Upload
mohammad-mahdi-bozorgzadeh
View
219
Download
0
Embed Size (px)
Citation preview
8/2/2019 Bear Creek System Impact Study
1/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
XXXX
Bear Creek Hydro Generation Project
System Impact Study
Report No.SPA 2005-27
August, 2005
System Planning (Lower Mainland & Vancouver Island)
British Columbia Transmission Corporation
British Columbia Transmission Corporation, 2005. All rights reserved.
i
8/2/2019 Bear Creek System Impact Study
2/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
DISCLAIMER OF WARRANTY, LIMITATION OF LIABILITY
This report was prepared by BCTC solely for use by XXXX for the purposes ofconnecting Bear Creek Hydro IPP into the Transmission System. This report is based on
information provided to BCTC as of the date of this report. Accordingly, this report issuitable only for such purposes, and is subject to any changes arising after the date of this
report.
Unless otherwise expressly agreed by BCTC, BCTC does not represent or warrant theaccuracy, completeness or usefulness of this report, or any information contained in this
report, for use or consideration by any third party, nor does BCTC accept any liability out
of reliance by a third party on this report, or any information contained in this report, orfor any errors or omissions in this report. Any use or reliance by third parties is at their
own risk.
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
ii
8/2/2019 Bear Creek System Impact Study
3/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
Executive Summary
This report indicates the interconnection cost estimates associated with the
interconnection of the proposed 19.3 MW of generation at XXXXs Upper Bear Creek
and Lower Bear Creek hydro electric generating facilities. The report also provides atechnical review and identifies major requirements to connect the proposed generation to
the Transmission System.
In order to connect the proposed 19.3 MW of generation at Upper and Lower Bear Creek
to the Transmission System, the following requirements are identified:
IPP to build a new 138 kV transmission circuit from its generating facilities to anew 138 kV substation next to the Clowhom substation. This new Bear Creek IPP
station will share the same ground grid with Clowhom. An overhead tie of no
more than 200 meters will tie this new station to Clowhom and power will go into
the Transmission System at Clowhoms existing 1L44 connection.
Sections of transmission circuit 1L44 must be upgraded to a higher summerthermal rating. Clowhom to Sechelt Creek Tap section must be upgraded to a
summer rating of not less than 240 amperes and Sechelt Creek Tap to Sechelt
section to a summer rating of not less than 300 amperes.
Line protection of 1L44 must be modified to including tripping of the circuitbreaker at the entrance to the new Bear Creek IPP station.
Bear Creek IPP transformers must have grounded wye HV and delta LVconfiguration.
Communication facilities will be required to enable communication with controlcentres.
In connection with the above, the subsequent Interconnection Facilities Study report and
PIR will discuss additional requirements.
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
iii
8/2/2019 Bear Creek System Impact Study
4/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
Table of Content
Executive Summary
1.0 Introduction 2
2.0 Purpose of Study 3
2.1 Terms of Reference 3
3.0 Data and Modeling 4
4.0 System Studies 4
4.1 Steady State Power Flow study 54.2 Short Circuit study 5
4.3 Transient Stability study 6
4.4 Protection study 74.5 Remedial Action Schemes 7
4.6 Black Start Capability 7
5.0 Reinforcement and Upgrades 8
6.0 Conclusion 8
AppendixOne-line Diagram: Normal System before Bear IPP 9
One-line Diagram: Normal System after Bear IPP 10
One-line Diagram: System with Bear IPP, 1L35 out of service 11One-line Diagram: System with Bear IPP, 1L32 out of service 12
Machine Data; Salient Pole Generator GENSAL 13Machine Data: Simplified Excitation System SEXS 14
Machine Data: Hydro Turbine-Governor HYGOV 15
Stability Plot 1: 10 cycle fault on Bears 138 kV line betweenUpper and Lower Bear near Lower Bear 16
Stability Plot 2: 9 cycle fault on Bears 138 kV line between
Lower Bear and Bear Station near Bear station 17Stability Plot 3: 9 cycle fault on 1L32 between SEC and
Gibsons (GIB) near SEC 18
Stability Plot 4: 8 cycle fault on 1L35 between SEC and
Malaspina (MSA) near SEC 19
Stability Plot 5: 9 cycle bus fault at SEC 20One-line Diagram: Clowhom AC Conceptual Protection 21
Control Diagram: Clowhom Generating Station 22Control Diagram: Bear Station BRK 23
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
iv
8/2/2019 Bear Creek System Impact Study
5/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
1.0 Introduction
XXXX (the IPP) is proposing to develop two hydro electric generating facilities at
Upper Bear Creek and Lower Bear Creek in the Clowhom Peninsula region of the
Sunshine Coast. These two hydro electric generating facilities are collectively referred toas the Bear Creek Hydro IPP in this report.
Upper Bear has a single 13.8 kV 13 MVA hydro generating unit running at 0.9 powerfactor. The maximum output from this unit is 11.7 MW. Lower Bear has a similar unit
rated at 8.5 MVA, with a maximum output of 7.65 MW. The distance between Upper
and Lower Bear is 7.5 km. XXXX proposes to build a 138 kV overhead transmission line
from Upper Bear to Lower Bear, and extend this line by a further 6.2 km to connect to theTransmission System near the Clowhom substation.
The Point of Interconnection is near the Clowhom Generating Station (COM). XXXXwill construct a 138 kV Bear Creek (BRK) substation near COM. The tie between COM
and BRK substation will not be more than 200 meters. Power generated by Bear CreekHydro IPP will enter the transmission system by way of the existing COM tie to
transmission line 1L44 which runs between COM and Sechelt (SEC).
The proposed in service date is September 2006.
The following diagram shows the IPP with its proposed generators, new 138 kVtransmission circuit, new BRK substation, transmission circuit 1L44, and nearby BCTC
substations (COM, SEC and Sechelt Creek IPP (SCG)).
SEC 138 COM 138
1L44
Bear Station
SCG T2
G2
Lower Bear
7.65 MW
Sechelt
Creek IPP
(138 kV)
T1
G1
Upper Bear
11.7 MW
Transmission
System
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
2
8/2/2019 Bear Creek System Impact Study
6/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
2.0 Purpose of Study
To ensure safe and reliable operation of the Transmission System with Bear Creek HydroIPP added to the system, the purpose of this study is to assess the impact on the
Transmission System arising from the integration of the IPP. The study identifies
Transmission System constraints and proposes required upgrades and reinforcements forthe network. The study also identifies the IPP requirements in order to connect to the
Transmission System.
2.1 Terms of Reference
This Interconnection Impact Study (IIS) was conducted under the following Terms of
Reference:
WECC reliability Criteria
Existing planning and operating criteria, standards and procedures that conform toWECC Reliability Criteria, to determine necessary transmission system
reinforcements have been followed.
Technical Studies
The following studies have been performed:
- Power flow analysis to assess the impacts on transmission network and operatingvoltage profiles.
- Transient stability analysis to assess system dynamics performance.- Protection study to assess protection requirements for the Transmission System.
Designations
The following are BCTC operating designations used throughout this report.
Item Operating Designation
BC Hydro BCH
BC Transmission Corporation BCTC
XXXX Break Creek Hydro generatingstation
IPP
Bear Creek IPP substation next to COM BRK
System Control Centre SCC
Northern Control Centre NCC
South Interior Control Centre SIC
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
3
8/2/2019 Bear Creek System Impact Study
7/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
Clowhom Generating Station COM
Sechelt Creek IPP Tap SCG
Sechelt substation SEC
Gibsons 138 kV substation GIB
Pender Harbor 138 kV substation PHR
Malaspina 138 kV substation MSA
138 kV transmission circuit connectingCOM, SCG and SEC
1L44
138 kV transmission circuit connecting
SEC and GIB
1L32
138 kV transmission circuit connecting
SEC, PHR and MSA
1L35
Interconnection Impact Study IIS
3.0 Data and Modeling
The study was carried out based on the data and information provided in the IPPs
Generation Interconnection Application dated March 1, 2005. The data provided in the
Application was used in the analysis and the results of the study are dependent on theiraccuracy. Whenever there was missing data required for the study, typical data for similar
equipment was used. Bear Creek Hydro IPP generating equipment with their respective
PSS/E models GENSAL, SEXS and HYGOV, are shown in the appendix.
A 2006/07 Heavy Winter load flow base case was used as the basis for the study. For the
Clowhom Peninsula where Bear Creek Hydro IPP will be connected, the following
assumptions were used:
COM generation 33 MW
SCG generation 16 MW
Upper Bear generation 11.7 MW
Lower Bear generation 7.65 MW
1L44 summer rating (COM to SCG) 170 amps
1L44 summer rating (SCG to SEC) 260 amps
1L44 circuit length 37.3 km
4.0 System Studies
Load flow, short circuit and transient stability studies were carried out to evaluate theimpact of the IPP on the Transmission System, and to identify the requirements in order
to connect the Bear Creek Hydro IPP into the Transmission System.
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
4
8/2/2019 Bear Creek System Impact Study
8/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
4.1 Steady State Power Flow Study
The IPP connects to the Transmission System via COM. All its generation,
together with those from COM and SCG, are evacuated to the main grid viatransmission line 1L44. 1L44 runs from COM to SEC, and collects generation
from COM and Bear Creek Hydro IPP at COM, and generation for SCG at some
point 6 km from COM. There is no customer load on 1L44 between COM andSEC. Loading on the transmission line depends entirely on the output from the
generators at COM, SCG and Bear Creek Hydro IPP. The present role of 1L44 isto transfer all the power from the generators connected to this line to the main
grid at SEC. The following table shows the existing thermal rating of 1L44, and
the flow on 1L44 before and after the integration of Bear Creek Hydro IPP.
1L44 Rating and Flows in Amperes
COM-SCG SCG-SEC
Rating No IPP With IPP Rating No IPP With IPP
Summer 170 137 220 260 205 288
Winter 280 137 220 440 205 288
It can be concluded from the above table that the summer thermal rating for the
entire length of 1L44 will be exceeded when Bear Creek Hydro IPP is added and
when all Bear Creek Hydro IPP, COM and SCG generators are generating at theirmaximum capacity.
There is no overloading on 1L44 during the winter for the above scenario.
In the event that 1L35 between SEC and MSA or 1L32 between SEC and GIB isout of service, all generation from the Clowhom Peninsula will flow into the grid
on the remaining circuit. There is sufficient capacity in the circuit and no overload
will occur. No abnormal voltages have been observed.
4.2 Short Circuit Study
Three Phase Short Circuit in MVA at the SEC and COM station buses are
affected by generation addition. The calculated fault levels are based on existing
system with no generation addition and with the proposed generation addition.
The calculated fault levels are derived from the Protection Planning ASPEN One
Liner Fault Study Case BRK2005_asp2004r2.olr. The power system is modeled
with 1.0 pu pre fault voltage, no shunts, and in the subtransient time frame. Thegeneration addition is modeled based on data provided by the customer.
IPP generation at Bear Creek Hydro IPP consists of Upper Bear and Lower Beargenerators. Upper Bear will have one 13 MVA generator @ 13.8 kV with
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
5
8/2/2019 Bear Creek System Impact Study
9/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
subtransient reactance of 1.99% and Lower Bear will have one 8.5 MVAgenerator @13.8 kV with subtransient reactance of 2%. The IPP transformers are
grounded wye on the 138 kV and delta on the 13.8 kV side.
The fault level for the Existing System with no Generation Addition1. For 3LG Bus fault at SEC 138 kV, Short Circuit MVA = 11452. For 3LG Bus fault at COM 138 kV, Short Circuit MVA = 5003. For 3LG Bus fault at SCG 138 kV, Short Circuit MVA = 545
The fault level for the Existing System with Proposed Generation Addition
1. For 3LG Bus fault at SEC 138 kV, Short Circuit MVA = 11952. For 3LG Bus fault at COM 138 kV, Short Circuit MVA = 5703. For 3LG Bus fault at SCG 138 kV, Short Circuit MVA = 610
The fault level contribution from the proposed IPP generation, in terms of itsimpact on the Transmission System, is not considered severe. IPP impact on the
fault duty of the system does not require any reinforcement.
4.3 Transient Stability Study
1L44 is a radial connection to the main transmission grid for all the generation in
the Clowhom Peninsula. When 1L44 is opened due to a fault, or due to a plannedoperation, all generators in the Clowhom Peninsula must stop generating. For
planned line outages, generators must be disconnected from the system before
opening the line. For forced outage, existing high speed line protection must trip
the breakers at COM and SCG. Since the tie between the new BRK substation andCOM is less than 200 meters, and BRK transformers have HV grounded wye, LV
delta configuration, existing 1L44 line protection can be modified to include
tripping of COM and the breaker at the entrance of the BRK substation. This willavoid the requirement and the cost of a Direct Transfer Trip for the IPP. However,
the IPP should have adequate protection for its equipment for such an event.
The swing centre is within the IPPs generator and out of step protection is
recommended.
For transient stability concerns, studies were performed to evaluate the impact on
the main system and on the IPP when there is a fault inside the IPP system or in
the Transmission System. The following scenarios were investigated, and
corresponding findings tabulated:
Description Stable
1 8 cycle fault on Bears 138 kV line between Upper and Lower Bearnear Lower Bear
*Yes
2 9 cycle fault on Bears 138 kV line between Upper and Lower Bear Yes
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
6
8/2/2019 Bear Creek System Impact Study
10/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
near Lower Bear
3 10 cycle fault on Bears 138 kV line between Upper and Lower Bear
near Lower Bear
Yes
4 8 cycle fault on Bears 138 kV line between Lower Bear and BearStation near Bear station
*Yes
5 9 cycle fault on Bears 138 kV line between Lower Bear and BearStation near Bear station
*Yes
6 10 cycle fault on Bears 138 kV line between Lower Bear and BearStation near Bear station
No
7 12 cycle fault on Bears 138 kV line between Lower Bear and BearStation and near Bear station
No
8 8 cycle fault on 1L32 between SEC and Gibsons (GIB) near SEC Yes
9 9 cycle fault on 1L32 between SEC and GIB near SEC Yes
10 10 cycle fault on 1L32 between SEC and GIB near SEC No
11 12 cycle fault on 1L32 between SEC and GIB near SEC No
12 8 cycle fault on 1L35 between SEC and Malaspina (MSA) near SEC Yes
13 9 cycle fault on 1L35 between SEC and MSA near SEC No14 10 cycle fault on 1L35 between SEC and MSA near SEC No
15 12 cycle fault on 1L35 between SEC and MSA near SEC No
16 40 cycle fault on 1L32 near GIB No
17 40 cycle fault on 1L35 near Pender Harbor (PHR) No
18 6 cycle bus fault at SEC Yes
19 8 cycle bus fault at SEC Yes
20 9 cycle bus fault at SEC Yes
21 10 cycle bus fault at SEC No
*Yes Bear IPP generators will be lost, but COM and SCG remains stable
4.4 Protection Study
Assumptions:
BRK and COM share the same ground grid, and the overhead tie is notmore than 200 meter.
BRK transformers have grounded wye on the high side, and delta on thelow side.
Existing high speed line protection for 1L44 will isolate COM and SCG in theevent of a fault resulting in the opening of 1L44. This protection can be modified
to include the IPP by tripping the circuit breaker at the entrance to the new Bearstation (BRK). No direct transfer trip to the IPP is required.
4.5 Remedial Action Schemes
No generation shedding is required.
4.6 Black Start Capability
BCTC does not require black start capability for the Bear Creek Hydro IPP.
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
7
8/2/2019 Bear Creek System Impact Study
11/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
5.0 Reinforcements and Upgrades
The required Transmission System upgrades for Bear Creek Hydro IPP
interconnection are described in the Bear Creek IPP Interconnection FacilityStudy, BCTC SPA Report SPA 2005-33.
6.0 Conclusions
6.1 The Bear Creek Hydro IPP interconnection was found to be technicallyfeasible.
6.2 Sections of 1L44 need to be upgraded to higher summer thermal ratings.
6.3 1L44 line protection needs to be modified to include tripping the BRKentrance circuit breaker in the event of a fault on 1L44.
6.4 No transient or temporary overvoltage problems are observed.
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
8
8/2/2019 Bear Creek System Impact Study
12/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
Appendix
One-Line Diagram 1: Normal System before Bear Creek Hydro IPP
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
9
8/2/2019 Bear Creek System Impact Study
13/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
One-Line Diagram 2: Normal System with Bear Creek Hydro IPP
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
10
8/2/2019 Bear Creek System Impact Study
14/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
One-Line Diagram 3: System with Bear Creek Hydro IPP, 1L35 Out of Service
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
11
8/2/2019 Bear Creek System Impact Study
15/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
One-Line Diagram 4: System with Bear Creek Hydro IPP, 1L32 Out of Service
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
12
8/2/2019 Bear Creek System Impact Study
16/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
Machine Data
Salient Pole Generator (Quadratic Saturation on d-Axis) model GENSAL:
Upper Bear G1 Lower Bear G2Tdo 4.24 3.55
Tdo 0.07 0.07
Tqo 0.11 0.11
Inertia, H 2 2
Speed Damping D 1 1
Xd 1.88 1.8
Xq 1.74 1.7
Xd 0.299 0.31
Xd=Xq .199 0.2
X1 0.19 0.19
S(1.0) 0.194 0.685S(1.2) 0.194 0.685
Xd, Xq, Xd, Xd, Xq, X1, H and D are in pu, machine MVA base
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
13
8/2/2019 Bear Creek System Impact Study
17/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
Machine Data
Simplified Excitation System model SEXS:
Upper Bear G1 Lower Bear G2TA/TB 1.0 1.0
TB 1.0 1.0
K 20 20
TE (sec) 0.5 0.5
Emin (pu on EFD base) -3.0 -3.0
Emax (pu on EFD base) 3.0 3
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
14
8/2/2019 Bear Creek System Impact Study
18/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
Machine Data
Hydro Turbine-Governor model HGOV:
Upper Bear G1 Lower Bear G2
R, permanent droop 0.05 0.05
R, temporary droop 5 5
Tr, governor time constant 15 15
Tffilter time constant 0.04 0.04
Tg servo time constant 0.2 0.2
+/- VELM, gate velocity limit 0.07 0.07
Gmax maximum gate limit 1 1
Gmin Minimum gate limit 0 0Tw water time constant 3.5 3.5
At turbine gain 1.1 1.1
Dturb turbine damping 0 0
qNL, no load flow 0.08 0.08
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
15
8/2/2019 Bear Creek System Impact Study
19/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
Stability Plot 1: 10 cycle fault on Bears 138 kV line between Upper and Lower Bear
near Lower Bear (3)
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
16
8/2/2019 Bear Creek System Impact Study
20/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
Stability Plot 2: 9 cycle fault on Bears 138 kV line between Lower Bear and BearStation near Bear station (5)
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
17
8/2/2019 Bear Creek System Impact Study
21/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
Stability Plot 3: 9 cycle fault on 1L32 between SEC and Gibsons (GIB) near SEC(10)
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
18
8/2/2019 Bear Creek System Impact Study
22/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
Stability Plot 4: 8 cycle fault on 1L35 between SEC and Malaspina (MSA) nearSEC (8)
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
19
8/2/2019 Bear Creek System Impact Study
23/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
Stability Plot 5: 9 cycle bus fault at SEC (11)
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
20
8/2/2019 Bear Creek System Impact Study
24/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
Clowhom AC Conceptual Protection One-line Diagram:
~
COM
138 kV
1L4413CB1
~
~
T1
C/S(52L)
UPPER BEAR LAKE13 MVA
LOWER BEAR LAKE8.5 MVA
COM (BCTC)
BRK (IPP)
COM Conceptual AC ProtectionOne Line Diagram
BEAR CREEK HYDRO ProjectSketch # 1
B.J. Burk July 07 2005
21LS
21L
*
Notes:* Inidicates New Relay
1CVT1
*
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
21
8/2/2019 Bear Creek System Impact Study
25/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
Control Diagram for Bear Station
DNP3.0 IED(provided by Bear Creek
Hydro IPP)
data from both UpperBear and Lower Bear
SIC
2 status
8 telemetry
LMC
DDC1
DataConcentrator
D20
ScopeStation:
DWG No SH R
BRK IPP
SK11 0
By:
Date: 24-June-
2005
G. Jang
SCC
SIC
________________________________________________________________________________________________________________________________________________ This document contains proprietary information and shall not be reproduced in whole or in part without the prior written consent of BCTC
22
8/2/2019 Bear Creek System Impact Study
26/26
Bear Creek Hydro IPP Interconnection System Impact Study August 2005
Control Diagram for Clowhom Generating Station
SIC
STIC
COMS223/T119
new relay alarms
4 new telemetry
ScopeStation:
DWG No SH R
COM
SK21 0
By:
Date: 08-July-
2005
G. Jang
New SEL-203X (at COM) 2 new relays
LMC
Edmonds(Remote Data Access)
BCH legacy protocol
SEL protocol
1 status