Bear Creek System Impact Study

Embed Size (px)

Citation preview

  • 8/2/2019 Bear Creek System Impact Study

    1/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    XXXX

    Bear Creek Hydro Generation Project

    System Impact Study

    Report No.SPA 2005-27

    August, 2005

    System Planning (Lower Mainland & Vancouver Island)

    British Columbia Transmission Corporation

    British Columbia Transmission Corporation, 2005. All rights reserved.

    i

  • 8/2/2019 Bear Creek System Impact Study

    2/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    DISCLAIMER OF WARRANTY, LIMITATION OF LIABILITY

    This report was prepared by BCTC solely for use by XXXX for the purposes ofconnecting Bear Creek Hydro IPP into the Transmission System. This report is based on

    information provided to BCTC as of the date of this report. Accordingly, this report issuitable only for such purposes, and is subject to any changes arising after the date of this

    report.

    Unless otherwise expressly agreed by BCTC, BCTC does not represent or warrant theaccuracy, completeness or usefulness of this report, or any information contained in this

    report, for use or consideration by any third party, nor does BCTC accept any liability out

    of reliance by a third party on this report, or any information contained in this report, orfor any errors or omissions in this report. Any use or reliance by third parties is at their

    own risk.

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    ii

  • 8/2/2019 Bear Creek System Impact Study

    3/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    Executive Summary

    This report indicates the interconnection cost estimates associated with the

    interconnection of the proposed 19.3 MW of generation at XXXXs Upper Bear Creek

    and Lower Bear Creek hydro electric generating facilities. The report also provides atechnical review and identifies major requirements to connect the proposed generation to

    the Transmission System.

    In order to connect the proposed 19.3 MW of generation at Upper and Lower Bear Creek

    to the Transmission System, the following requirements are identified:

    IPP to build a new 138 kV transmission circuit from its generating facilities to anew 138 kV substation next to the Clowhom substation. This new Bear Creek IPP

    station will share the same ground grid with Clowhom. An overhead tie of no

    more than 200 meters will tie this new station to Clowhom and power will go into

    the Transmission System at Clowhoms existing 1L44 connection.

    Sections of transmission circuit 1L44 must be upgraded to a higher summerthermal rating. Clowhom to Sechelt Creek Tap section must be upgraded to a

    summer rating of not less than 240 amperes and Sechelt Creek Tap to Sechelt

    section to a summer rating of not less than 300 amperes.

    Line protection of 1L44 must be modified to including tripping of the circuitbreaker at the entrance to the new Bear Creek IPP station.

    Bear Creek IPP transformers must have grounded wye HV and delta LVconfiguration.

    Communication facilities will be required to enable communication with controlcentres.

    In connection with the above, the subsequent Interconnection Facilities Study report and

    PIR will discuss additional requirements.

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    iii

  • 8/2/2019 Bear Creek System Impact Study

    4/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    Table of Content

    Executive Summary

    1.0 Introduction 2

    2.0 Purpose of Study 3

    2.1 Terms of Reference 3

    3.0 Data and Modeling 4

    4.0 System Studies 4

    4.1 Steady State Power Flow study 54.2 Short Circuit study 5

    4.3 Transient Stability study 6

    4.4 Protection study 74.5 Remedial Action Schemes 7

    4.6 Black Start Capability 7

    5.0 Reinforcement and Upgrades 8

    6.0 Conclusion 8

    AppendixOne-line Diagram: Normal System before Bear IPP 9

    One-line Diagram: Normal System after Bear IPP 10

    One-line Diagram: System with Bear IPP, 1L35 out of service 11One-line Diagram: System with Bear IPP, 1L32 out of service 12

    Machine Data; Salient Pole Generator GENSAL 13Machine Data: Simplified Excitation System SEXS 14

    Machine Data: Hydro Turbine-Governor HYGOV 15

    Stability Plot 1: 10 cycle fault on Bears 138 kV line betweenUpper and Lower Bear near Lower Bear 16

    Stability Plot 2: 9 cycle fault on Bears 138 kV line between

    Lower Bear and Bear Station near Bear station 17Stability Plot 3: 9 cycle fault on 1L32 between SEC and

    Gibsons (GIB) near SEC 18

    Stability Plot 4: 8 cycle fault on 1L35 between SEC and

    Malaspina (MSA) near SEC 19

    Stability Plot 5: 9 cycle bus fault at SEC 20One-line Diagram: Clowhom AC Conceptual Protection 21

    Control Diagram: Clowhom Generating Station 22Control Diagram: Bear Station BRK 23

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    iv

  • 8/2/2019 Bear Creek System Impact Study

    5/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    1.0 Introduction

    XXXX (the IPP) is proposing to develop two hydro electric generating facilities at

    Upper Bear Creek and Lower Bear Creek in the Clowhom Peninsula region of the

    Sunshine Coast. These two hydro electric generating facilities are collectively referred toas the Bear Creek Hydro IPP in this report.

    Upper Bear has a single 13.8 kV 13 MVA hydro generating unit running at 0.9 powerfactor. The maximum output from this unit is 11.7 MW. Lower Bear has a similar unit

    rated at 8.5 MVA, with a maximum output of 7.65 MW. The distance between Upper

    and Lower Bear is 7.5 km. XXXX proposes to build a 138 kV overhead transmission line

    from Upper Bear to Lower Bear, and extend this line by a further 6.2 km to connect to theTransmission System near the Clowhom substation.

    The Point of Interconnection is near the Clowhom Generating Station (COM). XXXXwill construct a 138 kV Bear Creek (BRK) substation near COM. The tie between COM

    and BRK substation will not be more than 200 meters. Power generated by Bear CreekHydro IPP will enter the transmission system by way of the existing COM tie to

    transmission line 1L44 which runs between COM and Sechelt (SEC).

    The proposed in service date is September 2006.

    The following diagram shows the IPP with its proposed generators, new 138 kVtransmission circuit, new BRK substation, transmission circuit 1L44, and nearby BCTC

    substations (COM, SEC and Sechelt Creek IPP (SCG)).

    SEC 138 COM 138

    1L44

    Bear Station

    SCG T2

    G2

    Lower Bear

    7.65 MW

    Sechelt

    Creek IPP

    (138 kV)

    T1

    G1

    Upper Bear

    11.7 MW

    Transmission

    System

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    2

  • 8/2/2019 Bear Creek System Impact Study

    6/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    2.0 Purpose of Study

    To ensure safe and reliable operation of the Transmission System with Bear Creek HydroIPP added to the system, the purpose of this study is to assess the impact on the

    Transmission System arising from the integration of the IPP. The study identifies

    Transmission System constraints and proposes required upgrades and reinforcements forthe network. The study also identifies the IPP requirements in order to connect to the

    Transmission System.

    2.1 Terms of Reference

    This Interconnection Impact Study (IIS) was conducted under the following Terms of

    Reference:

    WECC reliability Criteria

    Existing planning and operating criteria, standards and procedures that conform toWECC Reliability Criteria, to determine necessary transmission system

    reinforcements have been followed.

    Technical Studies

    The following studies have been performed:

    - Power flow analysis to assess the impacts on transmission network and operatingvoltage profiles.

    - Transient stability analysis to assess system dynamics performance.- Protection study to assess protection requirements for the Transmission System.

    Designations

    The following are BCTC operating designations used throughout this report.

    Item Operating Designation

    BC Hydro BCH

    BC Transmission Corporation BCTC

    XXXX Break Creek Hydro generatingstation

    IPP

    Bear Creek IPP substation next to COM BRK

    System Control Centre SCC

    Northern Control Centre NCC

    South Interior Control Centre SIC

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    3

  • 8/2/2019 Bear Creek System Impact Study

    7/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    Clowhom Generating Station COM

    Sechelt Creek IPP Tap SCG

    Sechelt substation SEC

    Gibsons 138 kV substation GIB

    Pender Harbor 138 kV substation PHR

    Malaspina 138 kV substation MSA

    138 kV transmission circuit connectingCOM, SCG and SEC

    1L44

    138 kV transmission circuit connecting

    SEC and GIB

    1L32

    138 kV transmission circuit connecting

    SEC, PHR and MSA

    1L35

    Interconnection Impact Study IIS

    3.0 Data and Modeling

    The study was carried out based on the data and information provided in the IPPs

    Generation Interconnection Application dated March 1, 2005. The data provided in the

    Application was used in the analysis and the results of the study are dependent on theiraccuracy. Whenever there was missing data required for the study, typical data for similar

    equipment was used. Bear Creek Hydro IPP generating equipment with their respective

    PSS/E models GENSAL, SEXS and HYGOV, are shown in the appendix.

    A 2006/07 Heavy Winter load flow base case was used as the basis for the study. For the

    Clowhom Peninsula where Bear Creek Hydro IPP will be connected, the following

    assumptions were used:

    COM generation 33 MW

    SCG generation 16 MW

    Upper Bear generation 11.7 MW

    Lower Bear generation 7.65 MW

    1L44 summer rating (COM to SCG) 170 amps

    1L44 summer rating (SCG to SEC) 260 amps

    1L44 circuit length 37.3 km

    4.0 System Studies

    Load flow, short circuit and transient stability studies were carried out to evaluate theimpact of the IPP on the Transmission System, and to identify the requirements in order

    to connect the Bear Creek Hydro IPP into the Transmission System.

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    4

  • 8/2/2019 Bear Creek System Impact Study

    8/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    4.1 Steady State Power Flow Study

    The IPP connects to the Transmission System via COM. All its generation,

    together with those from COM and SCG, are evacuated to the main grid viatransmission line 1L44. 1L44 runs from COM to SEC, and collects generation

    from COM and Bear Creek Hydro IPP at COM, and generation for SCG at some

    point 6 km from COM. There is no customer load on 1L44 between COM andSEC. Loading on the transmission line depends entirely on the output from the

    generators at COM, SCG and Bear Creek Hydro IPP. The present role of 1L44 isto transfer all the power from the generators connected to this line to the main

    grid at SEC. The following table shows the existing thermal rating of 1L44, and

    the flow on 1L44 before and after the integration of Bear Creek Hydro IPP.

    1L44 Rating and Flows in Amperes

    COM-SCG SCG-SEC

    Rating No IPP With IPP Rating No IPP With IPP

    Summer 170 137 220 260 205 288

    Winter 280 137 220 440 205 288

    It can be concluded from the above table that the summer thermal rating for the

    entire length of 1L44 will be exceeded when Bear Creek Hydro IPP is added and

    when all Bear Creek Hydro IPP, COM and SCG generators are generating at theirmaximum capacity.

    There is no overloading on 1L44 during the winter for the above scenario.

    In the event that 1L35 between SEC and MSA or 1L32 between SEC and GIB isout of service, all generation from the Clowhom Peninsula will flow into the grid

    on the remaining circuit. There is sufficient capacity in the circuit and no overload

    will occur. No abnormal voltages have been observed.

    4.2 Short Circuit Study

    Three Phase Short Circuit in MVA at the SEC and COM station buses are

    affected by generation addition. The calculated fault levels are based on existing

    system with no generation addition and with the proposed generation addition.

    The calculated fault levels are derived from the Protection Planning ASPEN One

    Liner Fault Study Case BRK2005_asp2004r2.olr. The power system is modeled

    with 1.0 pu pre fault voltage, no shunts, and in the subtransient time frame. Thegeneration addition is modeled based on data provided by the customer.

    IPP generation at Bear Creek Hydro IPP consists of Upper Bear and Lower Beargenerators. Upper Bear will have one 13 MVA generator @ 13.8 kV with

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    5

  • 8/2/2019 Bear Creek System Impact Study

    9/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    subtransient reactance of 1.99% and Lower Bear will have one 8.5 MVAgenerator @13.8 kV with subtransient reactance of 2%. The IPP transformers are

    grounded wye on the 138 kV and delta on the 13.8 kV side.

    The fault level for the Existing System with no Generation Addition1. For 3LG Bus fault at SEC 138 kV, Short Circuit MVA = 11452. For 3LG Bus fault at COM 138 kV, Short Circuit MVA = 5003. For 3LG Bus fault at SCG 138 kV, Short Circuit MVA = 545

    The fault level for the Existing System with Proposed Generation Addition

    1. For 3LG Bus fault at SEC 138 kV, Short Circuit MVA = 11952. For 3LG Bus fault at COM 138 kV, Short Circuit MVA = 5703. For 3LG Bus fault at SCG 138 kV, Short Circuit MVA = 610

    The fault level contribution from the proposed IPP generation, in terms of itsimpact on the Transmission System, is not considered severe. IPP impact on the

    fault duty of the system does not require any reinforcement.

    4.3 Transient Stability Study

    1L44 is a radial connection to the main transmission grid for all the generation in

    the Clowhom Peninsula. When 1L44 is opened due to a fault, or due to a plannedoperation, all generators in the Clowhom Peninsula must stop generating. For

    planned line outages, generators must be disconnected from the system before

    opening the line. For forced outage, existing high speed line protection must trip

    the breakers at COM and SCG. Since the tie between the new BRK substation andCOM is less than 200 meters, and BRK transformers have HV grounded wye, LV

    delta configuration, existing 1L44 line protection can be modified to include

    tripping of COM and the breaker at the entrance of the BRK substation. This willavoid the requirement and the cost of a Direct Transfer Trip for the IPP. However,

    the IPP should have adequate protection for its equipment for such an event.

    The swing centre is within the IPPs generator and out of step protection is

    recommended.

    For transient stability concerns, studies were performed to evaluate the impact on

    the main system and on the IPP when there is a fault inside the IPP system or in

    the Transmission System. The following scenarios were investigated, and

    corresponding findings tabulated:

    Description Stable

    1 8 cycle fault on Bears 138 kV line between Upper and Lower Bearnear Lower Bear

    *Yes

    2 9 cycle fault on Bears 138 kV line between Upper and Lower Bear Yes

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    6

  • 8/2/2019 Bear Creek System Impact Study

    10/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    near Lower Bear

    3 10 cycle fault on Bears 138 kV line between Upper and Lower Bear

    near Lower Bear

    Yes

    4 8 cycle fault on Bears 138 kV line between Lower Bear and BearStation near Bear station

    *Yes

    5 9 cycle fault on Bears 138 kV line between Lower Bear and BearStation near Bear station

    *Yes

    6 10 cycle fault on Bears 138 kV line between Lower Bear and BearStation near Bear station

    No

    7 12 cycle fault on Bears 138 kV line between Lower Bear and BearStation and near Bear station

    No

    8 8 cycle fault on 1L32 between SEC and Gibsons (GIB) near SEC Yes

    9 9 cycle fault on 1L32 between SEC and GIB near SEC Yes

    10 10 cycle fault on 1L32 between SEC and GIB near SEC No

    11 12 cycle fault on 1L32 between SEC and GIB near SEC No

    12 8 cycle fault on 1L35 between SEC and Malaspina (MSA) near SEC Yes

    13 9 cycle fault on 1L35 between SEC and MSA near SEC No14 10 cycle fault on 1L35 between SEC and MSA near SEC No

    15 12 cycle fault on 1L35 between SEC and MSA near SEC No

    16 40 cycle fault on 1L32 near GIB No

    17 40 cycle fault on 1L35 near Pender Harbor (PHR) No

    18 6 cycle bus fault at SEC Yes

    19 8 cycle bus fault at SEC Yes

    20 9 cycle bus fault at SEC Yes

    21 10 cycle bus fault at SEC No

    *Yes Bear IPP generators will be lost, but COM and SCG remains stable

    4.4 Protection Study

    Assumptions:

    BRK and COM share the same ground grid, and the overhead tie is notmore than 200 meter.

    BRK transformers have grounded wye on the high side, and delta on thelow side.

    Existing high speed line protection for 1L44 will isolate COM and SCG in theevent of a fault resulting in the opening of 1L44. This protection can be modified

    to include the IPP by tripping the circuit breaker at the entrance to the new Bearstation (BRK). No direct transfer trip to the IPP is required.

    4.5 Remedial Action Schemes

    No generation shedding is required.

    4.6 Black Start Capability

    BCTC does not require black start capability for the Bear Creek Hydro IPP.

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    7

  • 8/2/2019 Bear Creek System Impact Study

    11/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    5.0 Reinforcements and Upgrades

    The required Transmission System upgrades for Bear Creek Hydro IPP

    interconnection are described in the Bear Creek IPP Interconnection FacilityStudy, BCTC SPA Report SPA 2005-33.

    6.0 Conclusions

    6.1 The Bear Creek Hydro IPP interconnection was found to be technicallyfeasible.

    6.2 Sections of 1L44 need to be upgraded to higher summer thermal ratings.

    6.3 1L44 line protection needs to be modified to include tripping the BRKentrance circuit breaker in the event of a fault on 1L44.

    6.4 No transient or temporary overvoltage problems are observed.

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    8

  • 8/2/2019 Bear Creek System Impact Study

    12/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    Appendix

    One-Line Diagram 1: Normal System before Bear Creek Hydro IPP

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    9

  • 8/2/2019 Bear Creek System Impact Study

    13/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    One-Line Diagram 2: Normal System with Bear Creek Hydro IPP

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    10

  • 8/2/2019 Bear Creek System Impact Study

    14/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    One-Line Diagram 3: System with Bear Creek Hydro IPP, 1L35 Out of Service

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    11

  • 8/2/2019 Bear Creek System Impact Study

    15/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    One-Line Diagram 4: System with Bear Creek Hydro IPP, 1L32 Out of Service

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    12

  • 8/2/2019 Bear Creek System Impact Study

    16/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    Machine Data

    Salient Pole Generator (Quadratic Saturation on d-Axis) model GENSAL:

    Upper Bear G1 Lower Bear G2Tdo 4.24 3.55

    Tdo 0.07 0.07

    Tqo 0.11 0.11

    Inertia, H 2 2

    Speed Damping D 1 1

    Xd 1.88 1.8

    Xq 1.74 1.7

    Xd 0.299 0.31

    Xd=Xq .199 0.2

    X1 0.19 0.19

    S(1.0) 0.194 0.685S(1.2) 0.194 0.685

    Xd, Xq, Xd, Xd, Xq, X1, H and D are in pu, machine MVA base

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    13

  • 8/2/2019 Bear Creek System Impact Study

    17/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    Machine Data

    Simplified Excitation System model SEXS:

    Upper Bear G1 Lower Bear G2TA/TB 1.0 1.0

    TB 1.0 1.0

    K 20 20

    TE (sec) 0.5 0.5

    Emin (pu on EFD base) -3.0 -3.0

    Emax (pu on EFD base) 3.0 3

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    14

  • 8/2/2019 Bear Creek System Impact Study

    18/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    Machine Data

    Hydro Turbine-Governor model HGOV:

    Upper Bear G1 Lower Bear G2

    R, permanent droop 0.05 0.05

    R, temporary droop 5 5

    Tr, governor time constant 15 15

    Tffilter time constant 0.04 0.04

    Tg servo time constant 0.2 0.2

    +/- VELM, gate velocity limit 0.07 0.07

    Gmax maximum gate limit 1 1

    Gmin Minimum gate limit 0 0Tw water time constant 3.5 3.5

    At turbine gain 1.1 1.1

    Dturb turbine damping 0 0

    qNL, no load flow 0.08 0.08

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    15

  • 8/2/2019 Bear Creek System Impact Study

    19/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    Stability Plot 1: 10 cycle fault on Bears 138 kV line between Upper and Lower Bear

    near Lower Bear (3)

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    16

  • 8/2/2019 Bear Creek System Impact Study

    20/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    Stability Plot 2: 9 cycle fault on Bears 138 kV line between Lower Bear and BearStation near Bear station (5)

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    17

  • 8/2/2019 Bear Creek System Impact Study

    21/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    Stability Plot 3: 9 cycle fault on 1L32 between SEC and Gibsons (GIB) near SEC(10)

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    18

  • 8/2/2019 Bear Creek System Impact Study

    22/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    Stability Plot 4: 8 cycle fault on 1L35 between SEC and Malaspina (MSA) nearSEC (8)

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    19

  • 8/2/2019 Bear Creek System Impact Study

    23/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    Stability Plot 5: 9 cycle bus fault at SEC (11)

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    20

  • 8/2/2019 Bear Creek System Impact Study

    24/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    Clowhom AC Conceptual Protection One-line Diagram:

    ~

    COM

    138 kV

    1L4413CB1

    ~

    ~

    T1

    C/S(52L)

    UPPER BEAR LAKE13 MVA

    LOWER BEAR LAKE8.5 MVA

    COM (BCTC)

    BRK (IPP)

    COM Conceptual AC ProtectionOne Line Diagram

    BEAR CREEK HYDRO ProjectSketch # 1

    B.J. Burk July 07 2005

    21LS

    21L

    *

    Notes:* Inidicates New Relay

    1CVT1

    *

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    21

  • 8/2/2019 Bear Creek System Impact Study

    25/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    Control Diagram for Bear Station

    DNP3.0 IED(provided by Bear Creek

    Hydro IPP)

    data from both UpperBear and Lower Bear

    SIC

    2 status

    8 telemetry

    LMC

    DDC1

    DataConcentrator

    D20

    ScopeStation:

    DWG No SH R

    BRK IPP

    SK11 0

    By:

    Date: 24-June-

    2005

    G. Jang

    SCC

    SIC

    ________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC

    22

  • 8/2/2019 Bear Creek System Impact Study

    26/26

    Bear Creek Hydro IPP Interconnection System Impact Study August 2005

    Control Diagram for Clowhom Generating Station

    SIC

    STIC

    COMS223/T119

    new relay alarms

    4 new telemetry

    ScopeStation:

    DWG No SH R

    COM

    SK21 0

    By:

    Date: 08-July-

    2005

    G. Jang

    New SEL-203X (at COM) 2 new relays

    LMC

    Edmonds(Remote Data Access)

    BCH legacy protocol

    SEL protocol

    1 status