22
Project Finance case on Banda Gas To Power Project By Prateek Goyal (13125039) Ramswarup Bhaskar (14114019) To Dr. Anoop Singh Assistant Professor, IME Department IIT Kanpur March, 2015 DEPARTMENT OF INDUSTRIAL AND MANAGEMENT ENGINEERING INDIAN INSTITUTE OF TECHNOLOGY, KANPUR

Banda

Embed Size (px)

DESCRIPTION

Banda gas to power project

Citation preview

  • Project Finance case on Banda Gas To

    Power Project

    By

    Prateek Goyal (13125039)

    Ramswarup Bhaskar (14114019)

    To

    Dr. Anoop Singh

    Assistant Professor, IME Department

    IIT Kanpur

    March, 2015

    DEPARTMENT OF INDUSTRIAL AND MANAGEMENT ENGINEERING

    INDIAN INSTITUTE OF TECHNOLOGY, KANPUR

  • 1

    Table of Content

    Serial No. Topic Page No.

    1. Introduction 2

    2. The Project 2

    3. Power sector performance 3

    4. Project Objective 4

    5. Project Description 5

    6. Project Financing Plan 8

    7. Project Agreements 10

    8. Key Challenges 13

    9. Conclusion 14

    10. Appendices 15

    11. References 21

  • 2

    Introduction:

    The Western Africa is facing the daunting energy challenges. In Mauritania only 20% citizen has

    access to electricity & only 33% in Mali. Senegal has better number but there also 50%

    population is without electricity. In all the three countries electricity supply is unreliable and

    demand for power is increasing at 7% to 9% annually. As a result of evolving generation mix,

    coupled with high technical and commercial losses, poor efficiency and inefficient national

    revenue collection, the national power utilities of all three countries have been incurring financial

    deficits and relying on government support. Poor infrastructure and low access to energy have

    constrained GDP growth in all three countries.

    The finding of the gas fields in Mauritania are a game changer for the sub-region as they can be

    used to generate affordable and cleaner power compared to other thermal alternatives. However,

    private investors hesitating to invest in gas development because of the high political risks in the

    region and lack of creditworthiness of the developer in the sub-region.

    The Project:

    The Banda gas field is located approximately 55 km offshore Nouakchott and around 20km east

    of the Chinguetti oil field, at depths of approximately 200m-325m below sea level. The Banda

    Gas Project consists of two sub-sea wells tied back to an onshore gas processing plant via a

    subsea production manifold and a 10-inch sub-sea pipeline. The gas processing plant will be

    located 14 km north of Nouakchott and 6 km inland. Project cost is estimated to be US$650

    million. First gas can be delivered approximately 30 months from the final investment decision,

    which is expected to occur by mid-2014.

    The gas field's development forms part of the larger Banda Gas to Power project, which

    envisions the construction of a 120MW combined cycle power plant and a 180MW dual-fuel

    thermal gas-fired power plant, to be located north of Nouakchott, as well as installation of

    transmission lines.

  • 3

    Figure: The map of the location of the plant

    The total cost of this project is estimated to be 467.1 million USD. Gas will be fed from the

    Banda field to these power plants to generate electricity.

    The gas field was declared commercial in September 2012 and the environmental impact

    assessment (EIA) and front end engineering and design (FEED) were completed in the first half

    of 2013. The project approval is expected to be granted in the first half of 2015 and first

    production is slated for 2016.

    Power sector performance:

    The power sectors in all three countries suffer to various degrees from similar issues, including

    low access rates to electricity, relatively high technical and commercial losses, and high

    generation costs due to a dependence on oil-based thermal generation capacity. Tariffs are high

    but still insufficient to cover costs, resulting in reliance on government subsidies.

    Mauritanias electricity sector is characterized by a fragmented power system, low rates of

    electricity access and demand/supply imbalances. Domestic demand, excluding mining demand,

  • 4

    is expected to grow at about 9% per annum until 2020, then at 6% per annum after 2020, driven

    by progressive connection of load centers to the OMVS grid and economic growth.

    Senegal has steadily increased electrification rates (connections and installed capacity have

    doubled since 2000) reaching a national average of 50%, with almost fully electrified urban

    areas, but only covering about 25% of the rural population. Senegal remains heavily dependent

    on imported oil products for its energy supply affecting SENELECs financial and operational

    situation. About 90% of electricity is generated using oil products. Power demand in Senegal is

    expected to grow at 7% per annum over the period 2013-2020. Total installed generation

    capacity, including IPPs, is expected to double over the next seven years from 587 MW in 2013

    up to 1,097 MW in 2020.

    Malis currently installed capacity is 327 MW on interconnected grid versus 67 MW for isolated

    centers and the peak demand is expected to increase up to 457 MW by 2020. Lower cost energy

    imports from OMVS to meet increasing demand represent a least-cost solution for the country..

    Key power sector indicators

    Project Objectives:

    The Projects Development Objective (PDO) is to enable production of natural gas for

    generation of electricity to reduce the cost and increase the supply for Mauritanian households

    and industry, and enable regional integration through exports of electric power from Mauritania

    to Senegal and Mali.

  • 5

    To end extreme poverty and promote shared prosperity by providing the three countries access to

    additional, less expensive and cleaner electricity and promoting regional integration. Increased

    supply of electricity to households and small businesses in all three countries will ensure more

    access to income-generating opportunities leading to improved living standards.

    For facilitating electricity access to those households that are presently without (invariably the

    poor) and more reliable energy services to small and medium enterprises, which will in turn lead

    to economic growth.

    Project Description:

    The Banda Gas-to-Power Project consists of the following components:

    A. The upstream Banda offshore gas field production, transmission and processing

    infrastructure (the Banda Gas Project);

    B. Power generation from Banda gas in Mauritania (the SPEG Power Project); and

    C. Existing and new power transmission lines to evacuate power to the delivery points.

    The Banda gas field is located approximately 55 km offshore of Nouakchott. The Banda field

    shareholders are Tullow (67%), Petronas (15%), Kufpec (13%) and Premier Oil (5%). Tullow

    has prepared a field development plan which provides for production of up to 70 mmscfd per day

    of gas over 20 years.

    SPEG (Socit de Production dElectricit partir du Gaz) is a special purpose vehicle

    incorporated for the purpose of power generation, transmission and sales of power using Banda

    gas. SPEGs shareholders are SOMELEC (40%); KG Power, subsidiary of Kinross, an

    international gold mining company (34%); and SNIM, the national iron ore mining company

    (26%). SPEG Power Project, which will be installed north of Nouakchott, includes:

    Dual fuel plant of 180 MW (120 MW currently under construction by Wrtsila with an

    option to be extended to 180 MW that was exercised in June 2013); and

    Combined cycle gas turbines (CCGT) power plant with a capacity of 120 MW.

    Gas from the Banda offshore gas field developed by private developer Tullow will be sold to

    SPEG which will transform the gas through a 300 MW power plant. The SPEG electricity will

  • 6

    be sold to Mauritanias national utility, SOMELEC, which in turn will sell power to customers in

    Mauritania and export power to Senegal and Mali.

    Gas and electricity sale of the project

    Dual fuel power plant:

    The dual fuel power plant of approximately 120 MW capacity is based on dual fuel reciprocating

    engines. The plant is currently under construction by Wrtsila under an EPC contract. The plant

    consists of 8 engines, each of approximately 15 MW. The plant has the capability to run on

    heavy fuel oil (HFO) or Natural Gas. The plant is expected to be fully online by March 2015 and

    will initially run on HFO. As soon as natural gas is made available at the gas delivery point, the

    plant will then run on natural gas. At site conditions plant efficiency is estimated to be 41.4%

    running on HFO and 45.1% running on natural gas.

  • 7

    Wartsila is supplying eight 50DF dual-fuel generating sets for the Banda Gas to Power project.

    CCGT plant :

    The 120 MW CCGT plant will run with GE-6B gas turbines. Net efficiency is calculated to be of

    the order of 47% at yearly average site conditions. Units should be able to operate on light fuel

    oil (LFO) as backup fuel during (short) periods of unavailability of natural gas. The choice of

    LFO as backup fuel is linked to the choice of combustion technology (dry low NOx burners) and

    meeting World Bank emissions requirements. Given the high cost of LFO, this fuel 51 is

    intended to be used for short periods of time only. The backup fuel functionality is not intended

    to cope with the risk of potentially long delay in construction of the gas supply infrastructure. In

    such case, running the dual fuel plant on HFO will be more economical.

    Power generated by SPEG to SOMELEC will be evacuated through several routes:

  • 8

    (i) A greenfield high voltage transmission line to Nouadhibou with a spur to

    Tasiast, site of Kinross gold mine (the North HV line) owned and operated by

    SOMELEC and financed by the Saudi Fund,

    (ii) The existing OMVS high voltage transmission line that will be connected to

    the power plant through a short extension (the OMVS HV line and the OMVS

    HV extension), funded by SOMELEC and

    (iii) A new high voltage transmission line between Mauritania and Senegal, to be

    financed by AFD and IsDB, with a wheeling capacity of about 170 MW (the

    South HV line) to be built in one phase.

    Exports to Senegal will occur through the existing OMVS HV line and the South HV line.

    Exports to Mali will transit through the OMVS HV line and will not require additional

    transmission lines.

    Project Financing Plan:

    Banda Gas Project. The estimated investment cost is US$650 million. The Banda Gas JV

    partners have indicated that they will raise the necessary financing through equity contributions

    and that no commercial project debt will be raised. The Bank has been informed that it is Tullow

  • 9

    (as the major JV partner) intends to seek additional equity investors in the Banda Gas Project.

    Tullow is well advanced with their plans to secure at least one major investor prior to their

    investment decision and ultimately will target an equity level of 30% in the Banda Gas Project

    JV, and intends to remain as operator.

    SPEG Power Project. Total SPEG costs are estimated at US$467.1 million, including US$221.2

    million for the 180 MW dual fuel plant, US$217.3 million for the 120 MW CCGT plant, and

    amounts for administrative, working capital, and financing costs. The total project costs will be

    financed through shareholder equity. The dual fuel plant is being financed by SOMELEC, with

    funds already sourced for the dual fuel plant from IsDB and Arab Fund for Economic and Social

    Development (AFESD). Once the dual fuel plant is completed, SOMELEC will transfer its

    ownership to SPEG prior to receiving first gas from the Banda field. Although the CCGT

    financing, and working capital and various administrative costs of SPEG have not yet been

    secured in full, Kinross and SNIM, as shareholders of SPEG, have confirmed, in writing, that

    they will stand by their required equity contributions, enabling SPEG to reach a fully secured

    financing plan. In the longer term, SPEG will seek to raise debt at the project company level.

    European Investment Bank (EIB) and African Development Bank (AfDB) have each expressed

    interest in providing such loans to SPEG to refinance some of the equity, preferably before

    completion of SPEGs power plant. For sources and uses of funds refer appendix.

    Transmission Infrastructure. This includes three sub-components: (i) North HV line (US$170

    million); (ii) OMVS line extension (US$7 million9) which connects the SPEG power plant to the

    OMVS substation south of Nouakchott; and (iii) South HV line (US$170 million). SOMELEC

    has obtained US$100 million financing for the North HV line from the Saudi Fund and has

    received assurance from the Saudi Fund that they are prepared to bridge the funding gap

    estimated at US$70 million once procurement is complete. AFD and IsDB are appraising the

    financing of the South HV line: IsDB for the Senegal portion only and both institutions for the

    Mauritania portion. IsDB has approved financing for the Senegal portion of South HV line on

    March 23, 2014, whereas AFD will submit its project for Board approval by the end of May,

    2014.

  • 10

    Project Agreements:

    Gas Sales Agreement

    Following extensive negotiations on the price and volume of gas under the GSA, Tullow and

    SPEG have agreed on a price of US$12/mmBTU for first year operation with an annual inflation

    of 2% for a daily consumption up to 60 BBtu/day and and an annual load factor of 70% on a

    take-or-pay basis, which amounts on average to 42 BBtu/day. These gas volumes are sufficient

    to power the 300 MW of generation capacity foreseen under the SPEG Power Project.

    Power Purchase Agreements

    The direct off-taker of electricity generated by the SPEG Power Project is SOMELEC who has

    agreed on an umbrella PPA with SPEG that sets forth the terms and conditions for power

    purchase and supply. SOMELEC will in turn enter into secondary PPAs to sell power to SNIM

    and Kinross, and export a portion of its SPEG off-take to SENELEC and EDM. SENELEC and

    EDM agreed with SOMELEC to purchase 125 MW and 50 MW of power respectively. The

    electricity tariff is composed of a variable component for fuel, operation and maintenance costs,

    a fixed component mainly covering the investment cost of SPEG power plants and a take-or-pay

    component in case the purchaser does not offtake the minimum amount of energy. SPEGs sale

    of electricity to SOMELEC is conservatively expected to increase at an annual rate of 2%

    resulting in an increase of the load factor(it is defined as the ratio of actual power generated to

    the maximum power that can be generated under a 90.29% availability factor) from 77% in the

    first year of operation up to a capped level of 95%. This is driven by the rising demand on the

    national Mauritanian grid at 8% per annum; SENELEC, EDM, Kinross and SNIM were assumed

    to have a constant demand over the Projects horizon with a load factor of 85%.

    As per the PPA, SOMELECs payment to SPEG is based on the following tariff

    structure: (i) a non-escalating component of US$5.6 million per month corresponding to the

    investment cost of SPEG plus a fixed O&M cost of US$ 1million per month that is indexed

    to inflation; and (ii) a variable component of US 10.7 per kWh reflecting fuel and variable

    O&M expenditures. A third component is being considered to ensure that SOMELEC pays

    for the minimum amount of electricity corresponding to the gas take-or-pay volume even if

  • 11

    this volume has not been off-taken. This tariff structure is expected to be replicated at the

    secondary PPA level. Detailed breakdown of tariffs for SOMELEC for first year of operation in

    US per kWh is given in the appendices.

    World Bank Guarantees:

    The World Bank Groups proposed intervention in support of the 300 MW Banda Gas-to Power

    Project includes support from both IDA and MIGA through:

    (i) The IDA instruments being proposed, which include: an IDA Partial Risk Guarantee

    (PRG) for ensuring the SPEG's payment obligations towards Banda under the Gas

    supply Agreement (GSA), and for supporting SPEG by ensuring the credit worthiness

    of two public utilities, SENELEC (of Senegal), and EDM (of Mali), for the payment

    of electricity exports received under their respective Power Purchase Agreements

    (PPAs) from SPEG.

    PRG related agreements

  • 12

    (ii) MIGA guarantees covering: (a) equity investment of some of the JV partners against

    the risks of Transfer Restriction, Expropriation and War and Civil Disturbance. ( b)

    BoC coverage of the Production Sharing Agreement and (c) Termination payment

    under Breach of Contract (BoC) of the GSA backstopped by GoMR

    MIGA coverings

    Both the proposed IDA upstream gas PRG and MIGA guarantees are ultimately designed to

    provide credit enhancement and risk mitigation for SPEGs payment obligations under the

    GSA.

  • 13

    Cash Flow Forecasting:

    Revenues to SPEG Power Project are estimated. Cash flows forecasting for 20 years has been

    done and shown in the appendices. In terms of priorities, revenues will serve first gas

    expenditures, which account for 85% of total operating expenditures, then other operating

    expenditures and lastly dividends will be distributed to its shareholders (about US$1.1 billion

    over the project lifetime). The expenditure on gas can be found out from the table Banda gas

    field projected cashflows given in the appendix.

    Key Challenges:

    The overall Project risk rating is High:

    This reflects the complexity of reaching agreements among stakeholders with different

    incentives and securing timely construction of all parts of a project of this magnitude, in a

    risky country and sector environment.

    Potential for construction delays:

    Construction delays and cost overruns in the Banda Gas Project, the SPEG power plant

    and/or the transmission lines. There is a risk that the cost of the Project is higher than

    estimated once procurement is complete.

    Lower electricity demand than projected:

    There may be the case when the demand for the electricity is lower than the projected

    demand, so this risk is mitigated by the purchase power agreement (PPA).

    Assessment and Management of Environmental and Social Risks and Impacts,

    Biodiversity Conservation and Sustainable Management of Living Natural

    Resources :

    South HV line on the Mauritanian side passing through the Diawling National Park, an

    important migratory bird nesting place, and on Senegal side passing through Senegal

    River delta and sensitive ecological areas such as the Djoudj national Park. An alternative

  • 14

    route is proposed in the ESIA in order to minimize the impact, particularly on birds, on

    the sensitive ecological zones mentioned as the line crosses the Senegal River.

    Resource Efficiency and Pollution Prevention:

    Fresh water consumption is a potential impact. The generation of liquid effluents and the

    risk of accidental spillage of fuel or chemicals may generate potential impacts on surface

    and groundwater. contamination of soil and groundwater by fuel, stored chemicals and

    waste.

    Political and Security Risk:

    Mali has witnessed political and security turbulences over the past two years but now the

    situation is getting better and the political risk is not considered a major risk to achieving

    the Projects development objective

    Community Health, Safety, and Security:

    The GHG emissions for the project in terms of CO2 are estimated to be a little below

    100,000 t/yr. Depending on the situation, it may be necessary to relocate some residents

    to avoid the most significant adverse impacts from air pollution.

    Land Acquisition and Involuntary Resettlement

    Conclusion:

    The Project will enable the GoMR to obtain gas for its power sector thus enabling SOMELEC to

    reduce its average cost of production and put the state-owned company on a more financially

    sustainable path. It will also enable Senegal and Mali to obtain power at lower cost than

    alternatives being considered thus also enhancing the financial health of their respective power

    sectors.

  • 15

    Appendices

    Overall Project Map

  • 16

    ABBREVIATIONS AND ACRONYMS

  • 17

  • 18

    SPEG Sources and Uses of Funds

    Tariff breakdown for SOMELEC

  • 19

    Banda Gas field project Cash Flow

  • 20

    SPEG projected cash flows

    Unit

    2016

    2017

    2018

    2019

    2020

    2021

    2022

    2023

    2024

    2025

    2026

    2027

    2028

    2029

    2030

    2031

    2032

    2033

    2034

    2035

    2036

    Electr

    icity

    sold

    MWh

    1827

    072

    1863

    614

    1900

    886

    1938

    904

    1977

    682

    2017

    235

    2057

    580

    2098

    732

    2140

    706

    2183

    521

    2227

    191

    2271

    735

    2254

    180

    2254

    180

    2254

    180

    2254

    180

    2254

    180

    2254

    180

    2254

    180

    2254

    180

    2254

    180

    Reve

    nue

    Capit

    al Re

    cove

    ry Co

    mpon

    ent

    $MM

    67.60

    168

    68.95

    371

    70.33

    278

    71.73

    944

    73.17

    423

    74.63

    771

    76.13

    047

    77.65

    308

    79.20

    614

    80.79

    026

    82.40

    607

    84.05

    419

    83.40

    467

    83.40

    467

    83.40

    467

    83.40

    467

    83.40

    467

    83.40

    467

    83.40

    467

    83.40

    467

    83.40

    467

    Fuel

    Comp

    onen

    t$M

    M18

    2.707

    218

    6.361

    419

    0.088

    619

    3.890

    419

    7.768

    220

    1.723

    520

    5.758

    209.8

    732

    214.0

    706

    218.3

    521

    222.7

    191

    227.1

    735

    225.4

    1822

    5.418

    225.4

    1822

    5.418

    225.4

    1822

    5.418

    225.4

    1822

    5.418

    225.4

    18

    Fixed

    O& M

    Com

    pone

    nt$M

    M14

    .6165

    815

    .2070

    915

    .8214

    516

    .4606

    417

    .1256

    517

    .8175

    318

    .5373

    619

    .2862

    720

    .0654

    320

    .8760

    721

    .7194

    722

    .5969

    322

    .8707

    623

    .3281

    823

    .7947

    424

    .2706

    424

    .7560

    525

    .2511

    725

    .7561

    926

    .2713

    226

    .7967

    4

    Varia

    ble O

    & M

    Comp

    onen

    t$M

    M12

    .7895

    113

    .0453

    13.30

    6213

    .5723

    313

    .8437

    714

    .1206

    514

    .4030

    614

    .6911

    214

    .9849

    415

    .2846

    415

    .5903

    415

    .9021

    415

    .7792

    615

    .7792

    615

    .7792

    615

    .7792

    615

    .7792

    615

    .7792

    615

    .7792

    615

    .7792

    615

    .7792

    6

    Total

    Rev

    enue

    $MM

    277.7

    1528

    3.567

    528

    9.549

    295.6

    628

    301.9

    118

    308.2

    994

    314.8

    289

    321.5

    036

    328.3

    272

    335.3

    0334

    2.435

    349.7

    267

    347.4

    727

    347.9

    301

    348.3

    967

    348.8

    726

    349.3

    5834

    9.853

    135

    0.358

    135

    0.873

    335

    1.398

    7

    Fuel

    Cost

    $MM

    91.98

    187.0

    2619

    5.275

    202.5

    714

    211.6

    2721

    9.219

    228.6

    3623

    8.250

    124

    8.061

    325

    6.799

    426

    7.515

    827

    8.451

    228

    9.716

    629

    5.321

    530

    1.037

    430

    8.658

    631

    4.374

    532

    0.090

    432

    5.806

    333

    3.427

    533

    9.143

    4

    Othe

    r Ope

    rating

    Expe

    nditu

    re$M

    M16

    .2317

    633

    .0045

    934

    .4602

    935

    .7478

    937

    .3459

    438

    .6857

    140

    .3475

    342

    .0441

    443

    .7755

    245

    .3175

    447

    .2086

    749

    .1384

    551

    .1264

    552

    .1155

    653

    .1242

    554

    .4691

    655

    .4778

    556

    .4865

    457

    .4952

    358

    .8401

    559

    .8488

    4

    Opera

    ting P

    rofit

    $MM

    169.5

    032

    63.53

    688

    59.81

    375

    57.34

    355

    52.93

    8950

    .3947

    345

    .8453

    741

    .2094

    136

    .4903

    333

    .1860

    927

    .7105

    22.13

    716.6

    2969

    20.4

    9306

    -5.76

    496

    -14.25

    52-20

    .4944

    -26.72

    38-32

    .9434

    -41.39

    44-47

    .5936

    Depre

    ciatio

    n$M

    M21

    .925

    21.92

    521

    .925

    21.92

    521

    .925

    21.92

    521

    .925

    21.92

    521

    .925

    21.92

    521

    .925

    21.92

    521

    .925

    21.92

    521

    .925

    21.92

    521

    .925

    21.92

    521

    .925

    21.92

    521

    .925

    Gros

    s Pro

    fit$M

    M14

    7.578

    241

    .6118

    837

    .8887

    535

    .4185

    531

    .0139

    28.46

    973

    23.92

    037

    19.28

    441

    14.56

    533

    11.26

    109

    5.785

    496

    0.212

    096

    -15.29

    53-21

    .4319

    -27.69

    -36.18

    02-42

    .4194

    -48.64

    88-54

    .8684

    -63.31

    94-69

    .5186

    Tax

    %44

    .2734

    712

    .4835

    611

    .3666

    310

    .6255

    69.3

    0416

    98.5

    4091

    97.1

    7611

    25.7

    8532

    24.3

    696

    3.378

    328

    1.735

    649

    0.063

    629

    00

    00

    00

    00

    0

    PAT

    $MM

    103.3

    048

    29.12

    832

    26.52

    213

    24.79

    298

    21.70

    973

    19.92

    881

    16.74

    426

    13.49

    909

    10.19

    573

    7.882

    765

    4.049

    847

    0.148

    467

    -15.29

    53-21

    .4319

    -27.69

    -36.18

    02-42

    .4194

    -48.64

    88-54

    .8684

    -63.31

    94-69

    .5186

  • 21

    References:

    [1] http://www.miga.org/projects/index.cfm?esrsid=117

    [2] http://www.worldbank.org/projects/P145664?lang=en

    [3] http://documents.worldbank.org/curated/en/2014/05/19490845/mauritania-

    senegal-mali-banda-gas-power-project

    [4] http://www.offshore-technology.com/projects/banda-gas-field-development/

    [5] http://www-wds.worldbank.org/external/default/WDSContentServer/

    WDSP/IB/2014/04/23/000414397_20140425183413/Rendered/PDF/PID0A

    ppraisal00s0to0Power0April022.pdf

    [6] http://www-wds.worldbank.org/external/default/WDSContentServer/

    WDSP/IB/2014/05/13/000442464_20140513092605/Rendered/PDF/830250

    PAD0P107010Box385211B00OUO090.pdf