Architects & Engineers 109/27/2018

Batchelor Hall Building Systems RenewalGeneral Contractor Prequalification Conference

September 2, 2021

Please sign in. This is a mandatory meeting.

Page 2: Batchelor Hall Building Systems Renewal

Architects & Engineers 209/27/2018

Batchelor Hall Systems Renewal

1. Introductions

2. Batchelor Hall Systems Renewal Overview

3. Requirements for Prequalification

Agenda

Page 3: Batchelor Hall Building Systems Renewal

Architects & Engineers 309/27/2018

Batchelor Hall Systems Renewal

Drew Hecht, Director of Project Management

Blythe Wilson, Director of Project Management

John Franklin, Senior Project Manager

Carmen Long, Construction Contracts Manager

Betty Osuna, Contract Administrator

Vilma Kern, Project Manager

Introductions

Page 4: Batchelor Hall Building Systems Renewal

Architects & Engineers 409/27/2018

Batchelor Hall Systems Renewal

Batchelor Hall Systems Renewal OverviewJohn Franklin

Page 5: Batchelor Hall Building Systems Renewal

Architects & Engineers 509/27/2018

Batchelor Hall Systems Renewal

B a t c h e l o r H a l l S y s t e m s R e n e w a l L o c a t i o n

Building SiteProject Overview

Page 6: Batchelor Hall Building Systems Renewal

Architects & Engineers 609/27/2018

Batchelor Hall Systems Renewal

Project Overview

• Batchelor Hall was completed in 1965.• Four Levels + Basement + Roof.• Type II-A Building.• Occupancy Classification: Group B, Research Laboratory.• Project Scope: Infrastructure Renovation.• The main focus of the Batchelor Hall Renewal Project is the replacement

and/or upgrade the building Mechanical, Plumbing, Electrical, Conveyance, and Fire Protection Systems.

• This will need to be supported by Structural work (Concrete & Structural Steel), Roofing, Demolition, and Hazmat Abatement (among other things).

Page 7: Batchelor Hall Building Systems Renewal

Architects & Engineers 709/27/2018

Batchelor Hall Systems Renewal

Project Overview

• The project is divided into FOUR phases + a “prep” phase (Phase 0). • Each phase has a duration of approximately 6 months each.• Building will remain open and occupied during the entire construction

period. Emergency egress must be maintained for all building occupants.• Logistics, including access and egress, will be vitally important.

Page 8: Batchelor Hall Building Systems Renewal

Architects & Engineers 809/27/2018

Batchelor Hall Systems Renewal

Bui lding Logist ics

Page 9: Batchelor Hall Building Systems Renewal

Architects & Engineers 909/27/2018

Batchelor Hall Systems Renewal

Requirements for PrequalificationCarmen Long

Page 10: Batchelor Hall Building Systems Renewal

Architects & Engineers 1009/27/2018

Batchelor Hall Systems Renewal

• License Verification – B, General Contractor• Financial Review – Reviewed/Audited• Surety/Bond Verification – Bond $25,000,000• Insurance Verification – General, Auto, Workers Comp • Construction Experience• Responsible Performance on all Completed Projects • Staffing – Superintendent, Project Manager• Safety Program – IIPP, Safety Coordinator, EMR 1.25• Labor Compliance• Quality Assurance/Quality Control – QA/QC Coordinator• Disciplinary Measures• False Claims History• Termination History• Liquidated Damages• Claims History

Prequal i f icat ion

Page 11: Batchelor Hall Building Systems Renewal

Architects & Engineers 1109/27/2018

Batchelor Hall Systems RenewalPrequal i f icat ion

Page 12: Batchelor Hall Building Systems Renewal

Architects & Engineers 1209/27/2018

Batchelor Hall Systems Renewal

Prequal i f icat ion

Page 13: Batchelor Hall Building Systems Renewal

Architects & Engineers 1309/27/2018

Batchelor Hall Systems Renewal

Warm-Air Heating, Ventilating & Air Conditioning, Demolition/Abatement

• Prequal Package Available – September 7, 2021

• Mandatory Meeting – September 16, 2021

• Prequal Submittal – September 29, 2021

• Evaluation Completed – October 2021

General Contractors who wish to self-perform mechanical ordemo/abatement, must attend the subcontractor prequalificationconference and turn in a subcontractor prequalification package foreach trade. Prequalified subs for Mechanical and Demo/abatementwill be the only ones allowed to bid that scope even if you are aprequalified GC.

Separate Prequal i f icat ion - Subcontractor / Specialty Contractors

Page 14: Batchelor Hall Building Systems Renewal

Architects & Engineers 1409/27/2018

Batchelor Hall Systems Renewal

• One (1) copy of all Audited Financial Statements • Notarized Statement from Surety • Written declaration from insurance agent/broker/carrier stating that

your firm can obtain insurance coverage in the required limits and ratings

• Insurance Certificate• Letter from Workers’ Compensation carrier evidencing your EMR for

the past ten years• Resumes of all proposed Superintendent, Project Manager, QA/QC

Coordinator and Safety Coordinator• TOC for IIPP, QA/QC Program• Claim Data Sheets (as applicable)• Signature on Declaration

Required AttachmentsPrequalification Process

Page 15: Batchelor Hall Building Systems Renewal

Architects & Engineers 1509/27/2018

Batchelor Hall Systems Renewal

No contractor or subcontractor may be listed on a Bid for this project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)].

No contractor or subcontractor may be awarded any portion of this project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5.

This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.

This project is subject to General Prevailing Wages predetermined by the Department of Industrial Relations (DIR).

Public Works Compliance

Prequal i f icat ion

Page 16: Batchelor Hall Building Systems Renewal

Architects & Engineers 1609/27/2018

Batchelor Hall Systems Renewal

Due: September 13, 2021 at 12:00 PM

Location: Contractor to request One-Drive link tobe provided upon request to Betty Osuna

University will accept RFI’s for prequalificationprocess until September 7, 2021, 12:00 PM

Prequalification Deadlines

Page 17: Batchelor Hall Building Systems Renewal

Architects & Engineers 1709/27/2018

Batchelor Hall Systems Renewal

Questions

Betty OsunaContract Administrator(951) [email protected]

http://pdc.ucr.edu/

Page 18: Batchelor Hall Building Systems Renewal

Architects & Engineers 1809/27/2018

Batchelor Hall Systems Renewal

Thank You