E.B. Holzer AB-LTC Technical Review November 19, 2003 1 BEAM LOSS MONITORS The BLM system Status of the monitors Status of the electronics Delivery schedule, Integration, Installation Summary B. Dehning, G. Ferioli, J.L. Gonzalez, G. Guaglio, E.B. Holzer , V. Prieto, C. Zamantzas AB-LTC Technical Review November 19, 2003

BEAM LOSS MONITORS

  • Upload
    vonda

  • View
    43

  • Download
    0

Embed Size (px)

DESCRIPTION

BEAM LOSS MONITORS. The BLM system Status of the monitors Status of the electronics Delivery schedule, Integration, Installation Summary. B. Dehning, G. Ferioli, J.L. Gonzalez, G. Guaglio, E.B. Holzer , V. Prieto, C. Zamantzas AB-LTC Technical Review November 19, 2003. THE BLM SYSTEM. - PowerPoint PPT Presentation

Citation preview

Page 1: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

1

BEAM LOSS MONITORS

•The BLM system

•Status of the monitors

•Status of the electronics

•Delivery schedule, Integration, Installation

•Summary

B. Dehning, G. Ferioli, J.L. Gonzalez, G. Guaglio, E.B. Holzer, V. Prieto, C. Zamantzas

AB-LTC Technical ReviewNovember 19, 2003

Page 2: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

2

THE BLM SYSTEM

•Purpose:

– Machine protection against damage of equipment and magnet quenches.

– Setup of the collimators

– Localization of beam losses and help in identification of loss mechanism

– Machine setup and studies

•Challenges:

– Reliable (tolerable failure rate 10-7 per hour)

– High dynamic range (108)

– Fast (1 turn trigger generation for dump signal)

Page 3: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

3

Families of BLM’s

Description Number of detectors

BLMA Quadrupoles along the ring (6 per quadrupole), ionization chambers attached outside of cryostat, time resolution 2.5 ms.

~3000

BLMS Critical aperture limits or positions, ionization chambers, time resolutions 1 turn.

~400

BLMS* Critical positions for injection losses, extended dynamic range: BLMSI (ion. ch.) + BLMSS (SEM), time resolution 1 turn.

~100

Recent changes in the functional specification for BLMS* and BLMC (LHC-BLM-ES-0001.00 rev2.0)

Page 4: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

4

Description Number of

detectors

BLMC Collimation sections, BLMCI (ion. ch.) + BLMCS (SEM), time resolution 1 turn, used to set up the collimators.

~110

BLMB Primary collimators, not part of baseline scenario, for beam studies, bunch- by-bunch resolution.

10

Page 5: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

5

Inside view of an ionization chamber from SPS, Volume: ~ 1 Liter, Gas: N2, 30 Al disks of 0.5 mm, Typical bias voltage: 1500 V.

Installation of BLMAs on a SSS quadrupole

Page 6: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

6

The Readout Chain

Page 7: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

7

STATUS OF THE MONITORS

BLMA and BLMS

~3400 ionization chambers of 1 dm3 volume

Status of:

Technical Specification: ongoing, mostly done• Size (length, diameter)• Material (chamber, gas)• Production procedure (construction, cleaning, filling)

Design: Dec ’03 - Feb ’04

Prototyping: June/July ’04

Manufacturing Contracts: contract in preparation (to be produced in Protvino)

Page 8: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

8

Difficulties and possible consequences:– Ageing of chambers (investigate SPS chambers at next shutdown)

• Schedule does not leave time to test different chambers (gases, cleaning, filling procedures) for ageing.

• Consequence of ageing is an increased need for calibration.– Size of chamber to be coordinated with the requirements for

transport space along the magnets.

Page 9: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

9

BLMS* and BLMC

~ 200 locations with 1 ionization chamber (0.1 - 1 dm3) and 1 SEM detector (10 cm2)

Functional specifications: dynamic range increased recently (1011-1012) install two chambers with different (yet overlapping) response next to

each other. Open questions on feasibility of the envisaged measurements might require reiteration on the functional spec.:• Activation of the surrounding material (measurement of low level

signals)• BLMC: Background and cross-talk signals (from other collimators

and the second beam)

BLMSI & BLMCI: ionization chambers, same kind as BLMA & BLMS

Difficulties and possible consequences:– Activation, background and cross-talk– Implications on setting up of the collimators > problems with

disentangling the losses on each collimator, more beam-time needed

Page 10: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

10

BLMSS & BLMCS: SEM detectors. Deadline for production now advanced by 1 year, because BLMS* probably needed for sector test.

Status of SEM:

Technical Specification and Design: throughout 2004, will try to find existing chamber design which matches our requirements.

Manufacturing Contracts: Q4 ’04

Difficulties and possible consequences :– Vacuum needs to hold for the whole lifetime.– Test of chambers before installation (beam test).– Calibration of installed chambers will not be possible.– If no existing design can be reused, problem with schedule:

• BLMSS: for monitoring, not for machine protection• BLMCS: scheduled one year later

Page 11: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

11

BLMB

10 detectors

Planned to use standard ACEM detectors (or photo-multipliers), and acquisition systems of LHC BCT. Not part of baseline scenario,for refined beam observation.

Status:– Detectors on stock

Difficulties or trade-offs:– Lower end of signal limited by background from activation (installed

at primary collimators)– Possible redefinition of functional specifications after simulation

studies

Page 12: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

12

STATUS OF ELECTRONICS

~600 cards

Current design of current to frequency converter: Signals of 10 pA to

1 mA converted to frequencies of 0.05 Hz to 5 MHz.

Status of:

Technical Specification: done (W. Friesenbichler)

Design/Prototyping:– Current to frequency converter (CFC): choice of technology

(dynamic range 108), design, prototyping and testing including digital data transmission done (W. Friesenbichler),

Electronics in the tunnel: current to frequency converter + counter + optical data link

Page 13: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

13

– improvements pending (E. Effinger, 2004):• Test and calibration procedure implementation• Protection against high signal levels• Increase mean time between failures (double the analogue

electronics)• Radiation hardness (change of components)• Dynamic range (add ADC to get additional sensitivity below the

one count rate - 2 pA)• Operating conditions (temperature range)

– Counter and data link: to be done (2004)

Manufacturing Contracts: to be done– Pre-series to be delivered Q4 ’04– Series to be delivered Q2 ’05

Page 14: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

14

Difficulties and possible consequences:

– Low signal limit (noise on up to 250 m long cables from monitor to current to frequency converter in LSS and DS) > more beam-time for machine set-up and tuning (loss minimization).

– Radiation hardness, ageing > Calibration

– Temperature dependence after irradiation > Calibration

– Protection against high signal levels > change electronics in tunnel

– Reliability: Taking the conservative assumption that the loss is seen by one detector only, the estimated failure rate of the current design is 10-100 times to high (2*10-6/h). That corresponds to 0.7% of dangerous losses passing undetected and resulting in magnet destruction.

Page 15: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

15

At Surface: Threshold Comparator + data receiving

~340 cards (DAB with FPGA and VME64 interface)

Status of:

Technical Specification: done (C. Zamantzas)

Design/Prototyping:– Hardware developed together with BPM (J.L. Gonzalez) and

collaboration with TRIUMF:• First prototypes tested (SPS) done• Prototype boards May ’04

– Software (C. Zamantzas):• Design + software simulation first version (Jan. ’04)• FPGA implementation on test board Q1 ’04

on prototype board Q3 ’04

– Data link (LASER/diode) selection of components: ongoing (test measurement at PSI)

Page 16: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

16

Manufacturing Contracts:– Digital analysis board (DAB): together with BPM

• Prototype cards: May ’04• Pre-series all cards: August ’04• Contract: Q4 ’04• Delivery of all cards Q4 ’05

– LASER/Diode: off shelf

Difficulties or trade-offs: • Expected to fulfill the specifications

Page 17: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

17

BLMCOM: Combiner and Interface to machine controls

24 cards

Status of:

Technical Specification: to be done (Q2 ’04)

Design/Prototyping: to be done (Q3 ’04)

Manufacturing Contracts: produced at CERN (Q1 ’05)

Difficulties or trade-offs: • Expected to fulfill the specifications

Page 18: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

18

Delivery Schedule (Chambers and electronics)

CtC: changes in func. spec., cost increase for 200 - 300 new channels to be analyzed (Q1 ’04)

Installation schedule for LHC:to be finished Q4 ’06, no problems expected

– Cables: partly installed, according to schedule– Crates: together with BPM (to be defined soon)– Chambers + cables to tunnel crates or patch boxes (LSS):

finished Q4 ’06– Electronics: to be finished Q4 ’06

Installation schedule for sector test: to be finished Q4 ’05

Storage: no difficulties

Complete test at CERN before installation: foreseen

Quality control/acceptance issues: no difficulties expected

Page 19: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

19

Integration

Interference with other installations:– Machine protection and dump: tests of the combined system

foreseen

Services/cables already ordered:– Cables: yes, except:

– Cables for the recent upgrade of the functional specifications

– Collimation region (positions not yet defined)– Services for installation: 2 teams of 2 persons each, to be ordered– Software services: yes

Page 20: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

20

Planning for Installation in the Tunnel

Difficulties of access or co-habitation: no.

Needs for transport and handling: few pallets to each LHC point

Hardware Baseline

System is part of baseline

Documentation in EDMS: technical specifications of:– Ionization chambers: started, Feb. ’04– SEM: Q4 ’04– Current to freq. converter: Q4 ’04– Threshold comparator: Feb. ’04

MTF for manufacturing follow-up: to be done when production of components has started.

Page 21: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

21

SUMMARY

• Schedule is tight:

– Analog electronics is late by about 1 year (lack of manpower).

– Digital electronics is late by about 3 months (DAB board 7 month late).

– Ionization chamber still on schedule, but problems with availability of technical designer.

– SEM: If no existing system can be adapted - problem with the schedule.

• Demands on system have recently increased - implications on the schedule (SEM detectors for sector test) and on cost (200-300 new channels not yet financed).

Page 22: BEAM LOSS MONITORS

E.B. HolzerAB-LTC Technical Review November 19, 2003

22

• The BLM design is based on the functional specifications, which in turn rely on a provisional strategy for machine protection. Further changes in the BLM system will become more and more expensive.

• Identified possible conceptual and/or technical limitations. The main consequences, in case they cannot be solved will be

– higher need for beam-time for set-up and tuning of the machine

– increased number of downtimes.

• Apart from these limitations - production and installation of the BLM system can be in time for sector test and LHC.