1/2/2016 Batch Derivation in Production | SCN http://scn.sap.com/docs/DOC51594 1/9 Getting Started Newsletters Store Products Services & Support About SCN Downloads Industries Training & Education Partnership Developer Center Lines of Business University Alliances Events & Webinars Innovation Log On Join Us Hi, Guest Search the Community Activity Communications Actions Browse 0 Tweet created by K Kumar on Jan 23, 2014 7:55 AM, last modified by K Kumar on Jan 23, 2014 5:02 PM Batch Derivation : Transferring batch characteristics values or batch master fields from the sender batch to the receiving batch is called “Batch Derivation”. The component batches can pass on their Field values/characteristics values to the manufactured batch. Scenario : Minimum value of Manufacturing date and Expiry Date (SLED) of the component materials batches are to be transferred to header material batch during process order release automatically Process Flow: Create BOM and Recipe for Header material CS01 Create condition records for sender receiver materials DVCO Create Process Order COR1 Do the batch determination for components COR2 Release the process order COR2 Check for the batch derivation MSC3N Detailed Flow: Create BOM for header material as shown below....and also create master recipe for the header material.... Now go to transaction DVCO Batch Derivation in Production Share 1 Like Version 6

Batch Derivation in Production _ SCN

Embed Size (px)

DESCRIPTION

Batch Derivation in Production _ SCN

Citation preview

Page 1: Batch Derivation in Production _ SCN

1/2/2016 Batch Derivation in Production | SCN

http://scn.sap.com/docs/DOC51594 1/9

Getting Started Newsletters Store   

Products Services & Support About SCN Downloads

Industries Training & Education Partnership Developer Center

Lines of Business University Alliances Events & Webinars Innovation

Log On Join UsHi, Guest Search the Community

Activity Communications Actions

Browse

0 Tweet

created by K Kumar on Jan 23, 2014 7:55 AM, last modified by K Kumar on Jan 23, 2014 5:02 PM

Batch Derivation :

Transferring batch characteristics values or batch master fields from the sender batch to the receiving batch iscalled “Batch Derivation”.The component batches can pass on their Field values/characteristics values to the manufactured batch. Scenario :

Minimum value of Manufacturing date and Expiry Date (SLED) of the component materials batches are tobe transferred to header material batch during process order release automatically

Process Flow:

Create BOM and Recipe for Header material   CS01Create condition records for sender receiver materials  DVCOCreate Process Order  COR1Do the batch determination for components  COR2Release the process order  COR2Check for the batch derivation  MSC3N

Detailed Flow:

Create BOM for header material as shown below....and also create master recipe for the header material....

 Now go to transaction DVCO 

Batch Derivation in Production

Share 1Like

Version 6

Page 2: Batch Derivation in Production _ SCN

1/2/2016 Batch Derivation in Production | SCN

http://scn.sap.com/docs/DOC51594 2/9

Enter the relevant details Material, Plant, usage as shown below and select the derivation event as during Release ofprocess/production order 

 

then click on execute

Now click on create button

add two fields  SLED and Date of manufacture as shown below

 

Page 3: Batch Derivation in Production _ SCN

1/2/2016 Batch Derivation in Production | SCN

http://scn.sap.com/docs/DOC51594 3/9

 Drag and Drop these two to Left side materials to create sender and Receiver condition records….

 select the comarative as minimum as shown below for value selection during derivation...

 

Page 4: Batch Derivation in Production _ SCN

1/2/2016 Batch Derivation in Production | SCN

http://scn.sap.com/docs/DOC51594 4/9

Then Save

 Now check the batches of the two component materials and values of their Manufacturing date and SLED.... First component is 2160

 

 Batch S1 with MFG date as 14.08.2013 and SLED as 31.12.2014 

 Now check for second component is TRJ200 

Page 5: Batch Derivation in Production _ SCN

1/2/2016 Batch Derivation in Production | SCN

http://scn.sap.com/docs/DOC51594 5/9

 Batch 1234 with MFG date as 01.07.2013 and SLED as 31.07.2014 

 Now create process order for header material as shown below...

 

 

Page 6: Batch Derivation in Production _ SCN

1/2/2016 Batch Derivation in Production | SCN

http://scn.sap.com/docs/DOC51594 6/9

 Create batch for header material as shown below... 

save the order 

 go to change mode 

 

 Assign the batches to the components manually or through batch determination as shown below..... 

Page 7: Batch Derivation in Production _ SCN

1/2/2016 Batch Derivation in Production | SCN

http://scn.sap.com/docs/DOC51594 7/9

 Now Release the process order

Now save the process order

 

Now during process order release batch derivation gets triggered and values gets transferred to header batchautomatically...Now check in the Batch of the header material whether MFG date and SLED are updated as per therequirement...

MFG date: 01.07.2013 is the minimum of 14.08.2013 (Batch S1 material 2160) and 01.07.2013 (Batch 1234material TRJ200)Shelf Life Exp. Date: 31.07.2013 is the minimum of 31.12.2014 (Batch S1 material 2160) and 31.07.2013(Batch 1234 material TRJ200)  

Page 8: Batch Derivation in Production _ SCN

1/2/2016 Batch Derivation in Production | SCN

http://scn.sap.com/docs/DOC51594 8/9

Average User Rating

(3 ratings)

0 Tweet

 ThanksKumar

3090 Views   Tags: sap, batch_derivation

Share 1Like

8 Comments

Like (0)

Krishnendu Das Jan 23, 2014 9:51 AM

Hi Kumar, Think few texts are not properly uploaded. Like " atch : Regards,Krishnendu.

Like (0)

K Kumar Jan 23, 2014 10:00 AM (in response to Krishnendu Das)

Hi,Thanks for your observation...will edit the document.....  ThanksKumar

Like (0)

Kalyana Chakravarthy Jan 23, 2014 10:37 AM (in response to K Kumar)

Hi Kumar,   Thanks for sharing but,still the images & texts are not properly updated. Can youplease look into it & if possible reload few images & texts. 

RegardsKalyan

K Kumar Jan 24, 2014 4:01 AM (in response to Kalyana Chakravarthy)

Hi,updated all the missing texts and images...hope now the document iscomplete in all aspects...suggestions and changes are welcome...... Thanks

Page 9: Batch Derivation in Production _ SCN

1/2/2016 Batch Derivation in Production | SCN

http://scn.sap.com/docs/DOC51594 9/9

Follow SCNSite Index Contact Us SAP Help PortalPrivacy Terms of Use Legal Disclosure Copyright

Like (0)

Kumar

Like (0)

K Kumar Mar 28, 2014 4:05 AM (in response to Kalyana Chakravarthy)

Hi,Thanks for your feedback... RegardsKumar

Like (0)

ANIKET GAUTAM Jun 14, 2015 3:54 PM (in response to K Kumar)

Nice Doucment ...Thanx a lot for sharing

Like (0)

Eric Chen May 27, 2015 9:26 AM

Hi Kumar Very useful documentation for me, I have requirement on my project.Keep posting, many thanks!

Like (0)

Vignesh Veerasamy Jun 15, 2015 9:11 AM

Hello Kumar, Good work,nice documentation...keep posting.If possible can i get similar document for REM scenario as this is based out on PPPI. Thanks in Advance. Vignesh.V