Bongkot Booster Compressors Project Phase 4 WP16-Offshore Construction Contract No. ECM-12-0500 WP16-Offshore Construction Thai Nippon Steel & Sumikin Engineering & Construction Corp.,Ltd

BC4-Bongkot WP16 PRESENTATION - Rev.01

Embed Size (px)

Citation preview

Page 1: BC4-Bongkot WP16  PRESENTATION - Rev.01

Bongkot Booster Compressors Project Phase 4

WP16-Offshore Construction

Contract No. ECM-12-0500

WP16-Offshore Construction

Thai Nippon Steel & Sumikin Engineering & Construction Corp.,Ltd

Page 2: BC4-Bongkot WP16  PRESENTATION - Rev.01

Agenda

1. Scope of Work

2. Planning & Project Schedule

3. Work Method

4. Project Highlights

2

Page 3: BC4-Bongkot WP16  PRESENTATION - Rev.01

Booster Compressor (BC) Package Modification Works at WP16

� Demolition and relocation of structural elements at lower and upper deck

� Installation of Deck Extensions at west side of Lower & Upper Deck

� Install hand rail/ beam members/ deck plate/ doublers plate for BC skid base support

� Lifting and positioning of BC package

1. Scope of Work

3

� Lifting and positioning of BC package� BC package assembly, leveling, alignment and full

welding of skid base to the doublers support plate� Installation of loose items for BC package� Tie-in BC Package to platform System� Pressure testing� Installation and modification of relevant Electrical

and Instrument systems� Pre- commissioning and commissioning� Power brushing and touch up painting

Page 4: BC4-Bongkot WP16  PRESENTATION - Rev.01

2. Planning & Project Schedule

� Key Dates & Milestones

Key Dates Event Date

1 WP16 Structural fabrication completion 21-Mar-14

2 Work barge alongside at WP16 5-Jul-14

3 WP16 Deck extension installation completion 29-Jul-14

4 WP16 Booster compressor package installation complete 19-Jul-14

4

4 WP16 Booster compressor package installation complete 19-Jul-14

5 WP16 Offshore work completion 8-Aug-14

6 Final documentation 8-Sep-14

Note : This schedule is base on accommodation barge along-side at WP16 between 5-Jul-14 to 8-Aug-14

Page 5: BC4-Bongkot WP16  PRESENTATION - Rev.01

Offshore Schedule

5

Page 6: BC4-Bongkot WP16  PRESENTATION - Rev.01

Upper Deck

Stair

3. WORK METHOD (WP16)

Lower Deck

Page 7: BC4-Bongkot WP16  PRESENTATION - Rev.01

Deck Extension for

Header manifold

Page 8: BC4-Bongkot WP16  PRESENTATION - Rev.01

Lower Deck West Side.

Lower Deck North Side.

Page 9: BC4-Bongkot WP16  PRESENTATION - Rev.01

3.1 PREPARATORY WORKS

1. Set up, install personnel access Gangway betweenaccommodation Barge and WP16 Platform @ upperdeck and lower deck

2. Install hanging scaffolding access @ upper deck andlower deck

3. Install hot work shielding/habitat @ upper deck andlower deck

9

3. Install hot work shielding/habitat @ upper deck andlower deck

4. Demolish of existing handrail and obstruct item outfrom work area at lower deck and upper deck @ upperdeck and lower deck

5. Prepared of new joint and install stopper support atinterconnecting for install new deck extension @ upperdeck and lower deck

Page 10: BC4-Bongkot WP16  PRESENTATION - Rev.01

PIPING TIE-IN POINT

10

Page 11: BC4-Bongkot WP16  PRESENTATION - Rev.01

To be modify support6”-CG-26B3-F48

TIP-01

TIP-02

TIP-01

TIP-02

6”-CG-26AD-F48 (existing)

6”-CG-26AD-F48 (existing)

4”-CG-26A3-F48

Page 12: BC4-Bongkot WP16  PRESENTATION - Rev.01

6”-CG-26HK-F48 (existing)

TIP-03

TIP-04

6”-CG-26D3-F48

4”-CG-26C3-F48

6”-CG-26BE-F48 (existing)

TIP-03

TIP-04

Page 13: BC4-Bongkot WP16  PRESENTATION - Rev.01

6”-CG-26CF-F48 (existing)

TIP-05 TIP-06

TIP-05

TIP-06

6”-CG-26LM-F48 (existing)

4”-CG-26C3-F48

4”-CG-26C3-F48

Page 14: BC4-Bongkot WP16  PRESENTATION - Rev.01

TIP-07

TIP-08

TIP-08

TIP-07

6”-CG-2612-F48 (existing)

6”-CG-2612-F48 (existing)

6”-CG-2671-F48

Page 15: BC4-Bongkot WP16  PRESENTATION - Rev.01

TIP-10

TIP-10

4”-CG-2652-F48

TIP-09

TIP-09

6”-CG-2612-F48 (existing)

Page 16: BC4-Bongkot WP16  PRESENTATION - Rev.01

TIP-12

8”-AV-2617-B03 (existing)

TIP-12

TIP-13TIP-13

8”-AV-2617-B03

Page 17: BC4-Bongkot WP16  PRESENTATION - Rev.01

TIP-14

TIP-14

8”-AV-2617-B03

8”-AV-2617-B03 (existing)

Page 18: BC4-Bongkot WP16  PRESENTATION - Rev.01

8”-AV-2651-B03 (existing)

1”-AV-26100-B03

6”-AV-2651-B03 (existing)

TIP-15A TIP-15B

TIP-15A TIP-15B

Page 19: BC4-Bongkot WP16  PRESENTATION - Rev.01

6”-AV-26112-F48

TIP-16

3”-CD-2647-F48

3”-CD-2647-F48 (existing)

TIP-16

Page 20: BC4-Bongkot WP16  PRESENTATION - Rev.01

TIP-17A

3”-DO-2678-F48 (existing)

2”-CD-26110-B03

3”-DO-2678-F48 (existing)

TIP-17A

TIP-17B

TIP-17B

3”-DO-2678-F48 (existing)

Page 21: BC4-Bongkot WP16  PRESENTATION - Rev.01

3”-IG-2553-B03 (existing)

2”-IG-2553-B03 (existing)

2”-IG-2682-B03

TIP-18

Page 22: BC4-Bongkot WP16  PRESENTATION - Rev.01

3”-OD-2543-B91 (existing)

2”-OD-26110-B91

TIP-19

Page 23: BC4-Bongkot WP16  PRESENTATION - Rev.01

TIP-20

2”-OD-26113-B91

2”-OD-26113-B91 (existing)

TIP-20

Page 24: BC4-Bongkot WP16  PRESENTATION - Rev.01

4. Project Highlights

� CY boat runs for the mobilization will be directed from Petra Lyra (WP16) at Bongkot Field

� A shutdown is planned by 1-Aug-14 until 3-

24

A shutdown is planned by 1-Aug-14 until 3-Aug-14 for WP15