk/Conference%20papers/MDP_ICED%2099.pdfhttp://www.eclipse-research.co.uk/Conference%20papers/MDP_ICED%2099.pdfhttp://www.eclipse-research.co.uk/Conference%20papers/MDP_ICED%2099.pdfhttp://www.eclipse-research.co.uk/Conference%20papers/MDP_ICED%2099.pdf7/24/2019 BERPERAN.week3.DesignProcess.small
8/42
http://www.localhiddenvariable.com/ciid/interaction-design-process-diagram/
DESIGN PROCESSDESIGN PROCESS AND DESIGN MAP
Thursday, October 7, 2010
http://www.localhiddenvariable.com/ciid/interaction-design-process-diagram/http://www.localhiddenvariable.com/ciid/interaction-design-process-diagram/7/24/2019 BERPERAN.week3.DesignProcess.small
9/42
http://www.sidoruk.com/blog/index.php?entry=entry060503-180428
DESIGN PROCESSDESIGN PROCESS AND DESIGN MAP
Thursday, October 7, 2010
http://www.sidoruk.com/blog/index.php?entry=entry060503-180428http://www.sidoruk.com/blog/index.php?entry=entry060503-1804287/24/2019 BERPERAN.week3.DesignProcess.small
10/42
DESIGN PROCESSDESIGN PROCESS AND DESIGN MAP
Thursday, October 7, 2010
7/24/2019 BERPERAN.week3.DesignProcess.small
11/42
http://www.xostudy.com/xos_Process_Diagram.
DESIGN PROCESSDESIGN PROCESS AND DESIGN MAP
Thursday, October 7, 2010
http://www.xostudy.com/xos_Process_Diagramhttp://www.xostudy.com/xos_Process_Diagramhttp://www.xostudy.com/xos_Process_Diagram7/24/2019 BERPERAN.week3.DesignProcess.small
12/42
http://www.uml.org.cn/softwareprocess/200902193.asp
DESIGN PROCESSDESIGN PROCESS AND DESIGN MAP
Thursday, October 7, 2010
http://www.uml.org.cn/softwareprocess/200902193.asphttp://www.uml.org.cn/softwareprocess/200902193.asphttp://www.uml.org.cn/softwareprocess/200902193.asp7/24/2019 BERPERAN.week3.DesignProcess.small
13/42
http://www.itcon.org/1997/1/paper.htm
DESIGN PROCESSDESIGN PROCESS AND DESIGN MAP
Thursday, October 7, 2010
http://www.itcon.org/1997/1/paper.htmhttp://www.itcon.org/1997/1/paper.htm7/24/2019 BERPERAN.week3.DesignProcess.small
14/42
http://cgi.stanford.edu/~class-cee115-1076/wiki_win08/index.php?n=Projects.Assignment
DESIGN PROCESSDESIGN PROCESSAND DESIGN MAP
Thursday, October 7, 2010
http://cgi.stanford.edu/~class-cee115-1076/wiki_win08/index.php?n=Projects.Assignmenthttp://cgi.stanford.edu/~class-cee115-1076/wiki_win08/index.php?n=Projects.Assignmenthttp://cgi.stanford.edu/~class-cee115-1076/wiki_win08/index.php?n=Projects.Assignment7/24/2019 BERPERAN.week3.DesignProcess.small
15/42
DESIGN PROCESSDESIGN PROCESS AND DESIGN MAP
Thursday, October 7, 2010
7/24/2019 BERPERAN.week3.DesignProcess.small
16/42
Design Thinking | Learning Module | Dept. of Architecture | Universitas Islam Indonesia| Ilya F Maharika
BERPIKIR PERANCANGANDESIGN THINKING
Benarkah kita memerlukanpeta proses disain?
Thursday, October 7, 2010
7/24/2019 BERPERAN.week3.DesignProcess.small
17/42
DESIGN PROCESS http://www.h-associates.net/http://www.haeahn.co.kr/
http://www.bustler.net/index.php/article/chung-nam_government_complex/
Thursday, October 7, 2010
http://www.bustler.net/index.php/article/chung-nam_government_complex/http://www.bustler.net/index.php/article/chung-nam_government_complex/http://www.haeahn.co.kr/http://www.haeahn.co.kr/http://www.h-associates.net/http://www.h-associates.net/7/24/2019 BERPERAN.week3.DesignProcess.small
18/42
DESIGN PROCESS
http://www.bustler.net/index.php/article/chung-nam_government_complex/
http://www.h-associates.net/
http://www.haeahn.co.kr/
Thursday, October 7, 2010
http://www.haeahn.co.kr/http://www.haeahn.co.kr/http://www.h-associates.net/http://www.h-associates.net/http://www.bustler.net/index.php/article/chung-nam_government_complex/http://www.bustler.net/index.php/article/chung-nam_government_complex/7/24/2019 BERPERAN.week3.DesignProcess.small
19/42
DESIGN PROCESS
Thursday, October 7, 2010
7/24/2019 BERPERAN.week3.DesignProcess.small
20/42
DESIGN PROCESS
Thursday, October 7, 2010
7/24/2019 BERPERAN.week3.DesignProcess.small
21/42
DESIGN PROCESS
http://www.runebadone.com/
Thursday, October 7, 2010
http://www.runebadone.com/http://www.runebadone.com/7/24/2019 BERPERAN.week3.DesignProcess.small
22/42
DESIGN PROCESS
http://www.runebadone.com/
Thursday, October 7, 2010
http://www.runebadone.com/http://www.runebadone.com/7/24/2019 BERPERAN.week3.DesignProcess.small
23/42
DESIGN PROCESS
http://www.runebadone.com/
Thursday, October 7, 2010
http://www.runebadone.com/http://www.runebadone.com/7/24/2019 BERPERAN.week3.DesignProcess.small
24/42
DESIGN PROCESS
http://www.runebadone.com/
Thursday, October 7, 2010
http://www.runebadone.com/http://www.runebadone.com/7/24/2019 BERPERAN.week3.DesignProcess.small
25/42
RIBA STAGES OF WORK
Work Stage A: Inception
Work Stage B: Feasibility
Work Stage C: Outline Proposals
Work Stage D: Scheme Design Work Stage E: Detail Design
Work Stage F & G: Prepare production information &
bills of quantities
Work Stage H & J: Tender Action & Project Planning Work Stage K: Operations on site: report work
Work Stage L: Operations on site: record dwg
Thursday, October 7, 2010
7/24/2019 BERPERAN.week3.DesignProcess.small
26/42
WORK STAGE A:
INCEPTION
develop the brief in consultation with the client
(yourself) report feasibility, including budget give advice on how to proceed visit the site and give initial appraisal
advice on the need for other consultants and thescope of their services
advise on the need for any specialist work.
Thursday, October 7, 2010
7/24/2019 BERPERAN.week3.DesignProcess.small
27/42
WORK STAGE B:
FEASIBILITY
Carry out any studies which may beneeded to establish feasibility
review alternative design andconstruction approaches and costimplications
advise on statutory approvals needed,
including health & safety outline a timetable for the project.
Thursday, October 7, 2010
7/24/2019 BERPERAN.week3.DesignProcess.small
28/42
WORK STAGE C: OUTLINE PROPOSALS
prepare outline (sketch) proposals for preliminaryapproval.
Thursday, October 7, 2010
7/24/2019 BERPERAN.week3.DesignProcess.small
29/42
WORK STAGE D: SCHEME DESIGN
develop a scheme design following discussions aroundstage C
liaise with any other consultants and advise wheretheir work affects programme & budget
make a cost estimate enable agreements over spatial arrangement, materials
and appearance
prepare and submit a planning application (note noguarantees can be given that this can be obtained).
Thursday, October 7, 2010
7/24/2019 BERPERAN.week3.DesignProcess.small
30/42
WORK STAGE E: DETAIL DESIGN
finalise detail design including co-ordination withother consultants and suppliers and integration of
materials & sub-contracted work.
cost checks where appropriate advise where appropriate on the CDM regulations prepare and submit Building Regulations Application
and any other statutory requirements
negotiate as necessary on the latter.
Thursday, October 7, 2010
7/24/2019 BERPERAN.week3.DesignProcess.small
31/42
WORK STAGE F & G: PREPARE PRODUCTION
INFORMATION & BILLS OF QUANTITIES
Drawings, schedules & specification, provide
information to the Quantity Surveyor (if used) forbills of quantities.
complete information to enable contractors totender.
Thursday, October 7, 2010
WORK STAGE H & J TENDER ACTION &
7/24/2019 BERPERAN.week3.DesignProcess.small
32/42
WORK STAGE H & J: TENDER ACTION &
PROJECT PLANNING
Advise on a list of tenderers issue tender documents to agreed list of contractors receive tenders (with client presence if required), advise
on results and contractor appointment
OR arrange a price to be negotiated with onecontractor.
prepare the building contract and arrange signatures.
Thursday, October 7, 2010
7/24/2019 BERPERAN.week3.DesignProcess.small
33/42
WORK STAGE K: OPERATIONS ON SITE
Administer the terms of the building contract duringwork on site
visit the site at intervals to inspect the progress andquality of the work make periodic financial reports to the client including
any cost variations .
Thursday, October 7, 2010
WORK STAGE L OPERATIONS ON SITE
7/24/2019 BERPERAN.week3.DesignProcess.small
34/42
WORK STAGE L: OPERATIONS ON SITE
Administer the terms of the contract related tocompletion of the work
give general guidance on maintenance provide record drawings as required.
Thursday, October 7, 2010
WORK STAGE L OPERATIONS ON SITE
7/24/2019 BERPERAN.week3.DesignProcess.small
35/42
WORK STAGE L: OPERATIONS ON SITE
Administer the terms of the contract related tocompletion of the work
give general guidance on maintenance provide record drawings as required.
Thursday, October 7, 2010
BERPIKIR PERANCANGAN
7/24/2019 BERPERAN.week3.DesignProcess.small
36/42
Design Thinking | Learning Module | Dept. of Architecture | Universitas Islam Indonesia| Ilya F Maharika
BERPIKIR PERANCANGANDESIGN THINKING
Epilog
Thursday, October 7, 2010
PROSES DISAIN
7/24/2019 BERPERAN.week3.DesignProcess.small
37/42
PROSES DISAIN
SYNTHESIS
ANALYSIS
INSTRUCTION
Pemahaman pada umumnya sebuah proses disain
EVALUATION
Thursday, October 7, 2010
PROSES DISAIN
7/24/2019 BERPERAN.week3.DesignProcess.small
38/42
SYNTHESIS
ANALYSIS
INSTRUCTION
EVALUATION
Proses lompatan kembali yang ternyata inheren
PROSES DISAIN
Thursday, October 7, 2010
PROSES DISAIN
7/24/2019 BERPERAN.week3.DesignProcess.small
39/42
GENERATOR CONJECTURE ANALYSIS
Peta versi Darke, 1978
PROSES DISAIN
Thursday, October 7, 2010
BERPIKIR PERANCANGAN
7/24/2019 BERPERAN.week3.DesignProcess.small
40/42
Design Thinking | Learning Module | Dept. of Architecture | Universitas Islam Indonesia| Ilya F Maharika
BERPIKIR PERANCANGANDESIGN THINKING
Apa yang dimaksud dengan
masalah disain?
Apa hubungannya dengan
proses disain?
Thursday, October 7, 2010
DESIGN PROCESS
7/24/2019 BERPERAN.week3.DesignProcess.small
41/42
Minggu depan:download XMind!
DESIGN PROCESSDESIGN PROCESS AND DESIGN MAP
Thursday, October 7, 2010
REFERENSI UTAMA
7/24/2019 BERPERAN.week3.DesignProcess.small
42/42
REFERENSI UTAMAREFERENCE
Lawson, B. Bagaimana Cara Berpikir Disainer, terjemahan
dari How Designer Think, The Architectural Ltd. 1980,
Yogyakarta, Jalasutra, 2007