Upload
trankiet
View
216
Download
3
Embed Size (px)
Citation preview
1
BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION
LUCKNOW
Petition No. 401/06
IN THE MATTER OF: Approval of ARR and determination of tariff for
FY 2005-06, 2006-07 and 2007-08.
AND
IN THE MATTER OF: UP Jal Vidyut Utpadan Nigam Ltd.
12th Floor, Shakti Bhawan Extn.
14, Ashok Marg,
Lucknow
:Petitioner
Versus
1. U.P. Power Corporation Ltd., 7th Floor, Shakti Bhawan, 14,Ashok Marg,
Lucknow.
2. Madhyanchal Vidyut Vitaran Nigam Ltd., Prag Narain Road, Lucknow.
3. Poorvanchal Vidyut Vitaran Nigam Ltd., 132 KV S/s, Bhikari Vidyut Nagar,
Varanasi.
4. Paschimanchal Vidyut Vitaran Nigam Ltd., Victoria Park, Meerut.
5. Dakshinaanchal Vidyut Vitaran Nigam Ltd.,Vidyut Bhawan, Gailana Road, Agra
6. Kanpur Electric Supply Co. Ltd., KESA House, Kanpur.
7. Noida Power Company Ltd., Commercial Complex, H-Block, Alpha-II, Sector,
Greater Noida City.
:Respondents
2
ORDER
(Date of hearing 30.11.06, 8.1.07)
1 Background
1.1 Development of Regulatory Framework in Uttar Pradesh
The reforms in the power sector of Uttar Pradesh started with the enactment of Uttar
Pradesh Electricity Reforms Act, 1999 (UP Act No. 24 of 1999, herein after referred to
as the Reforms Act). Subsequently, Uttar Pradesh Electricity Reforms Transfer
Scheme, 2000 (hereinafter referred to as the Transfer Scheme) was notified according
to the provisions of sub-Sections (1) and (2) of Section 23 of the Reforms Act vide
notification No. 149/P-1/2000-24, Lucknow, January 14, 2000. Uttar Pradesh State
Electricity Board (UPSEB) was unbundled into three different entities, Uttar Pradesh
Power Corporation Limited (UPPCL), Uttar Pradesh Rajya Vidyut Utpadan Nigam
Limited (UPRVUNL) and Uttar Pradesh Jal Vidyut Nigam Limited (UPJVNL).
Uttar Pradesh Power Corporation Limited (UPPCL) was vested with the
responsibility of transmission and distribution of electricity. Uttar Pradesh Rajya
Vidyut Nigam Limited (UPRVUNL) was vested with the responsibility of generation
and sale of electricity from the thermal generating stations acquired by it through
Transfer Scheme. Similarly, Uttar Pradesh Jal Vidyut Nigam Limited (UPJVNL) was
vested with the responsibility of generation and sale of electricity from the hydro
generating assets of erstwhile UPSEB.
The power sector in India went through major change with the enforcement of the
Electricity Act 2003 w.e.f.10th June 2003. This act repealed all the erstwhile Electricity
Acts in the country viz. Indian Electricity Act, 1910 (9 of 1910), The Electricity
(Supply) Act, 1948 (54 of 1948) and the Electricity Regulatory Commissions Act, 1998
(14 of 1998).
Section 61 of EA 2003 requires the State Electricity Regulatory Commission to notify
terms and conditions for determination of tariff for generation, transmission and
3
distribution in the state. Section 86 of the Act mandates the Electricity Regulatory
Commission to determine tariff, inter alia, in respect of generating companies.
In exercise of power conferred under Section 181 read with provisions of the Section
61 of EA 2003, UPERC notified the Uttar Pradesh Electricity Regulatory Commission
(Terms and Conditions of Generation Tariff) Regulations, 2004 (hereinafter referred
to as Generation Regulations) effective from 18.6.05, the date of notification, for three
years.
Also under provision of Section 181 read with Section 9, 61, 86(1)(a), 86(1)(b) and
86(1)(e) of EA, 2003, the Commission issued another set of Regulations on 23rd March
2006, namely, Uttar Pradesh Electricity Regulatory Commission (Terms and
Conditions for Supply of Power and Fixation of Tariff for sale of power from Captive
Generating Plants, Co-generation, Renewable Sources of Energy and Other Non-
Conventional Sources of Energy based Plants to a Distribution Licensee) Regulations,
2005. These sets of regulations have been made effective from 28th July 2005 for a
period of five years unless ruled differently by the Commission. In these regulations
small hydro stations were defined as renewable sources of generation.
1.2 Background of Tariff Application by Uttar Pradesh Jal Vidyut Nigam
Limited
Uttar Pradesh Jal Vidyut Nigam Limited, an entity registered under the Indian
Companies Act 1956, is engaged in the business of hydro generation and sale of
electricity.
On 20th April 2005, the Petitioner was directed by the Commission to file a tariff
petition. On request, the Commission allowed the Petitioner to file tariff petition by
31st July 2005 and on subsequent request, further extension was granted till 30th
August 2005. In the meeting of Coordination Forum, held on 20th July 2006, the
Petitioner was again reminded to file tariff petition. This was in spite of the fact that
the Petitioner was under statutory obligation to have filed the petition in compliance
to the Generation Regulation. The Commission again wrote a letter to UPJVNL on
4
11th August 2006 and directed it to file its tariff petition. But it preferred to seek
another extension up to 20.9.06. The time was allowed.
After such an inordinate delay UPJVNL filed tariff petition on 06.10.2006, but only
for the FY 2006-07. Whereas UPERC (Terms and Conditions of Generation Tariff)
Regulations, 2004, which came into effect on 18th June 2005, required the Petitioner to
file petition for three years i.e. FY 2005-06 through FY 2007-08. The Commission
noted with dismay that the Petitioner was oblivious to its statutory duty of filing a
complete tariff petition as well as to its commercial interest.
The Commission heard the Petitioner on 30.11.06 and passed an order on 15th
December 2006 directing the Petitioner to submit tariff petition for the financial years
FY 2005-06 and FY 2007-08 in compliance of the provision made in the Generation
Regulations 2004. In this order the Commission also directed UPJVNL to submit
complete details in respect of its fixed assets, depreciation, loan, O&M and equity.
UPJVNL sought extension till 31st January 2007 for compliance of the order. The
matter was heard on 8.1.07 and the Commission, by Order dt. 9.1.07, allowed the
Petitioner to comply with order dt.15.12.06 latest by 24.1.07. Tariff computation for
FY-06 and FY 08 was finally filed on 18.1.07. Other information as sought (in Order
dt.15.12.06) were filed on 23rd January 2007.
Section 64 of EA, 2003, provides that the Commission shall issue a tariff order by
accepting the tariff application with such modifications or such condition as may be
specified in order or reject the application for reasons recorded in writing.
It may be noted that Generation Regulation has been framed by the Commission
after providing due opportunity to all interested parties to express their views and
these regulations are binding on the parties concerned. Under these regulations, the
Commission shall admit the petition for determination of tariff after prudence check.
Therefore, the input data considered by the Petitioner, for tariff proposal, shall be
subject to prudence check as per the provisions of the said regulations, Power
Purchase Agreements (PPA) signed with distribution licensee and past orders passed
by the Commission.
5
1.3 Salient Features of the Petition
This petition seeks approval of tariff in respect of the generating stations under the
control of the Petitioner including canal based generating stations. It is stated that
prior to 14-01-2000, the date of reorganization of UPSEB, there was no power
purchase agreement existing for sale of electricity from Petitioner’s generating
stations until MOU dated 14-01-2000 and 08-03-2005 were signed. A supplementary
agreement dated 16-07-2005 has also been signed in consideration of change in
capital structure capturing the effect of the Transfer Scheme 25th Jan 2001.
The petition states that the tariffs, for years FY 2001-02 to 2004-05, have been
determined by the Commission on the petitions filed by UPPCL and the tariff
proposal for the FY 2005-06 was also sent to UPPCL for filing. It is stated that the
tariff proposal for large generating plants are in accordance with UPERC (Terms and
Conditions of Generation Tariff) Regulations, 2004 and the tariff proposal of canal
based plants is based on “Uttar Pradesh Electricity Regulatory Commission (Terms
and Conditions for Supply of Power and Fixation of Tariff for sale of power from
Captive Generating Plants, Co-generation, Renewable Sources of Energy and Other
Non-Conventional Sources of Energy based Plants to a Distribution Licensee)
Regulations, 2005, dated 23-03-2006 (hereinafter referred to as CNCE Regulations).
There is an outstanding receivable of Rs. 799.00 Cr. from UPPCL as on July, 06. The
Petitioner has prayed to approve the tariff proposal and sought direction to
Respondent no.1 to make full payment.
The Petitioner has also brought in an old issue pertaining to tariff determination for
year 2003-04. It is stated that total cost of energy in that year was Rs. 88.61 Crores due
to impact of liability towards pension and GPF assigned to it by GoUP under
Revised Transfer Scheme. It is stated that the Commission approved only Rs. 53.20
Crores based on capital structure made on the basis of provisional Transfer Scheme.
The Petitioner has prayed to allow Rs. 29.84 Crores in the present tariff, the gap left
out as consequence of above.
6
Regarding change in equity, the Petitioner has stated that Rs. 352.59 Cr. is the equity
against the work in progress and remaining Rs. 19.59 Cr. against the plants owned by
the Petitioner at present. About interest on loan, it was clarified that the lending rate
was at 15 percent at the time of grant of loan by L.I.C.
1.4 Assets of Uttar Pradesh Jal Vidyut Nigam Limited
UPJVNL, in its application, has provided a description on the evolution of UPJVNL
vis-à-vis the structural changes that occurred in the power sector in the state of Uttar
Pradesh subsequent to unbundling of the erstwhile UPSEB. It had to undergo further
restructuring due to reorganization of the state of Uttar Pradesh into Uttranchal and
rest of the Uttar Pradesh. Prior to this bifurcation, all the assets of hydro generation
were under the control of Uttar Pradesh Jal Vidyut Nigam Limited. On
reorganisation of the State, the generating assets falling under the geographical
domain of Uttaranchal were vested in a new company, the Uttaranchal Jal Vidyut
Nigam Limited with effect from 9.11.01.
Vide the Transfer Scheme, all the hydel generating assets of erstwhile UPSEB were
transferred to UPJVNL with aggregate generating capacity of 1494.35 MW, which
included, abandoned hydro projects – Palra (3 X 0.2 MW) and Sumera (2 X 0.6 MW).
In addition to these power stations, two projects under construction were also
transferred to UPJVNL – Maneri Bhali Stage II (4 X 76 MW) and Lakhwar Vyasi (3 X
100 + 2 X 60 MW) in the form of Capital Works in Progress (CWIP). As on 31.3.1999
the values of assets and liabilities transferred to UPJVNL were:
Gross Fixed Assets Rs. 927.42 Crores
Total Long-Term Debt Rs. 866.04 Crores
Equity Rs. 182.59 Crores
Uttar Pradesh Electricity Reforms Transfer Scheme, 2000 was finalised vide
notification no. 348/P-1/2001-24, Lucknow, dated 25th January 2001, according to
the provisions of Section 23 of Reforms Act (read with clause 9 of the Transfer
Scheme vide dated 14th January 2000) and notification no. 183(2)/P-1/2001-24 dated
13th January 2001 of Govt. of Uttar Pradesh.
7
According to the revised and final Transfer Scheme, the assets and liabilities of
UPJVNL, as on 14.1.2000 stood as:
Gross Fixed Assets Rs. 943.38 Crores
Long-Term Debts Rs. 403.18 Crores
Equity Rs. 372.18 Crores
On reorganisation of the State of UP and formation of Uttarnchal, assets, liabilities
and control in respect of hydro generating stations located in Uttranchal were vested
in Uttarnchal Jal Vidyut Nigam Limited (UJVNL) with effect from 9th Nov, 2001. As a
consequence, the Petitioner was left with the following hydro generating assets:
Table 1.4-1 Generating Stations of UPJVNL
Rihand 6 X 50 MW
Obra (Hydro) 3 X 33 MW
Matatila 3 X 10 MW
Large Power Stations
Khara 3 X 24 MW
Nirgazini 2 X 2.5 MW
Chitaura 2 X 1.5 MW
Salawa 2 X 1.5 MW
Upper Ganga Canal
power Stations
Bhola Power Station 4 X 0.375 + 2 X 0.6 MW
Belka 2 X 1.5 MW
Babail 2 X 1.5
Under Construction
Power Stations
Sheetla 3 X 1.2 MW
TOTAL 526.1 MW
Ministry of Power, Govt. of India, vide notification no. 42/7/2000 R&R (Vol – III)
dated 2nd September 2005, has transferred LIC loan liability of Rs. 352.59 crores, taken
8
for Maneri Bhali Stage – II project to Uttaranchal. As a consequence of which, the
total loan liability of UPJVNL, which stood at Rs.403.18 Cr. as on 14.1.00, has reduced
to Rs. 50.59 Cr. w.e.f. 2nd Sept, 2005.
2 Annual Revenue Requirement of Uttar Pradesh Jal Vidyut
Nigam Limited
The Jal Vidyut Nigam submitted its first application for tariff on 6th October 2006.
This tariff application was only for the FY 2006-07, whereas the Uttar Pradesh
Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations
2004 required that the Petitioner should submit an application for multi-year tariff
covering the financial years FY 2005-06 through FY 2007-08. Accordingly the
Commission issued an order on 15th December 2006 directing the Petitioner to file its
petition for all the years covered under the multi year tariff (MYT) regulations. After
seeking time extensions, the Petitioner finally submitted their MYT application on
18th January 2007. In this application, the Petitioner has modified the original
application for FY 2006-07 vide affidavit dt.15.1.07.
2.1 Tariff of Large & UGC Power Stations of UPJVNL
The energy charges put up for approval in affidavit dt. 15.1.07 are summarised in the
table below.
Table 2.1-1 Summary of Tariff Application of UPJVNL
All figures in Rs. Crores
Power Station FY 2005-06 FY 2006-07 FY 2007-08
Rihand 16.96 17.76 18.78
Obra (H) 7.94 8.27 8.63
Matatila 3.83 3.85 4.02
Khara 43.01 42.04 41.11
U.G.C. 4.15 4.37 4.64
9
Total 75.89 76.29 77.18
As per submissions of the Petitioner:
(i) Assets: All assets of UPSEB have been created through loans or internal
generation of resources. While transferring these assets to successor,
UPJVNL, GoUP determined the value of Gross Fixed Assets (GFA)
comprising of debt and equity in the Transfer Scheme, vide final transfer
order no. 348/p-1/01-04 dt. 25.1.01. NFA values have been arrived at in
the notification by subtracting accumulated depreciation.
(ii) Debt equity ratio of 70:30 of GFA is stated to have been taken as per
UPERC (Terms & Conditions of Generation Tariff) Regulations, 2004. But
for tariff computation only NFA in relation with GFA has been examined
and amount of debt and equity fixed. Since 2.9.05, all financing of
additional capitalization has been stated to be in the ratio of 70:30.
(iii) Loan: MoP, Govt. of India, vide notification no.42/7/2000 R&R (Vol.III)
dt. 2.9.05, transferred loan liability of Rs. 352.59 Cr. out of total loan
liability of Rs.403.18 Cr. to Uttaranchal Vidyut Nigam Ltd. A loan amount
of Rs.99.32 Cr. has been taken for computation for tariff for FY 2005-06,
whereas prior to 2.9.05 the outstanding loans at the end of FY 2003-04 was
Rs.64.56 Cr. (as per audited books of accounts) Rate of interest on loan has
been taken as 14.29%.
(iv) Equity: The Transfer Scheme of GOUP did not allocate any portion of
equity or debt to any project. UPPCL allocated substantial portion of
equity to capital works in progress and Rs.19.59 Cr. distributed as equity
amongst the projects in operation 14.1.2000. The opening equity of Rs.
112.21 Cr. has been considered for FY 2005-06. The rate of return on
equity has been taken as 14%.
(v) Depreciation: The Petitioner has considered depreciation @2.57% for all
its generating stations.
(vi) Working Capital: In the calculation of working capital, maintenance
spares have been taken @1 % of GFA for 2005-06 and escalated @ 4% per
year up to FY-2007-08. The calculation of 2 months receivables has not
been shown. The rate of interest on working capital has been taken at
10
15%, same as the rate of surcharge on delayed payment mentioned in
retail tariff.
Noida Power Company Ltd. submitted its comments vide letter, no. P-77X /100
dt.13.2.07, stating that the interest rates on loan for Khara is very high at 14.29% and
the depreciation has been considered by the Petitioner uniformly at the rate of 2.57%
for all of its generating stations without justification. It is also submitted that the
interest on working capital is being charged at a rate of 15% in contradiction to
UPERC Regulations
2.1.1 Gross Fixed Assets and Depreciation of Large & UGC Projects
The Commission directed UPJVNL to furnish details of Gross Fixed Assets and
depreciation since the date of Transfer Scheme, vide order dated 15th December 2006,
in the specified format. The Petitioner has submitted the required data, in the
specified format on an affidavit dt.23.1.07. The Petitioner has not submitted the
following details as required by the order of 15.12.06:
(a) Depreciation as considered by the Commission for determination of tariff for
relevant years:
(b) Details of capital additions in respect to assets commissioned during relevant
years
(c) Detailed financial package; i.e. loan, its interest rate, repayment schedule etc.
(d) Details of equity infusion against the commissioned assets.
(e) Audited data of O&M expenditure
The Commission in its order dated 15.12.2006 observed in respect to cost & cost
structure,
“The UPERC (Terms and Conditions of Generation Tariff) Regulations, 2004 came into force
with effect from 18-06-2005, the date of notification, for three years and accordingly, the
Petitioner was required to file tariff proposal. Therefore, Petitioner is directed to file tariff for
11
year 2005-06 & 2007-08. However, for period prior to 18-06-2005, the tariff approved for
year 2004-05 shall continue.
The said Regulations apply in all cases where the tariff is determined based on capital cost. It
may be noted that as per Regulation-33, the actual expenditure incurred on the completion of
project forms the basis for determination of tariff. This Regulation further provides that in
case of existing generating stations, the project cost admitted by the Commission prior to
commencement of this Regulation shall form the basis for determination of tariff. As per
Regulation-36, in all cases, debt equity ratio on the date of commercial operation shall be
70:30 and where employed equity is more than 30 percent, it shall be limited to 30 percent
and rest considered as normative loan, but in case, it is less than 30 percent, actual debt-
equity shall be considered. The asset costs and cost structures of the Petitioner’s plants are
not the historical but are the costs and cost structures made on the basis of total gross fixed
asset, accumulated depreciation, equity and debt assigned to it by Transfer Schemes dated 14-
01-2000 and 25-01-2001. In light of the Regulations 2 (2) read with Regulation-33 and
Regulation-36, the allocation of above cost and associated capital structure among the plants
under control of the Petitioner might be considered as the costs as on 14-01-2000 for the
purpose of tariff determination. Therefore, such gross fixed assets and corresponding cost
structures, associated with plants are not subject to revisions. This means that opening gross
fixed assets of each year shall be traced from Transfer Scheme with due consideration of
capital additions made in preceding years and considered by the Commission for
determination of tariff from year 2000-01 to 2004-05.
Due to Reorganization of State of Uttar Pradesh, the hydro plants located in the State of
Uttaranchal are no longer under the ownership the Petitioner, as such; the gross fixed assets
assigned to such plants, on the basis of the Transfer Schemes, have no relevance to the plants
now left under the control of the Petitioner. Therefore, the Petitioner is directed to submit the
details, in respect to costs and cost structures of its plants, as per the Annexure-1, 2 & 3 to
this order. Besides above, the Petitioner shall also submit audited O&M expenses over the
year for the purpose of calculation of O&M cost and the detailed calculation of working
capital and justification for the claim of interest with the rate of 15% on working capital.
The Petitioner is also directed to submit full facts in respect to Rs. 29.80 Cr. not considered
by the Commission earlier. “
12
UPJVNL submitted that the final Transfer Scheme allocated GFA as a whole to the
Petitioner. It did not provide the break-up of the value of assets under each of the
power stations transferred to it. Also at the time of division of Uttar Pradesh into
Uttaranchal and Uttar Pradesh, the values of the assets transferred to UJVNL was
not specified. Thus the determination of assets and liabilities between Uttaranchal
and Uttar Pradesh remained unresolved. The Petitioner further stated that
UPJVNL has assigned values of fixed cost of assets by prorating the total GFA into
the power stations on the basis of their capacities. The Commission accepts the
same for want of any notification from the Government in this regard. The break-
up of assets and depreciation, since the date of final Transfer Scheme, as provided
by the Petitioner on affidavit dt.23.1.07is as below.
Table 2.1-2 GFA and Depreciation, FY 1999-00
All figures in Rs. Crores
Rihand Obra (H) Matatila Khara UGC Total GFA as on 14.01.2000. (As per Final Transfer Scheme)
63.08 24.03 13.87 327.89 10.55 432.49
Accumulated Depreciation (As on 14.01.2000.)
56.77 21.62 10.38 65.82 9.49 157.84
NFA as on 14.01.2000. (As per Final Transfer Scheme)
6.31 2.41 3.49 262.07 1.06 274.65
Additional Capitalisation (during FY 1999-00) (Due to Allocation of HO)
0.01 0.00 0.00 0.00 0.00 0.01
GFA at the end of Year 63.09 24.03 13.87 327.89 10.55 432.50
Table 2.1-3 GFA and Depreciation, FY 2000-01
All figures in Rs. Crores
Rihand Obra (H) Matatila Khara UGC Total GFA at the beginning of the year 63.09 24.03 13.87 327.89 10.55 432.50
13
Accumulated Depreciation at the beginning of the year
56.77 21.62 10.38 65.82 9.49 157.84
Additions during the year
Unit 0.00 0.00 0.02 0.00 0.00 0.02 HO 0.39 0.13 0.04 0.09 0.02 0.68
GFA at the end of the year 63.48 24.16 13.93 327.99 10.57 433.20
Depreciation for the year 0.00 0.00 0.33 14.40 0.00 14.73
NFA at the end of the year 6.71 2.54 3.22 247.77 1.08 260.63
14
Table 2.1-4 GFA and Depreciation, FY 2001-02
All figures in Rs. Crores
Rihand Obra (H) Matatila Khara UGC Total GFA at the beginning of the year 63.48 24.16 13.93 327.99 3.64
6.93* 433.20
Accumulated Depreciation at the beginning of the year
56.77 21.62 10.71 80.22 3.25 6.24* 172.57
Additions during the year
Unit 0.13 0.02 0.04 0.00 0.00 0.20 HO 0.15 0.05 0.02 0.04 0.01 0.25
GFA at the end of the year 63.76 24.23 13.98 328.02 3.65 433.65
Depreciation for the year 0.01 0.00 0.47 11.15 0.00 11.64
NFA at the end of the year 6.98 2.61 2.81 236.65 0.40 249.44
*Assets transferred to Uttaranchal on 9.11.01.
Table 2.1-5 GFA and Depreciation, FY 2002-03
All figures in Rs. Crores
Rihand Obra (H) Matatila Khara UGC Total
GFA at the beginning of the year 63.76 24.23 13.98 328.02 3.65 433.65
Accumulated Depreciation at the beginning of the year
56.78 21.62 11.18 91.37 3.25 184.21
Additions during the year
Unit 0.15 0.00 0.00 0.01 0.00 0.15
HO 0.02 0.01 0.00 0.00 0.00 0.03
GFA at the end of the year 63.93 24.25 13.98 328.03 3.65 433.84
Depreciation for the year 0.02 0.01 0.48 11.16 0.00 11.66
NFA at the end of the year 7.13 2.62 2.32 225.50 0.40 237.96
15
Table 2.1-6 GFA and Depreciation, FY 2003-04
All figures in Rs. Crores
Rihand Obra (H) Matatila Khara UGC Total GFA at the beginning of the year 63.93 24.25 13.98 328.03 3.65 433.84
Accumulated Depreciation at the beginning of the year
56.80 21.63 11.66 102.53 3.25 195.87
Additions during the year
Unit 0.12 0.16 0.16 0.22 0.01 0.67 HO 0.02 0.01 0.00 0.00 0.00 0.03
GFA at the end of the year 64.07 24.42 14.14 328.25 3.66 434.53
Depreciation for the year 0.03 0.01 0.47 11.15 0.00 11.67
NFA at the end of the year 7.24 2.78 2.01 214.57 0.41 226.99
Table 2.1-7 GFA and Depreciation, FY 2004-05
All figures in Rs. Crores
Rihand Obra (H) Matatila Khara UGC Total GFA at the beginning of the year 64.07 24.42 14.14 328.25 3.66 434.53
Accumulated Depreciation at the beginning of the year
56.84 21.64 12.13 113.68 3.25 207.54
Additions during the year
Unit 0.58 0.01 0.10 0.12 0.49 1.29 HO 0.00 0.00 0.00 0.00 0.00 0.01
GFA at the end of the year 64.65 24.42 14.24 328.36 4.15 435.83
Depreciation for the year 0.03 0.01 0.37 8.44 0.00 8.84
NFA at the end of the year 7.78 2.78 1.74 206.5 0.90 219.45
16
Table 2.1-8 GFA and Depreciation, FY 2005-06
All figures in Rs. Crores
Rihand Obra (H) Matatila Khara UGC Total GFA at the beginning of the year 64.65 24.42 14.24 328.36 4.15 435.83
Accumulated Depreciation at the beginning of the year
56.87 21.65 12.50 122.12 3.25 216.38
Additions during the year
Unit 0.60 0.08 0.01 0.03 0.00 0.72 HO 0.00 0.00 0.00 0.00 0.00 0.00
GFA at the end of the year 65.25 24.50 14.25 328.40 4.15 436.55
Depreciation for the year 0.04 0.01 0.02 8.44 0.01 8.65
NFA at the end of the year 8.34 2.84 1.73 197.83 0.89 211.52
Table 2.1-9 GFA and Depreciation, FY 2006-07
All figures in Rs. Crores
Rihand Obra (H) Matatila Khara UGC Total GFA at the beginning of the year 65.25 24.50 14.25 328.40 4.15 436.55
Accumulated Depreciation at the beginning of the year
56.91 21.66 12.52 130.56 3.26 225.03
Additions during the year 1.17 0.22 0.12 0.32 0.47 2.30
GFA at the end of the year 66.42 24.72 14.37 328.72 4.63 438.85
Depreciation for the year 0.06 0.01 0.01 8.44 0.02 8.54
NFA at the end of the year 9.45 3.05 1.84 189.71 1.34 205.28
17
Table 2.1-10 GFA and Depreciation, FY 2007-08
All figures in Rs. Crores
Rihand Obra (H) Matatila Khara UGC Total GFA at the beginning of the year 66.42 24.72 14.37 328.72 4.63 438.85
Accumulated Depreciation at the beginning of the year
56.7 21.67 12.53 139.00 3.29 233.57
Additions during the year 2.60 0.36 0.16 0.46 0.62 4.20
GFA at the end of the year 69.02 25.08 14.53 329.18 5.25 443.05
Depreciation for the year 0.08 0.02 0.01 8.45 0.03 8.59
NFA at the end of the year 11.97 3.39 1.99 181.72 1.93 200.89
The Commission observes that the addition in capital assets has not been detailed
although directed so by order dt.15.12.06, i.e. the Petitioner has not provided details
of the assets that are added and proposed to be added. Also no justification has been
provided for the requirement of such additions. The Petitioner is directed to provide
complete details of the additional capitalization done since the date of Transfer
Scheme and also the proposed additions in future years of the MYT period along
with justification for the same within fifteen days of the date of this tariff order.
The Computation of depreciation for FY 2005-06 has been done considering the
allocation of accumulated depreciation and the subsequent additions in the assets.
The Commission believes that for the FY 2006-07 & FY 2007-08 the depreciation have
been computed applying the same principles and applying the rates of depreciation
specified in the Uttar Pradesh Electricity Regulatory Commission (Terms and
Conditions of Tariff) Regulations 2004. However, the Petitioner has not provided the
details of computation of depreciation.
For the purpose of determination of tariff, the Commission approves the
Petitioner’s projections in respect of cost of assets and depreciation as above.
However UPJVNL shall justify the capitalisations considered.
18
The cost of fixed assets and depreciation approved as above shall be the base for
all future consideration, not subject to review, as adequate opportunity was
provided to the Petitioner to submit reliable and collated data. The Commission
has considered the same for determination of tariff.
2.1.2 Long-Term Loans
The final Transfer Scheme describes the following values of assets and liabilities of
UPJVNL, as on 14.1.2000:
Gross Fixed Assets Rs. 943.38 Crores
Long-Term Debts Rs. 403.18 Crores
Equity Rs. 372.18 Crores
Ministry of Power, Govt. of India, vide notification no. 42/7/2000 R&R (Vol – III)
dated 2nd September 2005 transferred partial loan liability of Rs. 352.59 crore, to
Uttaranchal Jal Vidyut Nigam Limited (in respect of Maneri Bhali Stage – II project).
The above decision of Govt. of India has lowered the loan liability of UPJVNL by
Rs.352.59 crores out of total debt of Rs.403.18 crores that stood as on 14.1.00. Thus the
outstanding loan of UPJVNL, as on 2nd Sep 2005 was Rs. 50.59 Crores.
The Commission, in its order dated 15th December 2006, directed the Petitioner to
provide details of loan and equity since the date of Transfer Scheme in respect of
each of the power stations. The Petitioner submitted revised tariff computation on
15.1.07, under affidavit, relying on Annexure-10 of affidavit dt. 30.9.06. Although it
was expected from the Petitioner to have computed tariff on the basis of the data
developed pursuant to order dt.15.12.06, the Petitioner has failed to explain the
manner in which the cost structure of tariff computation has been evolved. It is
relevant to cite the extracts from the Petitioner’s affidavit dt.15.1.07, which will bring
out the point:
“The Equity and Debt Ratio of 30:70 has been maintained as laid down in the UPERC
(Terms and Conditions of Generation tariff) Regulations, 2004 in respect of GFA values but
19
while determining the Tariff for the FY concerned the NFA values have only been taken into
consideration due to which ratio is bound to be disturbed even in the second year of operation
where in the loan portion is reduced due to its amortisation out of depreciation portion while
the Equity is maintained till the assets are not depreciated up to 70% of the GFA values.
In the Tariff Proposal the Cost Structure of each project has been maintained as the GFA
values have not been changed except when there were some Additions are Deletions in plant
itself. The Equity and Debt ratio of 30:70 is also maintained in respect of GFA values. Only
the Equity and Debt portions have been changed to match the NFA values according to the
Commissions directives, particularly as it will have no substantial effect on the over all Cost
Structure because if the Equity portion is substituted by the Debts or vice versa the financial
effect would be negligible because the computed over all interest on over due loans is worked
out to 14.29% while the rate of Return on Equity is 14%………. ”
The submission of UPJVNL in this revised petition is not understandable. Neither the
language, nor the content or logic of the submission of the Petitioner is clear. The
directions of the Commission in Order dt. 15.12.06 were explicit, objective and well
intended. The intention of the Commission’s directive was to understand the actual
financing structure of the power stations of the Petitioner. The Petitioner has
preferred to make a convoluted interpretation of the Uttar Pradesh Electricity
Regulatory Commission (Terms and Conditions of Tariff) Regulations 2004 and has
projected a normative debt and equity dividing the GFA into 70:30 ratio in the format
specified by the Commission. The Petitioner has pleaded that the Transfer Scheme
did not allocate any portion of equity or debt to any specific project. To determine
the loan and equity for tariff determination, the Petitioner has first examined if the
NFA of a power station was more than 30% of GFA. If it was, then UPJVNL has
considered 30% of GFA as equity and an amount equivalent to the difference of NFA
and 30% of GFA as outstanding loan. If the NFA fell short of 30% of GFA, then the
entire NFA was considered as equity. This methodology defies logic established by
the Commission in Generation Regulations. It appears that it is just a matter of
convenience to play with numbers of actual cost and financing, as if the Petitioner
is at liberty to shuffle the numbers according to its own suitability. The
Commission cannot accept the logic and interpretation framed by the Petitioner as
20
to the intent of the provisions of the Generation Regulations, which are
unambiguous and clear in this respect.
It may, once again, be emphasized that Regulation 36 makes it amply clear that the
original cost of fixed assets would be considered to have been financed at a debt
equity ratio of 70:30 if the actual equity employed was more than 30% of cost of the
fixed asset. Otherwise actual quantum of debt and equity would be considered. Since
the capital and financing structure of UPJVNL was to be traced from the date of
Transfer Scheme, as such, the Commission directed it by order dt.15.12.06 to provide
the relevant details from 14.1.2000. The Petitioner, in its submission, has failed to
capture all information as was intended in the format provided for that purpose.
Further, UPJVNL has also shown additional capitalisation in each year of its
operations, and structure of financing. The financing of all additions till 1st Sep
2005 (i.e. the date prior to the notification of Govt. of India transferring the loan
liability of Rs. 352.59 Crores to Uttaranchal Jal Vidyut Nigam Limited) has been
shown as funded through equity only. Since 2nd September 2005, the financing of
additional capitalisation has been shown at a debt equity ratio of 70:30. The
Petitioner has not provided details of assets so capitalised from such additional
debt and equity. The information presented to the Commission was in bits and
pieces. There are missing links that needs to be explained by the Petitioner to
substantiate its claims with supporting authenticated reports/documents. For
example, it needs to present to the Commission its audited accounting reports since
the date of Transfer Scheme. There is no record placed before the Commission
regarding the performance of the Petitioner for the FY 2004-05 comparing it with the
performance levels approved by the Commission in its tariff order for FY 2004-05.
Also the Petitioner has chosen to project the performance parameters for FY 2005-06
instead of presenting the actual performance though the year has already passed by.
Also it needs to explain all the assumptions, if any, and the details of computation for
each of the derived numbers.
Data calling had to be stopped at some stage so that the matter is decided. The
Commission cannot afford to waste more time in correcting records of the
21
Petitioner and therefore decides to accept the data submitted for period prior to
2.9.05 by it and examine the same under the provisions of the Generation
Regulations.
As pointed out earlier, the outstanding loan as on 2nd Sep 2005, was Rs. 50.59 Crores.
For the additional amount of debts considered since 2nd September 2005, there is no
documentary evidence before the Commission to ascertain that the Petitioner has
actually tied up additional loans for financing its additional capital expenditure.
Further, no documentary evidence has been produced before the Commission to
validate the claims of equity infusion.
The Commission also observed that according to the audited balance sheet of
UPJVNL for FY 2003-04, the outstanding loan at the end of FY 2003-04 was Rs.
64.65 Crores. This date was prior to 2nd Sep 2005, (i.e. the date when GoI
transferred the Loan amount of Rs. 352.59 Crores due to Maneri Bhali Stage II
Project to Uttaranchal). This presents a contradiction with respect to the actual
outstanding loan of UJVNL. The Petitioner has also not explained why it has
considered an outstanding loan amount of 99.32 Crores for computation of tariff
for the FY 2005-06 and what are the sources of such loan.
In absence of any authentic data, the Commission is constrained to consider that the
outstanding loan at the beginning of FY 2004-05 was Rs. 64.65 Crores, (according to
the audited balance sheet of the Petitioner for the FY 2003-04), and the loan amount
outstanding as on 2nd Sep 2005 as Rs. 50.59 Crores for determination of tariff. For the
FY 2005-06 a normative repayment of Rs. 6.645 Crores (1/10th of outstanding amount
at the beginning of the year) has been considered. It may be noted that the loan
liability of the Petitioner has not increased since 2nd September 2005, as the
Petitioner has not indicated any additional loan drawal after this date. The
Commission considers a normative repayment of Rs. 5.059 Crores (equivalent to
1/10th of the outstanding amount) each year subsequent to year 2005-06.
Regarding the allocation of the total outstanding loan to different projects, the
Petitioner has considered loan only in case of Khara project, commissioned during
22
the years 1992 and 1993, which is the newest asset of Petitioner. All other assets are
more than 30 years old. Hence, it is logical to ascribe the outstanding loan to Khara
project. Hence, the Commission considers that the entire outstanding loan is on
Khara Power Station and no outstanding loan for other Generating Stations.
2.1.3 Interest on Long Term Loans
UPJVNL has projected interest rate at 14.29% pa for the MYT period of FY 06
through FY 08. In the tariff order of FY 2004-05,the Commission considered interest
rate @ 11% pa while agreeing with the Petitioner’s estimation of interest rate. In the
same tariff order, the Commission also directed the Petitioner to restructure the loans
to further bring down the interest cost. The Petitioner has neither provided any
compliance report on the same nor provided the loan specific interest rates, as
directed by order dt.15.12.06. The Petitioner has also not shown fresh borrowings. As
such the rise in rate of interest on old debt does not stand to any justification.
On scrutiny of the audited balance sheet of the Petitioner for the FY 2003-04, as
submitted to the Commission, the opening balance and closing balance of loan both
stood at Rs. 64.65 Crores. The interest payment during the year as per in the audited
P/L account was Rs. 7.693 Crores, which translates into an interest rate of 11.90% pa.
On this issue it would be worthwhile to recall Section 38(i) of the Uttar Pradesh
Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations
2004, relating to interest on long-term loans:
“
(a) Interest on loan capital shall be computed loan wise on the loans arrived at in the
manner indicated in regulation 36.
(b) The loan outstanding as on 1st April shall be worked out as the gross loan as per
regulation 36 minus cumulative repayment as admitted by the Commission up to 31st March.
The repayment for the period 2005-08 shall be worked out on a normative basis.
23
(c) The generating company shall make every effort to swap the loan as long as it results
in net benefit to the beneficiaries. The costs associated with such swapping shall be borne by
the beneficiaries.
(d) The changes to the loan terms and conditions shall be reflected from the date of such
swapping and benefit passed on to the beneficiaries.
(e) In case of any dispute, any of the parties may approach the Commission with proper
application. However, the beneficiaries shall not withhold any payment as ordered by the
Commission to the generating company during pendency of any dispute relating to swapping
of loan.
(f) In case any moratorium period is availed of by the generating company, depreciation
provided for in the tariff during the years of moratorium shall be treated as repayment during
those years and the interest on loan capital shall be calculated accordingly.
(g) The generating company shall not make any profit on account of swapping of loan
and interest on loan.
Therefore, in view of the above and for the purpose of determination of tariff, the
Commission considers a rate of interest on loan at 11.00% as considered for the
year 2004-05 earlier. This shall be the rate of interest for 2005-06 onward for all
purposes in respect to existing loans.
Based on the discussion above, the outstanding loan, repayment and interest is
summarised in the table below and the Commission approves the same for the MYT
period of FY 2005-06 through FY 2007-08:
Table 2.1-11 Loans and Interest Approved
All figures in Rs. Crores
Rihand Obra Matatila Khara UGC Total
FY 2005-06
Loan outstanding at the 0.00 0.00 0.00 64.65 0.00 64.65
24
Rihand Obra Matatila Khara UGC Total
beginning of the year
Loan outstanding as on 02-
09-2005
(According to transfer of
loan to Uttaranchal,
effected by GoI)
0.00 0.00 0.00 50.59 0.00 50.59
Additional Drawal during
the year 0.00 0.00 0.00 0.00 0.00 0.00
Repayment During the
year
(Normative)
0.00 0.00 0.00 6.47 0.00 6.47
Loan outstanding at the
end of the year 0.00 0.00 0.00 50.59 0.00 50.59
Interest @ 11% on average
loan during the year 0.00 0.00 0.00 6.34 0.00 6.34
FY 2006-07
Loan outstanding at the
beginning of the year 0.00 0.00 0.00 50.59 0.00 50.59
Additional Drawal during
the year 0.00 0.00 0.00 0.00 0.00 0.00
Repayment During the
year 0.00 0.00 0.00 5.06 0.00 5.06
Loan outstanding at the
end of the year 0.00 0.00 0.00 45.53 0.00 45.53
Interest @ 11% on average
loan during the year 0.00 0.00 0.00 5.29 0.00 5.29
FY 2007-08
Loan outstanding at the
beginning of the year 0.00 0.00 0.00 45.53 0.00 45.53
Additional Drawal during 0.00 0.00 0.00 0.00 0.00 0.00
25
Rihand Obra Matatila Khara UGC Total
the year
Repayment During the
year 0.00 0.00 0.00 5.06 0.00 5.06
Loan outstanding at the
end of the year 0.00 0.00 0.00 40.47 0.00 40.47
Interest @ 11% on average
loan during the year 0.00 0.00 0.00 4.73 0.00 4.73
2.1.4 Equity
As explained in Para 2.1.2, the Commission’s directive of 15th Dec 2006 was intended
to understand the actual financing structure of the power stations of the Petitioner.
The Petitioner has claimed that the Transfer Scheme did not allocate any portion of
equity or debt to any specific project. To determine the loan and equity to be
considered for tariff determination, UPJVNL has first examined if the NFA of a
power station was more than 30% of GFA. If it was, then it has considered 30% of
GFA as equity and an amount equivalent to the difference of NFA and 30% of GFA
as outstanding loan. If the NFA fell short of 30% of GFA then the entire NFA was
considered as equity. The Commission has already observed that this methodology
defies any logic enshrined in the Generation Regulations. It is just a matter of
convenience that the Petitioner has put itself at liberty to develop a system best
suited to it. This cannot be accepted.
UPJVNL further submitted in Para 7 of affidavit dt.15.1.07, “it was Uttar Pradesh
Power Corporation Limited, which allocated substantial amount of equity to capital works in
progress leaving a small amount of Rs. 19.59 Crores to be distributed among the projects to
determine the tariff of hydro-electric projects wef 15.01.2000 and onwards as per Central
Electricity Authority Guidelines”. The Petitioner also stated that since the UPERC has
framed its own regulations these guidelines are no longer in force and therefore the
tariff proposal as submitted by the Petitioner might be examined on the principles so
determined.
26
In this respect the Commission observes that since the enforcement of the Transfer
Scheme, the tariff of UPJVNL has been determined based on the equity allocation
agreed to by the Petitioner with UPPCL, which is the gross equity for all the hydro
power stations of undivided Uttar Pradesh at Rs. 19.59 Crores. The Commission
accepted this in determination of tariff till FY 2004-05. Presently the Petitioner has
projected equity of Large & UGC Power Stations, as on 1st April 2005, at Rs. 112.21
Crores. The genesis of this number has not been submitted despite the fact that the
Commission, in order dt.15.12.06, directed UPJVNL to explain equity infusion. There
is no actual equity infusion of that extent by the Petitioner for creation of generating
asset since the Commission passed the tariff order dt.10.11.04 for FY 2004-05. The
Commission has provided adequate opportunity to the Petitioner to present the
correct values of equity and debt in respect of its power stations, which the Petitioner
has failed to avail. Regulation 36 of the Generation Regulations is unambiguously
clear in this respect as to how the equity is to be computed. There is no justification
or authentic report/document supporting it. The Commission recognises that the
Transfer Scheme ascribed a gross equity figure of Rs. 372.18 Crores to the hydro
power stations of undivided Uttar Pradesh. But the Petitioner itself, all along the
years since the date of Transfer Scheme (i.e. 14.1.2000), has mentioned equity as
Rs. 19.59 Crores vide schedule-1 (Revised) of Agreement dt. 16.7.05 (Annex-27 of
affidavit dt.30.9.06), It remains with the Petitioner to explain all the ambiguity.
Under the said circumstances the Commission would continue to attach with the
equity values as considered by it in the Tariff order dt.10.11.04 for FY 2004-05.
The Commission, however, accepts the equity addition projected after FY 2004-05
although the Petitioner has failed to explain equity infusions.
Table 2.1-12 Equity as Approved
Rihand Obra (H) Matatila Khara UGC Total
FY 2005-06 Equity at the beginning of the year 0.26 0.10 0.14 10.71 0.00 11.21
Equity Addition During the Year 0.35 0.04 0.02 0.41
27
Rihand Obra (H) Matatila Khara UGC Total Equity at the end of the year 0.61 0.14 0.14 10.73 0.00 11.62
FY 2006-07 Equity at the beginning of the year 0.61 0.14 0.14 10.73 0.00 11.62
Equity Addition During the Year 0.35 0.07 0.04 0.10 0.14 0.70
Equity at the end of the year 0.96 0.21 0.18 10.83 0.14 12.32
FY 2007-08 Equity at the beginning of the year 0.96 0.21 0.18 10.83 0.14 12.32
Equity Addition During the Year 0.78 0.11 0.05 0.14 0.19 1.27
Equity at the end of the year 1.74 0.32 0.23 10.97 0.33 13.59
The Petitioner is directed to ensure that equity infusion beyond 2007-08 are well
reasoned and made for creation of capital assets only.
2.1.5 Return on Equity
The Uttar Pradesh Electricity Regulatory Commission (Terms and Conditions of
Tariff) Regulations 2004 (Regulations 38(iii)) for the MYT period of FY 2005-06
through FY 2007-08 specifies that the return on equity shall be computed @ 14%on
the equity base. Accordingly the RoE for the MYT period is approved as below:
Table 2.1-13 Return on Equity
All figures in Rs. Crores
Rihand Obra (H) Matatila Khara UGC Total
FY 2005-06 0.06 0.02 0.02 1.50 0.00 1.60
FY 2006-07 0.11 0.02 0.02 1.51 0.01 1.67
FY 2007-08 0.19 0.04 0.03 1.53 0.03 1.82
28
2.1.6 Operation and Maintenance Expenses
The Uttar Pradesh Electricity Regulatory Commission (Terms and Conditions of
Tariff) Regulations 2004 (Regulations 38 (iv)) specify the methodology of computing
O&M Expenses for hydro stations. The regulations are reproduced below:
“(a) The operation and maintenance expenses including insurance, for the existing
generating stations which have been in operation shall be derived on the basis of actual
operation and maintenance expenses for the years 2000-2001 to 2004-05, based on the audited
balance sheets, excluding abnormal operation and maintenance expenses, if any, after
prudence check by the Commission.
The average of such normalised operation and maintenance expenses after prudence
check, for the years 2000-2001 to 2004-05 considered as operation and maintenance expenses
for the year 2002-03 shall be escalated at the rate of 4% per annum to arrive at operation and
maintenance expenses for the base year 2004-05.
The base operation and maintenance expenses for the year 2004-05 shall be escalated further
at the rate of 4% per annum to arrive at permissible operation and maintenance expenses for
the relevant year of tariff period.
(b) In case of the hydro electric generating stations, which have not been in existence for a
period of five years, the operation and maintenance expenses shall be fixed at 1.5% of the
capital cost as admitted by the Commission and shall be escalated at the rate of 4% per annum
from the subsequent year to arrive at operation and maintenance expenses for the base year
2004-05. The base operation and maintenance expenses shall be further escalated at the rate
of 4% per annum to arrive at permissible operation and maintenance expenses for the relevant
year.
(c) In case of the hydro electric generating stations declared under commercial operation on or
after the date of commencement of this regulation, the base operation and maintenance
expenses shall be fixed at 1.5% of the actual capital cost as admitted by the Commission, in
the year of commissioning and shall be subject to an annual escalation of 4% per annum for
the subsequent years till 31.3.2008.”
29
The Petitioner submitted O&M expenses on the basis of actual expenditure in Para
2.14 of affidavit dt. 30.9.06 without support of audited accounts. The Commission
directed the Petitioner in order dt.15.12.06 to submit audited accounts of O&M
expenses. The Petitioner has submitted actual O&M expenses on affidavit
dt.15.1.07 from FY 2001-02 to FY 2004-05. For the purpose of the said regulation,
actual expenditure of 5 years is required. The Petitioner has failed to provide data
for FY 200-01, therefore O&M expenses during FY 2000-01 has been considered at
the level of FY 2001-02. Based on above data, O&M expenses for the year FY 2005-
06, 2006-07 & 2007-08 are summarised in the table below. The Commission
approves the same for tariff determination.
Table 2.1-14 O&M Expenses
All figures in Rs. Crores
Rihand Obra (H) Matatila Khara UGC Total
Historical Cost
FY 2000-01 11.31 3.92 3.13 4.29 2.57 25.22
FY 2001-02 11.31 3.92 3.13 4.29 2.57 25.22
FY 2002-03 12.06 6.37 2.91 4.54 2.59 28.47
FY 2003-04 14.43 6.54 2.86 4.91 5.63 34.37
FY 2004-05 13.09 6.97 2.63 3.99 2.62 29.30
Average 12.44 5.54 2.93 4.40 3.20 28.51
Projections
FY 2005-06 14.00 6.23 3.30 4.95 3.60 32.08
FY 2006-07 14.56 6.48 3.43 5.15 3.74 33.36
FY 2007-08 15.14 6.74 3.57 5.36 3.89 34.70
Apart from these expenses the Petitioner has additionally claimed tariff petition
fee of Rs. 0.25 Cr. in each of the years under MYT.
The Commission admits one-time application fee of Rs. 0.25 Cr., which is admitted
under the tariff of FY 2005-06 as this amount does not reflect in actual O&M
30
expenses because the petitioner has for the first time approached the Commission
for determination of tariff. The break-up of the application fee as admitted by the
Commission is as under:
Table 2.1-15 Application Fees
Rs. Cr.
Rihand Obra (H) Matatila Khara UGC Total
FY 2005-06 0.15 0.05 0.01 0.03 0.01 0.25
FY 2006-07 0.00 0.00 0.00 0.00 0.00 0.00
FY 2007-08 0.00 0.00 0.00 0.00 0.00 0.00
2.1.7 Working Capital and Interest on Working Capital
The Uttar Pradesh Electricity Regulatory Commission (Terms and Conditions of
Tariff) Regulations 2004 specify that Working Capital shall cover:
(i) Operation and Maintenance expenses for one month;
(ii) Maintenance spares @ 1% of the historical cost escalated @ 4% per annum from the
date of commercial operation; and
(iii) Receivables equivalent to two months of fixed charges for sale of electricity, calculated
on normative capacity index
The detailed analysis of each of these components is provided below:
2.1.7.1 O&M Expenses
This has been already analysed in the previous Section.
2.1.7.2 Cost of Maintenance Spares
Historical cost from the date of commercial operation is not available for the power
stations. The Petitioner has considered the capital cost as on the date of Transfer
Scheme. As the power stations of UPJVNL are very old (except Khara), it may be
difficult to find out the historical cost. Hence, the Commission also accepts the
31
same. But the Commission directs UPJVNL to provide actual project cost of Khara
on CoD, as this power station is not very old (commissioned during 1992-93). The
Petitioner must provide the data within one week of the date of this order.
In the following table computation of the cost of maintenance spares is shown:
Table 2.1-16 Computation of Cost of Maintenance Spares
All figures in Rs. Crores
Rihand Obra (H) Matatila Khara UGC
Original Cost of Fixed Assets
as on 15-01-2000 63.08 24.03 13.87 327.89 3.62
Date of Commissioning 1962-66 1970-72 1964-66 1992-93 1929-37
Age of the power station as
on 01-04-2005 (years) 39 33 39 12 68
Cost of Maintenance Spares @
1% of historical cost 0.63 0.24 0.14 3.28 0.04
Cost of Maintenance Spares
for FY 2005-06 2.91 0.88 0.65 5.25 0.58
Cost of Maintenance Spares
for FY 2006-07 3.03 0.92 0.68 5.46 0.6
Cost of Maintenance Spares
for FY 2007-08 3.15 0.96 0.71 5.68 0.62
2.1.7.3 Receivables
Receivables have been considered as 2/12th of the total fixed charges (as computed
by the Commission) for each of the power stations.
32
2.1.7.4 Total Working Capital and Interest on Working Capital
The Uttar Pradesh Electricity Regulatory Commission (Terms and Conditions of
Tariff) Regulations 2004 specify that
“Rate of interest on working capital shall be the short-term Prime Lending Rate of State Bank
of India as on 1.4.2005 or on 1st April of the year in which the generating unit/station is
declared under commercial operation, whichever is later. The interest on working capital shall
be payable on normative basis notwithstanding that the generating company has not taken
working capital loan from any outside agency.”
The PLR of SBI as on 1st April 2005 was 10.25%. Hence the same has been
considered for computation of interest on working capital. The Commission
approves the working capital and the interest on working capital as below for FY
2005-06 through FY 2007-08.
Table 2.1-17 Working Capital and Interest on Working Capital, FY 2005-06
All figures in Rs. Crores
Rihand Obra (H) Matatila Khara UGC Total Operation and Maintenance expenses for one month
1.17 0.52 0.28 0.41 0.30 2.67
Maintenance spares @ 1% of the historical cost escalated @ 4% per annum from the date of commercial operation
2.91 0.88 0.65 5.25 0.58 10.27
Receivables equivalent to two months of fixed charges for sale of electricity, calculated on normative capacity index
2.49 1.10 0.60 3.70 0.63 8.52
Total Working Capital 6.56 2.49 1.53 9.37 1.51 21.46
Interest on Working Capital @ 10.25%
0.67 0.26 0.16 0.96 0.15 2.20
33
Table 2.1-18 Working Capital and Interest on Working Capital, FY 2006-07
All figures in Rs. Crores
Rihand Obra (H) Matatila Khara UGC Total Operation and Maintenance expenses for one month
1.21 0.54 0.29 0.43 0.31 2.78
Maintenance spares @ 1% of the historical cost escalated @ 4% per annum from the date of commercial operation
3.03 0.92 0.68 5.46 0.60 10.69
Receivables equivalent to two months of fixed charges for sale of electricity, calculated on normative capacity index
2.57 1.13 0.60 3.56 0.66 8.52
Total Working Capital 6.82 2.59 1.57 9.45 1.57 21.99
Interest on Working Capital @ 10.25%
0.70 0.27 0.16 0.97 0.16 2.26
Table 2.1-19 Working Capital and Interest on Working Capital, FY 2007-08
All figures in Rs. Crores
Rihand Obra (H) Matatila Khara UGC Total Operation and Maintenance expenses for one month
1.26 0.56 0.30 0.45 0.32 2.89
Maintenance spares @ 1% of the historical cost escalated @ 4% per annum from the date of commercial operation
3.15 0.96 0.71 5.68 0.62 11.12
Receivables equivalent to two months of fixed charges for sale of electricity, calculated on normative capacity index
2.69 1.18 0.63 3.51 0.69 8.70
34
Rihand Obra (H) Matatila Khara UGC Total
Total Working Capital 7.10 2.70 1.64 9.64 1.63 22.71
Interest on Working Capital @ 10.25%
0.73 0.28 0.17 0.99 0.17 2.34
2.1.8 Total Fixed Cost of Large & UGC Projects of UPJVNL for the MYT Period
Based on the analysis and computation presented in the foregoing Sections, the
total fixed cost of Large & UGC Projects of UPJVNL for the MYT period is
summarised below. The Commission approves the same.
Table 2.1-20 Total Fixed Cost of UPJVNL, FY 2005-06
All figures in Rs. Crores
Rihand Obra (H) Matatila Khara UGC Total
FY 2005-06
Interest on loan capital 0.00 0.00 0.00 6.34 0.00 6.34
Depreciation,
including Advance
Against Depreciation
0.04 0.01 0.14 8.44 0.01 8.65
Return on equity 0.06 0.02 0.02 1.50 0.00 1.60
Operation and
maintenance expenses
including insurance
and tariff application
fee
14.15 6.28 3.31 4.98 3.61 32.33
Interest on working
capital 0.67 0.26 0.16 0.96 0.15 2.20
Total 14.92 6.57 3.63 22.22 3.77 51.11
FY 2006-07
Interest on loan capital 0.00 0.00 0.00 5.29 0.00 5.29
Depreciation,
including Advance
Against Depreciation
0.06 0.01 0.01 8.44 0.02 8.54
35
Rihand Obra (H) Matatila Khara UGC Total
Return on equity 0.11 0.02 0.02 1.51 0.01 1.67
Operation and
maintenance expenses
including insurance
14.56 6.48 3.43 5.15 3.74 33.36
Interest on working
capital 0.70 0.27 0.16 0.97 0.16 2.26
Total 15.43 6.78 3.62 21.36 3.93 51.12
FY 2007-08
Interest on loan capital 0.00 0.00 0.00 4.73 0.00 4.73
Depreciation,
including Advance
Against Depreciation
0.08 0.02 0.01 8.45 0.03 8.59
Return on equity 0.19 0.04 0.03 1.53 0.03 1.82
Operation and
maintenance expenses
including insurance
15.14 6.74 3.57 5.36 3.89 34.70
Interest on working
capital 0.73 0.28 0.17 0.99 0.17 2.34
Total 16.14 7.08 3.78 21.06 4.12 52.18
2.2 Tariff of Mini/Micro Power Stations of UPJVNL
The UPJVNL has prayed in its tariff application for FY 2006-07, dated 6th October,
2006, that the tariff for its mini / micro hydro power stations for FY 2006-07 be
approved according to the “Uttar Pradesh Electricity Regulatory Commission (Terms
and Conditions for Supply of Power and Fixation of Tariff for sale of power from
Captive Generating Plants, Co-generation, Renewable Sources of Energy and other
Non-conventional Sources of Energy based Plants to a Distribution Licensee)
Regulations 2005” made effective from 28.7.05
The above Regulations covers canal based hydro stations with capacity below 25
MW capacity.
36
In order dated 15th December 2006, the Commission directed the Petitioner to bill
respondents as per tariff specified in the said regulation for supplies made from
UGC, Belka and Babail power stations.
The Petitioner, in affidavit dt.15.1.07, has submitted that it would be appropriate to
approve the rates as filed by it in the tariff proposal so that it is binding on the
respondents.
The assets of the UPJVNL includes the following mini/micro canal based hydro
power stations:
(1) Nirgazani 2 X 2.5 MW
(2) Chitaura 2 X 1.5 MW
(3) Salawa 2 X 1.5 MW
(4) Bhola 4 X 0.375 + 2 X 0.6 MW
(5) Belka 2 X 1.5 MW, and
(6) Babail 2 X 1.5
(7) Sheetla 3 X 1.2 MW
In its application dated 6th October 2006, the Petitioner has claimed (Section 2.02) that
Power Purchase Agreement executed with UPPCL on 18.12.2000 covered all the
major hydro power stations including canal based power stations under Upper
Ganga Canal (UGC) projects. The Petitioner further submitted that since the PPA is
still in force, the tariff proposal in respect of UGC power stations has been
incorporated in the tariff proposals for other large hydro power projects. The
Commission accepted the Petitioner’s application for tariff determination according
to Uttar Pradesh Electricity Regulatory Commission (Terms and Conditions of Tariff)
Regulations 2004 and determined the tariff for the UGC projects. The computation
and determination of tariff of UGC power stations have been provided in Section 2.1
of this order. In the paragraph above, the power stations listed in serial no. (1)
through (4) are these UGC power stations.
37
However, the Commission is not aware of any PPA executed between UPJVNL and
UPPCL for the plants Belka and Babail. The Petitioner has submitted that Belka and
Babail projects were commissioned on 29.01.2002 and 02.01.2002 respectively and
thereafter taken on commercial operation w.e.f. 01.01.2003 and 16.07.2002
respectively. The Petitioner did this without signing any PPA and its approval by the
Commission. In this respect, the Commission observed the following in the tariff
order dated 10th June 2003 for FY 2003-04.
“UPJVNL has submitted that its two new small EYC hydel power stations viz Belka (3 MW)
and Babail (3 MW) have been commissioned in district Saharanpur and would together
generate 20 MU of energy as per the discharge available in Yamuna canal. The Commission
has been informed that some power is already being procured from these stations by UPPCL,
without the PPA being submitted to the Commission for approval. The Commission has
taken a serious note of this matter and directs UPPCL to submit its PPA with UPJVNL
for these plants in the next three months in accordance with the Power Procurement
Guidelines issued by the Commission under the “Guidelines for Load Forecast, Resource
Plans and Power Procurement Process”. Till the time UPPCL finalises and submits PPA for
these stations to the Commission, the energy available from these stations will be treated as
in-firm energy and would not be considered for the purpose of the power procurement plan.”
Though, more than two years have passed after the said order but utilities have not
come up to the Commission for approving PPA.
In absence of PPA, the Commission would not have approved tariff for Belka and
Babail even if the Petitioner had made an application. Any power procurement by
the distribution licensees from these projects shall be continued to be treated as
infirm power procurement.
In its tariff application for FY 2004-05, (filed by UPPCL), the Petitioner did not
apply for tariff of Belka and Babail and for that reason, the Commission also did
not deliberate on the same. The Petitioner has submitted on affidavit dt.30.9.06
that it is supplying electricity generated from these generating stations to UPPCL
since the dates of Commissioning at the rate of Rs.2.25/Kwh. It is also informed
that PPA shall be finalized shortly. Therefore, in consideration of above, the
38
Petitioner is directed to file a separate petition for approval of tariff of these
generating stations along with PPA within one month of this order and continue
to bill UPPCL at provisional rate of Rs. 2.25/Kwh and the Respondent shall pay the
same without any demure.
With regard to the Sheetla power station, UPJVNL has mentioned in its petition of 6th
October that the power station has been synchronised and is likely to be put on
commercial operation w.e.f. 01.11.2006. The Commission has not received PPA from
the concerned parties for approval. The Petitioner is directed to submit the
agreement for sale of electricity from Sheetla project signed with the distribution
licensee in whose area it is located at rate specified by the Commission in CNCE
regulation for approval of the Commission.
3 Adjustment in Revenue Requirement for FY 2003-04
UPJVNL has claimed, on affidavit, that due to consideration of Provisional Transfer
Scheme instead of Revised (final) Transfer Scheme for determination of tariff for the
FY 2003-04, it has suffered a shortfall of Rs. 29.84 Crores. The Petitioner has prayed
for settlement along with the determination of tariff for MYT period of FY 2005-06
through FY 2007-08.
The Commission directed the Petitioner in Order dt.15.12.06 to submit full facts in
that regard. The Petitioner in affidavit 23.1.07 has stated that the details regarding
left out cost of Rs.29.84 Cr. in year 2003-04 is enclosed in Annexure-4 to the said
affidavit.
It is noted that Annexure-4 includes letters dt. 6.1.2004 and 5.7.2003 of the Petitioner
addressed to UPPCL with the request to UPPCL to incorporate the matter of left out
cost in ARR for the year FY 2003-04. UPJVNL submitted comments on ARR and tariff
application filed by UPPCL for the year 2003-04 vide letter dt.12.3.03. It is found in
39
this letter that the Petitioner did not raise the issue that UPPCL had omitted the cost
of Rs.29.84 Cr in its ARR application.
Petitioner has put up nothing on record to show if it had filed any petition for
seeking review of the order passed by the Commission in the matter of ARR and
tariff petition of UPPCL for year 03-04. As per Regulation no 150 of UPERC
(Conduct of Business) Regulations, 2004, a review of order might be sought within
90 days of such order. The Petitioner did not approach the Commission for review
of the Order within stipulated time. Hence, no consideration on the prayer of the
Petitioner can be made at such delayed stage.
4 Prayer for eligibility to bill for Taxes, Duties and Others
The Petitioner has prayed for allowing it to bill its consumers for taxes, duties, cess,
levies etc, if any is payable by UPJVNL to concerned authorities.
In this respect the Commission directs the Petitioner to carefully read the Uttar
Pradesh Electricity Regulatory Commission (Terms and Conditions of Generation
Tariff) Regulations 2004. In these regulations Income Tax on Core Business has been
recognised as a pass through component of cost. Regulations (7) & (8) describes the
mechanism of recovery of this cost. Under regulation 38(iv), the operation and
maintenance expenses including insurances shall be derived on the basis of actual
O&M expenses, based on audited accounts. This means, that other duties, cess, levies
etc, if any, except for tax on Income and foreign exchange variation, have been
considered as part of O&M expenses. Hence these expenses have already been taken
care of in tariff determination.
5 Payment of Arrears
40
In order dt.15.12.06, the Petitioner was advised to file a separate petition for
consideration of the Commission under Regulation 43 of the Generation Regulation
for recovery of dues from UPPCL. The Petitioner in its affidavit dt.15.1.07 has stated
that it would take up matter with the Government as both the Petitioner and UPPCL
are Undertakings of the same State Govt. In view of submission of the Petitioner, it
is inferred that the Petitioner has no grievance or financial hardship due to huge
receivables owed to it by UPPCL. The Petitioner is advised not to be complacent
with respect to timely payment of bills by sacrificing efficiency in operation,
optimum investments for R&M of old power stations, economical use of resources
by limiting borrowings, good performance and new capacity additions.
6 Billing and Payment
Billing and payment shall be made as per regulation 48 of the Regulation read with
Regulation 43 & 44. Since the capacity charge per unit of salable energy much less
than the lowest variable charges of the thermal generating station of the region as
such Regulation 39 cannot be applied on these generating stations. Therefore, the
rates of primary energy shall be calculated by dividing capacity charges by saleable
design energy subject to annual adjustment at the end of year for under recovery
such that full capacity charges are recovered by the Petitioner, if the generated
energy falls short of saleable energy due to unavailability of water. However, rate of
secondary energy shall be equal to the rate of primary energy. The capacity charges
for year 2005-06 and 2006-07 shall be recovered as per the practice in vogue and
actual availability achieved by the Petitioner. In case, the actual plant availability is
less than the target capacity index specified in the Regulation 32 of the Generation
Regulation, capacity charges shall be prorated. During 2007-08, recovery of capacity
charges shall be linked to capacity index as determined under Regulation 31 (x) in
respect to all generating stations except that of UGC.
The Generation Regulation came into force on 18.6.05 as such the capacity charges for
the period from 1st April, 05 to 17th June, 05 shall be prorated and recovered as per
41
past practice adopted by the Petitioner for recovery of these charges. From 18th June,
05 onward, recovery shall be made as per Regulations 48, read with Regulation 39 of
the Generation Regulations as mentioned in foregoing sub paragraph.
7 Renovation & Modernisation (R&M)
The Petitioner has discussed about R&M of its generating stations in the Petition.
The Petitioner is directed to submit firm financial and execution plan of R&M
works and new capacity additions for approval of the Commission. The Petitioner
is also directed to ensure that all information in respect to new capacity additions,
additional capitalization and R&M works are maintained in the manner as
directed in the Generation Regulations and the precarious situation of
inconsistency and asymmetry faced in this petition is not repeated in the next
tariff filing.
The Petition is hereby disposed of.
(R D Gupta) Member
(Vijoy Kumar) Chairman
Lucknow, dated 26th March, 2007