Upload
ramswarup-bhaskar
View
10
Download
1
Tags:
Embed Size (px)
DESCRIPTION
Banda gas to power project
Citation preview
Project Finance case on Banda Gas To
Power Project
By
Prateek Goyal (13125039)
Ramswarup Bhaskar (14114019)
To
Dr. Anoop Singh
Assistant Professor, IME Department
IIT Kanpur
March, 2015
DEPARTMENT OF INDUSTRIAL AND MANAGEMENT ENGINEERING
INDIAN INSTITUTE OF TECHNOLOGY, KANPUR
1
Table of Content
Serial No. Topic Page No.
1. Introduction 2
2. The Project 2
3. Power sector performance 3
4. Project Objective 4
5. Project Description 5
6. Project Financing Plan 8
7. Project Agreements 10
8. Key Challenges 13
9. Conclusion 14
10. Appendices 15
11. References 21
2
Introduction:
The Western Africa is facing the daunting energy challenges. In Mauritania only 20% citizen has
access to electricity & only 33% in Mali. Senegal has better number but there also 50%
population is without electricity. In all the three countries electricity supply is unreliable and
demand for power is increasing at 7% to 9% annually. As a result of evolving generation mix,
coupled with high technical and commercial losses, poor efficiency and inefficient national
revenue collection, the national power utilities of all three countries have been incurring financial
deficits and relying on government support. Poor infrastructure and low access to energy have
constrained GDP growth in all three countries.
The finding of the gas fields in Mauritania are a game changer for the sub-region as they can be
used to generate affordable and cleaner power compared to other thermal alternatives. However,
private investors hesitating to invest in gas development because of the high political risks in the
region and lack of creditworthiness of the developer in the sub-region.
The Project:
The Banda gas field is located approximately 55 km offshore Nouakchott and around 20km east
of the Chinguetti oil field, at depths of approximately 200m-325m below sea level. The Banda
Gas Project consists of two sub-sea wells tied back to an onshore gas processing plant via a
subsea production manifold and a 10-inch sub-sea pipeline. The gas processing plant will be
located 14 km north of Nouakchott and 6 km inland. Project cost is estimated to be US$650
million. First gas can be delivered approximately 30 months from the final investment decision,
which is expected to occur by mid-2014.
The gas field's development forms part of the larger Banda Gas to Power project, which
envisions the construction of a 120MW combined cycle power plant and a 180MW dual-fuel
thermal gas-fired power plant, to be located north of Nouakchott, as well as installation of
transmission lines.
3
Figure: The map of the location of the plant
The total cost of this project is estimated to be 467.1 million USD. Gas will be fed from the
Banda field to these power plants to generate electricity.
The gas field was declared commercial in September 2012 and the environmental impact
assessment (EIA) and front end engineering and design (FEED) were completed in the first half
of 2013. The project approval is expected to be granted in the first half of 2015 and first
production is slated for 2016.
Power sector performance:
The power sectors in all three countries suffer to various degrees from similar issues, including
low access rates to electricity, relatively high technical and commercial losses, and high
generation costs due to a dependence on oil-based thermal generation capacity. Tariffs are high
but still insufficient to cover costs, resulting in reliance on government subsidies.
Mauritanias electricity sector is characterized by a fragmented power system, low rates of
electricity access and demand/supply imbalances. Domestic demand, excluding mining demand,
4
is expected to grow at about 9% per annum until 2020, then at 6% per annum after 2020, driven
by progressive connection of load centers to the OMVS grid and economic growth.
Senegal has steadily increased electrification rates (connections and installed capacity have
doubled since 2000) reaching a national average of 50%, with almost fully electrified urban
areas, but only covering about 25% of the rural population. Senegal remains heavily dependent
on imported oil products for its energy supply affecting SENELECs financial and operational
situation. About 90% of electricity is generated using oil products. Power demand in Senegal is
expected to grow at 7% per annum over the period 2013-2020. Total installed generation
capacity, including IPPs, is expected to double over the next seven years from 587 MW in 2013
up to 1,097 MW in 2020.
Malis currently installed capacity is 327 MW on interconnected grid versus 67 MW for isolated
centers and the peak demand is expected to increase up to 457 MW by 2020. Lower cost energy
imports from OMVS to meet increasing demand represent a least-cost solution for the country..
Key power sector indicators
Project Objectives:
The Projects Development Objective (PDO) is to enable production of natural gas for
generation of electricity to reduce the cost and increase the supply for Mauritanian households
and industry, and enable regional integration through exports of electric power from Mauritania
to Senegal and Mali.
5
To end extreme poverty and promote shared prosperity by providing the three countries access to
additional, less expensive and cleaner electricity and promoting regional integration. Increased
supply of electricity to households and small businesses in all three countries will ensure more
access to income-generating opportunities leading to improved living standards.
For facilitating electricity access to those households that are presently without (invariably the
poor) and more reliable energy services to small and medium enterprises, which will in turn lead
to economic growth.
Project Description:
The Banda Gas-to-Power Project consists of the following components:
A. The upstream Banda offshore gas field production, transmission and processing
infrastructure (the Banda Gas Project);
B. Power generation from Banda gas in Mauritania (the SPEG Power Project); and
C. Existing and new power transmission lines to evacuate power to the delivery points.
The Banda gas field is located approximately 55 km offshore of Nouakchott. The Banda field
shareholders are Tullow (67%), Petronas (15%), Kufpec (13%) and Premier Oil (5%). Tullow
has prepared a field development plan which provides for production of up to 70 mmscfd per day
of gas over 20 years.
SPEG (Socit de Production dElectricit partir du Gaz) is a special purpose vehicle
incorporated for the purpose of power generation, transmission and sales of power using Banda
gas. SPEGs shareholders are SOMELEC (40%); KG Power, subsidiary of Kinross, an
international gold mining company (34%); and SNIM, the national iron ore mining company
(26%). SPEG Power Project, which will be installed north of Nouakchott, includes:
Dual fuel plant of 180 MW (120 MW currently under construction by Wrtsila with an
option to be extended to 180 MW that was exercised in June 2013); and
Combined cycle gas turbines (CCGT) power plant with a capacity of 120 MW.
Gas from the Banda offshore gas field developed by private developer Tullow will be sold to
SPEG which will transform the gas through a 300 MW power plant. The SPEG electricity will
6
be sold to Mauritanias national utility, SOMELEC, which in turn will sell power to customers in
Mauritania and export power to Senegal and Mali.
Gas and electricity sale of the project
Dual fuel power plant:
The dual fuel power plant of approximately 120 MW capacity is based on dual fuel reciprocating
engines. The plant is currently under construction by Wrtsila under an EPC contract. The plant
consists of 8 engines, each of approximately 15 MW. The plant has the capability to run on
heavy fuel oil (HFO) or Natural Gas. The plant is expected to be fully online by March 2015 and
will initially run on HFO. As soon as natural gas is made available at the gas delivery point, the
plant will then run on natural gas. At site conditions plant efficiency is estimated to be 41.4%
running on HFO and 45.1% running on natural gas.
7
Wartsila is supplying eight 50DF dual-fuel generating sets for the Banda Gas to Power project.
CCGT plant :
The 120 MW CCGT plant will run with GE-6B gas turbines. Net efficiency is calculated to be of
the order of 47% at yearly average site conditions. Units should be able to operate on light fuel
oil (LFO) as backup fuel during (short) periods of unavailability of natural gas. The choice of
LFO as backup fuel is linked to the choice of combustion technology (dry low NOx burners) and
meeting World Bank emissions requirements. Given the high cost of LFO, this fuel 51 is
intended to be used for short periods of time only. The backup fuel functionality is not intended
to cope with the risk of potentially long delay in construction of the gas supply infrastructure. In
such case, running the dual fuel plant on HFO will be more economical.
Power generated by SPEG to SOMELEC will be evacuated through several routes:
8
(i) A greenfield high voltage transmission line to Nouadhibou with a spur to
Tasiast, site of Kinross gold mine (the North HV line) owned and operated by
SOMELEC and financed by the Saudi Fund,
(ii) The existing OMVS high voltage transmission line that will be connected to
the power plant through a short extension (the OMVS HV line and the OMVS
HV extension), funded by SOMELEC and
(iii) A new high voltage transmission line between Mauritania and Senegal, to be
financed by AFD and IsDB, with a wheeling capacity of about 170 MW (the
South HV line) to be built in one phase.
Exports to Senegal will occur through the existing OMVS HV line and the South HV line.
Exports to Mali will transit through the OMVS HV line and will not require additional
transmission lines.
Project Financing Plan:
Banda Gas Project. The estimated investment cost is US$650 million. The Banda Gas JV
partners have indicated that they will raise the necessary financing through equity contributions
and that no commercial project debt will be raised. The Bank has been informed that it is Tullow
9
(as the major JV partner) intends to seek additional equity investors in the Banda Gas Project.
Tullow is well advanced with their plans to secure at least one major investor prior to their
investment decision and ultimately will target an equity level of 30% in the Banda Gas Project
JV, and intends to remain as operator.
SPEG Power Project. Total SPEG costs are estimated at US$467.1 million, including US$221.2
million for the 180 MW dual fuel plant, US$217.3 million for the 120 MW CCGT plant, and
amounts for administrative, working capital, and financing costs. The total project costs will be
financed through shareholder equity. The dual fuel plant is being financed by SOMELEC, with
funds already sourced for the dual fuel plant from IsDB and Arab Fund for Economic and Social
Development (AFESD). Once the dual fuel plant is completed, SOMELEC will transfer its
ownership to SPEG prior to receiving first gas from the Banda field. Although the CCGT
financing, and working capital and various administrative costs of SPEG have not yet been
secured in full, Kinross and SNIM, as shareholders of SPEG, have confirmed, in writing, that
they will stand by their required equity contributions, enabling SPEG to reach a fully secured
financing plan. In the longer term, SPEG will seek to raise debt at the project company level.
European Investment Bank (EIB) and African Development Bank (AfDB) have each expressed
interest in providing such loans to SPEG to refinance some of the equity, preferably before
completion of SPEGs power plant. For sources and uses of funds refer appendix.
Transmission Infrastructure. This includes three sub-components: (i) North HV line (US$170
million); (ii) OMVS line extension (US$7 million9) which connects the SPEG power plant to the
OMVS substation south of Nouakchott; and (iii) South HV line (US$170 million). SOMELEC
has obtained US$100 million financing for the North HV line from the Saudi Fund and has
received assurance from the Saudi Fund that they are prepared to bridge the funding gap
estimated at US$70 million once procurement is complete. AFD and IsDB are appraising the
financing of the South HV line: IsDB for the Senegal portion only and both institutions for the
Mauritania portion. IsDB has approved financing for the Senegal portion of South HV line on
March 23, 2014, whereas AFD will submit its project for Board approval by the end of May,
2014.
10
Project Agreements:
Gas Sales Agreement
Following extensive negotiations on the price and volume of gas under the GSA, Tullow and
SPEG have agreed on a price of US$12/mmBTU for first year operation with an annual inflation
of 2% for a daily consumption up to 60 BBtu/day and and an annual load factor of 70% on a
take-or-pay basis, which amounts on average to 42 BBtu/day. These gas volumes are sufficient
to power the 300 MW of generation capacity foreseen under the SPEG Power Project.
Power Purchase Agreements
The direct off-taker of electricity generated by the SPEG Power Project is SOMELEC who has
agreed on an umbrella PPA with SPEG that sets forth the terms and conditions for power
purchase and supply. SOMELEC will in turn enter into secondary PPAs to sell power to SNIM
and Kinross, and export a portion of its SPEG off-take to SENELEC and EDM. SENELEC and
EDM agreed with SOMELEC to purchase 125 MW and 50 MW of power respectively. The
electricity tariff is composed of a variable component for fuel, operation and maintenance costs,
a fixed component mainly covering the investment cost of SPEG power plants and a take-or-pay
component in case the purchaser does not offtake the minimum amount of energy. SPEGs sale
of electricity to SOMELEC is conservatively expected to increase at an annual rate of 2%
resulting in an increase of the load factor(it is defined as the ratio of actual power generated to
the maximum power that can be generated under a 90.29% availability factor) from 77% in the
first year of operation up to a capped level of 95%. This is driven by the rising demand on the
national Mauritanian grid at 8% per annum; SENELEC, EDM, Kinross and SNIM were assumed
to have a constant demand over the Projects horizon with a load factor of 85%.
As per the PPA, SOMELECs payment to SPEG is based on the following tariff
structure: (i) a non-escalating component of US$5.6 million per month corresponding to the
investment cost of SPEG plus a fixed O&M cost of US$ 1million per month that is indexed
to inflation; and (ii) a variable component of US 10.7 per kWh reflecting fuel and variable
O&M expenditures. A third component is being considered to ensure that SOMELEC pays
for the minimum amount of electricity corresponding to the gas take-or-pay volume even if
11
this volume has not been off-taken. This tariff structure is expected to be replicated at the
secondary PPA level. Detailed breakdown of tariffs for SOMELEC for first year of operation in
US per kWh is given in the appendices.
World Bank Guarantees:
The World Bank Groups proposed intervention in support of the 300 MW Banda Gas-to Power
Project includes support from both IDA and MIGA through:
(i) The IDA instruments being proposed, which include: an IDA Partial Risk Guarantee
(PRG) for ensuring the SPEG's payment obligations towards Banda under the Gas
supply Agreement (GSA), and for supporting SPEG by ensuring the credit worthiness
of two public utilities, SENELEC (of Senegal), and EDM (of Mali), for the payment
of electricity exports received under their respective Power Purchase Agreements
(PPAs) from SPEG.
PRG related agreements
12
(ii) MIGA guarantees covering: (a) equity investment of some of the JV partners against
the risks of Transfer Restriction, Expropriation and War and Civil Disturbance. ( b)
BoC coverage of the Production Sharing Agreement and (c) Termination payment
under Breach of Contract (BoC) of the GSA backstopped by GoMR
MIGA coverings
Both the proposed IDA upstream gas PRG and MIGA guarantees are ultimately designed to
provide credit enhancement and risk mitigation for SPEGs payment obligations under the
GSA.
13
Cash Flow Forecasting:
Revenues to SPEG Power Project are estimated. Cash flows forecasting for 20 years has been
done and shown in the appendices. In terms of priorities, revenues will serve first gas
expenditures, which account for 85% of total operating expenditures, then other operating
expenditures and lastly dividends will be distributed to its shareholders (about US$1.1 billion
over the project lifetime). The expenditure on gas can be found out from the table Banda gas
field projected cashflows given in the appendix.
Key Challenges:
The overall Project risk rating is High:
This reflects the complexity of reaching agreements among stakeholders with different
incentives and securing timely construction of all parts of a project of this magnitude, in a
risky country and sector environment.
Potential for construction delays:
Construction delays and cost overruns in the Banda Gas Project, the SPEG power plant
and/or the transmission lines. There is a risk that the cost of the Project is higher than
estimated once procurement is complete.
Lower electricity demand than projected:
There may be the case when the demand for the electricity is lower than the projected
demand, so this risk is mitigated by the purchase power agreement (PPA).
Assessment and Management of Environmental and Social Risks and Impacts,
Biodiversity Conservation and Sustainable Management of Living Natural
Resources :
South HV line on the Mauritanian side passing through the Diawling National Park, an
important migratory bird nesting place, and on Senegal side passing through Senegal
River delta and sensitive ecological areas such as the Djoudj national Park. An alternative
14
route is proposed in the ESIA in order to minimize the impact, particularly on birds, on
the sensitive ecological zones mentioned as the line crosses the Senegal River.
Resource Efficiency and Pollution Prevention:
Fresh water consumption is a potential impact. The generation of liquid effluents and the
risk of accidental spillage of fuel or chemicals may generate potential impacts on surface
and groundwater. contamination of soil and groundwater by fuel, stored chemicals and
waste.
Political and Security Risk:
Mali has witnessed political and security turbulences over the past two years but now the
situation is getting better and the political risk is not considered a major risk to achieving
the Projects development objective
Community Health, Safety, and Security:
The GHG emissions for the project in terms of CO2 are estimated to be a little below
100,000 t/yr. Depending on the situation, it may be necessary to relocate some residents
to avoid the most significant adverse impacts from air pollution.
Land Acquisition and Involuntary Resettlement
Conclusion:
The Project will enable the GoMR to obtain gas for its power sector thus enabling SOMELEC to
reduce its average cost of production and put the state-owned company on a more financially
sustainable path. It will also enable Senegal and Mali to obtain power at lower cost than
alternatives being considered thus also enhancing the financial health of their respective power
sectors.
15
Appendices
Overall Project Map
16
ABBREVIATIONS AND ACRONYMS
17
18
SPEG Sources and Uses of Funds
Tariff breakdown for SOMELEC
19
Banda Gas field project Cash Flow
20
SPEG projected cash flows
Unit
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
Electr
icity
sold
MWh
1827
072
1863
614
1900
886
1938
904
1977
682
2017
235
2057
580
2098
732
2140
706
2183
521
2227
191
2271
735
2254
180
2254
180
2254
180
2254
180
2254
180
2254
180
2254
180
2254
180
2254
180
Reve
nue
Capit
al Re
cove
ry Co
mpon
ent
$MM
67.60
168
68.95
371
70.33
278
71.73
944
73.17
423
74.63
771
76.13
047
77.65
308
79.20
614
80.79
026
82.40
607
84.05
419
83.40
467
83.40
467
83.40
467
83.40
467
83.40
467
83.40
467
83.40
467
83.40
467
83.40
467
Fuel
Comp
onen
t$M
M18
2.707
218
6.361
419
0.088
619
3.890
419
7.768
220
1.723
520
5.758
209.8
732
214.0
706
218.3
521
222.7
191
227.1
735
225.4
1822
5.418
225.4
1822
5.418
225.4
1822
5.418
225.4
1822
5.418
225.4
18
Fixed
O& M
Com
pone
nt$M
M14
.6165
815
.2070
915
.8214
516
.4606
417
.1256
517
.8175
318
.5373
619
.2862
720
.0654
320
.8760
721
.7194
722
.5969
322
.8707
623
.3281
823
.7947
424
.2706
424
.7560
525
.2511
725
.7561
926
.2713
226
.7967
4
Varia
ble O
& M
Comp
onen
t$M
M12
.7895
113
.0453
13.30
6213
.5723
313
.8437
714
.1206
514
.4030
614
.6911
214
.9849
415
.2846
415
.5903
415
.9021
415
.7792
615
.7792
615
.7792
615
.7792
615
.7792
615
.7792
615
.7792
615
.7792
615
.7792
6
Total
Rev
enue
$MM
277.7
1528
3.567
528
9.549
295.6
628
301.9
118
308.2
994
314.8
289
321.5
036
328.3
272
335.3
0334
2.435
349.7
267
347.4
727
347.9
301
348.3
967
348.8
726
349.3
5834
9.853
135
0.358
135
0.873
335
1.398
7
Fuel
Cost
$MM
91.98
187.0
2619
5.275
202.5
714
211.6
2721
9.219
228.6
3623
8.250
124
8.061
325
6.799
426
7.515
827
8.451
228
9.716
629
5.321
530
1.037
430
8.658
631
4.374
532
0.090
432
5.806
333
3.427
533
9.143
4
Othe
r Ope
rating
Expe
nditu
re$M
M16
.2317
633
.0045
934
.4602
935
.7478
937
.3459
438
.6857
140
.3475
342
.0441
443
.7755
245
.3175
447
.2086
749
.1384
551
.1264
552
.1155
653
.1242
554
.4691
655
.4778
556
.4865
457
.4952
358
.8401
559
.8488
4
Opera
ting P
rofit
$MM
169.5
032
63.53
688
59.81
375
57.34
355
52.93
8950
.3947
345
.8453
741
.2094
136
.4903
333
.1860
927
.7105
22.13
716.6
2969
20.4
9306
-5.76
496
-14.25
52-20
.4944
-26.72
38-32
.9434
-41.39
44-47
.5936
Depre
ciatio
n$M
M21
.925
21.92
521
.925
21.92
521
.925
21.92
521
.925
21.92
521
.925
21.92
521
.925
21.92
521
.925
21.92
521
.925
21.92
521
.925
21.92
521
.925
21.92
521
.925
Gros
s Pro
fit$M
M14
7.578
241
.6118
837
.8887
535
.4185
531
.0139
28.46
973
23.92
037
19.28
441
14.56
533
11.26
109
5.785
496
0.212
096
-15.29
53-21
.4319
-27.69
-36.18
02-42
.4194
-48.64
88-54
.8684
-63.31
94-69
.5186
Tax
%44
.2734
712
.4835
611
.3666
310
.6255
69.3
0416
98.5
4091
97.1
7611
25.7
8532
24.3
696
3.378
328
1.735
649
0.063
629
00
00
00
00
0
PAT
$MM
103.3
048
29.12
832
26.52
213
24.79
298
21.70
973
19.92
881
16.74
426
13.49
909
10.19
573
7.882
765
4.049
847
0.148
467
-15.29
53-21
.4319
-27.69
-36.18
02-42
.4194
-48.64
88-54
.8684
-63.31
94-69
.5186
21
References:
[1] http://www.miga.org/projects/index.cfm?esrsid=117
[2] http://www.worldbank.org/projects/P145664?lang=en
[3] http://documents.worldbank.org/curated/en/2014/05/19490845/mauritania-
senegal-mali-banda-gas-power-project
[4] http://www.offshore-technology.com/projects/banda-gas-field-development/
[5] http://www-wds.worldbank.org/external/default/WDSContentServer/
WDSP/IB/2014/04/23/000414397_20140425183413/Rendered/PDF/PID0A
ppraisal00s0to0Power0April022.pdf
[6] http://www-wds.worldbank.org/external/default/WDSContentServer/
WDSP/IB/2014/05/13/000442464_20140513092605/Rendered/PDF/830250
PAD0P107010Box385211B00OUO090.pdf