8/17/2019 Bedford School Board Presentations 4-14-16
1/60
NEW MIDDLE SCHOOL –
SCHOOL BOARD SCHEMATIC
DESIGN PRESENTATION
Bedford County Public Schools
April 14, 2016
8/17/2019 Bedford School Board Presentations 4-14-16
2/60
New Middle School
FLOOR PLANS
8/17/2019 Bedford School Board Presentations 4-14-16
3/60
New Middle School
First Floor Plan
MAIN ENTRY
COURTYARD
SERVICE
DINING/ AUDITORIUM
ENTRY
BUS LOOP/GYMNASIUM
ENTRY
6TH
8/17/2019 Bedford School Board Presentations 4-14-16
4/60
New Middle School
Second Floor Plan
COURTYARD
SECOND FLOORROOF GARDEN
SECOND FLOORROOF GARDEN
MEDIA CENTER
BELOW
GYMNASIUMBELOW
DININGBELOW
7
TH
8
TH
8/17/2019 Bedford School Board Presentations 4-14-16
5/60
New Middle School
OPTION 1
8/17/2019 Bedford School Board Presentations 4-14-16
6/60
New Middle School
Option 1 – Overall Middle & High School Site Plan
8/17/2019 Bedford School Board Presentations 4-14-16
7/60New Middle School
Option 1 – Middle School Site Plan
8/17/2019 Bedford School Board Presentations 4-14-16
8/60New Middle School
Option 1 – Overall High & Middle School Context Aerial
8/17/2019 Bedford School Board Presentations 4-14-16
9/60New Middle School
Option 1 – Middle School Aerial
8/17/2019 Bedford School Board Presentations 4-14-16
10/60
New Middle School
Option 1 – Middle School Aerial 2
8/17/2019 Bedford School Board Presentations 4-14-16
11/60
New Middle School
Option 1 – Middle School Axial Approach
8/17/2019 Bedford School Board Presentations 4-14-16
12/60
New Middle School
Option 1 – Middle School Front Overall
8/17/2019 Bedford School Board Presentations 4-14-16
13/60
New Middle School
Option 1 – Middle School Cafeteria Side
8/17/2019 Bedford School Board Presentations 4-14-16
14/60
New Middle School
Option 1 – Middle School Bus Loop Entry
8/17/2019 Bedford School Board Presentations 4-14-16
15/60
New Middle School
Option 1 – Middle School Courtyard Aerial 2
8/17/2019 Bedford School Board Presentations 4-14-16
16/60
New Middle School
OPTION 2
8/17/2019 Bedford School Board Presentations 4-14-16
17/60
New Middle School
Option 2 – Overall Middle & High School Site Plan
8/17/2019 Bedford School Board Presentations 4-14-16
18/60
New Middle School
Option 2 – Middle School Site Plan
8/17/2019 Bedford School Board Presentations 4-14-16
19/60
New Middle School
Option 2 – Overall High & Middle School Context Aerial
8/17/2019 Bedford School Board Presentations 4-14-16
20/60
New Middle School
Option 2 – Middle School Aerial
8/17/2019 Bedford School Board Presentations 4-14-16
21/60
New Middle School
Option 2 – Middle School Aerial 2
8/17/2019 Bedford School Board Presentations 4-14-16
22/60
New Middle School
Option 2 – Middle School Axial Approach
8/17/2019 Bedford School Board Presentations 4-14-16
23/60
New Middle School
Option 2 – Middle School Front Overall
8/17/2019 Bedford School Board Presentations 4-14-16
24/60
New Middle School
Option 2 – Middle School Front Overall Close
8/17/2019 Bedford School Board Presentations 4-14-16
25/60
New Middle School
Option 2 – Middle School Cafeteria Side
8/17/2019 Bedford School Board Presentations 4-14-16
26/60
New Middle School
Option 2 – Middle School Bus Loop Entry
8/17/2019 Bedford School Board Presentations 4-14-16
27/60
New Middle School
Option 2 – Middle School Courtyard Aerial 2
8/17/2019 Bedford School Board Presentations 4-14-16
28/60
New Middle School
8/17/2019 Bedford School Board Presentations 4-14-16
29/60
New Middle School
8/17/2019 Bedford School Board Presentations 4-14-16
30/60
New Middle School
Site
8/17/2019 Bedford School Board Presentations 4-14-16
31/60
New Middle School
Traffic Study
The turn lane warrant analysis is complete; existing
turn lanes from Big Island Highway into high schoolwill be adequate even after middle school traffic is
added.
The following ‘Concept Plan’ shows a connection
to Otterburn Circle for emergency access only.
The following ‘Road Construction Revenue Sharing’
exhibit has been sent to VDOT to initiate the
Revenue Sharing process. No response yet from
VDOT.
8/17/2019 Bedford School Board Presentations 4-14-16
32/60
New Middle School
8/17/2019 Bedford School Board Presentations 4-14-16
33/60
New Middle School
8/17/2019 Bedford School Board Presentations 4-14-16
34/60
New Middle School
Environmental
Wetland Delineation and Long Eared Bat
investigations are complete. The design team hasscheduled a Wetland Confirmation site visit with
the U.S. Corps of Engineers for April 26th
8/17/2019 Bedford School Board Presentations 4-14-16
35/60
New Middle School
Water
Water model provided by Bedford Regional Water
Authority indicates available flow is 500 gpm at 20psi at the high school. Plumbing fixtures at middle
school will likely require a booster pump.
Discussions with Building Official Donnie Dillon
confirmed that we must comply with 2012International Building Code and NFPA 13 for fire
protection. The design team is working to
determine if the existing water system can meet
these requirements or if a water tank and pump
will be needed. Working with Rich Gardiner on
this issue.
8/17/2019 Bedford School Board Presentations 4-14-16
36/60
New Middle School
Wastewater
The design team is evaluating the following
options: Pump station at middle school that will send wastewater
to high school pump station that will likely need
upgrades to accommodate additional flow.
Build a pump station that that will accommodate middleschool and high school. Existing high school pump
station would be removed from service.
Findings and recommendations will be presented
in the next couple weeks.
8/17/2019 Bedford School Board Presentations 4-14-16
37/60
New Middle School
Schedule
8/17/2019 Bedford School Board Presentations 4-14-16
38/60
New Middle School
April 14
S C H E M A T I C
D E S I G N D E V
C O N S T . D O C
8/17/2019 Bedford School Board Presentations 4-14-16
39/60
New Middle School
Questions & Next Steps
8/17/2019 Bedford School Board Presentations 4-14-16
40/60
LIBERTY HIGH SCHOOL
GYMNASIUM
SCHOOL BOARD SUMMARYPRESENTATION
Bedford County Public Schools
April 14, 2016
8/17/2019 Bedford School Board Presentations 4-14-16
41/60
Liberty High School Gymnasium Addition
Programming
8/17/2019 Bedford School Board Presentations 4-14-16
42/60
Liberty High School Gymnasium Addition
8/17/2019 Bedford School Board Presentations 4-14-16
43/60
Liberty High School Gymnasium Addition
8/17/2019 Bedford School Board Presentations 4-14-16
44/60
Liberty High School Gymnasium Addition
Building Diagrams
8/17/2019 Bedford School Board Presentations 4-14-16
45/60
Liberty High School Gymnasium Addition
94’ court length
1,322 seating capacity
8/17/2019 Bedford School Board Presentations 4-14-16
46/60
Liberty High School Gymnasium Addition
8/17/2019 Bedford School Board Presentations 4-14-16
47/60
Liberty High School Gymnasium Addition
8/17/2019 Bedford School Board Presentations 4-14-16
48/60
Liberty High School Gymnasium Addition
8/17/2019 Bedford School Board Presentations 4-14-16
49/60
Liberty High School Gymnasium Addition
8/17/2019 Bedford School Board Presentations 4-14-16
50/60
Liberty High School Gymnasium Addition
8/17/2019 Bedford School Board Presentations 4-14-16
51/60
Liberty High School Gymnasium Addition
8/17/2019 Bedford School Board Presentations 4-14-16
52/60
Liberty High School Gymnasium Addition
8/17/2019 Bedford School Board Presentations 4-14-16
53/60
Liberty High School Gymnasium Addition
8/17/2019 Bedford School Board Presentations 4-14-16
54/60
Liberty High School Gymnasium Addition
8/17/2019 Bedford School Board Presentations 4-14-16
55/60
Liberty High School Gymnasium Addition
Schedule
8/17/2019 Bedford School Board Presentations 4-14-16
56/60
Liberty High School Gymnasium Addition
8/17/2019 Bedford School Board Presentations 4-14-16
57/60
Cost
• Proposed Project
8/17/2019 Bedford School Board Presentations 4-14-16
58/60
SITEWORK $ 6,200,000 $ 6,400,000
NEW MIDDLE SCHOOL $ 23,800,000 $ 24,000,000
COMPETITION GYM $ 4,800,000 $ 5,000,000
Soft Costs (design, testing, mgmt.,procure, etc.)
$ 4,700,000 $ 4,700,000
Subtotal $ 39,500,000 $ 40,200,000
OTHER OWNER COSTS(furniture, technology, project
contingency)
$ 4,200,000 $ 4,200,000
Inflation (included in cost above) $ 0 $ 0
TOTAL PROJECT COST $ 43,700,000 $ 44,400,000
Proposed Project• New 700 student middle school• Approximately 120,000 SF• High school gym is a stand alone project on
LHS campus• Approximately 19,000 SF
• Upcoming Cost Impact Decisions
8/17/2019 Bedford School Board Presentations 4-14-16
59/60
Upcoming Cost Impact Decisions
• Site Conditions• Potential road construction revenue-sharing (VDOT)
• Wetlands – Corps of Engineers (Site visit 04/26/16)• Water supply – possible water tank for sprinkler system• Sanitary sewer design
• Systems Selection• HVAC, Controls, Lighting, Roofing, etc.
• Materials Selection• Exterior & interior walls, floors, equipment brands, etc.
• Alternate Funding for Specific Items• FF&E (Fixtures, furnishings & equipment)• Technology
8/17/2019 Bedford School Board Presentations 4-14-16
60/60
Questions & Next Steps